KR100762858B1 - The waterproof method of water tank use PE seet - Google Patents

The waterproof method of water tank use PE seet Download PDF

Info

Publication number
KR100762858B1
KR100762858B1 KR1020050018772A KR20050018772A KR100762858B1 KR 100762858 B1 KR100762858 B1 KR 100762858B1 KR 1020050018772 A KR1020050018772 A KR 1020050018772A KR 20050018772 A KR20050018772 A KR 20050018772A KR 100762858 B1 KR100762858 B1 KR 100762858B1
Authority
KR
South Korea
Prior art keywords
sheet
water tank
wall surface
fusion
heat
Prior art date
Application number
KR1020050018772A
Other languages
Korean (ko)
Other versions
KR20060097885A (en
Inventor
김기완
Original Assignee
김기완
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김기완 filed Critical 김기완
Priority to KR1020050018772A priority Critical patent/KR100762858B1/en
Publication of KR20060097885A publication Critical patent/KR20060097885A/en
Application granted granted Critical
Publication of KR100762858B1 publication Critical patent/KR100762858B1/en

Links

Images

Classifications

    • AHUMAN NECESSITIES
    • A21BAKING; EDIBLE DOUGHS
    • A21CMACHINES OR EQUIPMENT FOR MAKING OR PROCESSING DOUGHS; HANDLING BAKED ARTICLES MADE FROM DOUGH
    • A21C1/00Mixing or kneading machines for the preparation of dough
    • A21C1/14Structural elements of mixing or kneading machines; Parts; Accessories
    • A21C1/1495Arrangements for cooling or heating ; Arrangements for applying super- or sub-atmospheric pressure
    • AHUMAN NECESSITIES
    • A21BAKING; EDIBLE DOUGHS
    • A21CMACHINES OR EQUIPMENT FOR MAKING OR PROCESSING DOUGHS; HANDLING BAKED ARTICLES MADE FROM DOUGH
    • A21C1/00Mixing or kneading machines for the preparation of dough
    • A21C1/02Mixing or kneading machines for the preparation of dough with vertically-mounted tools; Machines for whipping or beating
    • AHUMAN NECESSITIES
    • A23FOODS OR FOODSTUFFS; TREATMENT THEREOF, NOT COVERED BY OTHER CLASSES
    • A23LFOODS, FOODSTUFFS, OR NON-ALCOHOLIC BEVERAGES, NOT COVERED BY SUBCLASSES A21D OR A23B-A23J; THEIR PREPARATION OR TREATMENT, e.g. COOKING, MODIFICATION OF NUTRITIVE QUALITIES, PHYSICAL TREATMENT; PRESERVATION OF FOODS OR FOODSTUFFS, IN GENERAL
    • A23L7/00Cereal-derived products; Malt products; Preparation or treatment thereof
    • A23L7/10Cereal-derived products

Abstract

본 발명은 PE시트를 이용한 저수조의 방수 공법에 관한 것으로, 보다 상세하게는 저수조의 벽면과 바닥면에, 상기 벽면과 바닥면에 걸쳐 연장된 길이를 갖는 일측 및 타측의 PE시트 중첩부위를 열융착기로 열융착할 때, 수동융착되는 부분이 없이 모두 상기 열융착기를 이용한 자동융착이 이루어질 수 있도록 한 PE시트를 이용한 저수조의 방수 공법에 관한 것으로서, 저수조의 콘크리트 벽면과 바닥면에 다수의 붙임용 시트를 고정하는 제1 공정과; 상기 저수조의 벽면에 고정된 붙임용 시트에 벽면과 바닥면에 걸쳐 연장된 길이를 갖는 일측 및 타측 PE시트를 서로 마주하는 단부측이 중첩되도록 열융착시키는 제2 공정과; 상기 PE시트의 중첩 부위를 벽면을 타고 열융착기로 자동융착을 하면서 하부측 모서리 부분에 대한 융착시에는 상기 모서리 부분의 안쪽으로 이 중첩된 PE시트를 밀어 가능한 밀착되게 하는 제3 공정과; 상기 제3 공정과 같이 모서리 부분의 안쪽으로 PE시트가 밀착된 상태에서 바닥면에 PE시트를 상기 바닥면에 다수 고정된 붙임용 시트에 열융착시킨 후, 나머지 PE시트의 중첩부위에 대한 자동융착을 수행하는 제4 공정으로 이루어짐으로써 시공의 신속성과 간편성 및 효율성을 확보할 수 있는 효과가 있다. The present invention relates to a waterproofing method of a water tank using a PE sheet, and more specifically, to the wall surface and the bottom surface of the water tank, one side and the other side of the PE sheet overlapping portion having a length extending over the wall surface and the bottom surface heat-sealing machine When heat-sealing, the invention relates to a waterproofing method of a water tank using a PE sheet to allow automatic fusion using the heat fusion machine without a part to be manually fused, a plurality of sheets for attaching to the concrete wall and bottom surface of the water tank A first step of fixing the; A second step of thermally fusion bonding the end sheets facing one another and the other side PE sheet having a length extending over the wall surface and the bottom surface to the pasting sheet fixed to the wall surface of the water tank so as to overlap each other; A third step of automatically bonding the overlapped portion of the PE sheet to a heat fusion splicer on a wall while pushing the overlapped PE sheet to the inner side of the corner portion as closely as possible when fused to the lower edge portion; In the state where the PE sheet is in close contact with the inside of the corner portion as in the third process, the PE sheet is thermally fused to the gluing sheet fixed to the bottom surface, and the fusion sheet is automatically bonded to the overlapping portions of the remaining PE sheets. By the fourth process to perform the effect there is an effect to ensure the speed and simplicity and efficiency of construction.

PE시트, 붙임용 시트, 양면, 하면, 날개, 열융착기, 타정못 PE Sheet, Gluing Sheet, Both Sides, Bottom, Wings, Heat Fusion Machine, Tableting Nail

Description

PE시트를 이용한 저수조의 방수 공법{The waterproof method of water tank use PE seet}The waterproof method of water tank use PE seet}

도 1a 및 도 1b는 일반적인 저수조의 구조를 나타낸 것으로서,1A and 1B show the structure of a general reservoir,

도 1a는 종단면도.1A is a longitudinal sectional view.

도 1b는 평단면도.1B is a plan sectional view.

도 2는 종래의 PE시트를 이용한 저수조의 방수 공법을 나타낸 단면도.Figure 2 is a cross-sectional view showing a waterproof method of the reservoir using a conventional PE sheet.

도 3은 도 2의 다른 예를 나타낸 단면도.3 is a cross-sectional view showing another example of FIG.

도 4는 도 1의 모서리 부분에 대한 방수 공법을 나타낸 전개도 및 사시도.4 is an exploded view and a perspective view showing a waterproof method for the corner portion of FIG.

도 5는 도 1의 벽체 돌출기둥에 대한 방수 공법을 나타낸 사시도.5 is a perspective view showing a waterproof method for the wall protrusion pillar of FIG.

도 6은 일반적인 열융착기를 나타낸 측면도.Figure 6 is a side view showing a typical heat welding machine.

도 7a 내지 도 7c는 도 1의 사각 기둥에 대한 방수 공법을 나타낸 것으로서,7A to 7C illustrate a waterproof method for the square pillar of FIG. 1,

도 7a는 사시도.7A is a perspective view.

도 7b는 단면도.7B is a sectional view.

도 7c는 다른 예를 나타낸 사시도.7C is a perspective view showing another example.

도 8은 도 1의 벽면과 바닥면 간의 방수 공법을 나타낸 사시도.8 is a perspective view showing a waterproof method between the wall surface and the bottom surface of FIG.

도 9a는 도 1의 슬리브에 대한 방수 공법을 나타낸 단면도.Figure 9a is a cross-sectional view showing a waterproof method for the sleeve of Figure 1;

도 9b는 도 9a의 다른 예를 나타낸 단면도.9B is a sectional view of another example of FIG. 9A;

도 10은 도 8에서 열융착기의 진행방향을 나타낸 평면도.FIG. 10 is a plan view illustrating a traveling direction of the heat welding machine of FIG. 8; FIG.

도 11은 본 발명에 의하여 PE시트의 부착상태를 나타낸 사시도.Figure 11 is a perspective view showing the attachment state of the PE sheet according to the present invention.

도 12a 및 도 12b는 본 발명에 의한 PE시트의 방수 공법을 나타낸 단면도.12a and 12b is a cross-sectional view showing a waterproof method of the PE sheet according to the present invention.

도 13은 본 발명의 다른 실시예를 나타낸 단면도.13 is a cross-sectional view showing another embodiment of the present invention.

*도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings

110:저수조110: reservoir

130:PE시트130: PE sheet

131,131a:양면 132:하면  131,131a: Both sides 132: When

133:접힘선 134:절개부  133: fold line 134: incision

134a:절개홈 135,135a:날개  134a: incision groove 135,135a: wings

136:용접부  136: weld

140:타정못 150:붙임용 시트140: tableting nail 150: sheet for pasting

170:열융착기170: heat fusion machine

171:기체 172,173:압착로울러  171: gas 172, 173: crimping roller

174:열풍노즐  174: hot air nozzle

180:슬리브 방수부180: sleeve waterproof

181:실링재 182:SUS 밴드  181: Sealing material 182: SUS band

183:고정플랜지 184:체결플랜지  183: fixed flange 184: tightening flange

185:패킹 187:볼트  185: Packing 187: Bolt

190:지지대190: support

본 발명은 PE시트를 이용한 저수조의 방수 공법에 관한 것으로, 보다 상세하게는 저수조의 벽면과 바닥면에, 상기 벽면과 바닥면에 걸쳐 연장된 길이를 갖는 일측 및 타측의 PE시트 중첩부위를 열융착기로 열융착할 때, 수동융착되는 부분이 없이 모두 상기 열융착기를 이용한 자동융착이 이루어질 수 있도록 한 PE시트를 이용한 저수조의 방수 공법에 관한 것이다. The present invention relates to a waterproofing method of a water tank using a PE sheet, and more specifically, to the wall surface and the bottom surface of the water tank, one side and the other side of the PE sheet overlapping portion having a length extending over the wall surface and the bottom surface heat-sealing machine When thermally smelting, the present invention relates to a waterproofing method of a water tank using a PE sheet to allow automatic fusion using the heat fusion machine without any part to be manually fused.

일반적으로 건물의 지하나 옥상에 설치되는 저수조는 통상 콘크리트 구조물로 이루어지고, 물이 담겨지는 특성상 내면의 방수처리는 필수적으로 요구된다.In general, the water tank installed in the basement or roof of the building is usually made of a concrete structure, the waterproofing of the inner surface is essentially required due to the nature of the water contained.

종래에는 주로 에폭시 수지도료나 유리섬유를 보강재로 한 열경화성 수지를 콘크리트 구조물로 된 저수조의 내면에 도포하는 방법으로 방수처리를 하였으나, 이는 영구적이지 못할 뿐만 아니라 시간이 많이 소요되고, 작업의 번거로움 및 불편성을 초래하는 문제점이 있었다.Conventionally, the heat-treatment method was mainly applied to the inner surface of a water tank made of a concrete structure by using a thermosetting resin mainly composed of epoxy resin or glass fiber as a reinforcing material, but this was not only permanent but time-consuming, and wasted. There was a problem causing inconvenience.

이에 따라 근래에는 도 1a 및 도 1b에 도시된 바와 같이 PE시트(polyethylene sheet)를 이용한 방수 구조가 제안된 바 있는 것으로서, 통상 저수조(110)는 전술한 바와 같이 콘크리트 구조물로 이루어지고, 대략 장방형의 함체로 형성되어 측방향을 따라 형성되는 각각의 벽면(111)과 바닥면(112) 및 천정면(113)을 구성하게 되며, 일측 벽면(111)을 슬리브(114)가 내.외측을 관통하고, 상기 슬리브(114)를 포함하여 벽면(111)과 바닥면(112) 및 천정면(113) 모두 PE시트(130)가 부착되어 방수가 이루어지도록 하고 있다.Accordingly, in recent years, a waterproof structure using a polyethylene sheet (PE sheet) has been proposed as shown in FIGS. 1A and 1B. In general, the reservoir 110 is made of a concrete structure as described above, and has a substantially rectangular shape. Each wall surface 111 and the bottom surface 112 and the ceiling surface 113 formed in the lateral direction formed by the enclosure is formed, the one side wall 111 through the sleeve 114 penetrates the inner and outer In addition, both the wall 114, the bottom 112, and the ceiling surface 113 including the sleeve 114 are attached to the PE sheet 130 to be waterproof.

그리고, 상기 저수조(110)는 건물의 구조적인 제한으로 벽면(111)에 벽체 돌출기둥(116)이 형성될 수 있으며, 그 중앙부 또는 외곽에 사각 기둥(117)이 형성될 수 있는 것으로서, 상기 벽체 돌출기둥(116) 및 사각 기둥(117) 역시 PE시트(130)에 의해서 방수가 이루어지고, 도 1a에 도시된 바와 같이 저수조(110)의 내부에는 여러가지 설치물, 예컨대 사다리(115) 등이 설치되며, 상기 사다리(115)는 통상 상.하로 높이 조절이 가능한 구조로 되어 상.하 단부측을 저수조(110)의 천정면(113)과 바닥면(112)에 밀착하여 고정시킴으로써 그 설치가 이루어진다.In addition, the reservoir 110 may have a wall protrusion pillar 116 formed on the wall surface 111 due to the structural limitation of the building, and the square pillar 117 may be formed at the center or the outer portion thereof. Protrusion pillar 116 and the square pillar 117 is also waterproof by the PE sheet 130, and as shown in Figure 1a is a variety of installations, for example, ladder 115 is installed inside the reservoir 110, The ladder 115 has a structure in which height can be adjusted up and down in general, and the upper and lower end sides are fixed to the ceiling surface 113 and the bottom surface 112 of the water tank 110 so as to be fixed.

도 2는 종래의 PE시트에 의한 방수 구조를 나타낸 단면도로서, 이에 도시된 바와같이 바탕면 처리된 저수조(110)의 내면을 따라 PE시트(130)를 공급하고, 서로 중첩되는 부위를 와셔(140a)가 끼워진 타정못(140)으로 박아 PE시트(130)에 대한 고정이 이루어지도록 하며, 물의 접촉에 따른 상기 타정못(140)의 부식 방지를 위하여 그 고정부위의 외측을 덧붙임 시트(150)로 융착하여 은폐토록 하였다.Figure 2 is a cross-sectional view showing a waterproof structure by a conventional PE sheet, as shown therein to supply the PE sheet 130 along the inner surface of the reservoir 110 treated with the surface, washer 140a ) Is inserted into the tableting nail 140 inserted into the PE sheet 130 and fixed to the PE sheet 130. In order to prevent corrosion of the tableting nail 140 according to water contact, the outside of the fixing part is added to the sheet 150. It was fused and concealed.

또한, 다른 예로서, 도 3에 도시된 바와같이 바탕면 처리된 저수조(110)의 내면에 일정면적을 가지는 붙임용 시트(160)를 와셔(140a)가 끼워진 타정못(140)과 결합시켜 저수조(110)의 내면에 일정 간격으로 배열되게 타격 고정한 후, 상기 붙임용 시트(160)가 대략 중앙 부위에 위치하도록 붙임용 시트(160)에 PE시트(130)를 열융착시켜 부착되게 하는 방법이 제안된 바 있다.In addition, as another example, as shown in Figure 3 by combining the tableting sheet 140 having a predetermined area on the inner surface of the reservoir 110, the base surface treatment with the tableting nail 140 fitted with the washer 140a After hitting and fixing to be arranged at a predetermined interval on the inner surface of 110, the method for heat-bonding the PE sheet 130 to the sheeting sheet 160 so that the sheeting sheet 160 is located approximately at the center portion. It has been proposed.

그리고, 상기 붙임용 시트(160)에 부착된 PE시트(130)의 각 단부는 서로 중첩되어 다시 열융착시켜 저수조(110)의 내면에 대한 PE시트(130)의 부착이 이루어 질 수 있도록 하는 것이며, 이러한 PE시트(130)를 이용한 시공은 저수조(110)의 벽면과 바닥면 및 천정면에 걸쳐 이루어진다.In addition, each end of the PE sheet 130 attached to the sheet for attaching 160 is superimposed on each other so that the PE sheet 130 is attached to the inner surface of the water storage tank 110 so as to be attached. , The construction using the PE sheet 130 is made over the wall surface and the bottom surface and the ceiling surface of the reservoir 110.

한편, 저수조(110)의 모서리 부위는 도 4에 도시된 바와같이 양면(131)(131a)과 상.하 일측면, 여기서는 하면(132)을 파선으로 나타낸 접힘선(133)을 중심으로 직각을 이루도록 접어 부착시키게 되는데, 이때 절개부(134)를 형성하여 하면(132)을 먼저 접고, 그 다음 양면(131)(131a)을 접어 절개부(134)에 의해서 형성된 양면(131)(131a)의 하단부 날개(135)(135a)를 하면(132) 상에 중첩하여 열융착시킴으로써 이루어진다.On the other hand, as shown in Figure 4, the corner portion of the reservoir 110 has a right angle with respect to the fold line 133, the upper and lower sides and upper and lower sides, here the lower surface 132, shown by a broken line. Folded to form, in which case the incision 134 is formed to fold the lower surface 132 first, and then the two sides (131, 131a) of the two sides (131, 131a) formed by the incision 134 The lower end wings 135 and 135a are formed by overlapping and heat-sealing on the lower surface 132.

그리고, 이러한 부착방법은 도 5에 도시된 바와 같은 벽체 돌출기둥(116)에 대해서도 동일하게 적용되고, 다만, 양면(131)(131a) 및 하단부 날개(135)(135a)가 반대 방향으로 접히는데 차이가 있으며, PE시트(130) 간의 중첩 부위에 대한 용접은 도 6에 도시된 바와같은 열융착기(170)가 사용된다.In addition, the attachment method is similarly applied to the wall protrusion pillar 116 as shown in FIG. 5, except that both sides 131 and 131a and the lower wing 135 and 135a are folded in opposite directions. There is a difference, and the welding to the overlapping portion between the PE sheet 130 is used a heat welder 170 as shown in FIG.

상기 열융착기(170)는 기체(171)의 하부측에 구비되는 상.하 압착로울러(172)(173)의 후방측에 열풍을 내뿜는 열풍노즐(174)이 구비되어 상기 기체(171)가 후퇴하면서 먼저 열풍으로 PE시트(130)의 중첩부위를 가열한 후, 이 가열된 PE시트(130)의 중첩 부위가 상기 상.하 압착로울러(172)(173)의 사이를 지나면서 상기 압착로울러에 의하여 압착됨으로써 열융착이 이루어지도록 하고 있다.The heat welding machine 170 is provided with a hot air nozzle 174 that emits hot air on the rear side of the upper and lower compression rollers 172 and 173 provided on the lower side of the base 171 so that the base 171 retreats. While first heating the overlapping portion of the PE sheet 130 with hot air, the overlapping portion of the heated PE sheet 130 passes through the upper and lower compression rollers 172 and 173 to the compression roller. By pressing, the thermal fusion is achieved.

이와함께 사각기둥의 경우는 도 7a 및 도 7b에 도시된 바와같이 PE시트(130)를 가로 및 세로 방향의 벽면을 따라 부착시키고, 상기 벽면(117a)과 바닥면(112) 사이의 경계는 별도의 수작업에 의해서 열풍에 의한 플라스틱 용접으로 용접부(136)를 형성하여 부착하거나, 도 7c에 도시된 바와같이 각면의 하단부에 하부 날개(137)를 형성하여 상기 하부 날개(137)를 따라 용접부(136)에 의한 수동융착을 행하게 되는 것으로서, 물론 상기 PE시트(130)는 저수조의 내면에 박히는 타정못(140)의 붙임용 시트(160)에 열융착되어 부착됨은 당연하다.(도 2 및 도 3 참조.)In addition, in the case of a square pillar is attached to the PE sheet 130 along the horizontal and vertical wall surface as shown in Figure 7a and 7b, the boundary between the wall surface 117a and the bottom surface 112 is separate The welding unit 136 is formed by attaching the welding unit 136 by manual welding by hot air, or as shown in FIG. 7C, a lower wing 137 is formed at the lower end of each surface to weld the welding unit 136 along the lower wing 137. As a manual fusion by the), of course, the PE sheet 130 is of course attached to the heat-sealed adhesive sheet 160 of the tableting nail 140 is embedded in the inner surface of the reservoir tank (Fig. 2 and 3). Reference.)

도 8은 PE시트(130)를 저수조의 벽면(111)과 바닥면(112)에 걸쳐 부착하는 상태를 나타낸 것으로서, 종래에는 도 8에 도시된 바와같이 벽면(111) 및 바닥면(112)에 일정 간격으로 다수 배열 고정된 붙임용 시트(160)에, 서로 대향되는 각각의 단부측을 서로 중첩시켜 상기 벽면(111)과 바닥면(112)에 걸쳐 열융착한 후, 다시 그 중첩 부위를 융착하게 되는데, 이때, 벽면(111)과 바닥면(112)의 경계를 이루는 모서리 부분, 즉 "A" 부분은 수동융착에 의해서 이루어진다.FIG. 8 illustrates a state in which the PE sheet 130 is attached over the wall surface 111 and the bottom surface 112 of the water tank, and conventionally, the wall surface 111 and the bottom surface 112 as shown in FIG. 8. The end sheets facing each other are overlapped with each other on the sheeting sheet 160 fixed in a plurality of rows at regular intervals and thermally fused over the wall surface 111 and the bottom surface 112, and then the overlapping portions are fused. At this time, the edge portion, that is, the "A" portion forming the boundary between the wall surface 111 and the bottom surface 112 is made by manual fusion.

이를 좀더 구체적으로 설명하면, 서로 중첩되고 절곡되어지는 일측 및 타측 PE시트(130a)(130b)의 접힘부분에 수평의 절개홈(134a)을 형성하여 그 모서리 부분의 안쪽으로 상기 PE시트(130a)(130b)의 접힘부분이 밀착되게 한 후, 바닥면(112)에서부터 그 겹칩 방향을 서로 반대로 어긋물림되게 하여 수동융착한 다음, 나머지 부분을 열융착기로 자동융착하도록 되어 있는 것이다.To describe this in more detail, a horizontal cut groove 134a is formed in the folded portions of the one side and the other side PE sheet 130a and 130b which are overlapped and bent to each other, and the PE sheet 130a into the inner side of the corner portion. After the folded portion of the 130b is in close contact with each other, the overlapping direction of the overlapping chip is shifted from the bottom surface 112 to each other and manually fused, and then the remaining portion is automatically fused with the heat fusion splicer.

도 9a는 저수조(110)의 내.외측을 관통하여 설치되는 슬리브(114)의 방수 구조를 나타낸 것으로서, 상기 슬리브 방수부(180)는 상기 슬리브(114)의 외측 둘레를 실링재(181)로 감싸고, 다시 상기 실링재(181)의 외주면에 PE시트(130)를 원형의 형태로 감싼 후, 상기 PE시트(130)를 적어도 2개 이상의 SUS 밴드(182)로 고정 하여 슬리브(114)에 대한 방수가 이루어지도록 하고 있다.9A illustrates a waterproof structure of the sleeve 114 installed through the inside and the outside of the reservoir 110, wherein the sleeve waterproof portion 180 surrounds the outer circumference of the sleeve 114 with a sealing material 181. In addition, after wrapping the PE sheet 130 in a circular shape on the outer circumferential surface of the sealing material 181, the PE sheet 130 is fixed with at least two or more SUS bands 182 to be waterproof to the sleeve 114. To be done.

도 9b는 상기 슬리브 방수부의 다른 실시예를 나타낸 것으로서, 이는 콘크리트 타설전에 미리 상기 슬리브(114)의 일측 단부에 탭 가공된 고정플랜지(183)를 용접으로 고정시킨 후, 콘크리트 타설 및 양생에 의하여 저수조(110)를 형성하고, 상기 저수조(110)의 내면을 전술한 바와 같이 부직포(120)를 포함하는 PE시트(130)를 이용하여 방수 처리를 하게 되는데, 이때 슬리브(114) 상의 PE시트(130) 및 부직포(120)는 제거되어 상기 슬리브(114)가 저수조(110)의 내부와 연통될 수 있도록 구성하며, 패킹(185)과 함께 체결플랜지(184)를 상기 고정플랜지(183)에 고무패킹(186)과 함께 볼트(187)로 체결하여 슬리브(114)에 대한 방수 처리가 이루어지도록 하고 있는 것이다.Figure 9b shows another embodiment of the sleeve waterproofing, which is fixed before welding the fixed flange (183) by tapping the one end of the sleeve 114 before the concrete casting, and the water tank by concrete pouring and curing To form the 110, the inner surface of the reservoir 110 is waterproofed using a PE sheet 130 including a nonwoven fabric 120, as described above, wherein the PE sheet 130 on the sleeve 114 ) And the nonwoven fabric 120 is removed so that the sleeve 114 can communicate with the interior of the water reservoir 110, and the fastening flange 184 together with the packing 185 is rubber-packed to the fixed flange 183. 186 is fastened with a bolt 187 to be waterproofed to the sleeve 114.

그러나, 이러한 종래의 PE시트를 이용한 저수조의 방수 시공방법에 있어서, 저수조의 벽면(111)과 바닥면(112)에 걸쳐 일측 및 타측 PE시트(130)를 중첩하여 부착시킬 때, 전술한 바와 같이 서로 경계를 이루는 모서리 부분에 대하여 열융착기를 이용한 자동융착이 이루어지지 않는다. However, in the waterproof construction method of the water tank using the conventional PE sheet, when the one side and the other side PE sheet 130 is superimposed and attached over the wall surface 111 and the bottom surface 112 of the water tank, as described above. The automatic fusion using the heat welding machine is not performed on the edge portions that border each other.

즉, 통상 열융착기(170)는 도 6에 도시된 바와 같이 기체(171)의 하부측 열풍노즐(174)을 통하여 열풍을 그 중첩 부위에 분사하면서 후퇴하고 예열된 PE시트(130)의 중첩부위는 상.하측 압착로울러(172)(173)의 사이를 지나면서 압축되어 열융착이 이루어지도록 되어 있기 때문에, 상기 열융착기(170)가 도 10에 도시된 바와 같이 그 경계부분에서 저수조(110)의 벽면(111) 또는 바닥면(112)에 닿아 더이상 후진하지 못함으로써 수동융착이 불가피하다.That is, the heat fusion splicer 170 is generally retracted while spraying hot air through the hot air nozzle 174 on the lower side of the base 171 as shown in FIG. 6 and overlapping the overlapped portion of the preheated PE sheet 130. Since the compression is performed while passing between the upper and lower compression rollers 172 and 173 to achieve heat fusion, the heat fusion unit 170 as shown in Figure 10 the reservoir 110 at its boundary portion as shown in FIG. Manual fusion is inevitable because it can no longer move back to the wall 111 or bottom 112 of the.

또한, 상기 수동융착시에는 PE시트(130a)(130b)가 경계를 이루는 상기 모서리 부분에 밀착되도록 PE시트(130a)(130b)의 접히는 부분에 절개홈(134a)을 형성해야 되고, 다시 서로 중첩되는 부위의 겹침 방향을 서로 반대로 달리하여 어긋 물림되게 해야 되는 등의 작업 공수가 많아 작업의 번거로움 및 불편성을 초래할 뿐만 아니라 작업 시간이 많이 소요됨으로써 시공의 신속성 저하와 비효율성을 초래하는 문제점이 있었다.In addition, during the manual fusion, the incision grooves 134a must be formed in the folding portions of the PE sheets 130a and 130b such that the PE sheets 130a and 130b closely adhere to the corner portions forming the boundary, and overlap each other again. There is a lot of work maneuvering such that the overlapping direction of the parts to be overlapped with each other is caused, which not only induces inconvenience and inconvenience, but also requires a lot of work time, resulting in a rapid decrease in construction and inefficiency. there was.

이에 본 발명은 상기한 바와 같은 종래의 제반 문제점을 해소하기 위하여 창안된 것으로서, 그 목적은 저수조의 벽면과 바닥면에, 상기 벽면과 바닥면에 걸쳐 연장된 길이를 갖는 일측 및 타측의 PE시트 중첩부위를 열융착기로 열융착할 때, 수동융착되는 부분이 없이 모두 상기 열융착기를 이용한 자동융착이 이루어질 수 있도록 함으로써 시공의 신속성과 간편성 및 효율성을 확보할 수 있도록 하는데 있다.Accordingly, the present invention has been made to solve the above-mentioned conventional problems, its purpose is to overlap the PE sheet of one side and the other side having a length extending over the wall surface and the bottom surface, on the wall surface and the bottom surface of the water tank When the parts are thermally fused with a heat fusion machine, the automatic fusion using the heat fusion machine can be performed without any part to be manually fused, thereby ensuring the speed, simplicity and efficiency of construction.

이러한 본 발명의 목적을 달성하기 위하여 저수조의 콘크리트 벽면과 바닥면에 다수의 붙임용 시트를 고정하는 제1 공정과; 상기 저수조의 벽면에 고정된 붙임용 시트에 벽면과 바닥면에 걸쳐 연장된 길이를 갖는 일측 및 타측 PE시트를 서로 마주하는 단부측이 중첩되도록 열융착시키는 제2 공정과; 상기 PE시트의 중첩 부위를 벽면을 타고 열융착기로 자동융착을 하면서 하부측 모서리 부분에 대한 융착시에는 상기 모서리 부분의 안쪽으로 이 중첩된 PE시트를 밀어 가능한 밀착되게 하는 제3 공정과; 상기 제3 공정과 같이 모서리 부분의 안쪽으로 PE시트가 밀착된 상태에서 바닥면에 PE시트를 상기 바닥면에 다수 고정된 붙임용 시트에 열융착시킨 후, 나머지 PE시트의 중첩부위에 대한 자동융착을 수행하는 제4 공정으로 이루어진 것을 특징으로 한 PE시트를 이용한 저수조의 방수 공법이 제공된다.In order to achieve the object of the present invention and the first step of fixing a plurality of sheets for attaching the concrete wall surface and the bottom surface of the reservoir; A second step of thermally fusion bonding the end sheets facing one another and the other side PE sheet having a length extending over the wall surface and the bottom surface to the pasting sheet fixed to the wall surface of the water tank so as to overlap each other; A third step of automatically bonding the overlapped portion of the PE sheet to a heat fusion splicer on a wall while pushing the overlapped PE sheet to the inner side of the corner portion as closely as possible when fused to the lower edge portion; In the state where the PE sheet is in close contact with the inside of the corner portion as in the third process, the PE sheet is thermally fused to the gluing sheet fixed to the bottom surface, and the fusion sheet is automatically bonded to the overlapping portions of the remaining PE sheets. There is provided a waterproofing method of a water tank using a PE sheet, characterized in that the fourth step of performing.

또한, 상기 제1 공정은 붙임용 시트를 앵커볼트에 의해서 저수조의 콘크리트 벽면에 고정되게 하는 것을 더 포함하는 것을 특징으로 한다.In addition, the first step is characterized in that it further comprises the fixing sheet for fixing to the concrete wall surface of the reservoir by the anchor bolt.

또한, 상기 제3 공정은 모서리 부분에 지지대를 설치하는 것을 더 포함하는 것을 특징으로 한다.In addition, the third step is characterized in that it further comprises installing a support on the corner portion.

이하, 첨부된 도면을 참조로 하여 본 발명의 PE시트를 이용한 저수조의 방수공법에 대하여 첨부된 도면을 참조로 하여 상세히 설명하기로 한다.Hereinafter, with reference to the accompanying drawings for the waterproof method of the water tank using the PE sheet of the present invention with reference to the accompanying drawings will be described in detail.

본 발명의 제1 공정은 저수조의 콘크리트 벽면과 바닥면에 다수의 붙임용 시트를 고정하는 것으로서, 이는 도 3에 도시된 바와 같이 바탕면 처리된 저수조(110)의 내면에 일정면적을 가지는 붙임용 시트(160)를 와셔(140a)가 끼워진 타정못(140)과 결합시켜 저수조(110)의 내면에 일정 간격으로 배열되게 타격 고정한 후, 상기 붙임용 시트(160)가 대략 중앙 부위에 위치하도록 붙임용 시트(160)에 PE시트(130)를 열융착시켜 부착되게 한다.The first process of the present invention is to fix a plurality of sheets for attaching the concrete wall and the bottom surface of the reservoir, which is for attaching having a certain area on the inner surface of the surface-treated reservoir 110 as shown in FIG. The sheet 160 is coupled to the tableting nail 140 in which the washer 140a is inserted, and then fixed to be arranged at regular intervals on the inner surface of the water storage tank 110, and then the attaching sheet 160 is attached to be positioned approximately at the center portion. The PE sheet 130 is thermally fused to the sheet 160 for adhesion.

또한, 상기 붙임용 시트(160)에 부착된 PE시트(130)의 각 단부는 서로 중첩되어 다시 열융착시켜 저수조(110)의 내면에 대한 PE시트(130)의 부착이 이루어질 수 있도록 한다.In addition, each end of the PE sheet 130 attached to the sheet for attaching 160 is overlapped with each other and heat-sealed again so that the PE sheet 130 to the inner surface of the reservoir 110 can be attached.

그리고, 상기 붙임용 시트(160)를 저수조(110)의 내면에 고정하는 수단으로 서, 앵커볼트가 사용될 수 있으며, 상기 앵커볼트로 붙임용 시트를 저수조(110)의 내면에 고정할 때에는, 먼저 콘크리트 벽면에 드릴로 구멍을 뚫어 그 구멍에 앵커를 박아 볼트를 체결하는 공정이 더 포함되고, 물과의 접촉을 감안할 때 상기 앵커볼트는 플라스틱 앵커를 사용하거나 부식이 않되는 스테인레스 재질로 이루어진다.And, as a means for fixing the sheet 160 for the storage tank 110, an anchor bolt may be used, when fixing the sheet for fixing with the anchor bolt on the inner surface of the reservoir 110, first Drilling a hole in the concrete wall surface is further included a process of fastening the anchor bolt in the hole, and considering the contact with water, the anchor bolt is made of a stainless steel that uses a plastic anchor or does not corrode.

본 발명의 제2 공정은 도 11에 도시된 바와 같이 저수조(110)의 벽면(111)에 고정된 붙임용 시트(160)에 벽면(111)과 바닥면(112)에 걸쳐 연장된 길이를 갖는 일측 및 타측의 PE시트(130a)(130b)를 서로 마주하는 단부측이 중첩되도록 열융착시키는 것으로서, 이때 열융착기(170)가 사용된다.The second process of the present invention has a length extending over the wall surface 111 and the bottom surface 112 to the bonding sheet 160 fixed to the wall surface 111 of the reservoir 110 as shown in FIG. One side and the other side of the PE sheet (130a, 130b) to heat-sealed so that the end side facing each other overlap, at this time the heat fusion machine 170 is used.

통상적으로 열융착기(170)는 도 6에 도시된 바와 같이 상기 열융착기(170)는 기체(171)의 하부측에 구비되는 상.하 압착로울러(172)(173)의 후방측에 열풍을 내뿜는 열풍노즐(174)이 구비되어 상기 기체(171)가 후퇴하면서 먼저 열풍으로 PE시트(130)의 중첩부위를 가열한 후, 이 가열된 PE시트(130)의 중첩 부위가 상기 상.하 압착로울러(172)(173)의 사이를 지나면서 상기 압착로울러에 의하여 압착됨으로써 열융착이 이루어지도록 하고 있다.Typically, the heat fusion machine 170, as shown in Figure 6, the heat fusion machine 170 is a hot air to the rear side of the upper and lower compression rollers 172, 173 provided on the lower side of the base 171. The hot air nozzle 174 is provided so that the base 171 retreats and first heats the overlapped portion of the PE sheet 130 with hot air, and then the overlapped portion of the heated PE sheet 130 is the upper and lower compression rollers. While passing between the (172) and (173), the pressing roller is pressed by the press roller so that thermal fusion is achieved.

본 발명의 제3 공정은 상기 PE시트(130a)(130b)의 중첩 부위를 벽면(111)을 타고 열융착기로 자동융착을 하면서 하부측 모서리 부분에 대한 융착시에는 도 12a 및 도 12b에 도시된 바와 같이 열융착기(170)로 마주하는 단부측이 서로 중첩된 PE시트(130a)(130b)를 상기 모서리 부분의 안쪽으로 밀어 그 안쪽에 가능한 밀착시키게 된다.The third step of the present invention is shown in Figure 12a and 12b during the fusion of the lower edge portion while the automatic fusion of the overlapping portion of the PE sheet (130a, 130b) by the heat fusion machine on the wall surface 111 As described above, the end faces facing the heat sealer 170 push the PE sheets 130a and 130b overlapped with each other to be in close contact with the inside of the corner portion.

이때 도 13에 도시된 바와 같이 모서리 부분에 지지대(190)를 설치할 수 있 고, 바닥면(112) 상에 놓인 PE시트(130a)(130b)는 상기 바닥면(112)에 다수 고정된 붙임용 시트(160)에 융착되지 않은 상태이므로 열융착기(170)로 PE시트(130a)(130b)를 모서리 부분의 안쪽으로 밀어 밀착시키는 것이 가능하다.In this case, as shown in FIG. 13, the support 190 may be installed at the corner portion, and the PE sheets 130a and 130b placed on the bottom surface 112 are attached to the bottom surface 112 by a plurality of fixings. Since the sheet 160 is not fused to the sheet 160, the PE sheets 130a and 130b may be pushed into the corner portion by the heat fusion unit 170 to closely contact each other.

본 발명의 제4 공정은 상기 제3 공정과 같이 벽면(111)과 바닥면(112) 사이의 모서리 부분의 안쪽으로 PE시트(130a)(130b)를 가능한 밀착되게 한 상태에서, 바닥면(112)에 놓인 PE시트(130a)(130b)를 상기 바닥면(112)에 다수 고정된 붙임용 시트(160)에 융착시킨 후, 열융착기(170)를 이용하여 나머지 PE시트(130a)(130b)의 중첩된 부위에 대한 자동융착을 수행하게 됨으로써 PE시트를 이용한 벽면과 바닥면 사이의 방수 처리를 완료하게 되는 것이다.In the fourth step of the present invention, the PE sheet 130a, 130b is brought into close contact with the inner side of the edge portion between the wall surface 111 and the bottom surface 112, as in the third process, and the bottom surface 112 is as close as possible. ) PE sheet (130a) (130b) placed on the fusion sheet 160 fixed to the plurality of fixing the bottom surface 112, and then the remaining PE sheet (130a) (130b) using a heat fusion machine (170) By performing the automatic fusion on the overlapped portion of the will be completed the waterproofing between the wall surface and the bottom surface using the PE sheet.

상술한 바와 같이 본 발명은 저수조의 벽면과 바닥면에, 상기 벽면과 바닥면에 걸쳐 연장된 길이를 갖는 일측 및 타측의 PE시트 중첩부위를 열융착기로 열융착할 때, 수동융착되는 부분이 없이 모두 상기 열융착기를 이용한 자동융착이 이루어질 수 있도록 함으로써 시공의 신속성과 간편성 및 효율성을 확보할 수 있는 효과를 갖게 된다.As described above, the present invention, when heat-sealing the PE sheet overlapping parts of one side and the other side having a length extending over the wall surface and the bottom surface with a heat fusion splicer on the wall surface and the bottom surface of the water tank, there is no manual fusion Both have the effect of ensuring the fastness and simplicity and efficiency of construction by enabling automatic fusion using the heat welding machine.

Claims (3)

저수조(110)의 콘크리트 벽면(111)과 바닥면(112)에 다수의 붙임용 시트(160)를 고정하는 제1 공정과;A first step of fixing the plurality of pasting sheets 160 to the concrete wall surface 111 and the bottom surface 112 of the reservoir 110; 상기 저수조(111)의 벽면(111)에 고정된 붙임용 시트(160)에 벽면(111)과 바닥면(112)에 걸쳐 연장된 길이를 갖는 일측 및 타측 PE시트(130a)(130b)를 서로 마주하는 단부측이 중첩되도록 열융착시키는 제2 공정과;One side and the other side PE sheet (130a, 130b) having a length extending over the wall surface 111 and the bottom surface 112 to the attachment sheet 160 fixed to the wall surface 111 of the reservoir 111 to each other. A second step of thermally fusion bonding such that end portions facing each other overlap; 상기 PE시트(130a)(130b)의 중첩 부위를 벽면을 타고 열융착기(170)로 자동융착을 하면서 하부측 모서리 부분에 대한 융착시에는 상기 모서리 부분의 안쪽으로 이 중첩된 PE시트(130a)(130b)를 밀어 가능한 밀착되게 하는 제3 공정과;The PE sheet 130a and 130b are automatically welded to the heat welding machine 170 on the overlapped portion of the wall while being fused to the lower edge portion, and the PE sheet 130a overlapped with the inside of the edge portion ( A third step of pushing 130b) as closely as possible; 상기 제3 공정과 같이 모서리 부분의 안쪽으로 PE시트(130a)(130b)가 밀착된 상태에서 바닥면(112)에 PE시트(130a)(130b)를 상기 바닥면(112)에 다수 고정된 붙임용 시트(160)에 열융착시킨 후, 나머지 PE시트(130a)(130b)의 중첩부위에 대한 자동융착을 수행하는 제4 공정으로 이루어진 것을 특징으로 한 PE시트를 이용한 저수조의 방수 공법.In the state in which the PE sheets 130a and 130b are in close contact with the inside of the corner portion as in the third process, a plurality of PE sheets 130a and 130b are attached to the bottom surface 112 and fixed to the bottom surface 112. After the heat-sealed to the sheet for 160, a waterproofing method of the water tank using a PE sheet, characterized in that the fourth step of performing the automatic fusion to the overlapping portion of the remaining PE sheet (130a, 130b). 제1항에 있어서,The method of claim 1, 상기 제1 공정은 붙임용 시트(160)를 앵커볼트에 의해서 저수조의 콘크리트 벽면에 고정되게 하는 것을 더 포함하는 것을 특징으로 한 PE시트를 이용한 저수조의 방수 공법.The first process is a waterproofing method of the water tank using the PE sheet, characterized in that further comprising fixing the sheet 160 for fixing to the concrete wall surface of the water tank by the anchor bolt. 삭제delete
KR1020050018772A 2005-03-07 2005-03-07 The waterproof method of water tank use PE seet KR100762858B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050018772A KR100762858B1 (en) 2005-03-07 2005-03-07 The waterproof method of water tank use PE seet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050018772A KR100762858B1 (en) 2005-03-07 2005-03-07 The waterproof method of water tank use PE seet

Publications (2)

Publication Number Publication Date
KR20060097885A KR20060097885A (en) 2006-09-18
KR100762858B1 true KR100762858B1 (en) 2007-10-02

Family

ID=37629429

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050018772A KR100762858B1 (en) 2005-03-07 2005-03-07 The waterproof method of water tank use PE seet

Country Status (1)

Country Link
KR (1) KR100762858B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636743A (en) * 2020-06-22 2020-09-08 扬州市通达建设发展有限公司 Sewage treatment plant grit chamber construction equipment

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108331415B (en) * 2017-01-20 2020-08-14 文昌株式会社 Water tank having waterproof structure using composite board
KR101980078B1 (en) * 2018-08-02 2019-08-29 주식회사 피엘테크코리아 Construction method and structure for PE lining using embedded type polyethylene sheet

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06341202A (en) * 1993-05-31 1994-12-13 Hakusui Kosan Kk Corner cant member at waterproof layer starting-up part
KR100227000B1 (en) * 1997-08-12 1999-10-15 Byun Moo Won Waterproof method of reinforced concrete of water tank
KR20000072869A (en) * 1999-05-01 2000-12-05 김경옥 Two-Package Type Inorganic Membranous Waterproof Stuff Having Excellent Elasticity, Hybrid Membranous Waterproof Sheet and Construction Method therefor
KR20020000814A (en) * 1999-05-29 2002-01-05 빌프리더 하이더 Substituted Phenylcyclohexane Carboxylic Acid Amides and Their Use as Adenosine Uptake Inhibitors

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06341202A (en) * 1993-05-31 1994-12-13 Hakusui Kosan Kk Corner cant member at waterproof layer starting-up part
KR100227000B1 (en) * 1997-08-12 1999-10-15 Byun Moo Won Waterproof method of reinforced concrete of water tank
KR20000072869A (en) * 1999-05-01 2000-12-05 김경옥 Two-Package Type Inorganic Membranous Waterproof Stuff Having Excellent Elasticity, Hybrid Membranous Waterproof Sheet and Construction Method therefor
KR20020000814A (en) * 1999-05-29 2002-01-05 빌프리더 하이더 Substituted Phenylcyclohexane Carboxylic Acid Amides and Their Use as Adenosine Uptake Inhibitors

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111636743A (en) * 2020-06-22 2020-09-08 扬州市通达建设发展有限公司 Sewage treatment plant grit chamber construction equipment

Also Published As

Publication number Publication date
KR20060097885A (en) 2006-09-18

Similar Documents

Publication Publication Date Title
US6169042B1 (en) Plastering fillet with attached reinforcing material
US8366849B2 (en) Method for lining a container and lining of a container
JP6403502B2 (en) Tunnel water stop structure and construction method
KR100762858B1 (en) The waterproof method of water tank use PE seet
KR100625861B1 (en) The waterproof method of water tank use PE seet
KR101554025B1 (en) PE lining of concrete water tank and construction method thereof
KR101447572B1 (en) Concrete waterproof sheet attaching method and concrete waterproof structure using the same
KR100762857B1 (en) The waterproof method of water tank use PE seet
KR101035909B1 (en) Fixing and finishing method for single-ply waterproofing sheet to parepet wall
KR200386919Y1 (en) The instollation fixing device of water tank with waterproof sturucture use PE seet
JP6598337B2 (en) Roof exterior structure and roof exterior construction method
KR100784508B1 (en) Waterproof structure and constructing method of the same
KR200386245Y1 (en) The sleeve waterproof structure of water tank use PE seet
JPH0336640Y2 (en)
JP4612962B2 (en) Construction method of basic insulation structure
JPS6282158A (en) Waterproof structure
JPH0714522Y2 (en) Sheet element
KR101053082B1 (en) Waterproof sheet attaching method
JPH0242800Y2 (en)
JPS632502Y2 (en)
JPS636702B2 (en)
KR100206517B1 (en) Lining structure of interior of water tank
JPS6354878B2 (en)
KR101243764B1 (en) Method for the prevention of the water spread of waterproof-sheet using multi-purpose metal bar
KR100733773B1 (en) Method for forming water-tight corners of bottom cloth for tent and the corners of bottom cloth

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
G170 Publication of correction
LAPS Lapse due to unpaid annual fee