KR100695223B1 - Construction method for stone block with electric power line - Google Patents

Construction method for stone block with electric power line Download PDF

Info

Publication number
KR100695223B1
KR100695223B1 KR1020050008400A KR20050008400A KR100695223B1 KR 100695223 B1 KR100695223 B1 KR 100695223B1 KR 1020050008400 A KR1020050008400 A KR 1020050008400A KR 20050008400 A KR20050008400 A KR 20050008400A KR 100695223 B1 KR100695223 B1 KR 100695223B1
Authority
KR
South Korea
Prior art keywords
power supply
slab
construction method
requires
mortar
Prior art date
Application number
KR1020050008400A
Other languages
Korean (ko)
Other versions
KR20060087641A (en
Inventor
김석배
김선미
Original Assignee
김석배
김선미
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김석배, 김선미 filed Critical 김석배
Priority to KR1020050008400A priority Critical patent/KR100695223B1/en
Publication of KR20060087641A publication Critical patent/KR20060087641A/en
Application granted granted Critical
Publication of KR100695223B1 publication Critical patent/KR100695223B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/024Sectional false floors, e.g. computer floors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/08Flooring or floor layers composed of a number of similar elements only of stone or stone-like material, e.g. ceramics, concrete; of glass or with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F2201/00Joining sheets or plates or panels
    • E04F2201/09Puzzle-type connections for interlocking male and female panel edge-parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Floor Finish (AREA)

Abstract

본 발명은 전원공급이 필요한 석판재 시공법에 관한 것으로서, 전원공급이 필요한 석판재(11)를 바닥에 시공할 경우 콘크리트(30) 위에 모르타르(20)를 붓기전 상기 석판재(11) 경계부분에 격리이음재(50)를 추가 배치하여 석판재를 조적함으로써 시공된 바닥재의 수평을 용이하게 맞출 수 있으며, 전원공급이 필요한 석판재(11)의 전원공급선(12)과 연결부(13)를 모르타르(20)와 분리시키는 기능을 가진다. The present invention relates to a method for constructing a slate material that requires power supply. When constructing a slate material 11 that requires power supply on a floor, the present invention relates to a boundary portion of the slate material 11 before pouring mortar 20 onto the concrete 30. By additionally arranging the slab material by additionally arranging the insulating joint material 50, the flooring material can be easily leveled, and the power supply line 12 and the connection part 13 of the stone material 11 requiring power supply are mortar 20. ) And the function to separate.

격리이음재(50)를 사용함으로써 전원공급이 필요한 석판재(11)를 유지보수할 경우 상기 시공된 전원공급이 필요한 석판재를 제거하는 과정과 재설치하는 과정이 개선되는 이점이 있다. When maintaining the slab 11 that requires power supply by using the isolation joint material 50, there is an advantage that the process of removing and reinstalling the slab that requires the power supply is improved.

석판재, 시공법, 전원공급, 연결부, 바닥재, 격리이음재,Slab, construction method, power supply, connection, flooring, isolation,

Description

전원공급이 필요한 석판재 시공법{CONSTRUCTION METHOD FOR STONE BLOCK WITH ELECTRIC POWER LINE}Construction method of stone material requiring power supply {CONSTRUCTION METHOD FOR STONE BLOCK WITH ELECTRIC POWER LINE}

도 1은 종래 석판재 시공방법을 도시한 단면도.1 is a cross-sectional view showing a conventional slab construction method.

도 2는 본 발명에 따른 전원공급이 필요한 석판재 시공법을 도시한 사시도.Figure 2 is a perspective view showing a stone plate construction method that requires a power supply according to the present invention.

도 3은 본 발명에 따른 전원공급이 필요한 석판재 시공법을 도시한 단면도.Figure 3 is a cross-sectional view showing a method for constructing a slab material that requires power supply according to the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

10 : 석판재 11 : 전원공급이 필요한 석판재10: Slab material 11: Slab material requiring power supply

12 : 전원공급선 13 : 연결부12: power supply line 13: connection

20 : 모르타르 30 : 콘크리트 20: mortar 30: concrete

40 : 자갈 50 : 격리이음재40: Gravel 50: Insulation Joint

본 발명은 전원 공급이 필요한 석판재 시공법에 관한 것으로서, 전원 공급이 필요한 석판재(11)를 바닥에 시공할 경우 모르타르(20)를 타설하기전 상기 전원공급이 필요한 석판재(11)간 경계부분 하단에 격리이음재(50)를 추가로 배치하여 전 원공급이 필요한 석판재(11) 조적시 바닥면의 수평을 쉽게 맞추는 기능을 제공함과 동시에, 전원 공급이 필요한 석판재(11)를 연결하는 부분을 모르타르(20)로부터 격리시키는 기능을 함으로써 시공의 신속함과 유지보수의 용이함을 제공한다.The present invention relates to a slab construction method that requires power supply, when installing the slab material 11 that requires power supply on the floor boundary portion between the slab material 11 that requires the power supply before pouring mortar (20) Part of connecting the slab 11 that requires power supply while providing the function of easily leveling the bottom surface when laying the slab 11 that requires power supply by additionally arranging the isolation joint material 50 at the bottom. By providing a function of isolating the mortar (20) provides the speed and ease of maintenance.

종래의 석판재(10) 시공법은 도 1에서와 같이 최하위층의 굵은 자갈층(40) 위에 콘크리트(30)를 타설하고 양생하여 굳은 다음, 시멘트와 모래를 배합한 모르타르(20)를 깔고, 석판재(10)를 줄눈을 이용하여 순차적으로 석판재(10)를 조적하는 방법이 있다. Conventional slab 10 construction method is to cast and cured concrete 30 on the coarse gravel layer 40 of the lowest layer as shown in Fig. 1, and then lay mortar 20 incorporating cement and sand, slab ( 10) using the joint there is a method of sequentially stacking the slab (10).

그러나, 전원공급이 필요한 석판재(11)를 기존 석판재(10) 시공법으로 시공할 경우 석판재 밑층인 모르타르층에 전원공급이 필요한 석판재(11)의 전원공급선(12)와 그 연결부(13)들이 직접 매몰되어 고정된다. However, when the slab material 11 that requires power supply is constructed by the existing slab material 10 construction method, the power supply line 12 of the slab material 11 that requires power supply to the mortar layer, which is the slab material layer, and its connection part 13 ) Are directly buried and fixed.

시공된 석판재가 일부 파손된 경우 유지보수가 이루어져야 하며, 기존 석판재 시공법으로 석판재를 시공한 경우 전원공급선(12)과 연결부(13)가 모르타르에 매몰이 되어 있기 때문에 파손된 석판재외 인접한 석판재들까지 철거해야 되는 번거러움이 발생하게 된다. If the installed slabs are partially damaged, maintenance should be performed. If slabs are installed by the existing slab construction method, the adjacent slabs besides the damaged slabs are damaged because the power supply line 12 and the connection part 13 are buried in mortar. The hassle to remove even to the field will occur.

본 발명은 상기와 같은 요구를 충족시키기 위해 창작된 것으로서, 본 발명의 목적은 전원공급이 필요한 석판재(11)를 시공할 때 모르타르(20)와 상기 석판재(11)사이에 전원공급선(12)과 그 연결부들(13)을 격리시키는 기능을 하는 격리이음재(50)를 사용함으로써 조적시 바닥면의 수평을 쉽게 맞추는 기능을 제공함과 동시에, 전원 공급이 필요한 석판재(11)를 연결하는 부분을 모르타르(20)로부터 격리시 키는 기능을 함으로써 시공의 신속함과 유지보수의 용이함을 제공한다.The present invention was created to meet the above demands, and an object of the present invention is to provide a power supply line 12 between the mortar 20 and the slab 11 when constructing a slab 11 that requires a power supply. ) And the connecting portion 13 to provide a function of easily leveling the floor surface during the erection by using an insulating joint material (50) that functions to isolate, the part connecting the slab material 11 that requires power supply By providing a function of isolating the mortar (20) provides the speed of construction and ease of maintenance.

상기와 같은 목적을 실현하기 위한 본 발명은 전원공급이 필요한 석판재 조적 시공시, 기존 석판재의 내부에 발광다이오드가 결합되고, 상기 광원에 전원을 공급하기 위한 전선과 연속적인 이음을 위한 전기적 기구, 즉, 암수 한 쌍으로 이루어지는 방수형 소켓 형태로 구성되는 것을 특징으로 하는 단제품을 전원공급이 필요한 석판재(11)라 하며, 도2에서와 같이 상기 여러 개의 석판재를 바닥에 고정하기 위해 모르타르(20) 작업이 이루어지는 과정에서 상기 전원공급이 필요한 석판재(11)와 인접한 전원공급이 필요한 석판재(11) 사이의 위치에 격리이음재(50)가 배치된 후 모르타르(20)를 타설하는 과정과, 이때 석판재 사이에 배치되는 격리이음재(50)는 유지보수시 배선연결부가 모르타르(20)에 고정이 되면 쉽게 분리하기 어려운 것을 해소시켜 주며, 또한 석판재 를 모르타르 윗면에 놓을 때 일정한 높이를 유지시켜 주는 효과도 있다. 상기 전원공급이 필요한 석판재(11)의 연결부(13)는 암수 한 쌍의 소켓형태로 이루어져 있으며, 이를 순차적으로 연결 접속함으로써 배선 결선작업이 전기적으로 결합하는 과정과, 격리이음재(50)가 플라스틱과 같이 경도가 강한 재질로 이루어지는 경우, 내부가 비어있는 정육면체 형태이며, 상단부 한면은 분리가 되고, 양측면에 배선홈이 한개씩 있는 것을 특징으로 한다. 격리이음재(50) 내부에 실리콘과 같은 방수재를 충진한 다음 석판재의 암수 소켓이 결합된 연결부(13)를 삽입하여 상단부 한면을 덮은 것으로 처리되는 상기 전원공급이 필요한 석판재의 암수 한쌍의 연결부(13)들을 방수처리하는 과정과, 상기 결선된 암수 한쌍의 연결부(13)들을 전원공급선(12)과 같이 격리이음재 내에 배치하는 과정으로 이루어지는 것을 특징으로 한다.The present invention for realizing the above object is the construction of a slate material requiring power supply, the light emitting diode is coupled to the inside of the existing slate material, the electrical mechanism for continuous connection with wires for supplying power to the light source, In other words, the single product, which is composed of a waterproof socket formed of a pair of male and female, is called a slab 11 that requires power supply, and as shown in FIG. (20) Process of pouring mortar (20) after the isolation joint member (50) is disposed at a position between the slab member (11) requiring power supply and the slab member (11) requiring power supply in the course of the work being performed. And, at this time, the insulating joint material 50 disposed between the slab solves the difficult to separate when the wiring connection is fixed to the mortar 20 during maintenance, and It also has the effect of maintaining a constant height when placing the slab on the top of the mortar. The connecting portion 13 of the stone plate material 11, which requires the power supply, is made of a male and female pair of socket types, and a process of electrically connecting the wiring connection work by sequentially connecting and connecting them, and the insulating joint material 50 is made of plastic. If the material is made of a strong hardness as described above, the interior is hollow cube shape, one side of the upper end is separated, characterized in that the wiring grooves on each side one by one. Filling the waterproofing material, such as silicon in the insulating joint material 50, and then inserting the connection portion 13 coupled to the male and female sockets of the slab to cover the upper surface of one side of the male and female pairs of male and female connections that require the power supply 13 And a process of waterproofing them and arranging the connected male and female pairs 13 in the isolation joint like the power supply line 12.

이하, 본 발명의 바람직한 실시예를 첨부한 도면을 참조하여 설명한다. 또한 본 실시예는 본 발명의 권리범위를 한정하는 것은 아니고, 단지 예시로 제시된 것이다.Hereinafter, with reference to the accompanying drawings, preferred embodiments of the present invention will be described. In addition, this embodiment is not intended to limit the scope of the present invention, but is presented by way of example only.

도 2는 본 발명에 의한 전원공급이 필요한 석판재 시공법을 도시한 사시도이다.Figure 2 is a perspective view showing a slab construction method that requires power supply according to the present invention.

여기에 도시된 바와 같이, 전원공급이 필요한 석판재(11)를 시공하기 위해서는 석판재가 모르타르 위에 놓이기 전, 상기 석판재의 구성품인 전원공급선(12)과 연결부(13)를 서로 결속하는 과정, 결속된 연결부 주위를 방수처리하는 과정, 상기 인접한 석판재의 각 전원공급선(12)과 각 연결부(13)를 격리이음재(50) 내부에 배치하는 과정이 먼저 이루어지고 석판재가 모르타르(20)에 놓이게 된다.As shown here, in order to construct the slab 11 that requires power supply, a process of binding the power supply line 12 and the connecting portion 13, which are components of the slab, to each other before the slab is placed on the mortar, The process of waterproofing around the connecting portion, the process of placing each power supply line 12 and each connecting portion 13 of the adjacent slab inside the isolation joint 50 is made first and the slab is placed on the mortar (20).

여기서, 격리이음재(50)의 재질로는 스티로폼과 같이 외압에 의해 쉽게 변형 이 이루어지는 특성을 가지는 것과 플라스틱, 철, 나무처럼 상자모양으로 성형되는 형태를 가지는 것을 특징으로 한다. Here, the material of the insulating joint material 50 is characterized in that it has a characteristic that is easily deformed by external pressure, such as styrofoam, and has a shape that is molded in a box like plastic, iron, wood.

특히, 상자모양인 경우, 가운데 부분이 전원공급이 필요한 석판재의 전원공급선과 연결부를 포함할 수 있는 공간을 가지고 있어야 한다.In particular, in the case of a box shape, the center part should have a space to include the power supply line and the connection part of the slab which requires power supply.

도 3은 본 발명에 의한 전원공급이 필요한 석판재 시공법을 도시한 단면도이다.3 is a cross-sectional view showing a method for constructing a slab material that requires power supply according to the present invention.

여기서 도시된 바와 같이 전원공급이 필요한 석판재(11)를 조적 시공하는 과정에 있어서 최하층은 굵은 자갈층(40)으로 이루어지며, 그 위에 콘크리트(30)를 일정 두께로 포장을 하여 굳을때까지 양생시킨다. 이 두 과정은 기존 석판재 시공법과 동일하다.As shown here, in the process of masonry (11) that requires power supply, the lowermost layer is made of a coarse gravel layer 40, and the concrete 30 is cured to a certain thickness thereon until cured. . Both processes are the same as the existing slab construction method.

상기 과정이 끝난 후, 격리이음재(50)를 콘크리트 바닥에 고정 배치한 후 석판재를 고정시키기 목적으로 시멘트와 모래를 일정비율로 섞은 모르타르(20)를 붓게 된다. After the end of the process, the insulating joint member 50 is fixedly placed on the concrete floor and then poured mortar 20 mixed with cement and sand at a predetermined ratio for the purpose of fixing the slab.

여기서 격리이음재(50) 내부는 각 전원공급선(12)과 각 연결부(13)를 결합된 것을 포함할 수 있는 공간을 가지는 것을 특징으로 하고 있으며, 상기 빈공간에는 방수재로 충진되는 것을 특징으로 하고 있다.Here, the interior of the isolation joint material 50 is characterized in that it has a space that can include a combination of each power supply line 12 and each connecting portion 13, characterized in that the empty space is filled with a waterproof material. .

상기한 바와 같이 본 발명은 전원 공급이 필요한 석판재(11)를 바닥에 시공할 경우 모르타르(20)를 타설하기전 상기 전원공급이 필요한 석판재(11)간 경계부분 하단에 격리이음재(50)를 추가로 배치하여 전원공급이 필요한 석판재(11) 조적 시 바닥면의 수평을 쉽게 맞추는 기능을 제공함과 동시에, 전원 공급이 필요한 석판재(11)를 연결하는 부분을 모르타르(20)로부터 격리시키는 기능을 함으로써 시공의 신속함과 유지보수의 용이함을 제공하는 이점이 있다.As described above, in the present invention, when installing the slab 11 that requires power supply on the floor, the insulating joint material 50 is disposed at the lower boundary between the slabs 11 that need the power supply before placing the mortar 20. By additionally providing the ability to easily level the floor surface when laying the slate (11) requiring power supply, and at the same time to isolate the part connecting the slate (11) requiring power supply from the mortar (20) The function has the advantage of providing fast construction and ease of maintenance.

Claims (3)

전원공급이 필요한 석판재(11) 조적 시공시,When masonry construction (11) requiring power supply, 상기 전원공급이 필요한 석판재(11)와 인접한 전원공급이 필요한 석판재(11) 사이의 위치에 격리이음재(50)가 배치한 후 모르타르(20)를 붓는 과정과,Pouring the mortar (20) after the isolation joint material (50) is disposed at a position between the stone material (11) requiring power supply and the stone material (11) requiring power supply; 상기 전원공급이 필요한 석판재(11)의 암수 한쌍의 연결부(13)들을 전기적으로 결합을 위해 결속하는 과정과,Binding the pairs of male and female connections 13 of the stone material 11 requiring power supply for electrical coupling; 상기 전원공급이 필요한 석판재(11)의 암수 한쌍의 연결부(13)들을 방수처리하는 과정과,Waterproofing the pair of male and female connection parts 13 of the stone plate material 11 that requires the power supply, 상기 결선된 암수 한쌍의 연결부(13)들을 전원공급선(12)과 같이 격리이음재(50) 내에 배치하는 과정으로 In the process of arranging the connected pair of male and female connections 13 in the isolation joint material 50, such as the power supply line 12 이루어지는 것을 특징으로 하는 전원공급이 필요한 석판재 시공법.Slab construction method requiring power supply, characterized in that made. 제 1항에 있어서, 상기 격리이음재(50)는The method of claim 1, wherein the isolation joint material 50 스티로폼과 같이 경도가 낮은 소재로 구성되는 경우 결합된 전원연결선과 연결부들이 일체가 석판재의 하중에 의해 격리이음재로 눌려 삽입되는 형태로 In the case of a material with low hardness, such as styrofoam, the combined power supply line and connecting parts are pressed into the isolation joint by the load of the slab and inserted into the isolation joint. 이루어지는 것을 특징으로 하는 전원공급이 필요한 석판재 시공법 Slab construction method requiring power supply, characterized in that made 제 1항에 있어서, 상기 격리이음재(50)는The method of claim 1, wherein the isolation joint material 50 플라스틱과 같이 경도가 높은 소재로 구성되는 경우 격리이음재 상단 내부에 빈공간을 만들어 결합된 전원연결선과 연결부들이 일체를 배치한 후 방수재를 보충하여 마무리 작업을 하는 것으로 If the material is made of hard material, such as plastic, it creates an empty space inside the upper part of the insulating joint material, and then combines the power cable and the connected parts together to finish the work by supplementing the waterproof material. 이루어지는 것을 특징으로 하는 전원공급이 필요한 석판재 시공법.Slab construction method requiring power supply, characterized in that made.
KR1020050008400A 2005-01-31 2005-01-31 Construction method for stone block with electric power line KR100695223B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050008400A KR100695223B1 (en) 2005-01-31 2005-01-31 Construction method for stone block with electric power line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050008400A KR100695223B1 (en) 2005-01-31 2005-01-31 Construction method for stone block with electric power line

Publications (2)

Publication Number Publication Date
KR20060087641A KR20060087641A (en) 2006-08-03
KR100695223B1 true KR100695223B1 (en) 2007-03-14

Family

ID=37176346

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050008400A KR100695223B1 (en) 2005-01-31 2005-01-31 Construction method for stone block with electric power line

Country Status (1)

Country Link
KR (1) KR100695223B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100195968B1 (en) 1996-05-27 1999-06-15 윤수규 Casting method of artificial stone in buildings
KR200394338Y1 (en) 2005-06-09 2005-08-31 김기영 Apparatus for fixing stone panel of building

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100195968B1 (en) 1996-05-27 1999-06-15 윤수규 Casting method of artificial stone in buildings
KR200394338Y1 (en) 2005-06-09 2005-08-31 김기영 Apparatus for fixing stone panel of building

Also Published As

Publication number Publication date
KR20060087641A (en) 2006-08-03

Similar Documents

Publication Publication Date Title
US10267011B2 (en) Pre-cast decorative retaining wall system
KR100695223B1 (en) Construction method for stone block with electric power line
KR20190069910A (en) Installation structure and method of precast concrete culvert
WO2006123862A1 (en) Floor panel
KR20090083661A (en) A block for constructing breast wall
KR0178708B1 (en) Manufacturing method of concrete block by using native rock
KR101550183B1 (en) Structural Block and Wall Construction method using the same
KR101054450B1 (en) Precasting structure
US20170029255A1 (en) Precast concrete pit
EP1242693A1 (en) Foundation
KR101166668B1 (en) Construction structure and method of PC stairs by non support system
KR20160064745A (en) Prefabricated multifunction safety step constructed at slope
KR200461055Y1 (en) Retaining wall with formative stone and formative stone
KR200461591Y1 (en) Retaining wall with formative stone and formative stone
KR101168859B1 (en) Retaining wall with formative stone and formative stone using the same
JPH09242088A (en) Concrete box for being buried underground
US20050000178A1 (en) Poured-in-place concrete construction components and method of construction
JP2005023777A (en) Reinforced decorated panel
KR20050002813A (en) Connector for connecting conduits carrying cables at a location where the cables cross each other
KR100356702B1 (en) wall outlet box
KR20200124543A (en) Block molding apparatus and its block
CN205090097U (en) Brickwork wall poling line structure
KR100559149B1 (en) Block for stair
EP3737801A1 (en) Foundation block
JP2020014308A (en) Trough buried structure and common ditch

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120305

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee