KR100614794B1 - Construction method using skip-floor - Google Patents

Construction method using skip-floor Download PDF

Info

Publication number
KR100614794B1
KR100614794B1 KR1020040109173A KR20040109173A KR100614794B1 KR 100614794 B1 KR100614794 B1 KR 100614794B1 KR 1020040109173 A KR1020040109173 A KR 1020040109173A KR 20040109173 A KR20040109173 A KR 20040109173A KR 100614794 B1 KR100614794 B1 KR 100614794B1
Authority
KR
South Korea
Prior art keywords
concrete
construction
formwork
floor
layered
Prior art date
Application number
KR1020040109173A
Other languages
Korean (ko)
Other versions
KR20060070640A (en
Inventor
박무용
황기수
최창식
Original Assignee
박무용
황기수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박무용, 황기수 filed Critical 박무용
Priority to KR1020040109173A priority Critical patent/KR100614794B1/en
Publication of KR20060070640A publication Critical patent/KR20060070640A/en
Application granted granted Critical
Publication of KR100614794B1 publication Critical patent/KR100614794B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3505Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the in situ moulding of large parts of a structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/166Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with curved surfaces, at least partially cast in situ in order to make a continuous concrete shell structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys

Abstract

본 발명은 1개층 또는 2개층을 건너뛰는 시공방식을 채택한 새로운 건축공법에 관한 것이다. The present invention relates to a new construction method employing a construction method that skips one floor or two floors.

본 발명은 고층 콘크리트 건물의 콘크리트/철골 구조물 구축시 1개층 또는 2개층을 건너뛰는 시공방식을 채택하여 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 등의 작업을 적어도 2개층 이상에서 동시에 수행할 수 있도록 함으로써, 인력과 자재의 투입 및 운영을 효율적으로 할 수 있고, 특히 공사기간을 30%에서 최고 50%까지 단축할 수 있으며, 궁극적으로 건축공사관리비 및 금융비용을 대폭 절감할 수 있는 새로운 건축공법을 제공한다.The present invention adopts a construction method that skips one or two floors when constructing a concrete / steel structure of a high-rise concrete building so that work such as formwork, reinforcing steel assembly, concrete placing and curing can be simultaneously performed on at least two floors. In this way, the input and operation of manpower and materials can be efficiently carried out, and in particular, the construction period can be shortened from 30% to up to 50%, and a new construction method can ultimately significantly reduce construction management and financial costs. to provide.

고층 콘크리트 건물, 콘크리트/철골 구조물, 스킵공법, 공기단축High-rise concrete building, concrete / steel structure, skip method, air shortening

Description

격층시공을 이용한 건축공법{Construction method using skip-floor} Construction method using skip-floor}             

도 1a 내지 1f는 본 발명에 따른 격층시공을 이용한 건축공법의 일 실시예를 보여주는 개략도Figure 1a to 1f is a schematic diagram showing an embodiment of the construction method using a layered construction according to the present invention

도 2a 내지 2f는 본 발명에 따른 격층시공을 위한 건축공법의 다른 실시예를 보여주는 개략도2a to 2f is a schematic view showing another embodiment of the construction method for the layered construction according to the present invention

〈도면의 주요부분에 대한 부호의 설명〉<Explanation of symbols for main parts of drawing>

10a~10f,20a~20f : 격층 콘크리트/철근 구조물10a ~ 10f, 20a ~ 20f: Diaphragm concrete / reinforced structure

11a~11f,21a~21f : 기둥 구조물 12a~12f,22a~22f : 바닥 구조물11a ~ 11f, 21a ~ 21f: pillar structure 12a ~ 12f, 22a ~ 22f: floor structure

13a~13d : 스킵층 바닥 구조물 23a~23d : 스킵하층 바닥 구조물13a ~ 13d: Skip Floor Floor Structure 23a ~ 23d: Skip Bottom Floor Structure

24a~24c : 스킵상층 바닥 구조물 30 : 동바리24a ~ 24c: Skip upper floor structure 30: Copper bar

본 발명은 격층시공을 이용한 건축공법에 관한 것으로서, 더욱 상세하게는 1개층 또는 2개층을 건너뛰는 시공방식을 채택하여 거푸집 설치, 철근조립, 콘크리 트 타설 및 양생 등의 작업을 적어도 2개층 이상에서 동시에 수행할 수 있도록 함으로써, 인력과 자재의 투입 및 운영을 효율적으로 할 수 있으며, 무엇보다도 공사기간을 획기적으로 단축할 수 있는 새로운 건축공법에 관한 것이다. The present invention relates to a construction method using a layered construction, and more particularly, by adopting a construction method that skips one or two floors, at least two or more operations such as formwork, reinforcing steel assembly, concrete placement and curing are performed. At the same time, it is possible to efficiently input and operate manpower and materials, and above all, to a new construction method that can significantly shorten the construction period.

일반적으로 고층 콘크리트 건물의 건축을 위해 선행되는 콘크리트/철골 구조물의 경우 벽체와 바닥을 구축하기 위한 거푸집 설치 및 철근조립을 먼저 수행하고 콘크리트 타설 및 양생의 과정을 거친 후, 계속해서 2층, 3층 내지 최상층의 거푸집 설치, 철근조립, 콘크리트 타설 및 양생의 과정을 축차적으로 수행하는 구축방법을 채택하고 있다. In the case of concrete / steel structures, which are generally preceded for the construction of high-rise concrete buildings, formwork and reinforcing reinforcement for building walls and floors are first performed, followed by concrete pouring and curing, and then the second and third floors. To build the formwork, reinforcing bar, concrete placement and curing of the top floor is adopted.

예를 들면, 고층 콘크리트 건물의 골조공사시 먼저 외벽과 내벽이 설치될 부위에 철근 등을 종횡으로 배열하여 배근공사를 하고, 계속해서 배근의 양측으로 내외 거푸집을 설치하여 콘크리트를 타설한 다음 콘크리트 양생이 완료되면, 다시 그 상측에 슬라브용 철근을 배근하고 거푸집을 설치한 다음 콘크리트 타설 및 양생을 거쳐 슬라브를 구축하며, 이렇게 내외벽 및 슬라브의 시공이 완료되면 거푸집 철거작업과 단열시공, 내외장재 시공을 차례로 수행하는 것으로 한개층에 대한 시공을 완료할 수 있다. For example, when framing a high-rise concrete building, the rebar works are first arranged horizontally and horizontally at the site where the outer wall and the inner wall are to be installed, and the concrete is then poured by installing internal and external formwork on both sides of the reinforcement. When this is completed, reinforce the slab reinforcing bar on the upper side, install the formwork, and then build the slab through concrete placing and curing, and when the interior and exterior walls and slabs are completed, the form is demolished, insulated, and installed We can complete construction on one floor by performing one by one.

위와 같이 최하층부터 최상층까지 한개층씩 순차적으로 시공을 해나가는 건축공법의 경우 콘크리트 타설 및 양생 등의 기간 동안 기다려야 하는 등 시공작업의 연속성이 떨어지면서 공사기간이 늘어나는 단점이 있으며, 특히 20~40층의 고층 콘크리트 건물을 시공하는 경우에는 이러한 공기지연 등으로 인력의 효율적인 투입 및 배치, 운영 등이 제대로 이루어지 못하는 단점이 있다. In the case of the construction method which is constructed one by one from the lowest floor to the highest floor as described above, there is a disadvantage in that the construction period is increased due to the continuity of the construction work such as waiting for the period of concrete casting and curing, etc. In the case of constructing a high-rise concrete building, there is a disadvantage in that efficient input, layout, and operation of manpower are not properly performed due to such air delay.

최근 각종 건물이 고층화되고 분양 또는 임대가 시공 후에 이루어지도록 법제화 됨에 따라 개발자의 금융부담이 막중하게 증가하는 실정이고, 이러한 이유로 공기단축을 위하여 다방면으로 노력이 이루어지고 있는 추세이다. Recently, as various buildings become higher and legislated to be sold or leased after construction, the financial burden of developers is greatly increased. For this reason, efforts are being made in various fields to reduce air.

따라서, 본 발명은 이와 같은 점을 감안하여 안출한 것으로서, 고층 콘크리트 건물의 콘크리트/철골 구조물 구축시 1개층 또는 2개층을 건너뛰는 시공방식을 채택하여 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 등의 작업을 적어도 2개층 이상에서 동시에 수행할 수 있도록 함으로써, 인력과 자재의 투입 및 운영을 효율적으로 할 수 있고, 특히 공사기간을 30%에서 최고 50%까지 단축할 수 있으며, 궁극적으로 건축공사관리비 및 금융비용을 대폭 절감할 수 있는 새로운 건축공법을 제공하는데 그 목적이 있다.
Therefore, the present invention has been devised in view of such a point, and adopts a construction method that skips one or two floors when constructing a concrete / steel structure of a high-rise concrete building, such as formwork installation, reinforcing steel assembly, concrete pouring and curing, etc. By allowing work to be performed simultaneously on at least two floors, it is possible to efficiently input and operate manpower and materials, and in particular, to shorten the construction period from 30% to up to 50%, and ultimately the construction management cost and The aim is to provide new construction methods that can significantly reduce financial costs.

상기 목적을 달성하기 위한 본 발명은 고층 콘크리트 건물의 콘크리트/철골 구조물을 구축하는 건축공법에 있어서, 콘크리트/철골 구조물 구축시 1개층 또는 2개층을 건너뛰는 방식으로 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업을 수행하여 격층 콘크리트/철골 구조물을 구축하되, 순차적으로 이루어지는 상위층에 대한 격층 콘크리트/철골 구조물의 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업과 스킵층 바닥 구조물에 대한 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업을 함께 병행하는 것을 특징으로 한다. In order to achieve the above object, the present invention provides a construction method for constructing a concrete / steel structure of a high-rise concrete building, and installs formwork, reinforcing steel assembly, and concrete in a manner of skipping one or two floors when constructing a concrete / steel structure. Curing work is carried out to build the stratified concrete / steel structure, but formwork of the stratified concrete / steel structure is sequentially installed on the upper layer, reinforcement assembly, concrete placing and curing work and formwork installation on the skip layer floor structure, reinforcement assembly, It is characterized in that the concrete pouring and curing work together.

또한, 상기 스킵층 바닥 구조물에 대한 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업은 적어도 2단 격층 콘크리트/철골 구조물 구축 후 수행하는 것을 특징으로 한다. In addition, the formwork, reinforcing bars, concrete placing and curing work for the skip layer floor structure is characterized in that it is carried out after at least two-stage layered concrete / steel structure construction.

또한, 상기 콘크리트/철골 구조물 구축시 2개층을 건너뛰는 경우 순차적으로 이루어지는 상위층에 대한 격층 콘크리트/철골 구조물의 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업과 하위 2개층의 스킵층 바닥 구조물에 대한 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업을 함께 병행하는 것을 특징으로 한다. In addition, when the two floors are skipped when building the concrete / steel structure, the formwork of the layered concrete / steel structure is sequentially installed, the reinforcing steel assembly, the concrete placing and curing work and the formwork for the skip layer floor structure of the lower two layers. It is characterized by the parallel installation, reinforcing bars, concrete pouring and curing work.

또한, 상기 격층 콘크리트/철골 구조물의 바닥 구조물 및 스킵층 바닥 구조물은 일반 거푸집, 또는 데크 플레이트, 또는 철근 일체형 데크 플레이트를 사용하여 시공하는 것을 특징으로 한다. In addition, the floor structure and the skip layer floor structure of the layered concrete / steel structure is characterized in that the construction using a general formwork, deck plate, or reinforced bar deck plate.

또한, 상기 격층 콘크리트/철골 구조물의 바닥 구조물 및 스킵층 바닥 구조물의 시공을 위한 거푸집은 선 시공된 하위층에서 동바리로 지지하는 방식, 또는 선 시공된 상위층에 거푸집을 메달아 지지하는 현수방식, 또는 선 구축된 콘크리트/철골 구조물의 기둥 구조물에 브라켓을 설치하고 이곳에 거푸집을 얹혀서 지지하는 브라켓 지지방식을 사용하여 설치하는 것을 특징으로 한다. In addition, the formwork for the construction of the floor structure and the skip layer floor structure of the layered concrete / steel structure is supported by a group in the lower layer of the pre-construction, or a suspension method of hanging the formwork on the upper layer of the pre-construction, or the line The bracket is installed on the column structure of the constructed concrete / steel structure, and the bracket is placed on the formwork.

또한, 상기 격층 콘크리트/철골 구조물의 기둥 구조물은 CFT 기둥, CFCT 기둥, 중공 PC 기둥 중 어느 하나를 적용할 수 있는 것을 특징으로 한다. In addition, the column structure of the laminated concrete / steel structure is characterized in that any one of the CFT column, CFCT column, hollow PC column can be applied.

본 발명에서 제공하는 건축공법은 층고에 따라 동바리 지지작업성, 철근의 이음, 공사 중의 안전성 확보 등을 고려하여 1개층을 건너뛰거나 2개층을 건너뛰는 방식으로 콘크리트/철골 구조물을 구축하는 공법이다. The construction method provided by the present invention is a method of constructing a concrete / steel structure in a manner of skipping one floor or skipping two floors in consideration of supporting workability of a copper bar, joint of reinforcing bars, and securing safety during construction according to the floor height. .

1) 1개층을 건너뛰는 경우1) If you skip one floor

콘크리트/철골 구조물은 기둥 구조물의 경우 대략 7m 이내의 높이로 시공되므로 일반적인 타설방법의 적용이 가능하다. Concrete / steel structures are constructed to a height of approximately 7m in the case of columnar structures, so that general casting methods can be applied.

또한, 기둥 구조물을 위한 수직 철근의 시공 편의성을 위하여 철근 선 가공 조립공법(Pre fabrication)이 바람직하다. In addition, the rebar line fabrication (Pre fabrication) is preferred for the convenience of construction of vertical rebar for the column structure.

또한, 거푸집의 지지를 위한 동바리의 경우 일반 거푸집용 동바리(V1~V4)를 사용할 수 있다. In addition, in the case of a copper bar for supporting the formwork can be used for general die copper (V1 ~ V4).

또한, 슬라브, 즉 바닥 구조물의 시공시 일반 거푸집을 사용할 수도 있고, 작업의 효율성 및 경제성을 고려하여 합성 데크 플레이트 또는 철근 일체형 데크 플레이트를 사용할 수 있다. In addition, it is also possible to use a general formwork for the construction of the slab, that is, floor structure, in consideration of the efficiency and economic efficiency of the work it is possible to use a composite deck plate or reinforced bar deck plate.

또한, 건너뛰게 되는 층(스킵층)의 기둥 구조물과 바닥 구조물의 연결을 위하여 정착 철근을 시공한다. In addition, a fixing reinforcing bar is constructed in order to connect the pillar structure and the floor structure of the skipped layer (skip layer).

이때, D16 이하 철근은 구부린 철근을 사용하고 D19 이상의 철근은 압접 또는 커플링 이음을 사용한다. At this time, the rebars below D16 use bent rebars, and the rebars above D19 use press welding or coupling joints.

2) 2개층을 건너뛰는 경우2) If you skip two floors

콘크리트/철골 구조물은 기둥 구조물의 경우 대략 7m 이상 10m 이내의 높이로 시공되므로 일반적인 타설방법의 적용시 콘크리트 재료의 분리현상이 발생할 수 있다.Concrete / steel structures are constructed at a height of approximately 7m or more and less than 10m in the case of columnar structures, which can cause segregation of concrete materials when the general pouring method is applied.

따라서, 이때에는 콘크리트 타설관을 기둥 구조물의 하부까지 내려서 타설하는 방법을 이용하는 것이 바람직하다. Therefore, in this case, it is preferable to use a method of pouring the concrete pouring pipe down to the lower part of the column structure.

여기서도 기둥 구조물을 위한 수직 철근의 시공 편의성을 위하여 철근 선 가공 조립공법(Pre fabrication)이 바람직하다. Here too, the rebar line fabrication method (Pre fabrication) is preferred for the convenience of construction of vertical rebar for the column structure.

또한, 기둥 구조물은 CFT(Concrete Filled in Tube) 기둥, CFCT(Concrete Filled in Carbon Tube) 기둥, 중공 PC 기둥 등을 적용할 수 있다. In addition, the pillar structure may be applied to a concrete filled in tube (CFT) column, a concrete filled in carbon tube (CFCT) column, a hollow PC column, and the like.

또한, 거푸집 동바리의 경우 일반 거푸집용 동바리의 사용이 곤란하므로 강관을 이용한 시스템 동바리를 사용하는 것이 바람직하다. In addition, in the case of the form circle, it is preferable to use a system circle using a steel pipe because it is difficult to use a general form copper.

또한, 바닥 구조물의 시공시 일반 거푸집을 사용할 수도 있고, 작업의 효율성 및 경제성을 고려하여 합성 데크 플레이트 또는 철근 일체형 데크 플레이트를 이용한 무지보 거푸집 공법을 사용할 수 있다. In addition, general formwork may be used for the construction of the floor structure, in consideration of the efficiency and economic efficiency of the work can be used a plain deck formwork using a composite deck plate or a reinforced deck plate.

특히, 바닥 구조물의 시공시 거푸집 지지방식으로는 브라켓 거푸집 공법(예를 들면, 기둥 구조물에 브라켓을 설치하고 이곳에 거푸집을 얹혀서 지지하는 공법)이나 현수 거푸집 공법(예를 들면, 선 시공된 상위층의 바닥 구조물로부터 와이어 등의 연결수단을 아래로 연장하여 이곳에 거푸집을 매달아 지지하는 공법)을 적용할 수 있다. In particular, as a formwork supporting method for the construction of floor structures, a bracket formwork method (for example, a bracket is installed on a pillar structure and a formwork is placed on the pillar support) or a suspension formwork method (for example, the upper layer of the pre-installed layer) By extending the connection means such as wires down from the floor structure, a method of hanging a formwork thereon may be applied.

또한, 건너뛰게 되는 층(스킵층)의 기둥 구조물과 바닥 구조물의 연결을 위하여 정착 철근을 시공한다. In addition, a fixing reinforcing bar is constructed in order to connect the pillar structure and the floor structure of the skipped layer (skip layer).

이때, D16 이하 철근은 구부린 철근을 사용하고 D19 이상의 철근은 압접 또 는 커플링 이음을 사용한다. At this time, the rebars below D16 use bent bars and the rebars above D19 use press welding or coupling joints.

이하, 첨부한 도면을 참조하여 본 발명을 상세히 설명하면 다음과 같다. Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 1a 내지 1f는 본 발명에 따른 격층시공을 이용한 건축공법의 일 실시예를 보여주는 개략도이다. Figure 1a to 1f is a schematic diagram showing an embodiment of the construction method using a layered construction according to the present invention.

도 1a 내지 1f에 도시한 바와 같이, 여기서는 1개층을 건너뛰는 방식으로 격층 콘크리트/철근 구조물을 구축하는 공법을 보여준다. As shown in FIGS. 1A-1F, the construction here shows a method of building a diaphragm concrete / rebar structure in a way that skips one floor.

1층 바닥 완료 후, 2층을 건너뛰면서 기둥 구조물(11a)과 바닥 구조물(12a)로 이루어진 1단의 격층 콘크리트/철근 구조물(10a)을 구축한다(도 1a).After completion of the first floor, the first floor of the second floor concrete structure 11a and the bottom structure (12a) consisting of a two-layered concrete / reinforced structure (10a) is constructed (Figure 1a).

여기서, 미설명 부호 30은 동바리를 나타낸다.Here, reference numeral 30 denotes a group.

즉, 1층과 2층의 기둥 구조물과 3층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생한다. That is, formwork (or deck plate) for the construction of the first and second floor pillar structures and the third floor floor structure is installed, the reinforcing bars are assembled, and concrete is then cured.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다.At this time, when the reinforcing bars are assembled, the skip layer is installed together with the reinforcing bars.

1단의 격층 콘크리트 구조물 구축 후, 4층을 건너뛰면서 기둥 구조물(11b)과 바닥 구조물(12b)로 이루어진 2단의 격층 콘크리트/철근 구조물(10b)을 구축한다(도 1b). After the construction of the first-tier diaphragm concrete structure, the second-level diaphragm concrete / reinforced structure 10b consisting of the column structure 11b and the bottom structure 12b is constructed while skipping the fourth floor (FIG. 1B).

즉, 3층과 4층의 기둥 구조물과 5층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생한다. In other words, formwork (or deck plate) for the construction of the three- and four-tiered pillar structure and the five-story floor structure is assembled, the reinforcing bars are assembled, and the concrete is then cured.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다.At this time, when the reinforcing bars are assembled, the skip layer is installed together with the reinforcing bars.

2단의 격층 콘크리트 구조물 구축 후, 6층을 건너뛰면서 기둥 구조물(11c)과 바닥 구조물(12c)로 이루어진 3단의 격층 콘크리트/철근 구조물(10c)을 구축한다( 도 1c). After the construction of the two-layered diaphragm concrete structure, the three-layered diaphragm concrete / reinforced structure 10c consisting of the column structure 11c and the bottom structure 12c is constructed while skipping the sixth floor (FIG. 1C).

즉, 5층과 6층의 기둥 구조물과 7층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생한다. That is, formwork (or deck plate) for the construction of the five- and six-story pillar structure and seven-story floor structure is assembled, the reinforcing bars are assembled, and then cured after pouring concrete.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다At this time, when the reinforcing bars are assembled, the skip layers are installed together with the connecting bars.

이와 동시에, 스킵층 바닥 구조물(13a)을 구축한다. At the same time, the skip layer bottom structure 13a is constructed.

즉, 2층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음 콘크리트 타설 후 양생한다. That is, formwork (or deck plate) for the construction of the two-story floor structure is installed, the reinforcing bars are assembled and then cured after concrete pouring.

다시 말해, 3단의 격층 콘크리트/철근 구조물의 구축과 스킵층 바닥 구조물의 시공을 동시에 수행한다. In other words, construction of the three-layered diaphragm concrete / reinforced structure and skipped floor structure are performed simultaneously.

3단의 격층 콘크리트 구조물 구축 후, 8층을 건너뛰면서 기둥 구조물(11d)과 바닥 구조물(12d)로 이루어진 4단의 격층 콘크리트/철근 구조물(10d)을 구축한다(도 1d). After the three-stage layered concrete structure construction, the four-stage layered concrete / reinforced structure (10d) consisting of the column structure (11d) and the bottom structure (12d) while skipping the eighth floor (FIG. 1D).

즉, 7층과 8층의 기둥 구조물과 9층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생한다. That is, formwork (or deck plate) for the construction of the seven-story and eight-story pillar structures and the nine-story floor structure is assembled, the reinforcing bars are assembled, and the concrete is then cured.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다At this time, when the reinforcing bars are assembled, the skip layers are installed together with the connecting bars.

이와 동시에, 스킵층 바닥 구조물(13b)을 구축한다. At the same time, a skip layer bottom structure 13b is constructed.

즉, 4층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음 콘크리트 타설 후 양생한다. That is, formwork (or deck plate) for the construction of the four-story floor structure is installed, the reinforcing bars are assembled, and then cured after concrete pouring.

다시 말해, 4단의 격층 콘크리트/철근 구조물의 구축과 스킵층 바닥 구조물의 시공을 동시에 수행한다. In other words, construction of the four-layered diaphragm concrete / reinforced structure and skipped floor structure are performed simultaneously.

위와 같은 과정을 반복하면서 격층 콘크리트/철근 구조물을 최상층까지 구축하고 이와 함께 스킵층에 대한 바닥 구조물 시공을 병행한다(도 1e 및 도 1f). While repeating the above process to build a stratified concrete / reinforced structure up to the top layer and parallel construction of the floor structure for the skip layer (Fig. 1e and 1f).

본 발명의 일 실시예에서는 13층까지의 구축예를 보여주고 있으며, 그 이상의 층도 위의 반복 시공을 통해 구축할 수 있음은 물론이다. In one embodiment of the present invention has been shown to build up to 13 floors, of course, it can be further constructed through the above-described repeated construction.

도 2a 내지 2f는 본 발명에 따른 격층시공을 위한 건축공법의 다른 실시예를 보여주는 개략도이다. Figure 2a to 2f is a schematic diagram showing another embodiment of the construction method for the layered construction according to the present invention.

도 2a 내지 2f에 도시한 바와 같이, 여기서는 2개층을 건너뛰는 방식으로 격층 콘크리트/철근 구조물을 구축하는 공법을 보여준다. As shown in Figures 2a to 2f, the construction here shows a method of building a diaphragm concrete / reinforced structure in a way that skips two floors.

1층 바닥 완료 후, 2층과 3층을 건너뛰면서 기둥 구조물(21a)과 바닥 구조물(22a)로 이루어진 1단의 격층 콘크리트/철근 구조물(20a)을 구축한다(도 2a).After completion of the first floor, the first and second stratified concrete / reinforced structures 20a consisting of the column structure 21a and the floor structure 22a are constructed while skipping the second and third floors (FIG. 2A).

여기서, 미설명 부호 30은 동바리를 나타낸다.Here, reference numeral 30 denotes a group.

즉, 1층 내지 3층의 기둥 구조물과 4층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생한다. That is, formwork (or deck plate) for the construction of the first and third floor pillar structure and the four-story floor structure is assembled, the reinforcing bars are assembled, and then cured after pouring concrete.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다.At this time, when the reinforcing bars are assembled, the skip layer is installed together with the reinforcing bars.

1단의 격층 콘크리트 구조물 구축 후, 5층과 6층을 건너뛰면서 기둥 구조물(21b)과 바닥 구조물(22b)로 이루어진 2단의 격층 콘크리트/철근 구조물(20b)을 구축한다(도 2b). After the construction of the first-tier diaphragm concrete structure, the second-level diaphragm concrete / reinforced structure 20b consisting of the column structure 21b and the bottom structure 22b is constructed while skipping the fifth and sixth floors (FIG. 2B).

즉, 4층 내지 6층의 기둥 구조물과 7층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생 한다. That is, formwork (or deck plate) for the construction of the four- to six-story pillar structure and the seven-story floor structure is assembled and the reinforcing bars, and then cured after pouring concrete.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다.At this time, when the reinforcing bars are assembled, the skip layer is installed together with the reinforcing bars.

2단의 격층 콘크리트 구조물 구축 후, 8층 및 9층을 건너뛰면서 기둥 구조물(21c)과 바닥 구조물(22c)로 이루어진 3단의 격층 콘크리트/철근 구조물(20c)을 구축한다(도 2c). After the construction of the two-layered diaphragm concrete structure, three-stage diaphragm concrete / reinforced structure 20c consisting of the column structure 21c and the bottom structure 22c is constructed while skipping the eighth and nineth floors (FIG. 2C).

즉, 7층 내지 9층의 기둥 구조물과 10층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생한다. That is, formwork (or deck plate) for the construction of the pillar structure and floor layer structure of the 7th to 9th floors are installed, the reinforcing bars are assembled, and the concrete is then cured.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다At this time, when the reinforcing bars are assembled, the skip layers are installed together with the connecting bars.

이와 동시에, 스킵하층 바닥 구조물(23a)을 구축한다. At the same time, a skipped lower floor structure 23a is constructed.

즉, 2층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음 콘크리트 타설 후 양생한다. That is, formwork (or deck plate) for the construction of the two-story floor structure is installed, the reinforcing bars are assembled and then cured after concrete pouring.

다시 말해, 3단의 격층 콘크리트/철근 구조물의 구축과 스킵하층 바닥 구조물의 시공을 동시에 수행한다. In other words, the construction of the three-stage stratified concrete / reinforced structure and the construction of the skipped lower floor structure are performed at the same time.

3단의 격층 콘크리트 구조물 구축 후, 11층과 12층을 건너뛰면서 기둥 구조물(21d)과 바닥 구조물(22d)로 이루어진 4단의 격층 콘크리트/철근 구조물(20d)을 구축한다(도 2d). After the construction of the three-layered diaphragm concrete structure, the four-layered diaphragm concrete / reinforced structure 20d consisting of the column structure 21d and the bottom structure 22d is constructed while skipping the 11th and 12th floors (FIG. 2D).

즉, 10층 내지 12층의 기둥 구조물과 9층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음, 콘크리트를 타설한 후 양생한다. That is, formwork (or deck plate) for the construction of the pillar structure of 10 to 12 stories and floor of 9 stories, and the reinforcing bars are assembled, and then cured after pouring concrete.

이때, 철근 조립시 스킵층의 정착 및 이음 철근도 함께 설치한다At this time, when the reinforcing bars are assembled, the skip layers are installed together with the connecting bars.

이와 동시에, 스킵상층 바닥 구조물(24a)과 스킵하층 바닥 구조물(23b)을 구축한다. At the same time, the skip upper layer bottom structure 24a and the skip lower layer bottom structure 23b are constructed.

즉, 3층 바닥 구조물 및 5층 바닥 구조물의 시공을 위한 거푸집(또는 데크 플레이트)을 설치하고 철근을 조립한 다음 콘크리트 타설 후 양생한다. That is, formwork (or deck plate) for the construction of the three-story floor structure and five-story floor structure is installed, the reinforcing bars are assembled, and then cured after concrete pouring.

다시 말해, 4단의 격층 콘크리트/철근 구조물의 구축과 스킵상하층 바닥 구조물의 시공을 동시에 수행한다. In other words, the construction of the four-layered diaphragm concrete / reinforced structure and the skip upper and lower floor structures are performed simultaneously.

위와 같은 과정을 반복하면서 격층 콘크리트/철근 구조물을 최상층까지 구축하고 이와 함께 스킵상하층에 대한 바닥 구조물 시공을 병행한다(도 2e 및 도 2f). Repeating the above process to build a stratified concrete / reinforced structure up to the top floor and with the construction of the floor structure for the skip upper and lower layers in parallel (Fig. 2e and 2f).

본 발명의 일 실시예에서는 19층까지의 구축예를 보여주고 있으며, 그 이상의 층도 위의 반복 시공을 통해 구축할 수 있음은 물론이다. In one embodiment of the present invention has been shown to build up to 19 floors, of course, it is possible to build more floors by repeating the above.

이와 같이 본 발명에서 제공하는 공법의 경우 1개층 또는 2개층을 건너뛰는 방식이므로 획기적인 공사기간 단축이 필요할 때 매우 유효하며, 기준 층이 많은 고층 건물에 적용될 때 보다 효과적이며 경제성을 기대할 수 있다. As such, the method provided by the present invention is very effective when a short construction period is required because it is a method of skipping one floor or two floors, and when the reference floor is applied to a high-rise building with many reference floors, it can be expected to be more effective and economical.

본 발명에서 제공하는 공법은 공사 계획에 따라 인력 투입 계획, 자재 투입 계획이 크게 좌우되므로 공법의 시공순서를 면밀히 고려한 후 공사 계획을 수립하는 것이 바람직하다. Since the construction method provided by the present invention greatly depends on the manpower input plan and the material input plan according to the construction plan, it is preferable to consider the construction order of the construction method and then establish the construction plan.

예를 들면, 2개층 내지 3개층을 동시에 타설할 것인지, 투입 인원의 연속적인 활용을 위하여 격일로 타설할 것인지 등을 고려하여 공사 계획을 세우는 것이 바람직하다. For example, it is desirable to plan the construction by considering whether two or three floors are to be placed at the same time or every other day for continuous utilization of input personnel.

이상에서와 같이 본 발명의 격층시공을 위한 건축공법은 다음과 같은 장점이 있다. As described above, the construction method for the layered construction of the present invention has the following advantages.

1) 건물 골조 공사기간을 30%에서 최고 50%까지 단축시킬 수 있다. 1) It can reduce the construction period of building frame from 30% up to 50%.

2) 적절한 공사 계획에 따라 가장 효율적으로 인력을 투입하거나 운영할 수 있다. 2) Manpower can be input or operated most efficiently according to appropriate construction plans.

3) 기둥 구조물을 충분한 높이로 시공함에 따라 철근 선 가공 조립공법 적용시 효과가 극대화된다.3) By constructing the column structure to a sufficient height, the effect is maximized when applying the rebar line processing assembly method.

4) 공사 기간의 획기적인 단축으로 건축공사관리비 및 금융비용을 절감할 수 있다. 4) Significant shortening of construction period can reduce construction cost and financial cost.

Claims (6)

고층 콘크리트 건물의 콘크리트/철골 구조물을 구축하는 건축공법에 있어서,In the construction method of building concrete / steel structure of high-rise concrete building, 콘크리트/철골 구조물 구축시 1개층 또는 2개층을 건너뛰는 방식으로 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업을 수행하여 격층 콘크리트/철골 구조물을 구축하되, 순차적으로 이루어지는 상위층에 대한 격층 콘크리트/철골 구조물의 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업과 스킵층 바닥 구조물에 대한 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업을 함께 병행하는 것을 특징으로 하는 격층시공을 이용한 건축공법.When constructing concrete / steel structures, it is possible to build a layered concrete / steel structure by installing formwork, reinforcing steel bars, concrete placing and curing by skipping one or two floors, but the layered concrete / steel structure for the upper layer sequentially A method of construction using layered construction, characterized in that the formwork, reinforcing steel assembly, concrete placing and curing work of the formwork for the skipped floor structure, and the formwork, reinforcing steel, concrete placing and curing work in parallel. 청구항 1에 있어서, 상기 스킵층 바닥 구조물에 대한 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업은 적어도 2단 격층 콘크리트/철골 구조물 구축 후 수행하는 것을 특징으로 하는 격층시공을 이용한 건축공법.The method according to claim 1, wherein the formwork, reinforcing steel assembly, concrete placing and curing work for the skipped floor structure is carried out after at least two-stage layered concrete / steel structure construction. 청구항 1에 있어서, 상기 콘크리트/철골 구조물 구축시 2개층을 건너뛰는 경우 순차적으로 이루어지는 상위층에 대한 격층 콘크리트/철골 구조물의 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업과 하위 2개층의 스킵층 바닥 구조물에 대한 거푸집 설치, 철근조립, 콘크리트 타설 및 양생 작업을 함께 병행하는 것을 특징으로 하는 격층시공을 이용한 건축공법.The method according to claim 1, wherein when the construction of the concrete / steel structure skips two floors, the formwork of the layered concrete / steel structure for the upper layer sequentially made, the reinforcing steel assembly, concrete casting and curing work and skip floor floor structure of the lower two floors Building construction method using a layered construction, characterized in that the formwork, reinforcing bars, concrete placing and curing work together. 청구항 1 내지 3 중 어느 한 항에 있어서, 상기 격층 콘크리트/철골 구조물의 바닥 구조물 및 스킵층 바닥 구조물은 일반 거푸집, 또는 데크 플레이트, 또는 철근 일체형 데크 플레이트를 사용하여 시공하는 것을 특징으로 하는 격층시공을 이용한 건축공법.The method of claim 1, wherein the floor structure and the skip layer floor structure of the layered concrete / steel structure is constructed using a general formwork, deck plate, or reinforced integral deck plate Used construction method. 청구항 1 내지 3 중 어느 한 항에 있어서, 상기 격층 콘크리트/철골 구조물의 바닥 구조물 및 스킵층 바닥 구조물의 시공을 위한 거푸집은 선 시공된 하위층에서 동바리로 지지하는 방식, 또는 선 시공된 상위층에 거푸집을 메달아 지지하는 현수방식, 또는 선 구축된 콘크리트/철골 구조물의 기둥 구조물에 브라켓을 설치하고 이곳에 거푸집을 얹혀서 지지하는 브라켓 지지방식을 사용하여 설치하는 것을 특징으로 하는 격층시공을 이용한 건축공법.The formwork according to any one of claims 1 to 3, wherein the formwork for the construction of the floor structure and the skip layer floor structure of the stratified concrete / steel structure is supported by the copper bar in the pre-installed lower layer, or in the upper layer of the pre-installed form. Hanging method for supporting medallions, or the installation method using a layered construction, characterized in that the bracket is installed on the column structure of the pre-concrete concrete / steel structure and installed by placing the formwork on it. 청구항 1 내지 3 중 어느 한 항에 있어서, 상기 격층 콘크리트/철골 구조물의 기둥 구조물은 CFT 기둥, CFCT 기둥, 중공 PC 기둥 중 어느 하나를 적용할 수 있는 것을 특징으로 하는 격층시공을 이용한 건축공법.The method according to any one of claims 1 to 3, wherein the column structure of the layered concrete / steel structure is applicable to any one of a CFT column, a CFCT column, and a hollow PC column.
KR1020040109173A 2004-12-21 2004-12-21 Construction method using skip-floor KR100614794B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040109173A KR100614794B1 (en) 2004-12-21 2004-12-21 Construction method using skip-floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040109173A KR100614794B1 (en) 2004-12-21 2004-12-21 Construction method using skip-floor

Publications (2)

Publication Number Publication Date
KR20060070640A KR20060070640A (en) 2006-06-26
KR100614794B1 true KR100614794B1 (en) 2006-08-22

Family

ID=37164237

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040109173A KR100614794B1 (en) 2004-12-21 2004-12-21 Construction method using skip-floor

Country Status (1)

Country Link
KR (1) KR100614794B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101445799B1 (en) * 2012-04-06 2014-10-01 삼성물산(주) Skip-floor Construction Method Using The Improved Semi-concrete filled tube Column Structure
KR101324161B1 (en) * 2013-03-29 2013-11-05 (주)한미글로벌건축사사무소 2-day-cycle concrete structure construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001107565A (en) 1999-10-06 2001-04-17 Kubota Kensetsu Kk Building construction method
KR20010044167A (en) * 2000-12-18 2001-06-05 윤요현 Method of earlier-separating dies for forming the lower part of con'c beam or slab from it

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001107565A (en) 1999-10-06 2001-04-17 Kubota Kensetsu Kk Building construction method
KR20010044167A (en) * 2000-12-18 2001-06-05 윤요현 Method of earlier-separating dies for forming the lower part of con'c beam or slab from it

Also Published As

Publication number Publication date
KR20060070640A (en) 2006-06-26

Similar Documents

Publication Publication Date Title
US20230417045A1 (en) Method for constructing a concrete floor in a multistorey building
CN213709853U (en) Prefabricated member, structural column, shear wall and semi-fabricated building structure
JP2008031733A (en) Bridge erection method
CN102235048B (en) Reinforced concrete hollow floor
JP2002089043A (en) Reinforced concrete structure and construction method for steel framed reinforced concrete, structure
KR100614794B1 (en) Construction method using skip-floor
CN111255260B (en) Prefabricated unit-based prefabricated house and construction method thereof
KR100763979B1 (en) Multi slab for construction of underground parking lot
KR102197994B1 (en) Construction method using beam-reinforced deck plate
CN211421475U (en) Connecting structure of prefabricated wall and beam
KR101518586B1 (en) Method for constructing precast concrete structural frame building using the precast concrete tilt-up frame
CN112359965A (en) Precast concrete assembled structure with rib mold structure and construction method thereof
JP4445366B2 (en) Reinforcement method for tower crane mount
KR100885765B1 (en) Composit panel comprising metal skeleton panel and thin panel connected by shearing connector and construction methods of exterior wall using the same
CN212224198U (en) Concrete prefabricated PC house unit
CN219710661U (en) Steel joint concrete precast shear wall
TWI822635B (en) Construction structure
JP2928002B2 (en) Column formwork structure
CN110295668B (en) Low-rise assembled steel concrete structure building and construction method thereof
JP2001020376A (en) Sc beam construction method for building
WO2020222630A1 (en) Hollow core slab manufactured by vibration casting without formwork
RU15111U1 (en) REINFORCED CONCRETE BUILDING FRAME
JPH06104993B2 (en) Construction method of steel pipe precast concrete columns
JPH09256549A (en) Frame unit for building frame of concrete building structure and method of construction using frame unit thereof
WO2019093772A1 (en) Beam-reinforced deck plate and construction method using same

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20110804

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20120816

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee