KR101324161B1 - 2-day-cycle concrete structure construction method - Google Patents

2-day-cycle concrete structure construction method Download PDF

Info

Publication number
KR101324161B1
KR101324161B1 KR20130034569A KR20130034569A KR101324161B1 KR 101324161 B1 KR101324161 B1 KR 101324161B1 KR 20130034569 A KR20130034569 A KR 20130034569A KR 20130034569 A KR20130034569 A KR 20130034569A KR 101324161 B1 KR101324161 B1 KR 101324161B1
Authority
KR
South Korea
Prior art keywords
floor
concrete
slab
layer
day
Prior art date
Application number
KR20130034569A
Other languages
Korean (ko)
Inventor
김봉기
이병일
Original Assignee
(주)한미글로벌건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)한미글로벌건축사사무소 filed Critical (주)한미글로벌건축사사무소
Priority to KR20130034569A priority Critical patent/KR101324161B1/en
Application granted granted Critical
Publication of KR101324161B1 publication Critical patent/KR101324161B1/en
Priority to CN201480002736.0A priority patent/CN104736779B/en
Priority to PCT/KR2014/002635 priority patent/WO2014157971A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/161Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/00612Uses not provided for elsewhere in C04B2111/00 as one or more layers of a layered structure
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/60Flooring materials
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/165Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with elongated load-supporting parts, cast in situ

Abstract

The present invention relates to a construction method capable of remarkably reducing construction periods for one floor by maximally reducing work elements and required time for each process and of rapidly developing required strength in an early stage by putting a high early-strength admixture in concrete. The bottom of a standard floor is divided into a plurality of working sections. After a slab mold and reinforcing bars are arranged and assembled in order of the section for marking on the bottom of a concrete slab, installing the reinforcing bars of a column, installing a mold for the column, installing the mold for a wall, installing a supporting post, and constructing the bottom of an upper floor, the concrete is placed on from the section of which a work is completed so that the standard floor is constructed in two days since the concrete is placed on the standard floor. The point of the construction method is in a production control system optimizing the management of the mold and breaking existing idea on an existing construction work management method. The present invention reduces construction time of 5-10 days by one floor to two days so that labor productivity is remarkably improved. The present invention also remarkably reduces indirect costs and financial costs through the reduction of the construction periods so that business performances of a client are largely improved.

Description

2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법{2-day-cycle concrete structure construction method}2-day-cycle concrete structure construction method

본 발명은 철근콘크리트구조 건물의 공사방법에 관한 것이다. 더 상세하게는 철근콘크리트공사 기간을 대폭 줄일 수 있는 공사방법이다.
The present invention relates to a method of constructing a reinforced concrete structure building. More specifically, it is a construction method capable of drastically reducing the period of construction of reinforced concrete.

철근콘크리트구조로 설계한 건물을 지으려면 먹메김, 기둥철근과 거푸집 설치, 동바리와 상부층 슬래브 거푸집과 철근을 조립하고 설치한 뒤 콘크리트를 붓고, 구조체로써 강도를 발현할 때까지 일정기간 양생을 거쳐 한개 층 공사가 완료된다. 콘크리트공사는 공정도 복합되고, 콘크리트를 양생하는 데 일정 기간이 필요하기 때문에 시간이 오래 걸려 한개 층 공사에 보통 7일~10일 소요된다. 건축물의 완공 시기는 건축주에게 중요한 관심사이다. 건물을 빨리 준공하면 건축물을 사용할 수 있는 시기가 앞당기고, 건설비에 투자한 비용을 더 빨리 걷어 들일 수 있기에 공사 기간을 줄일 수 있는 방안을 요구한다. In order to build a building with reinforced concrete structure, it is necessary to pour concrete, install reinforcing bars and formwork, assemble copper bar and upper slab formwork and reinforcement, pour concrete, and cure it for a certain period of time until strength is expressed as a structure. Floor construction is complete. The concrete construction process is complex and requires a certain period of time to cure concrete, which takes a long time and usually takes 7 to 10 days to construct a single floor. Completion time of the building is an important concern to the client. Completion of the building quickly will lead to a faster time to use the building, and will allow for a faster retrieval of the investment in construction costs.

이런 요구에 응하여 기술자들은 작업구획 나누기, 작업조 짜기, 작업 시간 연장 등 여러 방안을 찾았지만 한 층을 올리는데 개략 7~10일이 걸렸으며, 보통 업계에서는 한개 층 평균 공기의 한계는 5일로 인식되어 왔다.
In response to these demands, the technicians found several options, such as dividing the work area, weaving work, and extending the working time, but it took approximately 7 to 10 days to raise one floor, and the industry generally recognized the limit of one floor average air as 5 days. come.

본 발명은 종래 콘크리트공사에서 있던 여러 문제점을 해소하기 위한 것이다.The present invention is intended to solve various problems in conventional concrete constructions.

첫째, 본 발명은 철근콘크리트구조에서 한개 층 공사기간을 평균 이틀로 줄일 수 있는 방법을 개발하는 것이다.First, the present invention is to develop a method that can reduce the construction period of one floor in the reinforced concrete structure to an average of two days.

둘째, 본 발명은 한개 층 공사기간을 대폭 줄임으로써 인력과 장비를 효율성 있게 활용하는 방법을 개발하는 것이다.Second, the present invention is to develop a method of efficiently utilizing manpower and equipment by significantly reducing the construction period of one floor.

셋째, 본 발명은 한개 층 공사기간을 대폭 줄임으로써 전체 공사기간을 줄여 건축주가 더욱 빨리 건물을 사용할 수 있게 하는 방법을 개발하는 것이다.
Third, the present invention is to reduce the overall construction period by significantly reducing the construction period of one floor to develop a method that allows the owner to use the building more quickly.

위 과제를 해결하기 위해 본 발명은, 기준 층 바닥을 여러 개 작업 구획으로 나누고, 한쪽 구획에서부터 콘크리트 슬래브 바닥에 먹메김, 기둥철근 설치, 기둥 거푸집 설치, 벽체 거푸집 설치, 동바리 설치, 상부층 바닥을 만들기 위한 슬래브 거푸집과 철근을 설치한 뒤 작업이 완료된 구획부터 콘크리트를 타설하고, 다음 상부층으로 넘어가는 공사로서, 상기 콘크리트를 설계기준강도보다 25%이상 더 강도가 높은 콘크리트를 사용하여 초기에 강도가 빨리 나타나게 하고, 공사에 필요한 각 공정간 작업요소와 소요되는 시간을 최대한 압축하여 한개 층의 공사기간을 크게 줄일 수 있다. In order to solve the above problems, the present invention divides the reference floor floor into a number of work compartments, from one compartment to the concrete slab floors, pillar reinforcement installation, column formwork installation, wall formwork installation, copper bar installation, making the upper floor floor After installing the slab formwork and reinforcing bars for the concrete, the concrete is poured from the completed block and then transferred to the next upper floor. The construction period of one floor can be greatly reduced by compressing the work elements and the time required for each process.

또한, 효과를 더 높이기 위해 바닥은 평슬래브(Flat Plate Slab)구조로 설계한다. 나아가 위 동바리는 조립식을 사용하고, 콘크리트의 초기 강도가 0.5Mpa 이상이면 위층 바닥의 먹매김 작업에 들어간다. 그리고 콘크리트 강도가 14Mpa 이상이거나, 설계기준강도의 2/3이상이 발현되면 슬래브 거푸집을 해체함으로써 한 층을 공사하는 시간을 줄인다.
In addition, the floor is designed with a flat plate slab structure to further enhance the effect. Furthermore, the upper clubs use a prefabricated type, and when the initial strength of concrete is 0.5Mpa or more, it enters the feeding operation of the upper floor. And if the concrete strength is more than 14Mpa or more than 2/3 of the design standard strength, the slab formwork is dismantled to reduce the time to construct a floor.

본 발명은 철근콘크리트구조에서 한개 층 공사기간을 평균 이틀로 줄임으로써 인력과 장비를 효율성 있게 활용할 수 있다. 그리고 한개 층 공사기간을 대폭 줄임으로써 전체 공사기간을 줄여 건축주가 더욱 빨리 건물을 사용할 수 한다.
The present invention can efficiently utilize manpower and equipment by reducing the construction period of one floor in the reinforced concrete structure to an average of two days. By drastically shortening the construction period of one floor, the construction period can be shortened so that the owner can use the building more quickly.

본 발명을 상세하게 설명한다.The present invention will be described in detail.

콘크리트 골조공사에는 거푸집 설치, 철근 배근, 콘크리트 타설, 양생, 거푸집 해체 등 일련으로 여러 공정이 진행된다. 일정 품질을 확보하면서 공기를 줄이려면 작업을 빨리 하기 위해 인력을 많이 투입하는 것을 맨 먼저 고려한다. 그러나 아무리 인력을 많이 투입하더라도 콘크리트공사에는 절대 공기가 있어 줄일 수 있는 한계가 있다. 즉 콘크리트의 품질을 확보하기 위해서는 콘크리트 양생기간, 거푸집 존치기간 등을 지켜야 한다. 이들 조건을 만족할 때까지 그 다음 작업을 진행할 수 없다.Concrete frame construction involves a series of processes such as formwork, reinforcement, concrete pouring, curing, and demolishing formwork. To reduce the air while ensuring a constant quality, the first thing to consider is to put a lot of manpower in order to speed up the work. However, no matter how much manpower is applied, there is a limit to reduce the amount of concrete in construction. In other words, to ensure the quality of concrete, concrete curing period and the duration of the formwork must be maintained. The next task can not be performed until these conditions are satisfied.

기준층(N층) 바닥을 5개의 작업구획으로 나누고, 나눈 구획의 한쪽 구획에서부터 콘크리트 슬래브 바닥에 먹메김, 기둥철근 설치, 기둥 거푸집 설치, 벽체 거푸집 설치, 동바리 설치, 상부층 바닥을 만들기 위한 슬래브 거푸집과 철근을 설치한 뒤 작업이 완료된 구획부터 콘크리트를 타설하고, 기준층에서 그 상부층(N+1층)으로 올라가면서 공사한다.The floor of the reference layer (N-layer) is divided into five work compartments, and from one side of the divided section to the bottom of the concrete slab, there is a slab die for installing the column, reinforcing the column, installing the column formwork, After installing the reinforcing bars, pour the concrete from the compartment where the work is completed, and build it up from the reference layer to the upper layer (N + 1 layer).

구간은 기준층 바닥을 보통 5개 정도로 구획하지만 5개에 한정되는 것은 아니다. 바닥이 넓다면 5개 이상 더 나눌 수 있다. 보통은 5개 구간이면 무난하다고 본다.The segment covers the floor of the reference layer generally to about five but is not limited to five. If the floor is wide, you can divide more than five. Normally, it is considered to be acceptable if it is five segments.

거푸집 해체 시기는 전체 공기에 영향을 준다. 보통 거푸집 존치기간은 기온별(10~20℃) 시멘트 종류에 따라 통상 7일을 존치해야 한다. 압축강도를 기준을 삼으면 설계기준강도의 2/3 이상이면 거푸집을 해체해도 된다. The mold demolition time affects the entire air. Usually, the duration of the formwork is normally 7 days depending on the temperature (10 ~ 20 ℃) cement type. Based on compressive strength, formwork may be dismantled if it is at least two-thirds of the design reference strength.

거푸집을 빨리 해체하기 위해서는 콘크리트 초기 강도를 빨리 나오도록 해야 한다. 그래서 콘크리트에 조강혼화제를 넣어 초기강도를 빨리 발현시켜 각 공정에 소요되는 시간을 줄일 수 있게 한다.In order to dismantle the form quickly, the initial strength of the concrete should be brought out quickly. Therefore, it is possible to reduce the time required for each process by expressing the initial strength quickly by adding crude admixture to concrete.

콘크리트 초기강도가 빨리 나오도록 하기 위해 조강제를 쓰기도 하지만, 콘크리트 설계기준강도보다 더 높은 강도를 가진 콘크리트를 사용하여 목적을 이룰 수 있다. 즉 콘크리트 배합강도가 높을수록 초기 강도가 빨리 발현되는 것을 이용하는 것이다. 실제 콘크리트의 설계기준강도 27MPa이더라도 적용하는 콘크리트 강도를 35MPa인 것을 사용했더니 초기 강도가 더 빨리 나왔다.It is possible to achieve the purpose by using concrete with higher strength than the strength of the concrete design standard, although it is used as a roughing agent to make the early strength of the concrete come out quickly. That is, the higher the concrete mixing strength is, the faster the initial strength is expressed. Even when the actual reference strength of the concrete is 27 MPa, the concrete strength of the applied concrete is 35 MPa, and the initial strength is faster.

실제 사례에서 보면, 콘크리트 타설 뒤 5~7시간 경과되어 콘크리트 강도가 0.3 ~ 0.6MPa일 때 상부층 바닥에 먹매김 작업을 시작하고, 콘크리트 타설 뒤 11~14시간 경과되어 상기 콘크리트 강도가 4.6 ~ 6.6MPa이면 상부층 바닥에 자재 올리기 등 작업을 시작하고, 콘크리트 타설 뒤 24시간이 경과하여 상기 콘크리트의 강도가 14MPa 이상이거나, 설계기준강도의 3분의 2이상이면 기준층의 슬래브 거푸집을 해체한다.In the actual case, after 5-7 hours after the concrete is poured, when the concrete strength is 0.3 to 0.6 MPa, the filling operation starts at the bottom of the upper layer, and after 11 to 14 hours after the concrete is poured, the concrete strength is 4.6 to 6.6 MPa. The work starts to raise the material on the bottom of the upper layer, and 24 hours after the concrete is placed, the slab formwork of the reference layer is dismantled if the strength of the concrete is 14 MPa or more, or more than two thirds of the design reference strength.

위 사례를 표로 정리하면 다음과 같다.The above examples are summarized as follows.

경과 시간Elapsed time 발현강도
(MPa=10kg.f/cm2)
Expression intensity
(MPa = 10 kgf / cm2)
최적 강도Optimum strength 작업내용Work contents
5~7시간  5 to 7 hours 0.3 ~0.6 Mpa0.3 to 0.6 Mpa 0.5 MPa0.5 MPa 콘크리트 표면에 발자국이 안 생기는 정도의 경화상태이며 먹매김작업을 시행한다.It is hardened to have no footprint on the concrete surface and is fed. 11~14시간11-14 hours 4.6 ~ 6.6 MPa4.6 to 6.6 MPa 5.0 MPa5.0 MPa 1)구조체로써 역할을 할 수 있는 최소한의 기본 강도.
2)벽체 거푸집 탈형 및 슬래브 상부에 자재 야적 및 적치 가능함.
1) Minimum base strength that can serve as a structure.
2) Demonstrate the wall formwork and pile up and stack materials on top of slab.
24시간경과24 hours elapsed 14 ~ 19 MPa14 to 19 MPa 14MPa 이상 또는 설계기준강도의
2/3이상 강도
More than 14 MPa or design strength
2/3 or more strength
타설층 -1층 기둥거푸집 해체
타설층 -1층 슬래브거푸집 해체 타설층 -1층 코어옹벽거푸집 해체
Poured -1st floor pillar formwork
Pouring layer -1st floor slab formwork Pouring layer -1st floor core retaining wall formwork

작업시간을 줄이기 위해 동바리 또는 거푸집 자재는 조립식 자재를 사용하여 현장 작업시간을 줄일 수 있다.In order to reduce the working time, the dough or formwork can use prefabricated materials to reduce field work time.

본 발명에 대한 기준층 작업을 5개 작업 구간으로 나눴을 때 작업 내용을 단계별로 설명한다.When the reference layer work according to the present invention is divided into five work sections, the work content will be described step by step.

(1)단계: 첫째 날 8시에 기준층(N층)의 하부층(N-1층)에서 해체한 거푸집 자재를 N층 바닥에 올리고, N층의 기둥 철근 조립과 외벽 벽체 대형거푸집을 설치하기 시작한다.Step (1): At 8:00 on the first day, formwork material dismantled from the lower layer (N-1 layer) of the reference layer (N layer) is placed on the floor of the N layer, and the N-layer column reinforcement assembly and external wall wall formwork are started. do.

(2)단계: 첫째 날 10시~12시에 N층의 기둥 철근과 거푸집 설치를 완료하고, 그 상부층(N+1층) 1구간에 슬래브 거푸집을 설치한다.Step (2): On the first day, at 10 to 12 o'clock, complete the installation of column reinforcement and formwork on the N floor, and install the slab formwork on the first section of the upper layer (N + 1 floor).

(3)단계: 첫째 날 13시~15시에 N+1층의 2~3구간에 슬래브 거푸집 설치하고, 1구간 슬래브에 철근을 설치하고, N층의 벽체거푸집 설치를 시작한다.Step (3): At 13:00 to 15:00 on the first day, install slab formwork in sections 2-3 of the N + 1 floor, install reinforcing bars in the section 1 slab, and start installing wall formwork on the N floor.

(4)단계: 첫째 날 15시~18시에 N+1층 4구간 슬래브 거푸집 설치하고, 2구간 슬래브 철근을 설치하고, N층 벽체거푸집 설치를 완료한다.Step (4): At 15: 00-18: 00 on the first day, install four-slab slab of N + 1 floor, install slab rebar of two sections, and complete the installation of N-wall wall formwork.

(5)단계: 둘째 날 08시~10시 N+1층 5구간 슬래브 거푸집 설치하고, 3구간 슬래브 철근을 설치하고, N+1층의 1구간 콘크리트를 타설하기 시작한다.Step (5): From 08 o'clock to 10 o'clock on the second day, install the 5th section slab formwork on the N + 1 floor, install the 3rd section slab rebar, and start pouring the 1st section concrete on the N + 1 floor.

(6)단계: 둘째 날 10시~12시에 N+1층 4구간 슬래브 철근을 설치하고, N+1층의 2구간 콘크리트를 타설한다.Step (6): Slab rebar is installed on the 4th section of N + 1st floor at 10 ~ 12 o'clock on the second day, and 2nd section concrete of the N + 1st floor is placed.

(7)단계: 둘째 날 12시~15시에 N+1층 5구간 슬래브 철근을 설치하고, N+1층의 3구간 콘크리트를 타설하고, 오전에 타설된 슬래브 콘크리트 바닥의 경화상태가 발자국이 생기지 않는 상태 정도로 굳은 것을 확인한 후 N+2층을 위한 바닥 먹매김 작업에 들어간다.(7) Step: Install slab reinforcing bars on N + 1 floor 5 sections at 12 o'clock to 15:00 on the second day, cast 3 sections concrete on N + 1 floor, and harden the slab concrete floor in the morning. After confirming that it has hardened to a level that does not occur, the floor is fed to the N + 2 layer.

(8)단계: 둘째 날 15시~18시에 N+1층 4구간과 5구간에 콘크리트를 타설하여 2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법에 대한 한 주기(Cycle)를 완료하고, 익일 아침 08:00까지 양생한 후 N+2층 작업은 상기 (1)단계 작업부터 되풀이하여 공사한다.(8) Step: Complete the cycle of concrete structure construction method that raises one floor every two days by placing concrete in the 4th and 5th sections of the N + 1st floor at 15: 00-18: 00 on the second day, and the next morning After curing until 08:00, work on N + 2 floor will be repeated from step (1) above.

이 공법에서 슬래브 및 건물의 수평적 변위에 대한 구조체 강도를 확보하려면 콘크리트 양생일수를 확보해야 한다. 따라서, 이 공법에서는 최상층을 제외한 하부 7개층을 슬래브 하부에 동바리로 지지하는 것이 원칙이다.In this method, the concrete curing period must be secured in order to secure the structural strength of the slab and the horizontal displacement of the building. Therefore, in this method, it is a principle that the lower seven layers excluding the uppermost layer are supported on the lower side of the slab.

즉 슬래브 거푸집을 받치는 동바리는 N+8층 바닥콘크리트를 타설했을 때, N+7층에서 N+4층까지 동바리 지지 소요수량 100%를 설치하고, N+3층에서 N층까지는 소요수량의 50% 정도를 유지하는 것이 좋다. 물론 이때에도 거푸집은 상기 기준층 바닥의 콘크리트 강도가 4.6 ~ 6.6 MPa일 때 해체해야 하고, 작업층 상부층의 바닥 먹매김은 상부층의 바닥 콘크리트 강도가 0.3 ~ 0.6 MPa일 때 들어가면 된다.That is, when the concrete supporting the slab form is installed, it is necessary to install 100% of the required amount of support from the N + 7th floor to the N + 4th floor when the N + 8th floor concrete is laid, %. Of course, the mold should be disassembled when the concrete strength at the floor of the reference layer is 4.6 ~ 6.6 MPa, and the flooring of the upper layer of the working floor should be entered when the bottom concrete strength of the upper layer is 0.3 ~ 0.6 MPa.

본 발명에 따라 공사할 때의 진행과정과 종래 공법으로 공사할 때 공사 진행과정을 비교하면 다음 표와 같다.According to the present invention, the progress of the construction is compared with that of the conventional construction.

본 발명Invention 종래 공법Conventional method 1) 1일차 오전(08:00~12:00)1) First day morning (08:00 to 12:00) 1) 1일차
1) Day 1
-철근: 철근 양중 및 부위별 분배- Reinforcement: Reinforcement and distribution -철근: 수직부재 배근- Reinforcement: vertical member 기둥 선조립 및 코아 부위 철근 배근Pillar pre-assembly and core area reinforcement -형틀: 수직부재 거푸집 탈형 준비- Mold: Prepare for vertical member form demolding 옹벽 철근 배근 조립 1/4완료Reinforcement reinforcement assembly 1/4 completion -거푸집: Gang Form 인양- Form: Gang Form salvage 2) 2일차2) Day 2 Numbering 별 Form 인양Numbering Star Form -형틀: 수직부재 거푸집 탈형- Mold: Vertical member form demolding 기둥 및 Slab support 인양Column and Slab support lifting -Slab: 하부층 탈형 준비 작업-Slab: Under-floor demolding preparation work Slab 1/5 부위 설치Slab 1/5 site installation 2) 1일차 오후(13:00~18:00)2) 1st day afternoon (from 13:00 to 18:00) 3) 3일차3) Day 3 -철근: 기둥선조립 완료- Rebar: Completion of pre-installation -Slab: 하부층 탈형 준비 작업-Slab: Under-floor demolding preparation work 코아옹벽 철근배근Reinforcing steel core reinforcement Slab 철근 전체분 인양Slab Full-thickness mining 4) 4일차4) Day 4 Slab 철근 2/5 배근작업 완료Completed Slab Reinforcement 2/5 laying work -철근: Slab 철근 배근- Reinforcement: Slab reinforcement -거푸집: 코아옹벽 거푸집 인양 및 설치- Formwork: Lifting and installing of core retaining wall formwork -기계 및 전기: 배선작업- Mechanical and electrical: Wiring work Slab거푸집 전체 완료Slab die complete 3) 2일차 오전(08:00~12:00)3) Day 2 Morning (08:00 to 12:00) 5) 5일차5) Day 5 -철근: 코아 Slab 및 계단실 철근배근- Reinforcement: Core Slab and Stair Reinforcement -Con'c 타설: Slab 콘크리트 타설-Con'c Placement: Slab Concrete Casting Slab 철근 완료Completed Slab Reinforcement -보양 작업- Nursing work -거푸집: 타설층 -1층 기둥 거푸집 해체- Form: Dismantled floor - First floor Column form dismantling 타설층 -1층 Slab 거푸집 해체Slab form demolition 타설층 -1층 코아옹벽 거푸집 해체Throwing floor - 1st floor Core retaining wall form dismantling -Con'c타설:기둥 및 옹벽부위 콘크리트설-Con'c Placement: concrete pillar and retaining wall Slab 1/5 Con'c 타설 진행Slab 1/5 Con'c piling 4) 2일차 오후(13:00~18:00)4) 2nd day afternoon (from 13:00 to 18:00) -철근: 선조립장에서 선가공 조립- Reinforcement: Prefabricated assembly at the anchorage -거푸집: 타설층-1층 기둥 거푸집해체- Form: Dismantled floor - First floor Column form dismantling 타설층-1층 Slab 거푸집 해체Slab form demolition 타설층-1층 코아옹벽거푸집 해체Throwing floor - 1st floor Core retaining wall form dismantling 타설층-4층 -7층 동바리 다시 받침/양중Pouring floor - 4th floor - Con'c 타설: Slab 2/5- 전체 타설 완료Con'c Placement: Slab 2 / 5- Complete all casting -현장 시험체 시험/ 오전타설분- Field test body test / Morning test

이렇게 공사한다면 종래 공법이 한 층에 5~7일 소요되던 것을 2일로 줄일 수 있다.In this way, it can be reduced to two days when the conventional method takes five to seven days on one floor.

본 발명의 효과를 더욱 높이기 위하여 추가로 몇 가지 고려할 사항이 있다. In order to further enhance the effect of the present invention, there are some additional considerations.

첫째, 바닥설계는 평슬래브(Flat Plate Slab)구조로 설계하면, 기둥이나 벽체 거푸집 설치에 필요한 시간을 줄일 수 있어 시간을 더욱 단축할 수 있다.First, if the floor design is designed with a flat plate slab structure, the time required to install a column or a wall formwork can be shortened, thereby further shortening the time.

둘째, 벽체 거푸집 설치에 들어가는 시간을 줄이기 위해 되도록 벽량을 줄여 설계하면 좋다.Second, it is recommended to reduce the amount of wall as much as possible in order to reduce the time to install the wall formwork.

그 외에도 기술요소는 아니지만 작업자가 전체 작업공정을 이해하고, 타 공정 작업자와 손발을 맞추기 위해서는 사전 교육이 꼭 필요하다. 나아가 감리자 등 현장 작업관리자가 이 발명을 확실히 이해하고 품질관리 및 안전관리에 대응해야 한다.In addition, it is not a technical element, but it is necessary to pre-train the worker in order to understand the entire work process and to keep up with other process workers. Furthermore, the field manager, such as the supervisor, must understand this invention and respond to quality control and safety management.

이렇게 작업하면, 철근콘크리트 공사 전체 공기는 50~60%가 줄어든다. 이에 따라 현장관리비와 본사 관리비 등 간접 공사비가 대폭 절감될 수 있으며, 현장 작업자(형틀공, 철근공, 콘크리트공 등)의 생산성은 크게 높아질 수 있다. 또한, 건축주(사업주)는 건물을 빨리 인수받아 수익사업을 할 수 있다.By doing this, the total air of the reinforced concrete construction is reduced by 50 ~ 60%. As a result, indirect construction costs such as on-site maintenance costs and head office maintenance costs can be drastically reduced, and the productivity of field workers (molds, bars, concrete pits, etc.) In addition, the owner (employer) can acquire the building quickly and can do the profit business.

이하 본 발명의 보호범위를 청구항으로 구체화한다. 본 청구항은 발명의 구성요소의 일부 또는 전부를 단순 대체하거나 설계변경하는 것은 본 발명의 보호범위에 속하는 것으로 해설될 것이다.
Hereinafter, the protection scope of the present invention will be embodied in the claims. It is intended that the present invention cover only some of the components of the invention or the design modifications fall within the protection scope of the invention.

Claims (11)

삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 건축물의 평면을 연속한 5개 구간으로 나누고,
(1)단계: 첫째날 8시에 기준층(N층)의 하부층(N-1층)에서 해체한 거푸집 자재를 N층 바닥에 올리고, N층의 기둥 철근 조립과 외벽 벽체 대형거푸집을 설치하기 시작하고,
(2)단계: 첫째날 10시~12시에 N층의 기둥 철근과 거푸집 설치를 완료하고, 그 상부층(N+1층) 1구간에 슬래브 거푸집을 설치하고,
(3)단계: 첫째날 13시~15시에 N+1층의 2~3구간에 슬래브 거푸집 설치하고, 1구간 슬래브에 철근을 설치하고, N층의 벽체거푸집 설치를 시작하고,
(4)단계: 첫째날 15시~18시에 N+1층 4구간 슬래브 거푸집 설치하고, 2구간 슬래브 철근을 설치하고, N층 벽체거푸집 설치를 완료하고.
(5)단계: 둘째날 08시~10시 N+1층 5구간 슬래브 거푸집 설치하고, 3구간 슬래브 철근을 설치하고, 1구간 콘크리트를 타설하고.
(6)단계: 둘째날 10시~12시에 N+1층 4구간 슬래브 철근을 설치하고, 2구간 콘크리트를 타설하고,
(7)단계: 둘째날 12시~15시에 N+1층 5구간 슬래브 철근을 설치하고, 3구간 콘크리트를 타설하고, N+1층 바닥 먹매김 작업에 들어가고,
(8)단계: 둘째날 15시~18시에 N+1층 4구간과 5구간에 콘크리트를 타설하고,
N+2층에서 상기 (1)단계 작업을 되풀이하는 단계로 공사하는 것을 특징으로 하는 2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법.
Divide the plane of the building into five consecutive sections,
Step (1): At 8 pm on the first day, formwork material dismantled from the lower layer (N-1 layer) of the reference layer (N layer) is placed on the floor of the N layer, and the N-layer column reinforcement assembly and external wall wall formwork are started. ,
Step 2: Complete the installation of N-stage column reinforcement and formwork at 10 o'clock to 12 o'clock of the first day, and install the slab formwork in the first section of the upper layer (N + 1 layer),
(3) step: Slab formwork is installed in 2 ~ 3 sections of N + 1 floor on the first day at 13: 00 ~ 15: 00, rebar is installed in section 1 slab, and wall formwork of N floor is started.
(4) step: 1st floor Slab formwork of 4 sections of N + 1st floor is installed at 15: 00-18: 00 on the first day, 2nd section of slab reinforcement is installed, and N floor wall formwork is completed.
(5) Stage: Slab formwork is installed on the 5th section of the N + 1 floor on the 2nd day from 08:00 to 10:00, the slab reinforcement is installed on the 3rd section and concrete is poured.
(6) step: install slab reinforcing bars in 4 sections of N + 1F on 10th-12th day of the second day, cast 2 sections of concrete,
(7) step: install slab reinforcing bars on N + 1st floor 5th section from 12 o'clock to 15:00 on the second day, cast concrete on 3rd section, and enter flooring work on N + 1st floor,
Step 8: Place concrete in the 4th and 5th sections of the N + 1st floor at 15: 00-18: 00 on the second day,
Concrete structure construction method that goes up by one floor every two days, characterized in that the construction to repeat the step (1) in the N + 2 floor.
제6항에서,
상기 슬래브 거푸집을 받치는 동바리는, N+8층 바닥콘크리트를 타설했을 때, N+7층에서 N+4층까지 소요수량 100%를 설치하고, N+3층에서 N층까지는 소요수량의 50% 정도를 유지하는 것을 특징으로 하는 2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법.
The method of claim 6,
The slabs supporting the slab form 100% of the required amount from N + 7 to N + 4 floor when N + 8 floor floor concrete is placed, and 50% of the required amount from N + 3 floor to N floor. Concrete structure construction method that goes up one by one every two days characterized by maintaining the accuracy.
제 6항에서,
상기 (1)단계의 하부층(N-1층) 거푸집 해체는 상기 기준층 바닥의 콘크리트 강도가 4.6 ~ 6.6 Mpa일 때 해체하는 것을 특징으로 하는 2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법.
The method of claim 6,
The lower layer (N-1 layer) formwork disassembly of the step (1) is a concrete structure construction method that rises by one layer every two days, characterized in that when the concrete strength of the bottom of the reference layer is 4.6 ~ 6.6 Mpa.
제 8항에서,
상기 기준층 바닥의 콘크리트 강도가 5 MPa일 때 해체하는 것을 특징으로 하는 2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법.
9. The method of claim 8,
The concrete structure construction method that rises by one floor every two days, characterized in that the dismantling when the concrete strength of the floor of the reference layer is 5 MPa.
제 6항에서,
상기 (7)단계에서 N+1층의 먹매김은 N+1층 바닥 콘크리트 강도가 0.3 ~ 0.6 Mpa일 때 들어가는 것을 특징으로 하는 2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법.
The method of claim 6,
In the step (7), the N + 1 layer is filled with N + 1 floor concrete structure construction method that goes up by one layer every two days, characterized in that entered when the concrete strength is 0.3 ~ 0.6 Mpa.
제 10항에서,
상기 N+1층 바닥 콘크리트 강도가 0.3 MPa 이상일 때 먹매김에 들어가는 것을 특징으로 하는 2일에 한개 층씩 올라가는 콘크리트 구조체 공사방법.
11. The method of claim 10,
The concrete structure construction method that goes up by one layer every two days, characterized in that the entering into the N + 1 floor when the concrete strength is 0.3 MPa or more.
KR20130034569A 2013-03-29 2013-03-29 2-day-cycle concrete structure construction method KR101324161B1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
KR20130034569A KR101324161B1 (en) 2013-03-29 2013-03-29 2-day-cycle concrete structure construction method
CN201480002736.0A CN104736779B (en) 2013-03-29 2014-03-28 Rose the construction of concrete structure body method of a floor per two days
PCT/KR2014/002635 WO2014157971A1 (en) 2013-03-29 2014-03-28 Method for constructing concrete structure of which one floor is built every two days

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20130034569A KR101324161B1 (en) 2013-03-29 2013-03-29 2-day-cycle concrete structure construction method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020130099662A Division KR20140119614A (en) 2013-08-22 2013-08-22 2-day-cycle concrete structure construction method

Publications (1)

Publication Number Publication Date
KR101324161B1 true KR101324161B1 (en) 2013-11-05

Family

ID=49856473

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20130034569A KR101324161B1 (en) 2013-03-29 2013-03-29 2-day-cycle concrete structure construction method

Country Status (3)

Country Link
KR (1) KR101324161B1 (en)
CN (1) CN104736779B (en)
WO (1) WO2014157971A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839784A (en) * 2016-03-17 2016-08-10 杨春 Assemble-jacking type building construction method
CN114396158A (en) * 2021-12-24 2022-04-26 北京市第三建筑工程有限公司 Rapid graded formwork dismantling system and construction method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459328A (en) * 2020-10-13 2021-03-09 北京首钢建设集团有限公司 Construction method for large-area floor slab by adopting segmented line production

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060070640A (en) * 2004-12-21 2006-06-26 박무용 Construction method using skip-floor

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06135750A (en) * 1992-08-05 1994-05-17 Mitsubishi Materials Corp Admixture for concrete, concrete product using the same and production of concrete product
JP2001107565A (en) * 1999-10-06 2001-04-17 Kubota Kensetsu Kk Building construction method
KR20030009673A (en) * 2001-07-23 2003-02-05 소도건설 주식회사 construction method of collective high building by segmental process
JP4611163B2 (en) * 2005-09-29 2011-01-12 株式会社奥村組 How to build a multi-story building
KR100875240B1 (en) * 2007-09-19 2008-12-19 한국도로공사 High performance concrete composition for constructing bridge slab integrated with pavement and bridge slab construction method using the same
CN101608454B (en) * 2009-05-21 2011-05-11 朱奎 Cavity shallow foundation and construction method
KR101162971B1 (en) * 2010-12-03 2012-07-09 삼성물산 주식회사 Concrete Construction Method For Slab And Core Wall Construction The Same Time Using Temporary Columns

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060070640A (en) * 2004-12-21 2006-06-26 박무용 Construction method using skip-floor

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839784A (en) * 2016-03-17 2016-08-10 杨春 Assemble-jacking type building construction method
CN105839784B (en) * 2016-03-17 2018-03-16 杨春 Assembled jacking type construction techniques
CN114396158A (en) * 2021-12-24 2022-04-26 北京市第三建筑工程有限公司 Rapid graded formwork dismantling system and construction method

Also Published As

Publication number Publication date
CN104736779B (en) 2017-03-15
CN104736779A (en) 2015-06-24
WO2014157971A1 (en) 2014-10-02

Similar Documents

Publication Publication Date Title
AU2020200977B2 (en) Methods, systems and components for multi-storey building construction
CN101769008B (en) Method for constructing quake-proof masonry house by utilizing prefabricated constructional column ring beams
KR101324161B1 (en) 2-day-cycle concrete structure construction method
CN104631677A (en) Construction technology for hollow super-thick concrete terrace
CN111186011A (en) Automatic assembly line arrangement structure for factory prefabrication of laminated slab beams and production method
CN109853956A (en) Residential building construction method
CN104594204B (en) Urban light rail viaduct mountain type U beam Construction Supporting System and construction method
US3692446A (en) Apparatus for forming and lifting multi-story columns in one story increments
KR20190039011A (en) Construction method for wall and slab type structured building
CN211842522U (en) Automatic assembly line arrangement structure for factory prefabrication of laminated slab beams
CN102535841A (en) Construction technology of prefabricated wall panel
CN104164951A (en) Stair landing and construction method thereof
CN103452350A (en) Fabricated electronic workshop and construction method thereof
KR100963488B1 (en) Negative moment floor slab prestress introduction method for which precast concrete pc wire anchorage block and this were used
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
KR101270947B1 (en) Deck repairing construction method of bridge using precast concrete slab
KR20140119614A (en) 2-day-cycle concrete structure construction method
CN108130889B (en) Manufacturing method of stepped construction joint between main bottom plate of pump brake and side wall of runner layer
CN110409711A (en) A kind of Cast-in-situ Beam steel bar arrangement and its construction technology
EP3470603A1 (en) Method for erecting structural elements of building/construction of monolithic reinforced concrete and technological equipment to implement it
KR20120061423A (en) Concrete Construction Method For Slab And Core Wall Construction The Same Time Using Temporary Columns
WO2018126950A1 (en) Modular stairway
KR101315946B1 (en) Rc construction method for concrete lining in parallel
KR101962709B1 (en) Composite deck slab construction method with trench
CN215594550U (en) Disassembly-free laminated slab

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
A107 Divisional application of patent
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20161005

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20171010

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20181004

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20191007

Year of fee payment: 7