KR100567738B1 - Open caisson construction method for the structures constructed over the water - Google Patents

Open caisson construction method for the structures constructed over the water Download PDF

Info

Publication number
KR100567738B1
KR100567738B1 KR1020050042292A KR20050042292A KR100567738B1 KR 100567738 B1 KR100567738 B1 KR 100567738B1 KR 1020050042292 A KR1020050042292 A KR 1020050042292A KR 20050042292 A KR20050042292 A KR 20050042292A KR 100567738 B1 KR100567738 B1 KR 100567738B1
Authority
KR
South Korea
Prior art keywords
steel
water
well
river
steel well
Prior art date
Application number
KR1020050042292A
Other languages
Korean (ko)
Inventor
황인섭
Original Assignee
재현토건(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 재현토건(주) filed Critical 재현토건(주)
Priority to KR1020050042292A priority Critical patent/KR100567738B1/en
Application granted granted Critical
Publication of KR100567738B1 publication Critical patent/KR100567738B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/02Caissons able to be floated on water and to be lowered into water in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1685Shapes cylindrical
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Revetment (AREA)

Abstract

수중구조물의 기초 형성을 위한 우물통(open caisson) 설치공법에 관한 기술이 개시된다.Disclosed is a technique for installing an open caisson for forming a foundation of an underwater structure.

본 발명의 수중구조물의 강재우물통 설치공법은 기존의 하천이나 강가에서는 우물통을 인양할 수 있는 대규모의 우물통 인양장비의 투입이 불가능함으로 운반 가능한 무게만큼 우물통 본체를 다수 개로 분할하여 시공위치까지 여러 번 운반작업을 반복함으로써 강재우물통의 조립 및 시공이 가능하였던 것과는 달리 이미 육상에서 상당부분 조립된 강재우물통을 하천이나 강가의 육상과 근접한 수상작업대에서 완조립하여 완전한 형태의 강재우물통을 형성한 뒤 부력(浮力)과 소규모의 인양장비를 이용하여 해상의 시공위치까지 용이하게 운반함으로써 운반공정의 횟수를 획기적으로 단축하고 공기를 절감할 수 있으며 시공성이 향상되는 수중구조물의 강재우물통 설치공법에 관한 것이다.Steel well bucket installation method of the underwater structure of the present invention is not possible to put a large well bucket lifting equipment that can lift the well in the existing river or river banks by dividing the body of the well to the construction site as many as possible weight Unlike the steel wells, which can be assembled and constructed by repeating the transporting process several times, steel wells, which are already assembled on land, are assembled in a water platform close to the river or the river, forming a complete steel well. It is related to the steel well bucket installation method of underwater structures, which can greatly reduce the number of transportation processes, save air, and improve workability by using easy buoyancy and small lifting equipment to transport to the sea construction location. .

Description

수중구조물의 강재우물통 설치공법{Open caisson construction method for the structures constructed over the water}Open caisson construction method for the structures constructed over the water}

도 1a 내지 도 1e는 종래의 강재우물통 기초 시공방법의 시공공정을 순차적으로 도시한 도면이다.1A to 1E are diagrams sequentially illustrating a construction process of a conventional steel well base construction method.

도 2a 내지 2h는 본 발명의 수중구조물의 강재우물통 설치공법의 시공공정을 순차적을 도시한 도면이다.Figure 2a to 2h is a view showing the construction process of the steel well bucket installation method of the underwater structure of the present invention sequentially.

도 3은 도 2b의 'A'부분을 확대 도시한 도면이다.3 is an enlarged view of a portion 'A' of FIG. 2B.

도 4는 본 발명의 수중구조물의 강재우물통 설치공법의 포스트파일을 도시한 도면이다.Figure 4 is a view showing a post pile of the steel well bucket installation method of the underwater structure of the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

100 : 케이싱파이프 110 : 포스트파일100: casing pipe 110: post pile

111 : 보강플레이트 200 : 수상작업대111: reinforcement plate 200: water platform

210 : 가이드롤러 300 : 강재우물통210: guide roller 300: steel well bucket

310 : 바닥차수용 강재거푸집 400 : 인양장비(소규모)310: steel formwork for floor order 400: lifting equipment (small scale)

본 발명의 수중구조물의 강재우물통 설치공법은 하천이나 강가에서 강재우물통 공법 시공 시, 이미 육상에서 상당부분 조립된 강재우물통을 하천이나 강가의 육상과 근접한 수상작업대에서 완조립하여 완전한 형태의 강재우물통을 형성한 뒤 부력(浮力)과 소규모의 인양장비를 이용하여 해상의 시공위치까지 용이하게 운반함으로써 운반공정의 횟수를 획기적으로 단축하고 공기를 절감할 수 있으며 시공성이 향상되는 수중구조물의 강재우물통 설치공법에 관한 것이다.The steel water tank installation method of the underwater structure of the present invention, when the steel water tank construction method in rivers or rivers, the steel water tanks that are already assembled in large part on the land is completed by the water work platform close to the river or river lands to complete the steel water tanks After forming, by using buoyancy and small lifting equipment, it can be easily transported to the sea construction location, which greatly reduces the number of transportation processes, saves air, and installs steel wells for underwater structures with improved construction properties. It is about.

교량의 교각 또는 안벽 등의 기초 구조부로 구축하게 되는 강재 우물통(open caisson) 기초 시공방법은 지지력과 수평저항력이 큰 기초 형식으로 깊은 기초에 사용되는 공법으로서, 여러 개로 분리되어 운반되어진 강재 우물통들을 현장에서 조립하여 우물통 조립체로 건조시켜, 이 건조된 우물통 조립체를 교각 설치위치로 운반하여 침하시켜 우물통 조립체 내측 저면의 토사를 굴착함과 동시에 우물통의 자중 또는 적재하중에 의하여 소정의 깊이까지 침설하여 강재 우물통 조립체를 암반상에 정착시키고, 상기 우물통 조립체 내부에 채움콘크리트를 충진시킴으로써 기초 구조물을 구축하는 공법이다.Open caisson foundation construction method, which is constructed with foundation structures such as bridge piers or quay walls, is a foundation method with large bearing capacity and horizontal resistance, and is used for deep foundations. Assembled in the field and dried in the well assembly, transported and settled the dried well assembly to the pier installation position to excavate the earth and sand of the inner bottom of the well assembly at the same time by the weight or loading load of the well It is a method of building a foundation structure by submerging to a depth to fix the steel well assembly on the rock, and filling the filling concrete inside the well assembly.

이 우물통 기초 시공시 사용되는 우물통은 교각(橋脚)에는 원형 또는 타원형 의 단면형태가, 안벽(岸壁)에는 장방형의 단면형태로 제작되어지며, 주로 많이 사 용되는 우물통은 강재로 제작되어진 원통형의 철구조물로서, 그 직경이 12m∼15m이고, 높이는 3m, 4m, 5m의 크기인 단위체들을 연결 조립하여 제작한 우물통을 사용하게 된다.The wells used in the foundation of the wells are made of round or oval cross-sections on the piers and rectangular cross-sections on the inner walls, and the wells that are frequently used are made of steel. Cylindrical steel structure, the diameter of 12m ~ 15m, the height of the 3m, 4m, 5m of the wells made by connecting the assembled units are used.

이 강재 우물통은 수중 속에 설치되는 관계로 내외측 강판사이에 1∼2m의 간격을 두고 공간부를 형성하면서 수압을 지지하도록 트러스 구조체가 일체로 용접되어져 있으며, 한편, 최하단용으로 설치되는 강재 우물통에는 내외측 강판이 하단부에서 일체로 연결되어 그 사이에 공간부를 형성하여 물속에서 부력을 받게 되며, 침설시 단부를 보호하기 위한 커브슈가 덧대어져 있다.Since the steel well is installed in the water, the truss structure is integrally welded to support the water pressure while forming a space part between the inner and outer steel sheets at a distance of 1 to 2 m, while the lower steel well is installed for the bottom end. The inner and outer steel plates are integrally connected at the lower end to form a space therebetween to receive buoyancy in the water, and a curve shoe is padded to protect the ends during subsidence.

이와 같은 원통형의 강재 우물통은 대략 12∼15m의 높이로 한꺼번에 육상에서 연결 조립하여 건조시켜 교각의 설치위치로 운반되어져 설치하게 된다.Such a cylindrical steel well is approximately 12-15 m in height and is connected and assembled at the same time on land to be transported to the installation location of the piers are installed.

상기와 같은 강재 우물통 조립체에 의하여 시공되는 종래의 '우물통 기초공법'은 강재 우물통 조립체(A)를 지상에서 한꺼번에 제작하여 교각의 기초 설치위치로 운반하여, 도1a에서 도시하는 바와 같이, 이 강재 우물통의 내외측 강판 사이의 공간부에 콘크리트(1)를 채워 침하시켜 하상(河床)(a)에 거치시킨 다음, 도1b에서 도시하는 바와 같이, 수면위로 노출된 강재 우물통의 상단부에서 일정높이로 철근조립체 및 거푸집을 설치하여 콘크리트를 타설함으로써 강재 우물통 조립체(A)와 콘크리트벽체(C1)를 일체로 성형시킨다.The conventional 'water well foundation method' constructed by the steel well assembly as described above is to produce the steel well assembly (A) all at once from the ground and transported to the foundation installation position of the piers, as shown in Figure 1a, After filling the concrete 1 with the space between the inner and outer steel plates of the steel well, it is settled and mounted on the lower bed (a). Then, as shown in FIG. 1B, the upper end of the steel well exposed to the surface of the water well The steel well barrel assembly (A) and the concrete wall (C1) are integrally formed by placing the reinforcement assembly and the formwork at a certain height in order to pour the concrete.

이후, 도1c에서 도시하는 바와 같이, 우물통 조립체 내측의 하상 저면을 굴착하여 콘크리트 강재 우물통 조립체(A)를 침하시킨 다음, 도1d에서 도시하는 바와 같이, 이 콘크리트벽체(C1)의 상측에 다시 콘크리트벽체(C2)를 연결시공하고 내측 하상 저면의 토사층(S)과 연암층(R)을 굴착하는 작업을 단계별로 반복 실시하여 콘크리트 강재 우물통 조립체(A)를 소요 정착깊이까지 침설하여 암반상에 정착시킨 후, 정착된 콘크리트 강재 우물통 조립체(A)의 내부 하측에 수중콘크리트(2)를 타설하여 밀폐시키고 그 위에 수용된 물을 외부로 빼낸다.Thereafter, as shown in FIG. 1C, the bottom bottom of the well assembly is excavated to settle the concrete steel well assembly A, and then, as shown in FIG. 1D, above the concrete wall C1. Connect the concrete wall (C2) again and repeat the work of excavating the soil layer (S) and the soft rock layer (R) on the bottom of the inner lower floor step by step to settle the concrete steel well assembly (A) to the required settlement depth and rock After settling on, the submerged concrete 2 is poured into the inner lower side of the settled concrete steel well assembly A and sealed, and the water contained thereon is drawn out.

이후, 도1e에서 도시하는 바와 같이, 물을 빼낸 우물통 조립체(A)의 내부 공간부에 모래, 자갈 또는 채움콘크리트(3)로 속채움하여 콘크리트 강재 우물통 기초구조를 구축한 후, 이 콘크리트 강재 우물통 기초의 상단에서 교각의 캡콘크리트 (4)와 일체로 시공하여 기초콘크리트부(F)를 형성하고, 그 위에 교각의 기둥콘크리트부(P)를 시공하는 방법으로 이루어지는 것이 통상적인 방법이었다.Thereafter, as shown in FIG. 1E, after filling the internal space of the drainage well assembly A with sand, gravel or filling concrete 3 to build a concrete steel well foundation structure, the concrete At the upper end of the steel well basin, the construction was integrally performed with the cap concrete 4 of the pier to form the foundation concrete portion F, and the pillar concrete portion P of the pier was constructed on the conventional method. .

상기와 같은 종래의 강재 우물통공법은 전술된 바와 같이 대략 12~15m의 높이로 육상에서 완조립된 강재 우물통이 시공위치로 운반되어져야 하기 때문에 이를 운반할 수 있는 대규모의 인양장비가 필수적으로 요구된다. As described above, the conventional steel well hole method requires a large lifting device capable of transporting the steel well barrel, which has been assembled on land with a height of approximately 12 to 15 m as described above, to be transported to the construction position. Required.

그러나 하천이나 강가와 같이 협소한 장소에서는 완조립된 강재 우물통을 운반할 수 있는 대규모의 인양장비 투입이 불가능함으로 강재 우물통을 운반 가능한 무게만큼 여러 개의 조립체로 분할하여 시공위치로 운반한 뒤 조립하여 시공하게 된다. 따라서 이러한 종래의 설치공법은 여러 번의 운반공정을 반복하여야만 함으로 공정이 번거롭게 되고 공기기간의 장기화를 초래하게 되며 공사비가 증가하게 되는 등 시공작업상 비효율적이라는 문제점이 있다.However, in a narrow place such as a river or a river, it is impossible to input a large lifting equipment that can carry a completed steel well, so that the steel well can be divided into several assemblies as much as possible weight and transported to the construction site. Will be installed. Therefore, such a conventional installation method has a problem that it is inefficient in construction work, such as the process is cumbersome and the air period is prolonged and the construction cost is increased by having to repeat several transport processes.

상기 문제점을 해결하고자 안출된 본 발명의 수중구조물의 강재우물통 설치공법은 하천이나 강가에서 강재우물통 공법 시공 시, 이미 육상에서 상당부분 가조립된 강재우물통을 하천이나 강가의 육상과 근접한 수상작업대에서 완조립하여 완전한 형태의 강재우물통을 형성한 뒤 부력(浮力)과 소규모의 인양장비를 이용하여 해상의 시공위치까지 용이하게 운반함으로써 운반공정의 횟수를 획기적으로 단축하고 공기를 절감할 수 있으며 시공성이 향상되는 수중구조물의 강재우물통 설치공법을 제공하는데 목적이 있다.The steel well barrel installation method of the underwater structure of the present invention devised to solve the above problems is completed when the steel well barrel construction method in rivers or rivers, the steel well barrels are already pre-assembled in a large portion on the water or near the river or river shores After forming a complete steel well, it can be easily transported to the construction position of the sea by using buoyancy and small lifting equipment, which can drastically reduce the number of transportation processes and save air, and improves the workability. The purpose is to provide a steel well installation method for underwater structures.

상기 목적을 달성하고자 하는 본 발명의 수중구조물의 강재우물통 설치공법은 (a) 하천이나 강가의 육상과 근접한 수상에서, 수면으로부터 해저를 향한 일정깊이까지 사석 정리한 후 수상에 케이싱파이프를 굴착시킨 뒤 상기 케이싱파이프 내부에 포스트파일을 삽입하여 해저 지반에 고정시키고 케이싱파이프는 인발하는 단계; (b) 상기와 같이 설치되는 다수개의 포스트파일과 포스트파일 사이 수면에 수상작업대를 설치하는 단계; (c) 상기 수상작업대 상부에서 바닥차수용 강재거푸집 및 이미 육상에서 상당부분 가조립된 강재우물통을 완조립하여 상기 수상작업대와 일체화시킨 뒤 강재우물통 내부의 하단부 일정높이까지 물을 유입시켜 수상작업대와 바닥차수용 강재거푸집 및 강재우물통을 수면 아래 사석정리 면까지 침하시키는 단계; (d) 상기 강재우물통 내부의 물을 양수처리하고 상기 바닥차수용 강재거푸집 및 강재우물통을 인상시켜 기초 설치위치로 이동시키는 단계; (e) 상기 바닥 차수용 강재거푸집을 제거하고, 강재우물통은 기초 설치위치에 정위치시킨 뒤 강재우물통에 콘크리트를 타설하는 단계; 및 (f) 상기 수상작업대를 수면으로 인상한 뒤 상기 (c) 내지 (e)단계를 반복하며 수상구조물의 기초를 형성하는 단계;를 포함한다.The steel well bucket installation method of the underwater structure of the present invention to achieve the above object is (a) after excavating the casing pipe in the water after arranging the sandstone to a certain depth from the water surface to the bottom of the river or the river, close to the land. Inserting a post pile into the casing pipe to fix it to the seabed and drawing the casing pipe; (b) installing a water platform on the water surface between the plurality of postfiles and postfiles installed as described above; (c) The steel formwork for bottom-ordering and the steel wells already assembled on the ground in the upper part of the above water work platform are completed and integrated with the water work platform, and then water is introduced into the lower part of the steel water tank to a certain height, so that the water work platform and the floor are in the bottom. Sinking the steel dies and the steel wells for the order down to the surface of the sand; (d) pumping the water in the steel well and raising the steel formwork and the steel well for the bottom order to move to the base installation position; (e) removing the steel formwork for the bottom order, placing the steel well at the foundation installation position and placing concrete in the steel well; And (f) raising the surface of the water platform to repeat the steps (c) to (e) to form the base of the water structure.

본 발명의 수중구조물의 강재우물통 설치공법은 기존의 하천이나 강가에서는 거대한 우물통 인양장비의 투입이 불가능하여 운반 가능한 무게만큼 우물통 본체를 다수 개로 분할하여 시공위치까지 여러 번 운반작업을 반복함으로써 강재우물통의 조립 및 시공이 가능하였던 것과는 달리 이미 육상에서 상당부분 조립된 강재우물통을 하천이나 강가의 육상과 근접한 수상작업대에서 완조립하여 완전한 형태의 강재우물통을 형성한 뒤 부력(浮力)과 소규모의 인양장비를 이용하여 해상의 시공위치까지 용이하게 운반함으로써 운반공정의 횟수를 획기적으로 단축하고 공기를 절감할 수 있으며 시공성이 향상되는 바, 이와 같은 구성에 의하여 상기한 본 발명의 기술적 과제를 달성할 수 있게 된다.Steel well installation method of the underwater structure of the present invention is not possible to put a huge well lifting equipment in the existing rivers or rivers by splitting the well body by a plurality of wells as much as the weight that can be transported by repeating the transport operation several times to the construction site Unlike the assembly and construction of the buckets, the steel wells, which have been largely assembled on the land, are assembled in a water platform close to the river or the river, forming a complete steel well and then buoyancy and small lifting Easily transported to the construction location of the sea by using the equipment can significantly shorten the number of transportation processes and reduce the air and improves the construction, it is possible to achieve the above technical problem of the present invention by such a configuration Will be.

이하 첨부한 도면과 함께 상기와 같은 본 발명의 개념이 바람직하게 구현된 실시예를 통하여 본 발명을 더욱 상세하게 설명한다. 다만 이는 이 기술 분야에서 통상의 지식을 가진 자가 본 발명을 더욱 명확하게 이해하고 용이하게 실시할 수 있도록 하기 위한 것이며, 전술한 사항들 이외에 본 발명이 가지는 또 다른 기술적 특징 및 장점들은 후술하는 본 발명에 따른 바람직한 실시예에 대한 설명을 통하여 당업자에게 더욱 확실하게 이해될 수 있을 것이다.Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings. However, this is intended to enable those of ordinary skill in the art to more clearly understand and easily implement the present invention, and other technical features and advantages of the present invention other than the foregoing are described below. It will be more clearly understood by those skilled in the art through the description of the preferred embodiment according to.

도 2a 내지 2h는 본 발명의 수중구조물의 강재우물통 설치공법의 시공공정을 순차적을 도시한 도면이고, 도 3은 도 2b의 'A'부분을 확대 도시한 도면이고, 도 4는 본 발명의 수중구조물의 강재우물통 설치공법의 포스트파일(110)을 도시한 도면이다.Figure 2a to 2h is a view showing a sequence of the construction process of the steel well bucket installation method of the underwater structure of the present invention, Figure 3 is an enlarged view 'A' portion of Figure 2b, Figure 4 is underwater of the present invention The figure shows the post pile 110 of the steel well installation method of a structure.

이하 첨부도면을 기준으로 본 발명의 수중구조물의 강재우물통 설치공법의 바람직한 실시예를 설명하면 다음과 같다.Hereinafter, a preferred embodiment of the steel well bucket installation method of the underwater structure of the present invention based on the accompanying drawings.

본 발명의 수중구조물의 강재우물통 설치공법은 하천이나 강가와 같이 시공장소가 협소하여 대규모의 인양장비 투입이 불가능한 곳에 적합한 공법으로써, 우선 도 2a에 도시된 바와 같이 육상과 근접한 수상에서 수면으로부터 해저를 향한 일정깊이까지 사석으로 정리한다.Steel well container installation method of the underwater structure of the present invention is a suitable method where a large amount of lifting equipment is impossible due to the narrow of the city plant, such as rivers and rivers, first, the seabed from the water surface in the water near the land as shown in Figure 2a Arrange it in the past to a certain depth.

이후 가이드 빔이 설치된 바지(barge)를 이용하여 수상에 케이싱파이프(100)를 해저 지반까지 굴착하고, 상기 케이싱파이프(100) 내부에 포스트파일(110)을 삽입하여 해저 지반에 고정시킨 뒤 케이싱파이프(100)를 인발한다. After excavating the casing pipe (100) to the sea floor using a barge (barge) is installed, the guide pipe is inserted into the casing pipe (100) by fixing the post pile 110 to the seabed ground and then the casing pipe Draw 100.

인발된 케이싱파이프(100)를 바지를 이용하여 다음 위치로 이동시킨 뒤 상기 작업을 반복하여 포스트파이프(110)를 설치한다. 이때 포스트파이프(110)는 육상과 가까운 곳에서부터 먼 곳 순으로 항타하며 설치한다. 또한 이때 상기와 같이 설치 되는 포스트파이프(110)는 도 4에 도시된 바와 같이 내부에 보강플레이트(111)가 설치되어 있어 내구성이 향상된다. The drawn casing pipe 100 is moved to the next position using the pants, and the above operation is repeated to install the postpipe 110. At this time, the postpipe 110 is installed while navigating in the order of distant place close to the land. In addition, at this time, the postpipe 110 installed as described above has a reinforcement plate 111 installed therein, as shown in FIG. 4, thereby improving durability.

이때 상기 포스트파일(110)은 후술되는 수상작업대(200)의 지지수단으로, 육상과 근접한 수상에 위치되어 굴착됨으로써 수상작업대(200) 또한 육상과 근접하여 설치되게 한다. 따라서 상기와 같이 설치되는 포스트파일(110)로 인해 수상작업대(200)는 육상에 위치된 인양장비(400)의 작업범위 내에 속하도록 위치됨으로써 후술되는 바와 같이 육상에서 이미 상당부분 가조립된 강재우물통(300)이 크레인과 같은 인양장비(400)로 운반 가능하게 되고 운반공정 횟수가 획기적으로 단축되어 공기가 절감되고 시공성이 향상되게 된다.At this time, the post pile 110 is a support means of the water work platform 200, which will be described later, is located in the water near the land and excavated so that the water work platform 200 is also installed close to the land. Therefore, due to the post pile 110 is installed as described above is located within the working range of the lifting equipment 400 is located on the land by the steel well barrel already assembled in a substantial portion as described later ( 300 can be transported to the lifting equipment 400, such as a crane and the number of times of the transport process is significantly shortened to reduce the air and improve the construction.

또한 이때 사용되는 인양장비(400)는 기존의 강재우물통 공법에서 사용되던 대규모의 인양장비보다 소규모의 것으로 하천이나 강가에 용이하게 투입이 가능한 소규모의 것이다.In addition, the lifting equipment 400 used at this time is smaller than that of the large-scale lifting equipment used in the existing steel well construction method and is a small one that can be easily introduced into a river or a river.

도 2b에 도시된 바와 같이 상기와 같이 설치되는 다수개의 포스트파일(110)과 포스트파일(110) 사이 수면에 수상작업대(200)를 설치한다. As shown in Figure 2b is installed on the water surface 200 between the plurality of post pile 110 and the post pile 110 is installed as described above.

이때 수상작업대(200)는 인양작업 시의 안전성을 고려하여 4등분으로 분할 제작된 수상작업대(200)를 설치하는 것이 바람직하다. 즉 크레인과 같은 인양장비(400)를 이용하여 인양작업을 시행할 때 4등분으로 분할된 수상작업대(200)는 보다 수월하게 시공위치로 이동시킬 수 있어 운반 및 취급이 용이하게 되고, 인양 시 안전성이 확보된다. At this time, it is preferable to install the water work platform 200, which is divided into four parts in consideration of the safety during lifting work. That is, when performing the lifting operation using the lifting equipment 400, such as a crane, the water platform 200 divided into four parts can be moved to the construction position more easily, so that it is easy to transport and handle, and safety when lifting This is secured.

또한 상기와 같은 4등분으로 나누어진 수상작업대(200)는 수상작업대(200) 조립체 하나 당 130톤의 부력을 감당하게 되고, 이러한 수상작업대(200) 조립체가 조립 설치됨으로써 하나의 수상작업대(200)를 이루게 된다. In addition, the water surface workbench 200 divided into four parts as described above is to bear the buoyancy of 130 tons per one of the water work platform 200 assembly, the water work platform 200 is assembled by the installation of one water work platform 200 Will be achieved.

또 상기와 같은 수상작업대(200) 내부에는 에어밸브와 에어 흡입구가 장착되어 있어 후술되는 바와 같이 수상작업대(200)를 인상할 경우 보다 손쉽게 수면으로 인상된다. 또한 도 3에 도시된 바와 같이 상기 수상작업대(200)에는 포스트파일(110)과 접하는 부분에 가이드롤러(210)가 부착되어 있어 포스트파일(110)의 외주면을 따라 수상작업대(200)가 보다 손쉽게 상하로 이동된다.In addition, since the air valve and the air suction port is mounted inside the above water work platform 200, when the water work platform 200 is raised as described below, the water surface is more easily raised. In addition, as shown in FIG. 3, the guide roller 210 is attached to the water pile 200 in contact with the post pile 110, so that the water bench 200 is more easily along the outer circumferential surface of the post pile 110. It is moved up and down.

도 2c에 도시된 바와 같이 상기 수상작업대(200) 상부에 바닥차수용 강재거푸집(310)을 설치하고 그 상부에 강재우물통(300)을 위치시킨다. As shown in FIG. 2C, the steel formwork 310 for bottom order is installed on the waterborne work platform 200, and the steel well barrel 300 is positioned at the upper portion thereof.

이때 상기 강재우물통(300)은 이미 육상에서 상당부분 가조립된 강재우물통(300)으로써 육상에 위치된 인양장비(400)로 인양되어 수상작업대(200) 상부에 위치된다. 따라서 기존의 하천이나 강가에서 대규모의 인양장비의 투입이 불가능하여 운반 가능한 무게만큼 우물통 본체를 다수 개로 분할하여 시공위치까지 여러 번 운반작업을 반복함으로써 강재우물통의 조립 및 시공을 행하였던 것과는 달리 이미 육상에서 상당부분 조립된 강재우물통(300)을 하천이나 강가의 육상과 근접한 수상작업대(200)에서 완조립하여 완전한 형태의 강재우물통(300)을 형성함으로써 운반공정의 횟수를 획기적으로 단축하고 공기를 절감한다.At this time, the steel well (300) is already lifted into the lifting equipment 400 located on the land as a steel well (300) that is prefabricated in a substantial portion of the land is located on the water work platform (200). Therefore, unlike the existing river or river, it is impossible to insert a large amount of lifting equipment, so that the main body of the well is divided into several parts by the weight that can be transported, and the transportation work is repeated several times until the construction position. By assembling the steel well (300) assembled in large part on the land in the water work platform (200) close to the river or river on the ground to form a complete steel well (300) by dramatically reducing the number of times of the transport process and air Save.

또한 상기와 같이 설치되는 강재우물통(300)은 수상작업대(200) 상부에서 완 조립되어 바닥차수용 강재거푸집(310)과 함께 고정와이어로 수상작업대(200)와 일체화된다. 이후 일체화된 수상작업대(200)와 바닥차수용 강재거푸집(310) 및 강재우물통(300)의 풍랑, 홍수 등 기타 외부 원인에 의한 전도 방지 및 안전성 확보를 위해 강재우물통(300) 내부의 하단부 일정높이까지 물을 유입시키고 상기 일체화된 수상작업대(200)와 바닥차수용 강재거푸집(310) 및 강재우물통(300)을 수면 아래 사석정리 면까지 침하시킨다. 따라서 전술된 바와 같은 강재우물통(300)은 부력(浮力)에 의해 보다 수월하게 수면에 부상하게 되며 전도 방지 및 안전성이 확보된다. In addition, the steel well 300 is installed as described above is fully assembled in the upper water work platform 200 is integrated with the water work platform 200 with a fixed wire together with the steel formwork 310 for the bottom order. Afterwards, the height of the lower part of the lower part of the steel well (300) in order to prevent falling and safety by other external causes such as the wind and flood of the steel work form (310) and the bottom-order steel formwork (310) and the steel well (300) Water is introduced into the sink to the integrated water surface workbench 200 and the bottom form steel formwork 310 and the steel well 300 to the bottom of the surface of the sandstone cleanup. Therefore, the steel well 300 as described above is more easily floated on the water surface by buoyancy (浮力) and the fall prevention and safety is secured.

또한 도면에 도시되지는 않았지만 상기 바닥차수용 강재거푸집(310)의 상단에는 강재우물통 받침대가 설치되어 있어 바닥차수용 강재거푸집(310)과 강재우물통(300) 사이가 견고하게 연결되며 어떠한 틈새도 발생되지 않아 차수성이 높게된다.In addition, although not shown in the drawing, the upper end of the steel sheet for the bottom order 310 is installed with a steel well pedestal so that the bottom between the steel formwork 310 and the steel well 300 is firmly connected and any gaps are generated. It is not high degree of ordering.

도 2d에 도시된 바와 같이 상기 강재우물통(300) 내부의 물을 양수처리하고 상기 바닥차수용 강재거푸집(310) 및 강재우물통(300)을 인상시켜 기초 설치위치로 이동시킨다. 이때 바닥차수용 강재거푸집(310) 및 강재우물통(300)을 이동시키는 인양장비(400)는 기존의 강재우물통 공법에서 필수적으로 요구되던 대규모의 인양장비 대신 하천이나 강가에 투입 가능한 소규모의 인양장비(400)로써, 이러한 소규모의 인양장비(400)와 부력(浮力)을 이용하여 보다 수월하게 상기 바닥차수용 강재거푸집(310) 및 강재우물통(300)을 기초 설치위치로 이동시킨다.As shown in FIG. 2d, the water inside the steel well 300 is pumped and the bottom form steel die 310 and the steel well 300 are raised to move to the basic installation position. At this time, the lifting equipment 400 for moving the floor order steel formwork 310 and the steel well barrel 300 is a small lifting equipment that can be put into a river or riverside instead of a large lifting equipment that was required by the existing steel well construction method. 400, by using the small lifting equipment 400 and buoyancy (바닥 浮 보다) to move the bottom order steel formwork 310 and the steel well 300 to the base installation position more easily.

도 2e에 도시된 바와 같이 상기 바닥차수용 강재거푸집(310)을 제거하고, 강재우물통(300)은 기초 설치위치에 배치시킨다. 이때 바닥차수용 강재거푸집(310)과 함께 강재우물통 받침대도 함께 제거된다. 이후 강재우물통(300)에 콘크리트를 타설하며 강재우물통(300) 침설에 따른 기초 위치를 측량하고 강재우물통(300)을 정위치하여 최종 침설한다.As shown in FIG. 2E, the bottom formwork steel formwork 310 is removed, and the steel well barrel 300 is disposed at a foundation installation position. At this time, along with the steel formwork for the bottom order 310 is also removed along the steel well base. Then, the concrete is poured into the steel well (300), the foundation position is measured according to the steel well (300) settled, and the steel well (300) is correctly positioned and finally settled.

도 2f에 도시된 바와 같이 수상작업대(200) 내부에 설치되어 있는 에어 흡입구에 공기를 투입하고 내부 물을 에어밸브를 이용하여 배출시키면서 상기 수상작업대(200)를 인상시킨다. 이때 상기 수상작업대(200)는 전술된 바와 같이 포스트파일(310)과 접하는 부분에 가이드롤러(210)가 부착되어 있어 포스트파일(110)의 외주면을 따라 수상작업대(200)가 보다 손쉽게 상하로 이동된다.As shown in FIG. 2F, air is introduced into the air suction port installed in the water platform 200, and the water platform 200 is raised while discharging the internal water using an air valve. At this time, the water work platform 200 is attached to the guide roller 210 in contact with the post pile 310 as described above, the water work platform 200 is moved up and down more easily along the outer circumferential surface of the post file 110 do.

전술된 바와 같이 수면으로 인상된 수상작업대(200) 상부에 바닥차수용 강재거푸집(310)을 설치하고 그 상부에 강재우물통(300)을 위치시켜 상기 공정을 반복함으로써 수상구조물의 기초를 형성한다.As described above, by installing the steel formwork 310 for the bottom order on the upper surface of the water work platform 200 raised to the water surface and by placing the steel well 300 on the upper portion of the water structure to form the basis of the water structure.

본 발명의 수중구조물의 강재우물통 설치공법은 기존의 하천이나 강가에서는 우물통을 인양할 수 있는 대규모의 인양장비의 투입이 불가능하여 운반 가능한 무게만큼 우물통 본체를 다수 개로 분할하여 시공위치까지 여러 번 운반작업을 반복 함으로써 강재우물통의 조립 및 시공이 가능하였던 것과는 달리 이미 육상에서 상당부분 조립된 강재우물통을 하천이나 강가의 육상과 근접한 수상작업대에서 완조립하여 완전한 형태의 강재우물통을 형성한 뒤 부력(浮力)과 하천이나 강가에 투입 가능한 소규모의 인양장비를 이용하여 해상의 시공위치까지 용이하게 운반함으로써 운반공정의 횟수를 획기적으로 단축하고 공기를 절감할 수 있으며 시공성이 향상되는 수중구조물의 강재우물통 설치공법을 제공하는데 효과가 있다.Steel well box installation method of the underwater structure of the present invention is not possible to put a large lifting equipment that can lift the well in the existing river or river banks by dividing the body of the well as many times as much as the weight that can be transported to the construction site several times Unlike the steel tanker, which was able to be assembled and constructed by repeating the transporting operation, the steel tanker, which was already assembled in large part on the land, was completely assembled in the water work platform close to the river or riverside to form a complete steel tank and then buoyancy ( By using small-scale lifting equipment that can be inserted into rivers and rivers or rivers, it can be easily transported to the construction site of the sea, thereby significantly reducing the number of transportation processes, saving air, and installing steel wells of underwater structures with improved construction. It is effective in providing the process.

Claims (4)

(a) 하천이나 강가의 육상과 근접한 수상에서, 수면으로부터 해저를 향한 일정깊이까지 사석 정리한 후 수상에 케이싱파이프를 굴착시킨 뒤 상기 케이싱파이프 내부에 포스트파일을 삽입하여 해저 지반에 고정시키고 케이싱파이프는 인발하는 단계;(a) In the water close to the river or river surface, after arranging the sandstone to a certain depth from the water surface to the seabed, excavate the casing pipe in the water, insert the post pile inside the casing pipe, and fix the casing pipe to the sea bed. The drawing step; (b) 상기와 같이 설치되는 다수개의 포스트파일과 포스트파일 사이 수면에 수상작업대를 설치하는 단계;(b) installing a water platform on the water surface between the plurality of postfiles and postfiles installed as described above; (c) 상기 수상작업대 상부에서 바닥차수용 강재거푸집 및 이미 육상에서 상당부분 가조립된 강재우물통을 완조립하여 상기 수상작업대와 일체화시킨 뒤 강재우물통 내부의 하단부 일정높이까지 물을 유입시켜 수상작업대와 바닥차수용 강재거푸집 및 강재우물통을 수면 아래 사석정리 면까지 침하시키는 단계;(c) The steel formwork for bottom-ordering and the steel wells already assembled on the ground in the upper part of the above water work platform are completed and integrated with the water work platform, and then water is introduced into the lower part of the steel water tank to a certain height, so that the water work platform and the floor are in the bottom. Sinking the steel dies and the steel wells for the order down to the surface of the sand; (d) 상기 강재우물통 내부의 물을 양수처리하고 상기 바닥차수용 강재거푸집 및 강재우물통을 인상시켜 기초 설치위치로 이동시키는 단계;(d) pumping the water in the steel well and raising the steel formwork and the steel well for the bottom order to move to the base installation position; (e) 상기 바닥차수용 강재거푸집을 제거하고, 강재우물통은 기초 설치위치에 정위치시킨 뒤 강재우물통에 콘크리트를 타설하는 단계; 및 (e) removing the steel formwork for the bottom order, placing the steel well at the foundation installation position and placing concrete in the steel well; And (f) 상기 수상작업대를 수면으로 인상한 뒤 상기 (c) 내지 (e)단계를 반복하며 수상구조물의 기초를 형성하는 단계;(f) raising the surface of the water platform to repeat the steps (c) to (e) and forming the base of the water structure; 를 포함하는 수중구조물의 강재우물통 설치공법.Steel well installation method of the underwater structure including a. 제1항에서, 상기 수상작업대 내부에는 에어밸브와 에어 흡입구가 장착되어 있고, 상기 수상작업대는 포스트파일과 인접하는 부분에 가이드롤러가 설치되어 있는 것을 특징으로 하는 수중구조물의 강재우물통 설치공법.The method of claim 1, wherein an air valve and an air inlet are mounted in the water work platform, and the water work platform is provided with a guide roller at a portion adjacent to the post pile. 제1항에서, 상기 바닥차수용 강재거푸집 상단에는 강재 우물통받침대가 설치되어 있고, 상기 강재 우물통받침대는 (e)단계에서 바닥차수용 강재거푸집과 함께 제거되는 것을 특징으로 하는 수중구조물의 강재우물통 설치공법.The steel well of the underwater structure of claim 1, wherein a steel well bucket stand is installed at an upper end of the bottom order steel formwork, and the steel well support is removed together with the bottom order steel formwork in step (e). Bucket installation method. 제1항에서, 상기 포스트파일 내부에는 보강플레이트가 설치된 것을 특징으로 하는 수중구조물의 강재우물통 설치공법.The method of claim 1, wherein the reinforcement plate is installed inside the post pile.
KR1020050042292A 2005-05-20 2005-05-20 Open caisson construction method for the structures constructed over the water KR100567738B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050042292A KR100567738B1 (en) 2005-05-20 2005-05-20 Open caisson construction method for the structures constructed over the water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050042292A KR100567738B1 (en) 2005-05-20 2005-05-20 Open caisson construction method for the structures constructed over the water

Publications (1)

Publication Number Publication Date
KR100567738B1 true KR100567738B1 (en) 2006-04-04

Family

ID=37180237

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050042292A KR100567738B1 (en) 2005-05-20 2005-05-20 Open caisson construction method for the structures constructed over the water

Country Status (1)

Country Link
KR (1) KR100567738B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020081530A (en) * 2001-04-18 2002-10-28 동부엔지니어링 주식회사 Well form for the base operation of pier and it's operation method
KR20030021833A (en) * 2001-09-08 2003-03-15 (주)청호종합기술단 Land-side protection wall of steel for well form case operation of bridge base part and it's operation method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020081530A (en) * 2001-04-18 2002-10-28 동부엔지니어링 주식회사 Well form for the base operation of pier and it's operation method
KR20030021833A (en) * 2001-09-08 2003-03-15 (주)청호종합기술단 Land-side protection wall of steel for well form case operation of bridge base part and it's operation method

Similar Documents

Publication Publication Date Title
US9567720B2 (en) Offshore platform for a marine environment
JP5057223B2 (en) Temporary wall construction method using steel segments
JP6010070B2 (en) Temporary closing method for existing underwater structures
EP3118374A1 (en) Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
CN108179735A (en) A kind of boulder bed large-sized deep water foundation construction platform and method
KR100714179B1 (en) Concrete Well Construction Method Using Weight Reducing Method and Concrete Well Thereof
CN113737780A (en) Underwater rock-socketed concrete pile and construction method thereof
KR100383409B1 (en) Construction Method of Direct Foundation for using Caisson
KR101256274B1 (en) Reverse Drill Method With precast type Caisson and Jacket
KR20110107888A (en) Construction method of the pier without the temporary dam in the sea or the river
AU2012313196B2 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
WO2016109962A1 (en) Construction method for fixing offshore marine platform to a seabed having layers of a soil/clay nature
CN111794256A (en) Construction method of underwater pile cap in river flood discharge area
CN111691447A (en) Slow sinking type caisson construction method for reducing load of immersed tube tunnel tube top
CN111827130A (en) Construction method of water bridge pile foundation and bearing platform without trestle
US3091937A (en) Underwater foundation structure and method therefor
KR100768552B1 (en) steel well foundation construction and equipment
KR101117927B1 (en) Construction method of marine structure
KR100567738B1 (en) Open caisson construction method for the structures constructed over the water
KR100418268B1 (en) Well form bucket of division style for the base operation of pier and it&#39;s operation method
KR100403641B1 (en) Operation method of well form bucket of one style for the base operation of pier
US2935854A (en) Offshore drilling platform
CN109629587B (en) Steel caisson pile body structure for bank abrupt slope and construction method

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20100329

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee