KR101117927B1 - Construction method of marine structure - Google Patents

Construction method of marine structure Download PDF

Info

Publication number
KR101117927B1
KR101117927B1 KR1020110104977A KR20110104977A KR101117927B1 KR 101117927 B1 KR101117927 B1 KR 101117927B1 KR 1020110104977 A KR1020110104977 A KR 1020110104977A KR 20110104977 A KR20110104977 A KR 20110104977A KR 101117927 B1 KR101117927 B1 KR 101117927B1
Authority
KR
South Korea
Prior art keywords
bracket
installing
installation step
installation
slab
Prior art date
Application number
KR1020110104977A
Other languages
Korean (ko)
Inventor
허두홍
Original Assignee
현대건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대건설주식회사 filed Critical 현대건설주식회사
Priority to KR1020110104977A priority Critical patent/KR101117927B1/en
Application granted granted Critical
Publication of KR101117927B1 publication Critical patent/KR101117927B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0039Methods for placing the offshore structure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0056Platforms with supporting legs

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

PURPOSE: A marine structure construction method is provided to reduce construction time and costs by making a working condition like land. CONSTITUTION: A marine structure construction method is as follows. A plurality of supporting pile is established in the submarine ground. The bottom bracket is established on the lower part of the supporting pile(S22). A top bracket is established in the upper of the bottom bracket(S23). The structure is established on the upper side of the top bracket in order to be exposed to sea water. The structure is up pulled and to remove the top bracket. The top end portion of the structure is settled on the lower bracket which is exposed to sea water.

Description

해상구조물 가설 공법{Construction method of marine structure} Construction method of marine structure

본 발명은 해상구조물 가설 공법에 관한 것으로서, 보다 상세하게는 해상에 구조물을 설치하기 위한 공법에 있어서, 해저 지반에 복수개의 지지파일을 설치하는 파일 설치 단계와, 상기 지지파일의 하부에 하부브라켓을 설치하고, 상기 하부브라켓의 상측에 상부브라켓을 설치하는 브라켓 설치 단계와, 상기 구조물이 해상에 노출되도록 상기 상부브라켓의 상측에 상기 구조물을 설치하는 구조물 설치 단계와, 상기 구조물을 인양하고 상기 상부브라켓을 제거하여 상기 구조물의 상단부가 해상 위로 노출된 상태로 상기 하부브라켓에 안착시키는 인양 및 안착 단계를 포함하여, 구조물의 운반, 진수를 위한 대형 장비가 불필요하고 육상 건설과 같은 환경을 조성함으로써 비용을 절감, 작업 효율 증대 및 공사 기간을 단축할 수 있는 해상구조물 가설 공법에 관한 것이다.The present invention relates to a construction method for constructing an offshore structure, and more particularly, in a construction method for installing a structure on an offshore, a pile installation step of installing a plurality of support piles on a seabed, and a lower bracket under the support pile. And installing a bracket for installing the upper bracket on the upper side of the lower bracket, and installing the structure on the upper side of the upper bracket so that the structure is exposed to the sea, and lifting the structure and lifting the upper bracket. Including the lifting and seating step of seating on the lower bracket with the upper end of the structure exposed to the sea by removing the structure, large equipment for transporting and launching the structure is unnecessary, and the environment is reduced by creating an environment such as land construction. Construction of offshore structures to increase work efficiency and shorten construction period Relate to.

일반적으로, 해상에 구조물을 설치하는 공법으로는 가물막이 공사 후 구조물을 시공하는 방법과, 구조물을 육상에서 제작하고 운반 후에 해상에 설치하는 방법이 주로 사용되었다.In general, as a method of installing a structure on the sea, a method of constructing a structure after construction of a temporary curtain and a method of manufacturing the structure on land and installing it on the sea after transportation are mainly used.

전자의 가물막이를 이용한 공법은, 수면 이하의 건식 공사 구역을 확보하기 위한 임시구조물로서, 토석 또는 시트파일 등으로 공사 구역을 포위하는 차수벽 형태의 구조물을 구축한 후 내부의 물을 제거한 후 구조물을 설치하는 방법이다.The construction method using the former temporary barrier is a temporary structure to secure the dry construction area below the water surface, and after constructing the structure of the order wall that surrounds the construction area with earth or sheet pile, etc. How to install.

하지만, 상기의 방법은 가물막이 공사를 위한 비용이 과다하게 소요되며, 작업장 내로 침투수가 유입되어 작업성 저하 및 양수 비용이 추가적으로 발생하게 되고, 가물막이 공사를 위한 시공기간이 추가로 발생하게 된다. 또한, 가물막이 특성상 작업공간이 협소하게 되어 작업성이 저하되는 단점이 있다.However, the above method is excessively expensive for the construction of the temporary curtain, infiltration water flows into the workplace, the workability and pumping costs are additionally generated, and the construction period for the temporary curtain construction is additionally generated. In addition, there is a disadvantage that the work space is narrowed due to the nature of the temporary film, the workability is reduced.

한편, 구조물을 육상에서 제작하고 운반 후에 해상에 설치하는 방법은 주로 대형 해상 크레인선을 이용하여 구조물을 들어서 설치하는 권양 공법을 사용하여 왔다.On the other hand, the method of manufacturing the structure onshore and installed on the sea after transport has mainly used the hoisting method of lifting and installing the structure using a large offshore crane ship.

그러나, 크레인에 의한 권양공법은 크레인의 권양 능력 및 크레인선의 해상 작업조건 즉, 계류장치를 위한 공간 확보, 수심, 날씨 해류에 의한 조건 등에 영향을 크게 받고 구조물의 크기 및 중량에 제한이 있었다. However, the hoisting method by the crane was greatly influenced by the hoisting capacity of the crane and the offshore working conditions of the crane ship, that is, the space for mooring, depth, weather currents, and the like, and the size and weight of the structure were limited.

또한, 시공의 안정성 또한 충분히 확보되지 못하여 구조물 제작시, 크레인의 권양 능력에 맞추어 소규모의 블록으로 제작 후 현장에서 연결 작업을 해야 하므로 많은 비용이 발생되고, 블록간 누수가 발생하며, 초중량 구조물 취급에 따른 작업 위험 부담이 증가되었다.In addition, the stability of construction is not secured enough, so when manufacturing the structure, it is necessary to make a small block in accordance with the lifting capacity of the crane, so that the connection work in the field is incurred a lot of costs, leaks between blocks, and handling super-heavy structures The increased risk of work incurred.

또한, 경우에 따라 2대의 크레인을 조합하여 복합 권양하는 경우 선단의 계류장치간의 간섭 방지를 위해 더욱 충분한 작업공간이 필요하고, 시공의 정밀도가 요구되며, 시공의 안정성 또한 충분히 확보되지 못하는 문제점이 발생하였다.In addition, in some cases, a combination of two cranes in combination hoisting requires a more sufficient working space to prevent interference between the mooring devices of the tip, construction accuracy is required, and construction stability is also not secure enough It was.

특히, 수심이 얕은 곳에서 해상 크레인선을 이용하는 경우 동원되는 해상 장비의 작업성과 안정성을 확보하기 위하여 대규모 준설 작업이 필요하게 되어, 공사 기간이 길어지고 비용이 증가되는 문제점이 있다.In particular, when using the offshore crane ship in a shallow depth of water is required a large dredging work to ensure the workability and stability of the mobilized offshore equipment, there is a problem that the construction period is long and the cost is increased.

대한민국 등록특허공보 10-0658882 (2006.12.11) "해상구조물 설치공법 및 그 장치"Republic of Korea Patent Publication 10-0658882 (2006.12.11) "Marine structure installation method and its device"

따라서, 본 발명의 목적은 이와 같은 종래의 문제점을 해결하기 위한 것으로서, 해저 지반에 고정된 지지파일에 설치된 브라켓의 상측에 가시설을 시공하여 구조물을 건설함으로써, 육상과 같은 작업 조건을 조성하여 작업 효율 증대 및 공사 기간을 단축할 수 있는 해상구조물 가설 공법을 제공함에 있다.Therefore, an object of the present invention is to solve such a conventional problem, by constructing a structure by constructing a temporary facility on the upper side of the bracket installed on the support pile fixed to the seabed ground, to create a working condition such as land, work efficiency To provide a construction method for offshore structures that can increase and shorten the construction period.

또한, 해상 위의 가시설에서 구조물을 제작하고 승강부를 이용하여 수중에 설치된 하부브라켓에 단순히 안착시켜 시공하므로 육상제작이 불필요하게 되어 공사기간이 단축되며, 해상 운반을 위한 비용을 절감할 수 있는 해상구조물 가설 공법을 제공함에 있다.In addition, since the structure is manufactured at the temporary facility on the sea and is simply mounted on the lower bracket installed in the water by using the lifting part, it is unnecessary to make the on-shore production, thus shortening the construction period and reducing the cost for sea transport. To provide a hypothesis.

상기 목적은, 본 발명에 따라, 해상에 구조물을 설치하기 위한 공법에 있어서, 해저 지반에 복수개의 지지파일을 설치하는 파일 설치 단계;와, 상기 지지파일의 하부에 하부브라켓을 설치하고, 상기 하부브라켓의 상측에 상부브라켓을 설치하는 브라켓 설치 단계;와, 상기 구조물이 해상에 노출되도록 상기 상부브라켓의 상측에 상기 구조물을 설치하는 구조물 설치 단계;와, 상기 구조물을 인양하고 상기 상부브라켓을 제거하여 상기 구조물의 상단부가 해상 위로 노출된 상태로 상기 하부브라켓에 안착시키는 인양 및 안착 단계;를 포함하는 것을 특징으로 하는 해상구조물 가설 공법에 의해 달성된다.The object is, according to the present invention, in the construction method for installing the structure on the sea, pile installation step of installing a plurality of support piles on the seabed ground; And, install a lower bracket on the lower portion of the support pile, the lower Bracket installation step of installing the upper bracket on the upper side of the bracket; And, Installing the structure to install the structure on the upper side of the upper bracket so that the structure is exposed to the sea; And, lifting the structure to remove the upper bracket Lifting and seating step of seating on the lower bracket with the upper end of the structure exposed over the sea; is achieved by the offshore structure construction method comprising a.

또한, 상기 브라켓 설치 단계는 상기 하부브라켓이 상기 구조물의 하면을 지지하도록 높낮이를 조절하여 상기 하부브라켓을 설치하는 하부브라켓 설치 단계;와, 동일한 높이로 상기 상부브라켓을 설치하는 상부브라켓 설치 단계;를 포함하는 것이 바람직하다.In addition, the bracket installation step is a lower bracket installation step of installing the lower bracket by adjusting the height so that the lower bracket supports the lower surface of the structure; and, an upper bracket installation step of installing the upper bracket to the same height; It is preferable to include.

또한, 상기 브라켓 설치 단계는 상기 지지파일의 상기 하부브라켓 설치 위치에 기중화탱크를 설치하고 내부의 해수를 배출하여 상기 하부브라켓을 설치하기 위한 상태를 조성하는 기중화탱크 설치단계;와, 상기 구조물 안착시 밀착하여 해수의 유입을 방지하도록 상기 하부브라켓의 상면에 방수부재를 설치하는 방수부재 설치 단계;를 더 포함하는 것이 바람직하다.In addition, the bracket installation step is the air tank installation step of installing the air tank in the lower bracket installation position of the support pile and discharge the seawater inside to establish a state for installing the lower bracket; and, the structure It is preferable to further include a; waterproofing member installation step of installing a waterproofing member on the upper surface of the lower bracket in close contact to prevent the inflow of sea water.

또한, 상기 구조물 설치 단계 이전에 상기 상부브라켓의 상측에 해상에서 상기 구조물을 설치하기 위한 수상 공간을 제공하는 가시설을 설치하는 가시설 설치 단계;를 더 포함하고, 상기 구조물은 상기 가시설의 상측에 설치되는 것이 바람직하다.The apparatus may further include: installing a temporary facility to provide a water space for installing the structure at sea on the upper side of the upper bracket prior to the installation of the structure; wherein the structure is installed on the upper side of the temporary facility It is preferable.

또한, 상기 가시설은 수상에서의 작업공간을 제공하는 작업대와, 상기 작업대의 상면에 설치되어 상기 구조물의 하면이 상기 하부브라켓에 정합되도록 상기 구조물의 하부 형상을 형성하는 거푸집을 포함하는 것이 바람직하다.In addition, the temporary facility preferably includes a workbench for providing a work space in the water and the formwork is formed on the upper surface of the workbench to form a lower shape of the structure so that the lower surface of the structure is matched to the lower bracket.

또한, 상기 구조물 설치 단계는 상기 가시설의 상부에 상기 구조물의 기초가 되는 하부구조물의 기초슬래브와 내부 공간을 구획하는 벽체를 설치하는 하부구조물 설치 단계;와, 상기 기초슬래브 설치시 상기 하부구조물을 인양하기 위한 앵커를 설치하는 앵커 설치 단계;를 포함하는 것이 바람직하다.In addition, the step of installing the structure is a substructure installation step of installing a wall for partitioning the internal slab and the base slab of the substructure that is the foundation of the structure on the upper portion of the temporary installation; and, when installing the foundation slab lifting the substructure It is preferable to include; anchor installation step of installing an anchor for.

또한, 상기 구조물 설치 단계 이후에 상기 복수 개의 지지파일 상단부를 연결하는 지지부재와, 상기 지지부재와 상기 구조물 사이에 설치되는 승강부를 설치하는 승강부 설치 단계;를 실시하는 것이 바람직하다.In addition, the lifting unit installation step of installing a support member for connecting the upper end of the plurality of support piles and the support member and the structure is installed after the structure installation step; preferably.

또한, 상기 인양 및 안착 단계 이후에 상기 하부구조물 내에 유입된 해수를 배출하는 해수 배출 단계;와, 상기 지지파일과 상기 기초슬래브 사이에 충진재를 충진하는 충진 단계;와, 상기 하부브라켓 상부에 안착된 상기 하부구조물을 고정하여 부력에 의한 유동을 방지하도록 상기 기초슬래브 상부의 상기 지지파일에 고정브라켓을 설치하는 고정브라켓 설치 단계;로 구성되는 하부구조물 고정 단계를 더 포함하는 것이 바람직하다.In addition, the seawater discharge step of discharging the seawater introduced into the lower structure after the lifting and seating step; and a filling step of filling the filler between the support pile and the foundation slab; And, seated on the upper bracket It is preferable to further include a substructure fixing step consisting of; a fixing bracket installation step of installing a fixing bracket on the support pile of the upper part of the foundation slab to prevent the flow by buoyancy by fixing the lower structure.

또한, 상기 하부구조물 고정 단계를 상기 벽체에 의하여 구획된 상기 하부구조물의 내부에서 외부 순서로 구획된 공간마다 각각 실시하는 것이 바람직하다.In addition, the step of fixing the substructure is preferably performed for each space partitioned in the outer order in the interior of the substructure partitioned by the wall.

또한, 상기 하부구조물 고정 단계 이후에 상기 지지부재 및 상기 승강부를 제거하고 상기 기초슬래브 상부로 노출되는 상기 지지파일을 절단하는 철거 단계;를 더 포함하는 것이 바람직하다.The demolition step of removing the support member and the elevating part after the fixing the lower structure and cutting the support pile exposed to the upper part of the foundation slab may be further included.

또한, 상기 철거 단계 이후에 상기 기초슬래브 및 상기 고정브라켓의 상부를 매립하는 하부슬래브를 설치하는 하부슬래브 설치 단계;를 더 포함하는 것이 바람직하다.In addition, the lower slab installation step of installing a lower slab to bury the upper portion of the base slab and the fixing bracket after the demolition step; preferably further comprises a.

또한, 상기 하부슬래브 설치 단계 이후에 상기 하부구조물의 상부에 상부구조물을 설치하는 상부구조물 설치단계;를 더 포함하는 것이 바람직하다.
In addition, after the lower slab installation step, the upper structure installation step of installing the upper structure on top of the lower structure; preferably further comprises a.

본 발명에 따르면, 해저 지반에 고정된 지지파일에 설치된 브라켓의 상측에 가시설을 시공하여 구조물을 건설함으로써, 육상과 같은 작업 조건을 조성하여 작업 효율 증대 및 공사 기간을 단축할 수 있는 해상구조물 가설 공법이 제공된다.According to the present invention, by constructing a temporary structure on the upper side of the bracket installed on the support pile fixed to the seabed ground, construct the structure, the construction of offshore structures that can increase the work efficiency and shorten the construction period by creating working conditions such as onshore This is provided.

또한, 해상 위의 가시설에서 구조물을 제작하고 승강부를 이용하여 수중에 설치된 하부브라켓에 단순히 안착시켜 시공하므로 육상제작이 불필요하게 되어 공사기간이 단축되며, 해상 운반을 위한 비용을 절감할 수 있는 해상구조물 가설 공법이 제공된다.In addition, since the structure is manufactured at the temporary facility on the sea and is simply mounted on the lower bracket installed in the water by using the lifting part, it is unnecessary to make the on-shore production, thus shortening the construction period and reducing the cost for sea transport. Hypothesis techniques are provided.

도 1은 본 발명 해상구조물 가설 공법의 흐름도이고,
도 2 내지 도 14는 본 발명 해상구조물 가설 공법의 시공 방법을 나타낸 도면이다.
1 is a flow chart of the present invention marine structure construction method,
2 to 14 is a view showing a construction method of the marine structure construction method of the present invention.

설명에 앞서, 동일한 구성을 가지는 구성요소에 대해서는 동일한 부호를 사용하여 대표적으로 일실시예에서 설명하기로 한다.Prior to the description, components having the same configuration will be representatively described in one embodiment using the same reference numerals.

이하, 첨부한 도면을 참조하여 본 발명의 일실시예에 따른 해상구조물 가설 공법에 대하여 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail with respect to the offshore structure construction method according to an embodiment of the present invention.

도 1은 본 발명 해상구조물 가설 공법의 흐름도이고, 도 2 내지 도 13은 본 발명 해상구조물 가설 공법의 각 단계별 시공 방법을 나타낸 도면이다.1 is a flow chart of the marine structure construction method of the present invention, Figures 2 to 13 are views showing the construction method for each step of the marine structure construction method of the present invention.

도 1을 참조하면, 본 발명에 따른 해상구조물 가설 공법은 파일 설치 단계(S10)와, 브라켓 설치 단계(S20)와, 가시설 설치 단계(S30)와, 구조물 설치 단계(S40)와, 승강부 설치 단계(S50)와, 인양 및 안착 단계(S60)와, 하부구조물 고정 단계(S70)와, 철거 단계(S80)와, 하부슬래브 설치 단계(S90)와, 상부구조물 설치 단계(S100)를 포함하여 구성된다.Referring to Figure 1, the construction method for offshore structures according to the present invention, pile installation step (S10), bracket installation step (S20), temporary installation step (S30), structure installation step (S40), lifting unit installation Including the step (S50), lifting and mounting step (S60), the lower structure fixing step (S70), the dismantling step (S80), the lower slab installation step (S90), the upper structure installation step (S100) It is composed.

본 발명은 건축물을 해상에 건설하기 위하여 건축물의 기초가 되는 구조물을 가설하기 위한 방법에 관한 것으로서, 도 15를 참조하면 본 실시예에 따른 구조물은 수중 내에 설치되어 기초가 되는 하부구조물(10)과, 하부구조물(10)의 상부에 설치되어 해수면 위로 노출되는 상부구조물(20)로 구성된다.
The present invention relates to a method for constructing a structure that is a foundation of a building to build a building on the sea, referring to FIG. 15, the structure according to the present embodiment is installed in the water and is the foundation 10 and the foundation. The upper structure 20 is installed on the lower structure 10 and is exposed to the sea level.

도 2를 참조하면, 파일 설치 단계(S10)는 해저 지반에 구조물의 자중을 지지하는 복수 개의 지지파일(31)을 해상 항타기를 이용하여 항타하는 단계로서, 구조물이 설치될 위치 및 파일의 항타 위치를 측량한 후 설계 위치에 복수 개의 지지파일(31)을 일단은 해저 지반에 고정되고 타단은 해수면 위로 노출되도록 항타하여 설치하며, 설치 후에는 지지력, 연직도 및 파일 위치 확인 평가를 통하여 안정성을 검사하는 것이 바람직하다.Referring to Figure 2, the pile installation step (S10) is a step of driving a plurality of support piles 31 for supporting the self-weight of the structure on the seabed using the sea helm, the position where the structure is to be installed and the driving position of the pile After surveying, install a plurality of support piles 31 at the design position to be fixed to the seabed ground and the other end to be exposed to the sea level.After installation, the stability is checked through the evaluation of bearing capacity, verticality and pile position check. It is desirable to.

한편, 본 실시예에서 지지파일(31)은 강관을 사용하며, 항타 후에는 지지파일(31)의 소정 위치에 지지파일(31)의 부식을 방지하는 방식부재(32)를 설치하여 지지파일의 부식을 방지한다.
On the other hand, in the present embodiment, the support pile 31 uses a steel pipe, and after driving, the anticorrosive member 32 is installed at a predetermined position of the support pile 31 to prevent corrosion of the support pile 31. Prevent corrosion.

브라켓 설치 단계(S20)는 지지파일의 하부브라켓(41) 설치 위치에 기중화탱크(40)를 설치하고 해수를 배출하는 기중화탱크 설치 단계(S21)와, 지지파일(31)의 하부에 하부브라켓(41)을 설치하는 하부브라켓 설치 단계(S22)와, 하부브라켓(41)의 상면에 방수부재(42)를 설치하는 방수부재 설치 단계(S23)와, 지지파일(31)의 상부에 상부브라켓(43)을 설치하는 상부브라켓 설치 단계(S24)를 포함하여 구성된다.Bracket installation step (S20) is installed in the tank mounting tank (40) in the lower bracket (41) installation position of the support pile and the tank tank installation step (S21) for discharging sea water, and the lower portion of the support pile 31 Lower bracket installation step (S22) for installing the bracket 41, waterproof member installation step (S23) for installing the waterproof member 42 on the upper surface of the lower bracket 41, and the upper portion of the support pile 31 It is configured to include an upper bracket installation step (S24) for installing the bracket (43).

도 3을 참조하면, 기중화탱크 설치 단계(S21)는 수중에 위치하는 하부브라켓(41)의 설치 위치에 기중화탱크(40)를 설치하고 해수를 배출하여 하부브라켓(41)을 용이하게 설치하기 위한 환경을 조성하는 단계이다.Referring to Figure 3, the tank installation step (S21) is installed in the tank mounting tank 40 in the installation position of the lower bracket 41 located in the water and discharge the sea water to easily install the lower bracket (41) It is a step to create an environment for doing so.

기중화탱크(40)는 원통형으로 제작되어 하부가 하부브라켓(41)의 설치 위치보다 낮은 위치에 설치되고 수면 위로 노출되도록 설치되며, 기중화탱크(40)와 지지파일(31) 사이에는 고무 재질의 차수부재(미도시)가 설치되어 해수의 유입을 방지한다.Lifting tank 40 is made of a cylindrical shape is installed so that the lower portion is installed at a lower position than the lower bracket (41) installation position and exposed over the water surface, rubber material between the tank and the support pile (31) The order member (not shown) is installed to prevent the inflow of sea water.

따라서, 기중화탱크(40) 내부의 해수를 배출하고 해수의 유입을 방지함으로써, 하부브라켓(41)을 수중에서 설치하지 않고, 기중화탱크(40) 내부에서 작업을 함으로써 용이하게 하부브라켓(41)을 설치할 수 있다.Therefore, by discharging the seawater inside the air tank 40 and preventing the inflow of sea water, the lower bracket 41 can be easily operated by working in the air tank 40 without installing the lower bracket 41 in the water. ) Can be installed.

도 4를 참조하면, 하부브라켓 설치 단계(S22)는 하부구조물(10)의 하면이 하부브라켓(41)에 안착되도록, 하부구조물(10)의 하면 형상에 따라 하부브라켓(41)의 설치 높낮이를 조절하여 지지파일(31)에 설치하는 단계이다.Referring to Figure 4, the lower bracket installation step (S22) is to install the height of the lower bracket 41 according to the shape of the lower surface of the lower structure 10, so that the lower surface of the lower structure 10 is seated on the lower bracket (41). The adjustment step is to install on the support pile (31).

도 6에 도시된 바와 같이, 본 실시예에서는 하부구조물(10)의 하면의 형상과 대응하도록 하부브라켓(41)의 설치 높낮이를 달리하여 설치된다.As shown in FIG. 6, in this embodiment, the height of the lower bracket 41 is differently installed so as to correspond to the shape of the lower surface of the lower structure 10.

방수부재 설치 단계(S23)는 하부브라켓(41)의 상면에 하부구조물(10) 안착시 지지파일(31)과 하부구조물(10) 사이의 공간으로 해수가 침투하는 것을 방지하도록 방수부재(42)를 설치하는 단계로서, 본 실시예에서 방수부재(42)는 소정 두께의 고무패드가 사용되며, 설치된 하부브라켓(41)의 상면에 방수부재(42)를 안착시켜 설치한다.Waterproof member installation step (S23) is a waterproof member 42 to prevent seawater from penetrating the space between the support pile 31 and the lower structure 10 when the lower structure 10 is seated on the upper surface of the lower bracket (41). As a step of installing the waterproof member 42 in this embodiment, a rubber pad of a predetermined thickness is used, and is installed by mounting the waterproof member 42 on the upper surface of the lower bracket 41 installed.

한편, 방수부재 설치 단계(S23)가 완료된 후에는, 설치된 기중화탱크(40)를 철거한다.On the other hand, after the waterproofing member installation step (S23) is completed, the installed tank 20 is removed.

상부브라켓 설치 단계(S24)는 해수면 위로 노출된 지지파일(31)의 상부에 철거 가능하도록 상부브라켓(43)을 지지파일(31)에 볼트로 결합하여 설치하는 단계이다.The upper bracket installation step (S24) is a step of coupling the upper bracket 43 to the support pile 31 by bolts so as to be dismantled on the upper portion of the support pile 31 exposed to the sea level.

이때, 상부브라켓(43)은 후술하는 가시설(50)이 해상 위에 설치되도록 해수면 위에 설치되는 것이 바람직하다.
At this time, the upper bracket 43 is preferably installed on the sea surface so that the temporary facility 50 to be described later is installed on the sea.

가시설 설치 단계(S30)는 상부브라켓(43)의 상부에 가시설(50)을 설치하여 수상 작업 공간을 마련하는 단계로서, 작업대 설치 단계(S31)와 거푸집 설치 단계(S32)를 포함하여 구성된다.The provisional installation step (S30) is a step of providing a temporary work space by installing the provisional facility 50 on the upper bracket 43, it comprises a worktable installation step (S31) and formwork installation step (S32).

도 5를 참조하면, 작업대 설치 단계(S31)는 해상 작업 공간을 제공하는 작업대(51)를 설치하는 단계로서, 복수 개의 지지파일(31)에 설치된 각각의 상부브라켓(43)의 상면에 메인빔(52)을 볼트로 고정하여 설치하고, 메인빔(52)의 상면에 메인빔(52)과 교차하도록 크로스빔(53)을 볼트로 고정하여 설치하며, 크로스빔(53)의 상면에 지지목재(54)를 소정 간격으로 복수개 배치한 후, 지지목재(54)의 상면에 바닥재(55)를 설치한다.Referring to Figure 5, the work table installation step (S31) is a step of installing a work platform 51 for providing a marine work space, the main beam on the upper surface of each upper bracket 43 installed in the plurality of support piles 31 (52) is fixed to the bolts, and installed on the top surface of the main beams 52 to fix the cross beams 53 with bolts so as to intersect with the main beams 52, the support wood on the top surface of the cross beams (53) After arranging a plurality of 54 at predetermined intervals, the floor 55 is provided on the upper surface of the support timber 54.

따라서, 상술한 바와 같이 해상 위에 작업대(51)을 설치함으로써, 육상과 같은 작업 환경이 조성되어 작업 효율이 증대되고, 공사기간이 단축되는 효과가 있다.Therefore, as described above, by installing the work bench 51 on the sea, a work environment such as onshore is created to increase work efficiency and shorten the construction period.

본 실시예에서 메인빔(52) 및 크로스빔(53)은 H형강이 사용되며, 바닥재(55)는 합판이 사용되나, 이에 제한되는 것은 아니다.In the present embodiment, the main beam 52 and the cross beam 53 are H-shaped steel, and the flooring material 55 is plywood, but is not limited thereto.

도 6을 참조하면, 거푸집 설치 단계(S32)는 하부구조물(10)이 하부브라켓(41)에 정합되어 안착되도록 하부구조물(10)의 형상을 형성하는 거푸집(56)을 설치하는 단계로서, 본 실시예에서 거푸집(56)은 완성된 작업대(51)의 상면에 일반적인 Eps Block(Expanded Polystyerene Block)을 사용하여 하면의 형상과 대응되도록 설치한다.
Referring to Figure 6, the formwork installation step (S32) is a step of installing the formwork 56 to form the shape of the substructure 10 so that the lower structure 10 is matched and seated on the lower bracket (41), In the embodiment, the formwork 56 is installed to correspond to the shape of the lower surface using a general Eps Block (Expanded Polystyerene Block) on the upper surface of the finished work table 51.

도 6을 참조하면, 구조물 설치 단계(S40)는 하부구조물(10)을 제작하는 단계로서, 하부구조물 설치 단계(S41)와 앵커 설치 단계(S42)를 포함하여 구성된다.Referring to FIG. 6, the structure installation step S40 is a step of manufacturing the substructure 10, and includes a substructure installation step S41 and an anchor installation step S42.

하부구조물 설치 단계(S41)는 작업대(51)의 상면에 설치된 거푸집(56)에 철근을 설치하고 콘크리트를 타설하여 기초슬래브(11) 및 벽체(12)를 포함하는 하부구조물(10)을 건설하며, 지지파일(31)이 관통하는 부위에는 지지파일(31)의 직경보다 약 20cm 더 크게 구멍을 형성하여 하부구조물(10) 하강시 지지파일(31)과 마찰 및 간섭을 방지하도록 설치한다.Substructure installation step (S41) is to install the reinforcement in the formwork 56 installed on the upper surface of the workbench 51 and to build the substructure 10 including the foundation slab 11 and the wall 12 by placing concrete In the portion through which the support pile 31 penetrates, a hole is formed to be about 20 cm larger than the diameter of the support pile 31 so as to prevent friction and interference with the support pile 31 when the lower structure 10 descends.

벽체(12)는 기초슬래브(11)의 상면에 하부구조물(10)의 공간을 구획하는 외부벽체(13)와 내부벽체(14)가 설치되며, 본 실시예에서는 도면에 도시된 바와 같이 기초슬래브(11)를 둘러싸는 외부벽체(13)의 내측에 내부벽체(14)가 복수 개 설치되어 내부를 구획하였으나, 이에 제한되는 것은 아니고, 설계자의 설계 의도에 따라 변경될 수 있다.The wall 12 is provided with an outer wall 13 and an inner wall 14 partitioning the space of the lower structure 10 on the upper surface of the foundation slab 11, in this embodiment the foundation slab as shown in the figure Although a plurality of inner walls 14 are provided inside the outer wall 13 surrounding the 11 to partition the inside, the present invention is not limited thereto and may be changed according to a designer's design intention.

한편, 후술하는 상부구조물 설치 단계(S100)에서 상부구조물(20) 설치를 용이하게 하기 위하여, 작업발판(21)이 외부벽체(13)의 상면에 외측으로 돌출되어 설치된다.On the other hand, in order to facilitate the installation of the upper structure 20 in the upper structure installation step (S100) to be described later, the working scaffold 21 is provided to protrude outward on the upper surface of the outer wall (13).

앵커 설치 단계(S42)는 후술하는 승강부(60)에 의하여 하부구조물(10)을 인상하기 위하여 앵커(15)를 설치하는 단계로서, 기초슬래브(11)의 상부로 앵커(15)가 노출되도록 설치되고 후술하는 유압잭(62)과 동일한 개수로 설치되며, 하부구조물 설치 단계(S41)와 앵커(15)를 동시에 설치하는 것이 바람직하다.
Anchor installation step (S42) is a step of installing the anchor 15 to raise the lower structure 10 by the lifting unit 60 to be described later, so that the anchor 15 is exposed to the upper portion of the foundation slab (11). Installed and installed in the same number as the hydraulic jack 62 to be described later, it is preferable to install the substructure installation step (S41) and the anchor 15 at the same time.

도 7을 참조하면, 승강부 설치 단계(S50)는 하부구조물(10)을 인양 및 하강하기 위하여 지지부재(61)와 유압잭(62) 및 승강용 강봉(63)으로 구성되는 승강부(60)를 설치하는 단계로서, 복수 개의 지지파일(31) 상단부를 H-형강으로 구비되는 지지부재(61)를 설치하여 견고하게 연결하고, 지지부재(61) 상면에 유압잭(62)을 설치한 후, 기초슬래브(11)에 설치된 앵커(15)와 유압잭(62)에 승강용 강봉(63)을 각각 설치한다.Referring to FIG. 7, the elevating unit installation step S50 includes an elevating unit 60 including a supporting member 61, a hydraulic jack 62, and an elevating steel bar 63 to lift and lower the lower structure 10. As a step of installing, after installing the support member 61 is provided with a plurality of the upper end of the support pile 31 of the H-shaped steel and firmly connected, and after installing the hydraulic jack 62 on the upper surface of the support member 61, The lifting and lowering steel bars 63 are respectively installed on the anchor 15 and the hydraulic jack 62 provided on the foundation slab 11.

본 실시예에서는 유압잭(62) 4개를 하나의 그룹으로 하여 7개 그룹, 총 28개의 유압잭을 지지부재(61)에 설치하고, 각각의 앵커(15)와 유압잭(62)에 승강용 강봉(63)을 설치한다.In the present embodiment, four hydraulic jacks 62 as one group, seven groups and a total of 28 hydraulic jacks are installed on the support member 61, and the steel rods for elevating the respective anchors 15 and the hydraulic jacks 62 63).

이때, 각각의 그룹으로 묶어진 유압잭(62)은 동일한 펌프(P)에 연결되어, 구조물 전체를 승강시에 동시에 가압하여 인양하는 것이 바람직하며, 또한, 유압잭(62)의 하중 지지 능력과 구조물의 하중을 고려하여 유압잭(62)의 종류 및 설치 개수를 설계하는 것이 바람직하다.
At this time, the hydraulic jacks 62 grouped in each group are connected to the same pump P, and it is preferable to simultaneously lift and lift the whole structure at the time of lifting and lowering. It is preferable to design the type and number of installation of the hydraulic jack 62 in consideration of the load.

도 8 내지 10를 참조하면, 인양 및 안착 단계(S60)는 승강부(60)가 설치된 하부구조물(10)을 인양한 후에 작업대(51) 및 거푸집(56)을 제거하고 하부브라켓(41)에 안착시키는 단계이다.8 to 10, the lifting and seating step (S60) removes the workbench 51 and the formwork 56 after lifting the lower structure 10, the lifting unit 60 is installed on the lower bracket 41 This is the step of seating.

작업자간 무전을 통하여 7개의 그룹으로 묶어진 유압잭(62)에 동시에 유압을 가하여 하부구조물(10)을 인양하고, 하부구조물(10)이 인양된 상태에서 작업대(51)과 거푸집(56) 및 상부브라켓(43)을 제거한다.At the same time, the hydraulic jack 62, which is bundled into seven groups, is hydraulically applied to lift the lower structure 10, and the workbench 51, the formwork 56, and the upper portion in the state in which the lower structure 10 is lifted. Remove the bracket (43).

이 후, 하부구조물(10)을 저속으로 하강시켜 하부브라켓(41)의 상부에 안착시키며, 이때, 지지파일(31)과 기초슬래브(11) 사이에 형성된 공간으로 해수가 유입되므로 부력이 발생하지 않는다. 또한, 하강시, 하부브라켓(41)의 상면에 형성된 방수부재(42)가 하부구조물(10) 하면에 밀착하게 되어 시공중 차수 역할을 한다.Thereafter, the lower structure 10 is lowered at a low speed and seated on the upper portion of the lower bracket 41. At this time, buoyancy does not occur because seawater flows into the space formed between the support pile 31 and the foundation slab 11. Do not. In addition, when descending, the waterproof member 42 formed on the upper surface of the lower bracket 41 is in close contact with the lower surface of the lower structure 10 to serve as the order during construction.

하부구조물(10) 내부는 해수가 충수된 상태이므로 부력이 발생하지 않아 평형 상태를 유지할 수 있다.Since the inside of the substructure 10 is filled with seawater, buoyancy does not occur and thus can maintain an equilibrium state.

상술한 바와 같이, 하부구조물(10)을 해상 운반없이 가시설(50)에서 제작하고, 승강부(60)를 이용하여 하부구조물(10) 인양하여 단순히 안착시키므로, 비용이 절감되고 공사기간이 절약되는 효과가 있다.
As described above, since the lower structure 10 is manufactured in the temporary facility 50 without sea transportation, and the lower structure 10 is simply lifted and seated by using the lifting unit 60, the cost is reduced and the construction period is saved. It works.

하부구조물 고정 단계(S70)는 하부브라켓(41)의 상면에 안착된 하부구조물(10)을 고정하기 위한 단계로서, 해수 배출 단계(S71)와, 충진 단계(S72)와, 고정브라켓 설치 단계(S73)을 포함하여 구성되며, 내부벽체(14)에 의하여 구획된 하부구조물(10)의 내부 공간 중 내부에서 외부 순서로 각각의 단계를 실시한다.The lower structure fixing step (S70) is a step for fixing the lower structure 10 seated on the upper surface of the lower bracket 41, seawater discharge step (S71), filling step (S72), and fixing bracket installation step ( S73), each step is performed in the outer order from the inside of the inner space of the substructure 10 partitioned by the inner wall (14).

도 11을 참조하면, 먼저 펌프(P)를 이용하여 A구역의 해수를 외부로 배출하고, A구역을 건조 상태로 유지하면서 지지파일(31)과 기초슬래브(11) 사이의 공간에 충진재(71)를 충진하고, 고정브라켓(72)을 지지파일(31)과 기초슬래브(11)의 상면에 설치한다.Referring to FIG. 11, first, the seawater of the area A is discharged to the outside using a pump P, and the filler 71 is filled in the space between the support pile 31 and the base slab 11 while maintaining the area A in a dry state. ) And the fixing bracket 72 is installed on the upper surface of the support pile 31 and the foundation slab 11.

이때, 충진재(71)는 급결제가 포함된 무수축 콘크리트가 사용되나, 이에 제한되는 것은 아니다.At this time, the filler 71 is used, but is not limited to non-condensed concrete containing a fastener.

상술한 방법을 하부구조물(10) 내부에서 A구역, B구역, C구역 순서로 각각 실시함으로써, 해수의 부력에 대한 안정성 및 내부 건조 상태가 확보된다.
By performing the above-described method in the order of Zone A, Zone B and Zone C in the substructure 10, respectively, stability of buoyancy of the seawater and internal drying state are ensured.

도 12를 참조하면, 철거 단계(S80)는 하부구조물(20)이 하부브라켓(41)에 안착된 이후, 후술하는 하부슬래브(16) 및 상부구조물(20)을 설치하기 위하여, 불필요한 시설을 철거하는 단계로서, 상부브라켓(43)의 상부로 돌출되는 지지파일(31)과, 앵커(15) 및 승강부(60)를 제거한다.Referring to Figure 12, the demolition step (S80), after the lower structure 20 is seated on the lower bracket 41, in order to install the lower slab 16 and the upper structure 20 to be described later, dismantling unnecessary facilities As a step, the support pile 31 and the anchor 15 and the lifting portion 60 protruding to the upper portion of the upper bracket 43 are removed.

이때, 지지파일(31)을 절단한 후, 지지파일(31) 내부에 두부보강 철근을 배치하고 콘크리트를 타설하여 두부보강을 실시하며, 방수를 위하여 지지파일(31) 주변에 수팽창성 지수제를 배치한다.
At this time, after cutting the support pile 31, the head reinforcement reinforcement is placed inside the support pile 31, concrete is poured to strengthen the head, and the water-expandable index agent is applied around the support pile 31 for waterproofing. To place.

도 13을 참조하면, 하부슬래브 설치 단계(S90)는 철거 단계(S80)가 완료된 이후에 실시되며, 고정브라켓(72)이 노출된 기초슬래브(11)의 상면에 하부슬래브(16)를 설치하여 하부구조물(10)의 바닥면을 마감한다.Referring to Figure 13, the lower slab installation step (S90) is carried out after the dismantling step (S80) is completed, by installing the lower slab 16 on the upper surface of the foundation slab 11 exposed the fixing bracket 72 The bottom surface of the substructure 10 is closed.

이때, 하부슬래브(16) 설치 후, 기존에 설치된 시설물과 하부슬래브(16)가 접촉하는 접촉면을 치핑(Chipping)하여 밀착하도록 하는 것이 바람직하다.
At this time, after the lower slab 16 is installed, it is preferable to chip the contact surface where the existing facility and the lower slab 16 is in contact with each other by chipping.

도 14를 참조하면, 상부구조물 설치 단계(S100)에서는 시공된 하부구조물(10)의 상부에 작업발판(21)을 이용하여 하부슬래브(16)의 상측에 설치된 내부벽체(14) 및 외부벽체(13)에 슬래브 및 벽체 등을 설치하여 구조물의 시공을 마감하고, 건축, 전기, 설비, 소방 등 기타공사를 시공하여 구조물 설치를 완료하는 단계이다.Referring to FIG. 14, in the upper structure installation step (S100), the inner wall 14 and the outer wall installed on the upper side of the lower slab 16 using the working scaffold 21 on the upper structure 10. 13) Finishing the construction of the structure by installing slabs and walls, and completing the installation of the structure by constructing other works such as construction, electricity, facilities, and firefighting.

이 후, 완료된 구조물의 상면에 설계자가 설계한 건축물을 시공하여 공사를 완료한다.After that, the construction of the building designed by the designer on the upper surface of the completed structure is completed.

상술한 바와 같이, 해저 지반에 고정된 지지파일(31)에 가시설(50)을 설치하고 설치위치에서 수평이동 없이 수직이동만으로 구조물을 설치함으로써, 육상과 같은 작업 환경을 조성하여 작업 효율이 증대되어 품질 확보가 가능하며, 시공기간이 단축되고 구조물의 해상 운반이 불필요하여 비용이 절감된다.As described above, by installing the temporary facility 50 on the support pile 31 fixed to the seabed ground and installing the structure only by vertical movement without horizontal movement at the installation position, by creating a working environment such as land, work efficiency is increased Quality can be secured, construction time is shortened, and the cost of transportation is reduced because there is no need for sea transport of the structure.

본 발명의 권리범위는 상술한 실시예에 한정되는 것이 아니라 첨부된 특허범위 내에서 다양한 형태의 실시예로 구현될 수 있다. 특허범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 누구든지 변형 가능한 다양한 범위까지 본 발명의 청구범위 기재의 범위 내에 있는 것으로 본다.
The scope of the present invention is not limited to the above-described embodiments but may be implemented in various forms of embodiments within the scope of the appended patents. Without departing from the gist of the invention as claimed in the patent scope, those skilled in the art to which the invention pertains are considered to be within the scope of the claims described in the present invention to various extents that can be modified.

10: 하부구조물 11: 기초슬래브 12:벽체 13: 외부벽체
14: 내부벽체 15: 앵커 16: 하부슬래브
20: 상부구조물 21: 작업발판 31: 지지파일 32: 방식부재
40: 기중화탱크 41: 하부브라켓 42: 방수부재 43: 상부브라켓 50: 가시설 51: 작업대 52: 메인빔 53: 크로스빔 54: 지지목재 55: 바닥재 56: 거푸집 60: 승강부 61: 지지부재 62: 유압잭 63: 승강용 강봉 71: 충진재 72: 고정브라켓
10: substructure 11: foundation slab 12: wall 13: outer wall
14: internal wall 15: anchor 16: lower slab
20: superstructure 21: working step 31: support pile 32: anticorrosive member
40: lifting tank 41: lower bracket 42: waterproof member 43: upper bracket 50: temporary 51: work bench 52: main beam 53: cross beam 54: support wood 55: flooring 56: formwork 60: lifting portion 61: support member 62 : Hydraulic jack 63: Steel rod for elevating 71: Filling material 72: Fixed bracket

Claims (12)

해상에 구조물을 설치하기 위한 공법에 있어서,
해저 지반에 복수개의 지지파일을 설치하는 파일 설치 단계;
상기 지지파일의 하부에 하부브라켓을 설치하고, 상기 하부브라켓의 상측에 상부브라켓을 설치하는 브라켓 설치 단계;
상기 구조물이 해상에 노출되도록 상기 상부브라켓의 상측에 상기 구조물을 설치하는 구조물 설치 단계;
상기 구조물을 인양하고 상기 상부브라켓을 제거하여 상기 구조물의 상단부가 해상 위로 노출된 상태로 상기 하부브라켓에 안착시키는 인양 및 안착 단계;를 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
In the construction method for installing the structure at sea,
A file installation step of installing a plurality of support files on the seabed;
Bracket installation step of installing a lower bracket on the lower portion of the support pile, the upper bracket on the upper side of the lower bracket;
A structure installation step of installing the structure on the upper side of the upper bracket so that the structure is exposed to the sea;
Lifting and seating step of lifting the structure and removing the upper bracket to be seated on the lower bracket in a state where the upper end of the structure is exposed above the sea; construction method of the offshore structure comprising a.
제1항에 있어서,
상기 브라켓 설치 단계는 상기 하부브라켓이 상기 구조물의 하면을 지지하도록 높낮이를 조절하여 상기 하부브라켓을 설치하는 하부브라켓 설치 단계;와, 동일한 높이로 상기 상부브라켓을 설치하는 상부브라켓 설치 단계;를 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 1,
The bracket installation step may include a lower bracket installation step of installing the lower bracket by adjusting the height so that the lower bracket supports the lower surface of the structure; and an upper bracket installation step of installing the upper bracket at the same height. Offshore structure construction method characterized in that.
제2항에 있어서,
상기 브라켓 설치 단계는 상기 지지파일의 상기 하부브라켓 설치 위치에 기중화탱크를 설치하고 내부의 해수를 배출하여 상기 하부브라켓을 설치하기 위한 상태를 조성하는 기중화탱크 설치단계;와, 상기 구조물 안착시 밀착하여 해수의 유입을 방지하도록 상기 하부브라켓의 상면에 방수부재를 설치하는 방수부재 설치 단계;를 더 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 2,
The bracket installation step may include installing the air tank to the lower bracket installation position of the support pile and discharging the seawater inside to establish a condition for installing the lower bracket; and, when mounting the structure The method of installing the offshore structure further comprises a; waterproofing member installation step of installing a waterproofing member on the upper surface of the lower bracket in close contact to prevent the inflow of sea water.
제3항에 있어서,
상기 구조물 설치 단계 이전에 상기 상부브라켓의 상측에 해상에서 상기 구조물을 설치하기 위한 수상 공간을 제공하는 가시설을 설치하는 가시설 설치 단계;를 더 포함하고, 상기 구조물은 상기 가시설의 상측에 설치되는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 3,
And a provisional installation step of installing a provisional facility for providing an aquatic space for installing the structure at sea above the upper bracket before the installation step of the structure; wherein the structure is installed on the upper side of the provisional facility Offshore structure construction method.
제4항에 있어서,
상기 가시설은 수상에서의 작업공간을 제공하는 작업대와, 상기 작업대의 상면에 설치되어 상기 구조물의 하면이 상기 하부브라켓에 정합되도록 상기 구조물의 하부 형상을 형성하는 거푸집을 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 4, wherein
The temporary facility includes a work platform providing a work space in the water, and a formwork formed on the upper surface of the work platform to form a lower shape of the structure so that the lower surface of the structure is matched to the lower bracket. Hypothesis method.
제5항에 있어서,
상기 구조물 설치 단계는 상기 가시설의 상부에 상기 구조물의 기초가 되는 하부구조물의 기초슬래브와 내부 공간을 구획하는 벽체를 설치하는 하부구조물 설치 단계;와, 상기 기초슬래브 설치시 상기 하부구조물을 인양하기 위한 앵커를 설치하는 앵커 설치 단계;를 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 5,
The installation step of the structure is a substructure installation step of installing a wall for partitioning the internal slab and the base slab of the substructure that is the foundation of the structure on the upper portion of the temporary installation; And, when the foundation slab installation Offshore structure construction method comprising the; anchor installation step of installing the anchor.
제6항에 있어서,
상기 구조물 설치 단계 이후에 상기 복수 개의 지지파일 상단부를 연결하는 지지부재와, 상기 지지부재와 상기 구조물 사이에 설치되는 승강부를 설치하는 승강부 설치 단계;를 실시하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 6,
And a lifting unit installation step of installing a support member connecting the plurality of support pile upper ends and the lifting unit installed between the support member and the structure after the installation of the structure.
제7항에 있어서,
상기 인양 및 안착 단계 이후에 상기 하부구조물 내에 유입된 해수를 배출하는 해수 배출 단계;와, 상기 지지파일과 상기 기초슬래브 사이에 충진재를 충진하는 충진 단계;와, 상기 하부브라켓 상부에 안착된 상기 하부구조물을 고정하여 부력에 의한 유동을 방지하도록 상기 기초슬래브 상부의 상기 지지파일에 고정브라켓을 설치하는 고정브라켓 설치 단계;로 구성되는 하부구조물 고정 단계를 더 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 7, wherein
Seawater discharge step of discharging the seawater introduced into the substructure after the lifting and seating step; And, Filling step of filling the filler between the support pile and the base slab; And, The lower seated on the lower bracket The offshore structure construction method of claim 1, further comprising a fixing bracket installation step of installing a fixing bracket on the support pile of the upper portion of the foundation slab to prevent the flow by buoyancy by fixing the structure.
제8항에 있어서,
상기 하부구조물 고정 단계를 상기 벽체에 의하여 구획된 상기 하부구조물의 내부에서 외부 순서로 구획된 공간마다 각각 실시하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 8,
And fixing the substructures for each of the spaces partitioned in the external order from the inside of the substructures partitioned by the wall.
제9항에 있어서,
상기 하부구조물 고정 단계 이후에 상기 지지부재 및 상기 승강부를 제거하고 상기 기초슬래브 상부로 노출되는 상기 지지파일을 절단하는 철거 단계;를 더 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
10. The method of claim 9,
And removing the support member and the elevating unit after the fixing of the substructure and cutting the support pile exposed to the upper portion of the foundation slab.
제10항에 있어서,
상기 철거 단계 이후에 상기 기초슬래브 및 상기 고정브라켓의 상부를 매립하는 하부슬래브를 설치하는 하부슬래브 설치 단계;를 더 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 10,
And a lower slab installation step of installing a lower slab to bury the upper portion of the base slab and the fixed bracket after the dismantling step.
제11항에 있어서,
상기 하부슬래브 설치 단계 이후에 상기 하부구조물의 상부에 상부구조물을 설치하는 상부구조물 설치단계;를 더 포함하는 것을 특징으로 하는 해상구조물 가설 공법.
The method of claim 11,
And an upper structure installation step of installing the upper structure on top of the lower structure after the lower slab installation step.
KR1020110104977A 2011-10-14 2011-10-14 Construction method of marine structure KR101117927B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110104977A KR101117927B1 (en) 2011-10-14 2011-10-14 Construction method of marine structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110104977A KR101117927B1 (en) 2011-10-14 2011-10-14 Construction method of marine structure

Publications (1)

Publication Number Publication Date
KR101117927B1 true KR101117927B1 (en) 2012-02-24

Family

ID=45840545

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110104977A KR101117927B1 (en) 2011-10-14 2011-10-14 Construction method of marine structure

Country Status (1)

Country Link
KR (1) KR101117927B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101287923B1 (en) * 2012-10-24 2013-07-19 (주)동국 The construction method for foundation slab of marine bridge
KR101643853B1 (en) 2015-10-06 2016-08-10 아주지오텍(주) Dry tank for underwater file casing
KR102078934B1 (en) 2018-08-29 2020-04-07 조장희 Base supporting structure for bridge type floating structure and method of constructing the same

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5941507A (en) * 1982-08-31 1984-03-07 Mitsui Eng & Shipbuild Co Ltd Assembly of leg for high-level landing type vertically movable working platform
KR100823005B1 (en) * 2001-12-05 2008-04-16 주식회사 포스코 Wharf construction method
KR100854338B1 (en) * 2008-04-02 2008-08-26 최승희 Construction structure of open caisson cofferdam using holding type sheet pile
KR100937740B1 (en) * 2009-08-07 2010-01-20 정석으뜸기술(주) A method of constructing precast concrete house under water using caisson

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5941507A (en) * 1982-08-31 1984-03-07 Mitsui Eng & Shipbuild Co Ltd Assembly of leg for high-level landing type vertically movable working platform
KR100823005B1 (en) * 2001-12-05 2008-04-16 주식회사 포스코 Wharf construction method
KR100854338B1 (en) * 2008-04-02 2008-08-26 최승희 Construction structure of open caisson cofferdam using holding type sheet pile
KR100937740B1 (en) * 2009-08-07 2010-01-20 정석으뜸기술(주) A method of constructing precast concrete house under water using caisson

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101287923B1 (en) * 2012-10-24 2013-07-19 (주)동국 The construction method for foundation slab of marine bridge
KR101643853B1 (en) 2015-10-06 2016-08-10 아주지오텍(주) Dry tank for underwater file casing
KR102078934B1 (en) 2018-08-29 2020-04-07 조장희 Base supporting structure for bridge type floating structure and method of constructing the same

Similar Documents

Publication Publication Date Title
US10253475B2 (en) Construction device and method for offshore wind turbine foundation with piling performed later
KR102033794B1 (en) Offshore wind turbine foundation, corresponding offshore wind turbine and method for their installation on site
US9567720B2 (en) Offshore platform for a marine environment
CA2728430C (en) Support structure for use in the offshore wind farm industry
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
KR101407427B1 (en) Marine Pile Installing Apparatus and Installing Method Using It
JP6619204B2 (en) Deadline method and water barrier structure
KR101354383B1 (en) Working platform for underwater explosion work using small barges
JPS5911008B2 (en) Push-up type offshore platform equipment
JP2017503101A5 (en)
KR101713850B1 (en) Jackup rig with length adjustable leg
US3528254A (en) Offshore platform structure and construction method
US4266887A (en) Self-elevating fixed platform
DK171998B1 (en) Procedure for installing a marine structure
CN107882055A (en) A kind of construction method of blower fan cushion cap
KR101117927B1 (en) Construction method of marine structure
JP6105044B2 (en) Partially floating offshore platform for offshore wind power, bridges and offshore structures, and construction method
CN202969333U (en) Steel truss rock-socketed wharf structure
US3890794A (en) Method of replacing piling
KR101703441B1 (en) Cassion manufacturing method of bottom-up, pre-cast and a base plate type using floating dock, system, floating dock and cassion using thereof
KR101041282B1 (en) Construction Method of Marine Structure
US2935854A (en) Offshore drilling platform
KR101154623B1 (en) Device for constructing pier in the water and pier constructing method using the same
US3104531A (en) Mobile marine drilling foundation
KR101510453B1 (en) Method for constructing steel house bridge footing using steel plate

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150210

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160205

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170207

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180209

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20200210

Year of fee payment: 9