KR100442523B1 KR10-2002-0011899A KR20020011899A KR100442523B1 KR 100442523 B1 KR100442523 B1 KR 100442523B1 KR 20020011899 A KR20020011899 A KR 20020011899A KR 100442523 B1 KR100442523 B1 KR 100442523B1
Authority
KR
South Korea
Prior art keywords
inner tube
steel pipe
pipe
propulsion
ecosystem
Prior art date
Application number
KR10-2002-0011899A
Other languages
Korean (ko)
Other versions
KR20020028967A (en
Inventor
오범용
Original Assignee
건양씨앤이 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 건양씨앤이 주식회사 filed Critical 건양씨앤이 주식회사
Priority to KR10-2002-0011899A priority Critical patent/KR100442523B1/en
Publication of KR20020028967A publication Critical patent/KR20020028967A/en
Application granted granted Critical
Publication of KR100442523B1 publication Critical patent/KR100442523B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0621Shield advancing devices
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A40/00Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
    • Y02A40/60Ecological corridors or buffer zones

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

본 발명은 야생동물의 이동이 빈번한 지역 선정하여 시공여부에 따라 생태계 이동로를 시공하는 방법에 있어서, 이중강관을 압입추진공법을 이용하여 생태계 이동로를 시공함을 특징으로 하는 대구경 강관 압입추진공법을 이용한 생태계 이동로 및 그 시공방법에 관한 것이다.The present invention is a method for constructing an ecosystem moving path according to construction by selecting a region where the movement of wild animals is frequent, the large-diameter steel pipe indentation and promotion method characterized in that the construction of the ecosystem moving path using the double steel pipe press-propulsion method The present invention relates to an ecosystem and a construction method thereof.

Description

대구경 강관 압입추진공법을 이용한 생태계 이동로 시공방법{The method for construction using pressure-input propulsion of ecosystem travel load}The method for construction using pressure-input propulsion of ecosystem travel load}

본 발명은 대구경 강관 압입추진공법을 이용한 생태계 이동로 및 그 시공방법에 관한 것으로서, 상세히 설명하면, 고속도로나 도로의 하부에 야생동물들의 이동을 위한 이동로의 제조에 있어 관로공사에 사용되는 강관 압입추진공법을 이용하여 이중파이프형상의 외관(강관)내에 삽입되는 내관(강관)으로 형성된 생태계 이동로를 시공하는 대구경 강관 압입추진공법을 이용한 생태계 이동로 시공방법에 관한 것이다.The present invention relates to an ecosystem moving path and a construction method using the large-diameter steel pipe indentation and promotion method, which will be described in detail, the steel pipe indentation used in the pipeline construction in the production of a moving path for the movement of wild animals in the highway or the lower part of the road The present invention relates to a method for constructing an ecosystem moving path using a large-diameter steel pipe indentation and protruding method for constructing an ecosystem moving path formed of an inner tube (steel pipe) inserted into a double pipe shape (steel pipe) using a propulsion method.

산악지형이 국토의 70% 이상을 차지하는 국내상황에서의 야생동물 보호사업에 있어서 무엇보다 중요한 것은 국토개발과 조화되는 선에서의 야생동물 서식지의 확보와 야생동물 이동영역의 확보하는 것이다. 그러나 과거부터 이루어진 백두대간 횡단도로와 기타 산악 지형의 횡단도로에 의해 야생동물의 이동성이 확보되지 못해 서식지 확보 및 먹이 확보에 많은 야생동물이 어려움을 겪었으며, 차량과의 충돌사고로 인해 많은 동물들이 피해을 입었던 것 또한 사실이다.The most important aspect of wildlife protection projects in the domestic situation where the mountainous terrain occupies more than 70% of the land is to secure wildlife habitat and wildlife movement areas in line with national development. However, due to the lack of mobility of wild animals due to the cross-roads of the Baekdudaegan Crossing Road and other mountainous terrain, many wild animals have had difficulty in securing habitat and food. The damage is also true.

이러한 상황 인식 하에 정부는 1995년부터, 전국 그린네트워크화 사업의 일환으로 야생동물 이동통로 사업을 구상한 이래 1996년부터 지리산 사암재 및 오대산 구룡령에 시범사업으로 야생동물 이동통로을 설치 및 설치중에 있고, 환경부 및 한국도로공사등의 기관에서도 이 분야에 많은 정성을 기울이고 있다.In recognition of this situation, since 1995, the government has envisioned the wildlife movement route project as part of the national green network project, and since 1996, it has been installing and installing the wildlife movement route as a pilot project for Jirisan sandstone and Odaesan Kowloon-Ryeong. Institutions such as the Korea Highway Corporation are also paying much attention to this field.

생태통로는 생태적 네트워크가 필수적으로 갖추고 있어야 하는Ecological pathways must be indispensable

① 주요 서식처 유형의 보전을 확보하기 위한 핵심지역(core area). ②개별적 종의 핵심지역간 확산(disperse) 및 이주(migrate)를 위한 회랑(corridor) 또는 디딤돌(stepping stone). ③서식처의 적절한 다양성 제공과 최적크기로의 네트워크의확산을 가능케 하는 복원(restoration) 또는 자연개발지역(nature development area). ④오염 또는 배수등 외부로부터의 잠재적 위협으로부터 네트워크를 보호하기 위한 완충지역과 밀접한 관련을 맺고 있다.(1) Core areas to ensure conservation of key habitat types. ② Corridors or stepping stones for disperse and migrate between key regions of individual species. (3) Restoration or nature development areas that provide adequate diversity of habitats and enable the spread of networks to optimal sizes. 4. It is closely related to the buffer zone to protect the network from potential threats from outside such as pollution or drainage.

생태통로의 개념 및 기능에 대해서 여러 가지 의견이 제시되고 있으나 위의 4가지 요소와의 관계를 고려할 때 ① 생태계의 비오토프(Biotop) 시스템에서의 요소로서 서식처의 연결, ② 이동경로의 보전, ③ 서식지 범위의 보전, ④ 충돌에 의한 위험성의 경감, ⑤ 가장자리의 파괴된 서식처의 대체로서 새로운 서식처의 제공 등으로 정의 내릴 수 있다.Various opinions have been proposed on the concept and function of ecological pathways, but considering the relationship with the above four factors, ① linking habitats as elements of the biotope system of ecosystems, ② conservation of migration pathways, ③ habitats It can be defined as conservation of scope, (4) reduction of the risk of collisions, (5) the provision of new habitats as substitutes for damaged habitats at edges (5).

생태통로의 개념은 여전히 새롭고 국가별로 일정한 차이를 보여주고 있으며 현재까지의 건설된 통로들은 비교적 소규모 형태를 나타내고 있다.The concept of ecological pathways is still new and shows some differences between countries, and the pathways built to date are relatively small.

생태이동통로의 유형 및 사례를 살펴보면, 서식처의 분절에 따른 야생동물의 이동을 돕기 위한 동물이동통로는 설치되는 지점의 특징 및 목표종의 특성 등을 고려하여 다양한 형태의 구조물들이 동물이 도로를 횡단하는 것을 돕기 위하여 설치되어 오고 있다. 이러한 구조물들은 80년대말 90년대 초에 걸쳐 설치되기 시작하였고 대부분 유럽지역에 위치하고 있는 것으로 나타났으며 북미지역에 있어서도 일부 설치되고 있는 것으로 알려지고 있다. Forman 등 (1995)의 경우 (1) 양서류 터널(amphibian tunnel), (2) 암거(culvert) 및 생태관(ecopipe), (3)지하통로(underpass), (4) 다리 (overpass), (5) 경관커넥터 (landscape connecter)의 5가지로 크게 나누고 있다.Looking at the types and examples of ecological pathways, various types of structures cross the road considering the characteristics of the site and the target species to help the wildlife move along the segment of the habitat. It has been installed to help. These structures began to be installed in the late '80s and early' 90s, mostly in Europe, and are known to be part of North America. Forman et al. (1995) (1) amphibian tunnel, (2) culvert and ecopipe, (3) underpass, (4) overpass, (5) It is divided into five types of landscape connecters.

국내의 경우, 환경부(1995)에서는 (1) 완벽한 생태통로(네발달린 육상동물이동가능), (2) 징검다리식 생태통로(조류, 곤충등 이동가능)로 크게 구분짓고 있으나 구체적인 유형을 제시하고 있지는 못하고 있는 것으로 나타나고 있다. 이러한 국내외의 유형구분을 토대로 각종사례를 종합하여 생물이동통로의 유형을 통합하여 6개의 유형으로 재 설정할 수 있으며 각각의 특징과 사례는 다음과 같다.In Korea, the Ministry of Environment (1995) categorizes into (1) perfect ecological pathways (moving four-footed terrestrial animals) and (2) stepping-legged ecological pathways (algae, insects, etc.), but suggests specific types. It does not appear to be. Based on these types of domestic and international classification, various cases can be integrated and reconfigured into six types by integrating the types of biological movement pathways.

1) 생태교량(ecoduct)1) ecoduct

: a)개념 및 특징: 야생동물의 이동을 위하여 도로상단부에 교량 및 박스를 설치하는 형식으로서 여러가지 유형중 가장 적극적이며 대형의 시설물이다 (국내에서 생태교량(Ecobridge) 라는 명칭으로 주로 소개되어지고 있는 것이 이 유형에 해당한다고 볼 수 있다). 생태교량(Ecoduct)라는 용어의 경우 네델란드에서 사용되어지는 개념으로서 가장 실험적이지만 근래 들어 일반대중뿐만 아니라 정부당국에 의해서도 점차 설치가 이루어지고 있다. b) 단점: 외국에 비하여 급한 경사를 지닌 법면에 설치되는 경우가 대부분인 한국의 경우, 급경사 법면에서 반대편 급경사 법면으로의 야생 동물의 이동이 힘든 편이며, 생태교량이 지형구조상(급경사 법면) 도로에 지나치게 접근할 수밖에 없기 때문에 차량의 소음이나 조명으로 인한 동물 이동에 많은 장애가 나타날 수 있다. 또한 도로 개설후 설치시, 교량공사 등으로 인하여 도로교통에 많은 장애를 줄 수 있으며, 주변 자연환경도 많은 훼손을 가져올 수 있다.a) Concepts and features: Bridges and boxes are installed at the top of the road for the movement of wild animals. The most active and large-scale facilities of various types are mainly introduced in Korea under the name Ecobridge. This type). The term ecoduct is the most experimental concept used in the Netherlands, but recently it is gradually being installed not only by the general public but also by government authorities. b) Disadvantages: In Korea, which is installed on steep slopes in comparison with foreign countries, the movement of wild animals from steep slopes to opposite steep slopes is difficult, and ecological bridges can be found on roads with steep slopes. Because of the excessive access, many obstacles to animal movement due to vehicle noise or lighting can occur. In addition, when the road is installed after installation, it may cause a lot of obstacles to road traffic due to bridge construction, etc., and may also cause a lot of damage to the surrounding natural environment.

2)소형동물 이동통로(small wildlife tunnel)2) small wildlife tunnel

: a) 개념 및 특징: 오소리, 너구리등의 소형동물을 위한 유형으로서 가장 단순한 형태로 볼 수 있다. 생태관(ecopipe)으로도 불려지는 형태로서 도로개설 전. 후 모두 설치가 가능한 유형이며, 현재까지 그 효과가 가장 확실히 검증된 시설이라 할 수 있다. b) 단점: 현재까지 그 효과가 가장 확실히 검증된 시설이지만, 아직 중, 대형 포유류를 위한 생태관(ecopipe) 적 개념의 이동통로가 개발된 적이 없다.a) Concepts and Features: A type for small animals such as badgers and raccoons. Also called an ecopipe, before the road was opened. It is the type that can be installed afterwards, and it is the most proven facility to date. b) Disadvantages: To date, its effectiveness has been most proven, but no ecopathic pathway has been developed for medium and large mammals.

3) 양서류 이동 및 유도수단(amphibian tunnel and conducting measure)3) amphibian tunnel and conducting measure

:a) 개념 및 특징: 양서류는 서식을 위해 적절한 습도가 유지되어야 하며 이로 인하여 도로개설에 따른 주변환경의 변화와 분절 등이 발생할 경우 상당히 취약함을 나타나게 된다. 이에 따라 도로 개설에 따른 배수목적으로 설치된 구조물을 활용하여 이들의 서식과 이동에 도움을 주도록 하는 고려가 필요하다.: a) Concepts and Features: Amphibians should be kept in proper humidity for habitat, which makes them very vulnerable to changes in the surrounding environment and to segmentation. Therefore, it is necessary to consider the structures installed for drainage purposes according to the opening of the roads to assist them in their habitat and movement.

이와 더불어 배후의 습지 등으로부터 산란 등의 목적을 위해 이동할 경우를 대비한 별도의 유도통로를 개설하는 것 역시 고려되어야 한다. 도로 주변에 설치된 U자형 측구 등은 이러한 양서류의 이동에 있어 결정적인 장애 요소로 작용할 수 있다.In addition, the establishment of a separate guide passage should be considered in case of migration for the purpose of spawning, etc. from behind wetlands. U-shaped sideways installed around the road can act as a critical obstacle to the movement of these amphibians.

4) 지하통로(underpass, 일명 사각 박스형)4) Underpass (aka square box type)

: a)개념 및 특징: 이는 기존 및 신규 도로밑에 사각형 박스를 설치하여 지하통로를 만드는 공법으로 야생동물들이 도로 위를 횡단하지 않고 도로 밑으로 이동하게 하는데 특징이 있다. b) 단점: 사각박스형의 공법으로 지하통로를 개설시 강관압입 추진공법에 비하여 설치비가 많이 소요되며 도로 위를 주행하는 차량의 소음 및 도로 주행시의 충격이 지하통로로 전달되어 야생동물의 이동에 많은 지장을 줄 수 있다. 그리고 지하통로의 특성상, 생태교량에 비해 통로 내 조명이 어두워 주행성 이동 동물들은 이용을 기피할 수가 있다.a) Concepts and features: This is a method of constructing underground passages by installing rectangular boxes under existing and new roads, which makes it possible for wild animals to move below the road without crossing it. b) Disadvantage: When opening the underground passage with the rectangular box type construction method, it costs more installation cost than the steel pipe pressurizing propulsion method. It can interfere. In addition, due to the nature of the underground passage, the lighting in the passage is darker than that of the ecological bridge, so that the mobile animals can avoid the use.

5) 생태적 관거(Eco culvert)5) Eco culvert

:a) 개념 및 특징: 도로개설시 교차하는 소규모 하천의 경우, 콘크리트관을 매설하여 배수를 시행하는 방식에 생태적 고려를 추가하는 개념이다. 관거의 양측 입구부에 적절한 자연소재를 배치하여 야생동물이 이동할 수 있는 조건을 제공해 줌으로서 배수 및 이동통로의 유지라는 2가지 목표를 동시에 달성할 수 있으며 기존 시설의 보완을 통해 쉽게 설치되어 질 수 있다.: a) Concepts and Features: In case of small streams intersecting when opening roads, the concept of adding ecological considerations to the method of laying drainage by laying concrete pipes. By placing appropriate natural materials at the entrances on both sides of the conduit to provide conditions for wildlife movement, two goals of drainage and maintenance of the passage can be achieved simultaneously, and can be easily installed by supplementing existing facilities. have.

6) 생태적 교각 및 그루터기벽6) ecological piers and stumps

: a) 개념 및 특징: 본 유형의 경우, 대규모 시설보다는 기존의 시설에 있어 소규모의 시설을 부착 또는 보완함으로서 야생동물이 이동할 수 있도록 지원하는 시설이라고 보는 것이 타당하다. 그루터기 벽의 경우, 야생동물의 이동뿐만 아니라 곤충 및 소형 포유류의 서식 공간인 다공질 공간의 제공을 통한 동물의 서식 환경 제공이라는 차원에서의 접근이라고 할 수 있다.a) Concepts and features: For this type of facility, it is reasonable to consider a facility that supports the movement of wild animals by attaching or supplementing small facilities in existing facilities rather than large ones. In the case of the stump wall, it can be said that the approach is not only for the movement of wild animals but also for providing an animal habitat environment through the provision of a porous space, which is a habitat for insects and small mammals.

중, 대형 야생동물의 이동이 빈번한 외국의 설치 상황을 근거로 국내에서는 생태교량 및 지하통로형의 이동통로가 많이 계획되고 있고, 또 설치중이나, 이러한 중, 대형야생동물의 이동통로를 하나 설치하는데 드는 비용이 보통 20억원 정도 드는 점을 감안하면 같은비용으로 국내 야생동물의 대부분을 차지하는 중, 소형 야생동물을 위한 더 많은 이동통로을 설치할 방법을 연구중에 있다.On the basis of the foreign installation situation where medium and large wild animals are frequently moved, many ecological bridges and underground passage-type mobile passages are planned in Korea. Considering that the cost is usually about 2 billion won, most of the domestic wildlife is being used at the same cost, and more mobile passages for small wildlife are being researched.

대한민국등록실용신안공보 등록번호 제20-0236021호에는 플퓸관에 빠진 양서류 등의 동물들이 지표면으로 빠져 나올 수 있게 생태이동로를 지중에 형성하여 생태이동관을 구비하여 플륨관으로 인하여 생태계 파괴를 막는 생태계 보호용 플륨관이 기재되어 있으며, 동 공보 등록번호 제20-0222405호에는 양서류가 이동하는 통로를 갖는 유자형 수로가 기재되어 있고, 동 공보 등록번호 제0238751호에는 자연생태계를 고려한 수로용 콘크리트제품이 기재되어 있으나,In Korea Registration Utility Model Publication No. 20-0236021, an ecological transport route is formed in the ground so that animals such as amphibians in the plump tube can escape to the surface of the earth. A protective plum tube is described, and Publication No. 20-0222405 describes a waterway with a passage through which amphibians travel. The Publication No. 0238751 describes concrete products for waterways considering natural ecosystems. Although listed,

상기 종래의 기술들은 시멘트몰탈을 이용하여 수로용 또는 관을 거푸짚을 이용하여 생태계 이동로를 제조하여 원료와 시공시간이 장기화되는 문제점이 있으며, 기존에 형성된 고속도로에는 설치하지 못하는 문제점이 있어 왔다.The conventional techniques have a problem in that raw materials and construction time are prolonged by manufacturing an ecosystem moving path using a waterway or pipes using cement mortar, and there is a problem in that existing highways cannot be installed.

상기와 같은 문제점을 해결하고자, 본 발명은 이미 사용되는 고속도로에 양서류나 동물 및 곤충들이 안전하게 이동할 수 있는 생태계 이동로를 공장에서 제조된 관을 압입추진공법을 이용하여 고속도로 하부에 관통시켜 시공시간을 단축시켜 인건비 및 원료를 절감하여 경제적인 대구경 강관 압입추진공법을 이용한 생태계 이동로 및 그 시공방법을 제공하는 것을 그 목적으로 하는 것이다.In order to solve the above problems, the present invention penetrates the pipe manufactured at the factory using the pressurization propulsion method through the ecosystem movement path that allows amphibians or animals and insects to safely move on the highway that is already used, and thus the construction time. The purpose of the present invention is to provide an ecological migration path and construction method using economical large-diameter steel pipe indentation and promotion method by shortening labor costs and raw materials.

도1은 본 발명의 압입추진공법을 이용한 생태계 이동로 시공 공정도1 is a process diagram illustrating the construction of an ecosystem using an indentation propulsion method of the present invention

도2는 본 발명의 압입추진공법을 이용한 생태계 이동로시공 측면 상세도Figure 2 is a detailed view of the ecosystem movement road construction using the indentation promotion method of the present invention

도3은 본 발명의 외관 및 내관 시공 상태 일단면도Figure 3 is one end view of the exterior and inner tube construction state of the present invention

도4는 본 발명의 외관 끝단에 용접되는 슈(shoe) 상세도4 is a shoe detail welded to the exterior end of the present invention;

도5는 본 발명의 생태계 이동로 평면 상세도Figure 5 is a detailed view of the ecosystem movement path of the present invention

도6은 본 발명의 생태계 이동로 측면 상세도Figure 6 is a detailed view of the ecosystem movement path of the present invention

<도면의 부호설명><Description of the Drawings>

외관(1), 유입잭(2), 스틸파이프(3,4), 반발지지벽(5), 기초콘크리트(6), 레일(7), 사각받침대(8), 추진보조관(9), 슈(shoe)(10), 방음방진제그라우트파이프 (11), 에어벤트파이프(12), 유도철책(13), 채광기(14), 태양광집광장치(15), 토양 (16), 그라우트펌프카(Grout pumpercar)(17), 내관지지대(18), 배수로(19), 고무판 (20), 판넬(21), 방음벽(22)Exterior (1), inflow jack (2), steel pipes (3, 4), rebound support wall (5), foundation concrete (6), rail (7), square support (8), propulsion auxiliary pipe (9), Shoe (10), soundproof dustproof grout pipe (11), air vent pipe (12), guide rail (13), miner (14), solar concentrator (15), soil (16), grout Grout pumpercar 17, inner pipe support 18, drainage channel 19, rubber plate 20, panel 21, soundproof wall 22

상기와 같은 목적을 달성하고자, 본 발명은 도로 개착 없이 굴착으로 도로에 압입 추진하는 공법이 보급되고 있는 점에 감안하여 기존의 이동통로에 비하여 훨씬 저렴한 비용으로 설치할 수 있는 대구경 강관압입 추진공법을 응용한 친환경적 한국형 생태통로 개발 공법인 압입추진공법을 이용하여 이중파이프형상의 외관(강관)내에 삽입되는 내관(강관)으로 형성된 대구경 강관 압입추진공법을 이용한 생태계 이동로 및 그 시공방법에 관한 것이다.In order to achieve the above object, the present invention is applied to the large diameter steel pipe pressurization propulsion method that can be installed at a much lower cost than the existing mobile passage in view of the spread of the press-propulsion method to the road by excavation without road attachment. The present invention relates to an ecosystem and a construction method using a large-diameter steel pipe indentation and protruding method formed by an inner pipe (steel pipe) inserted into a double pipe shape (steel pipe) using an indentation and propulsion method, which is an eco-friendly Korean ecological pathway development method.

본 발명에서 이용되는 강관압입은 도로나 철도를 관통 굴착하여 관로 공사를 시공하는 방법은 널리 알려진 통상의 방법을 본 발명에서는 생태계 이동로로 사용하는 이동로를 설치하는데 사용하도록 개발한 것이다.Steel pipe indentation used in the present invention is a method for constructing a pipeline construction by drilling through roads or railways is developed to use a well-known conventional method in the present invention to install a moving path used as an ecosystem moving path.

이러한 압입추진 공사를 수행하는데는 대, 소형의 굴착기와 유압잭, 햄머장치, 호이스트, 콤프레셔, 크레인 등의 많은 장비가 동원되어 필요시에 각각 개별적으로 사용되어 왔다. 타격식 공법은 고압 햄머장치로 강관을 타격하여 압입시키면서 강관 내부의 흙을 빼내는 공법으로서 소음과 진동이 심하고 암반 노출시 시공이 불가능하며 유압식 공법은 유압잭으로 강관을 밀어서 압입시키는 공법으로 지하 매설물을 보호하며 시공할 수 있고 소음 및 진동이 없으며 암반 지역에서도 시공이 가능하므로 많이 사용하고 있다.In order to perform such a press-fitting construction, a large and small excavator, a hydraulic jack, a hammer device, a hoist, a compressor, a crane, and the like have been mobilized and used individually, if necessary. The blow method is a method of extracting soil inside the steel pipe while hitting and injecting the steel pipe with a high pressure hammer. It is widely used because it can be installed, no noise and vibration, and can be installed in rock area.

본 발명의 강관압입 추진공법을 응용한 한국형 생태통로는 주 이용대상 야생동물을 한국에 분포하는 야생동물의 거의 대부분을 차지하는 중, 소형 야생동물로 규정하여 개발하였다. 그리하여 생태 통로의 직경도 설치 예정지역의 주 이용대상의 야생동물의 크기를 고려하여 3600mm 부터 2000mm까지 자유로이 변경할 수 있도록 하였다. 그리고 야생동물의 주된 이동 예상통로가 절개지 법면에 위치할 경우, 법면에 유도철책을 설치하여 생태통로까지 유인하여 야생동물이 지형적 거부감 없이 생태통로를 이용하도록 하였다.The Korean ecological pathway applying the steel pipe pressurization propulsion method of the present invention was developed by defining a small wild animal, which takes up most of the wild animals distributed in Korea. Thus, the diameter of the ecological pathway could be freely changed from 3600mm to 2000mm in consideration of the size of the wild animal of the main target area. And if the main route of the expected movement of wild animals is located on the incision site, the guide rail is installed on the surface to attract the ecological path so that the wild animals can use the ecological path without topographical objection.

또한 기존 지하통로형 생태통로의 가장 큰 약점인 도로에서 파생되는 소음 및 진동을 통로내에 전달되는 것을 차단하기 위하여 이중강관 추진공법 및 방음,방진재 충진 공법을 이용하여 생태통로내의 진동 및 소음을 최소화하였다. 그리고 주행성 야생동물의 이동을 최대한 확보하기 위해 조명장치를 설치하여 통로 내에 최대한 자연광이 유도되도록 하였다.In addition, in order to block the transmission of noise and vibration derived from the road, which is the weakest point of the existing underground passage-type ecological passage, the vibration and noise in the ecological passage were minimized by using the double steel pipe propulsion method and the soundproofing and dustproof material filling method. . In addition, the lighting device was installed to maximize the movement of the wild animals to maximize the natural light.

도로의 소음 및 진동, 조명으로 인한 야생동물의 이동성 장해요인을 최대한 줄이기 위하여 생태통로의 출입구와 도로와의 간격을 최소 20m 이상 확보하여 자연 상태의 삼림에서 야생동물의 생태통로내의 진, 출입을 하게 하였다.In order to reduce the mobility obstacles of wild animals due to the noise, vibration and lighting of the road, the distance between the entrance and the road of the ecological passage should be at least 20m to allow for the entry and exit of the ecological pathway of the wildlife in the natural forest. It was.

본 발명에서 사용되는 방음방진제는 당분야에서 사용되는 통상의 물질이며, 폴리올레핀계수지, 우레탄수지, 폴리올레핀계발포제, 우레탄계발포제 또는 그들의 혼합물 등을 사용하며, 본 발명에서는 방음방진제의 재질이 주요 기술이 아니므로 상세한 설명은 생략하기로 하였다.The soundproof dustproof agent used in the present invention is a conventional material used in the art, and uses polyolefin resin, urethane resin, polyolefin foaming agent, urethane foaming agent or mixtures thereof, and the like. Since the description is not a detailed description thereof will be omitted.

이하 본 발명을 실시예를 통하여 상세히 설명하기로 한다.Hereinafter, the present invention will be described in detail through examples.

실시예Example

제1공정(사전조사:현지조사; 환경영향평가 및 지질조사)Phase 1 (Preliminary Survey: Local Survey; Environmental Impact Assessment and Geological Survey)

야생동물의 이동이 빈번한 지역 선정한 다음, 강관압입 추진작업을 위한 지질조사 및 분석한 후에 적정여부를 판단한 다음, 적정시에After selecting the area where the movement of wild animals is frequent, geological survey and analysis for steel pipe intrusion propulsion work are carried out to determine the appropriateness, and then

제2공정(강관압입 추진공사)2nd Process (Steel Pipe Press-in Construction)

이동통로 주 이용 동물의 크기에 맞춰 강관구경 선정한 다음,After selecting the steel pipe diameter according to the size of the animal used for the passage,

전진기지내에 바닥에 기초콘크리트(6)를 20Cm 두께로 타설한 다음,After placing the foundation concrete (6) 20 cm thick on the floor in the forward base,

흙막이 가시설공을 설치하여 반력지지벽(4)을 설치한 후에(도1참조),After installing the retaining wall, and installing the reaction support wall (4) (see Fig. 1),

기초콘크리트(6) 기초 위에 강관 추진 및 추진장비 거치를 위해 레일(4)을 설치하고 외관(추진강관)(1)의 센터와 수령을 측량하여 설치한 다음에,After installing the rail (4) for the steel pipe propulsion and propulsion equipment mounting on the foundation concrete (6) foundation, surveying and installing the center and reception of the exterior (propulsion steel pipe) (1),

외관(추진강관) (1)선단부에 선단 슈(shoe)(9)를 제작하여 용접하여 부착하고, 선단 유도장치를 외관(추진강관)(1) 선두부내부에 설치하여 압입 추진시 외관(추진강관)(1)의 방향을 조절하며(도2참조), 상기 외관(추진강관)(1)을 압입 추진한 후 토사를 긁어내기 안정면까지 관내 토사를 굴착하여 대차를 이용 윈치(Winch)로 끌어내어 전진기지 측면에 덤핑(Dumping)한 후에,Appearance (propulsion steel pipe) (1) Produce and attach a tip shoe (9) to the distal end, and attach it. Adjust the direction of the steel pipe) (1) (see Fig. 2), and press-propelled the appearance (propulsion steel pipe) (1) and scrape the soil out to excavate the soil inside the pipe to the stable surface, and pull the truck to the winch (Winch) After dumping on the side of the forward base,

제3공정(내관설치 및 방음,방충격용 약재주입)3rd process (inner pipe installation and sound injection

외관(추진강관)(1)을 유압잭(2)을 작동시켜 일정위치까지 (도달구) 압입추진시킨 후에, 내관(10)을 설치하기 전에 관내 방음, 방진제 주입을 위한 방음 방진제 그라우트파이프(Groutpipe)(12)와 에어벤트파이프(Airvent pipe)(11)를 설치하고 유입잭(2)을 상기 외관(1)을 압입하는 방법과 동일하게 외관(1)내에 내관(10)을 시공한 다음(내관(10)압입시 내관(10)하부에 고무판(20)과 내관지지대(18)를 함께 압입하여), 내관(10)을 외관(1)내로 압입하여 설치가 완료되면 그라우트펌프카(Grout pumpercar)(17)를 사용하여 외관(1)과 내관(10)사이의 공간에 야생동물의 이동에 장애가 되는 도로부분에서의 충격 및 소음을 최소화하기 위해 통상의 친환경성 내진, 내충격약재인 방음, 방진제를 주입하며 이때 주입압을 1,5~2.5Kg/Cm를 유지하여 시공한 다음, 압입추진공법을 이용한 생태계 이동로를 시공한 후에,After the external (propulsion steel pipe) 1 is pushed in by pushing the hydraulic jack 2 to a certain position (reach), and before installing the inner pipe 10, the soundproof dustproof grout pipe for soundproofing and injecting dustproof material in the pipe ( Install the inner pipe 10 in the exterior 1 in the same way as to install the Groutpipe 12 and the air vent pipe 11 and press the inlet jack 2 into the exterior 1 (In case of pressurizing the inner tube 10, press the rubber plate 20 and the inner tube support 18 together under the inner tube 10), press the inner tube 10 into the outer tube 1, and when the installation is completed, the grout pumpercar In order to minimize the impact and noise in the road part that impedes the movement of wild animals in the space between the exterior (1) and the inner tube (10) using the (17), environmentally-friendly earthquake-resistant, shock-resistant medicine soundproof, dustproof At this time, the injection pressure is maintained at 1,5 ~ 2.5Kg / Cm, and then the ecosystem is moved using the indentation method. After constructing the furnace,

제4공정(내관내에 친환경 조성)4th process (Environment-friendly creation in the inner building)

야생동물에게 환경적인 위화감을 주지 않기 위해 내관(10)의 내부에 친환경적인 접착재료를 이용하여 통나무 벽면 등의 판넬(21)을 시공하고, 벽면 사이에 넝클등을 삽입하고, 일정조명을 위한 조명장치(14)를 내관(10) 천정 일측에 설치하며, 야생동물의 이동시 내관(1)의 바닥에서 오는 위화감을 줄이기 위해 토양(흙바닥)(16)을 설치한 다음,In order not to give environmental discomfort to wild animals, construct panels 21 such as log walls using eco-friendly adhesive materials inside the inner tube 10, insert a shank between the walls, and illuminate for constant lighting. The device 14 is installed on one side of the ceiling of the inner tube 10, and the soil (dirt) 16 is installed to reduce the discomfort coming from the bottom of the inner tube 1 when the wildlife moves.

제5공정(이동로접속 연결통로 조성)5th Process (Establishment of Mobile Passage Connection)

도로의 하단에 매설된 외관(1)의 양선단부에서 삼림지역으로 약 20m 정도의 방음벽(22)을 설치하고,A soundproof wall 22 of about 20m is installed from the front end of the exterior 1 buried at the bottom of the road into the forest area.

야생동물을 상기와 같이 시공된 이동로로 유도하기 위하여 도로의 측면에서 삼림안으로 20m 떨어져 설치한 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결하는 유도철책(13)을 설치하여 압입추진공법을 이용한 생태계 이동로를 시공하였다.In order to guide the wild animals to the constructed moving road as described above, by installing a guide rail (13) connecting the tip of the constructed moving road and the side of the road with a gentle slope installed 20 m away from the side of the road into the forest An ecological pathway using the indentation propulsion method was constructed.

상기와 같이 설치한 후에는 필요에 따라 조명장치는 통상의 전구나 광섬유를 이용할 수 있으며, 동력은 전기나 태양광집광장치 등을 이용하며, 태양광집광장치 이용시에는 유인통로상부에 태양광집광장치를 설치하고, 조명 장치를 이용하여 통로내를 일정 조도를 유지할 수 있으며, 동물 이동 상황의 주기적 체크 및 미비사항 보완하여 보수하는 것이다.After the installation as described above, the lighting device may use a conventional light bulb or optical fiber as needed, and the power may be electricity or a solar light collecting device, and when using the solar light collecting device, a solar light collecting device is placed on the manned passage. It is possible to maintain a constant illuminance in the aisle by using a lighting device, and to repair by supplementing the periodic check and deficiencies of the animal movement situation.

이하 도면을 참고하여 설명하면 다음과 같다.Hereinafter, description will be given with reference to the drawings.

도1은 본 발명의 압입추진공법을 이용한 생태계 이동로 시공 공정도, 도2는본 발명의 압입추진공법을 이용한 생태계 이동로 시공 측면 상세도, 도3은 본 발명의 외관 및 내관 시공 상태 일단면도, 도4는 본 발명의 외관 끝단에 용접되는 슈(shoe) 상세도, 도5는 본 발명의 생태계 이동로 평면 상세도, 도6은 본 발명의 생태계 이동로 측면 상세도를 도시한 것이며, 외관(1), 유입잭(2), 스틸파이프 (3,4), 반발지지벽(5), 기초콘크리트(6), 레일(7), 사각받침대(8), 추진보조관(9), 슈(shoe)(10), 방음방진제그라우트파이프(11), 에어벤트파이프(12), 유도철책(13), 채광기(14), 태양광집광장치(15), 토양(16), 그라우트펌프카(Grout pumpercar) (17), 내관지지대(18), 배수로(19), 고무판(20), 판넬(21), 방음벽(22)을 나타낸 것임을 알 수 있다.1 is a construction process diagram of the ecosystem moving road using the indentation promotion method of the present invention, Figure 2 is a detailed side view of the construction of the ecosystem moving road using the indentation promotion method of the present invention, Figure 3 is a cross-sectional view of the exterior and inner tube construction state of the present invention, Figure 4 is a shoe (shoe) detailed view welded to the exterior end of the present invention, Figure 5 is a detailed view of the ecosystem movement path of the present invention, Figure 6 shows a detailed view of the ecosystem movement path of the present invention, the appearance ( 1), inlet jack (2), steel pipes (3, 4), rebound support wall (5), foundation concrete (6), rail (7), square support (8), propulsion auxiliary pipe (9), shoe ( shoe (10), soundproof dustproof grout pipe (11), air vent pipe (12), guide rail (13), miner (14), solar concentrator (15), soil (16), grout pump car ( Grout pumpercar (17), the inner tube support 18, the drainage channel 19, the rubber plate 20, the panel 21, it can be seen that the sound insulation wall (22).

구조를 살펴보면 도1은 본 발명의 시공상태를 도시한 것으로서, 시공장소와 일정간격으로 이격되는 대치되는 곳에 형성된 반발지지벽(5)과, 상기 반발지지벽 (5)의 전방 하부에 형성된 기초콘크리트(6)와, 상기 기초콘크리트(6)의 상부에 형성된 레일(7)과, 상기 반발지지벽(5)전방 상부와 레일(7)의 상부에 설치된 유압잭(2)과, 상기 유압잭(2)의 전방에 설치된 다수개의 추진보조관(9)과, 상기 추진보조관(9)의 전방에 설치된 사각받침대(8)와, 상기 사각받침대 상부에 형성되는 외관(1)과, 상기 외관(1)의 선단에 형성된 슈(shoe)(10)로 구성된 압입추진공법을 이용한 생태계 이동로 시공장치인 것이다.Looking at the structure Figure 1 shows the construction state of the present invention, the resilient support wall 5 formed in the opposing space spaced from the factory and a predetermined interval, and the foundation concrete formed in the front lower portion of the rebound support wall (5) (6), a rail (7) formed on the upper portion of the foundation concrete (6), a hydraulic jack (2) provided on the upper portion of the rebound support wall (5) and the rail (7), and the hydraulic jack (2) A plurality of propulsion auxiliary pipe (9) installed in front of the, and the square support (8) installed in front of the propulsion auxiliary pipe (9), the external appearance (1) formed on the rectangular support top, and the external appearance (1) It is an ecological movement furnace construction apparatus using a press-fitted push method consisting of a shoe (shoe) 10 formed at the tip of the.

도2를 살펴보면 상기 외관(1)과 내관(10)사이에 설치되어 방음방진제를 충전시키기 위해 형성된 방음방진제그라우트파이프(11)와, 에어벤트파이프(12)를 나타낸 것이며, 상기 방음방진제그라우트파이프(11)는 파이프로 그라우트펌프카 (Groutpumpercar)(17)에 연결되어 상기 그라우트펌프카(Grout pumpercar)(17)에서 방음방진제를 펌핑하여 외관(1)과 내관(10)에 주입시켜 시공하는 것이다.2 shows a soundproof dustproof grout pipe 11 and an air vent pipe 12 formed between the exterior 1 and the inner tube 10 to fill the soundproof dustproof agent, and the soundproof dustproofer The grout pipe 11 is connected to a grout pump car 17 by a pipe and pumps the soundproof dustproof agent from the grout pumper car 17 to the exterior 1 and the inner pipe 10 to be constructed. will be.

도3은 본 발명의 외관 및 내관 시공 상태를 나타내기 위하여 도시한 것이며,Figure 3 is shown to show the appearance and the inner tube construction state of the present invention,

도4는 외관(1)의 선단에 슈(shoe)(9)가 용접되어 부착된 상태를 도시한 것으로서, 유압잭에서 전달된 압입추진력이 외관(1)의 손상을 입히지 않도록 슈(shoe) (9)를 부착하는 것이다.4 shows a state in which a shoe 9 is welded and attached to the front end of the exterior 1, so that the push-in thrust force transmitted from the hydraulic jack does not damage the exterior 1; ) Is attached.

도5 및 도6은 본 발명의 생태계 이동로 평면 및 측면을 나타낸 것으로서,5 and 6 show the ecosystem movement path and side view of the present invention,

내관(강관)(10) 양측면에 설치된 판넬(21)과, 상부 일측에 형성되어 관내로 빛을 발산하는 조명장치(14)와, 상기 내관(10)의 하부에 설치된 토양(16)과, 상기 토양(16)의 양단에 형성된 배수로(19)와, 상기 내관(10)의 외측하부와 외관(강관) (1)내부에 형성되어 내관(10) 지지하는 내관지지대(18)와, 상기 내관지지지대(18)상부와 내관(1)사이에 형성되어 내관(10)을 보호하는 고무판(20)과, 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결되어 설치된 유도철책 (13)으로 구성된 생태계 이동로인 것이다.Panel 21 provided on both sides of the inner tube (steel pipe) 10, an illumination device 14 formed on one side of the upper side to emit light into the tube, the soil 16 installed in the lower portion of the inner tube 10, and A drainage passage 19 formed at both ends of the soil 16, an inner tube support 18 formed in the outer lower portion and the outer tube (1) of the inner tube 10 and supporting the inner tube 10, and the inner tube support Rubber plates 20 formed between the upper part of the zone 18 and the inner tube 1 to protect the inner tube 10, and guide rails installed by connecting the front end portion of the moving path constructed as above and the side of the road with a gentle slope (13). It is an ecosystem migration path consisting of).

상기와 같은 본 발명은 생태교량 및 지하통로 공법에 비하여 시공비용이 저렴하고, 생태교량 및 지하통로 공법에 비하여 시공기간이 짧으며, 생태교량 및 지하통로 공법에 비하여 공사중 주변 자연환경에 미치는 영향이 적으며 도로의 교통량 차단 등의 장애영향도 없고, 종래의 공법에 비하여 이동통로내의 야생동물 이동에 큰 영향을 미치는 통로에의 교통소음 전달 및 차량이동시의 도로진동이 통로 내에 미치는 것을 최소화하여 야생동물 이동이 최대한 확보될 수 있도록 하였으며, 조명장치에 의해 주행성의 야생동물 들이 거부감 없이 이동통로를 이용하도록 하였고, 야생동물 이동통로의 시작지점과 종점지점을 최대한 도로의 측면에서 벗어난 삼림안에 설치하여 야생동물들이 도로의 영향을 받지 않고 이동통로에 진입하도록 하였고, 도로 측면에서 야생동물 이동통로의 시작 지점과 종점지점을 유도 철책망으로 연결하여 야생동물들이 도로에 근접하지 않고 이동통로로 진입하도록 하였으며, 도로 하부에 설치된 이동통로 와 연결하여 이동통로의 시작지점과 종점지점까지 방음벽 을 설치하여 이동통로내에 소음 및 차량조명이 유입되는 것을 방지하는 장점이 있는 것이다.The present invention as described above is cheaper construction cost than the ecological bridge and underground passage method, the construction period is shorter than the ecological bridge and underground passage method, and the effect on the surrounding natural environment during construction compared to the ecological bridge and underground passage method It is small and there is no obstacle effect such as blocking traffic on the road, and the traffic noise is transferred to the passage which has a great influence on the movement of wild animals in the moving passage as compared with the conventional method, and the road vibration when moving the vehicle is minimized in the passage. To ensure maximum mobility, the lighting device allows the wild animals of the driving system to use the movement path without reluctance, and the start and end points of the wildlife movement passage are installed in the forest as far as possible from the side of the road. To enter the traffic passage without being influenced by the road, By connecting the start point and the end point of the wildlife movement route with guided iron fence, the wild animals entered the movement route without being close to the road, and connected with the movement passage installed at the lower part of the road. By installing a soundproof wall up to have the advantage of preventing the inflow of noise and vehicle lighting in the mobile passage.

Claims (3)

이중파이프형상의 외관(강관)내에 삽입되는 내관(강관)으로 형성된 대구경 강관 압입추진공법을 이용한 생태계 이동로에 있어서,In the ecosystem movement path using the large-diameter steel pipe indentation and thrust method formed of the inner pipe (steel pipe) inserted into the double pipe shape (steel pipe), 내관(강관)(10) 양측면에 설치된 판넬(21)과, 상부 일측에 형성되어 관내로 빛을 발산하는 조명장치(14)와, 상기 내관(10)의 하부에 설치된 토양(16)과, 상기 토양(16)의 양단에 형성된 배수로(19)와, 상기 내관(10)의 외측하부와 외관(강관) (1)내부에 형성되어 내관(10) 지지하는 내관지지대(18)와, 상기 내관지지지대(18)상부와 내관(1)사이에 형성되어 내관(10)을 보호하는 고무판(20)과, 상기와 같이 시공된 이동로의 선단부와 도로측면을 완만한 경사로 연결되어 설치된 유도철책 (13)으로 구성되어 있음을 특징으로 하는 대구경 강관 압입추진공법을 이용한 생태계 이동로.Panel 21 provided on both sides of the inner tube (steel pipe) 10, an illumination device 14 formed on one side of the upper side to emit light into the tube, the soil 16 installed in the lower portion of the inner tube 10, and A drainage passage 19 formed at both ends of the soil 16, an inner tube support 18 formed in the outer lower portion and the outer tube (1) of the inner tube 10 and supporting the inner tube 10, and the inner tube support Rubber plates 20 formed between the upper part of the zone 18 and the inner tube 1 to protect the inner tube 10, and guide rails installed by connecting the front end portion of the moving path constructed as above and the side of the road with a gentle slope (13). Ecological transportation path using large diameter steel pipe indentation and protruding method, characterized in that consisting of. 야생동물의 이동이 빈번한 지역 선정하여 시공여부에 따라 생태계 이동로를 시공하는 방법에 있어서, 압입추진공법을 이용하여 생태계 이동로를 시공함을 특징으로 하는 대구경 강관 압입추진공법을 이용한 생태계 이동로 시공방법.In the method of constructing the ecosystem moving path according to the construction status by selecting the area where the movement of wild animals is frequent, the construction of the ecosystem moving path using the large-diameter steel pipe press-pushing method characterized by constructing the ecosystem moving path by using the press-fit method. Way. 청구항 2에 있어서, 압입추진공법을 이용한 시공방법은,The method of claim 2, wherein the construction method using the press-fitting propulsion method, 제1공정 (사전조사:현지조사; 환경영향평가 및 지질조사)Phase 1 (Preliminary Survey: Local Survey; Environmental Impact Assessment and Geological Survey) 강관압입 추진작업을 위하여 통상의 방법으로 지질조사 및 분석한 후에 적정여부를 판단한 다음, 적정시에After the geological survey and analysis in the usual way for the steel pipe pressurization, 제2공정(강관압입 추진공사)2nd Process 전진기지내에 바닥에 기초콘크리트(6)를 20Cm 두께로 타설한 다음,After placing the foundation concrete (6) 20 cm thick on the floor in the forward base, 흙막이 가시설공을 설치하여 반력지지벽(4)을 설치한 후에, 기초콘크리트(6) 기초위에 강관 추진 및 추진장비 거치를 위해 레일(4)을 설치하고 외관(추진강관) (1)의 센터와 수령을 측량하여 설치한 다음에,After installing the reinforcement block and installing the reaction force supporting wall (4), the rail (4) is installed on the foundation concrete (6) to mount the steel pipe propulsion and propulsion equipment, and the center of the exterior (propulsion steel pipe) (1) After surveying and installing the receipt, 외관(추진강관)(1)선단부에 선단 슈(shoe)(9)를 제작하여 용접하여 부착하고, 선단 유도장치를 외관(추진강관)(1) 선두부내부에 설치하여 압입 추진시 외관(추진강관)(1)의 방향을 조절하며, 외관(추진강관)(1)을 압입 추진한 후 토사를 긁어내기 안정면까지 관내 토사를 굴착하여 대차를 이용 윈치(Winch)로 끌어내어 전진기지 측면에 덤핑(Dumping)한 후에,Appearance (propulsion steel pipe) (1) Produce and attach a tip shoe (9) to the tip and attach it, and install the tip induction device inside the facade (propulsion steel pipe) (1). Adjust the direction of steel pipe (1), press-in and push the exterior (propulsion steel pipe) (1) and scrape the soil out. Excavate the soil in the pipe to the stable surface and pull it out to the winch using the truck to dump it on the side of the forward base. After dumping, 제3공정(내관설치 및 방음,방충격용 약재주입)3rd process (inner pipe installation and sound injection 외관(추진강관)(1)을 유압잭(2)을 작동시켜 일정위치까지 (도달구) 압입시킨 후에, 내관(10)을 설치하기 전에 관내 방음, 방진제 주입을 위한 방음 방진제 그라우트파이프(Groutpipe)(12)와 에어벤트파이프(Airvent pipe)(11)를 설치하고 유입잭(2)을 상기 외관(1)을 압입하는 방법과 동일하게 외관(1)내에 내관(10)을 시공한 다음(내관(10)압입시 내관(10)하부에 고무판(20)과 내관지지대(18)를 함께 압입하여), 내관(10)을 외관(1)내로 압입하여 설치가 완료되면 그라우트펌프카(Grout pumpercar)(17)를 사용하여 외관(1)과 내관(10)사이의 공간에 야생동물의 이동에 장애가 되는 도로부분에서의 충격 및 소음을 최소화하기 위해 통상의 친환경성 내진,내충격약재인 방음, 방진제를 주입하며 이때 주입압을 1,5~2.5Kg/Cm를 유지하여 시공한 다음, 압입공법을 이용한 생태계 이동로를 시공한 후에,After injecting the external (propulsion steel pipe) 1 into the position (reach) by operating the hydraulic jack 2, and before installing the inner pipe 10, the soundproof dustproof groutpipe for soundproofing and injecting dustproof material in the pipe (12) and an air vent pipe (11) are installed and the inner pipe (10) is installed in the exterior (1) in the same way as the inlet jack (2) press-fits the exterior (1) ( When the inner tube 10 is press-fitted, the rubber plate 20 and the inner tube support 18 are press-fitted together under the inner tube 10, and the inner tube 10 is press-fitted into the outer case 1, and when the installation is completed, a grout pumpercar In order to minimize the impact and noise in the road part that impedes the movement of wild animals in the space between the exterior (1) and the inner tube (10) by using the (17), environmentally sound-proof, shock-resistant medicines soundproof, dustproof At this time, the injection pressure is maintained at 1,5 ~ 2.5Kg / Cm, and then the ecosystem movement path using the indentation method is constructed. after, 제4공정(내관내에 친환경 조성)4th process (Environment-friendly creation in the inner building) 야생동물에게 환경적인 위화감을 주지 않기 위해 내관(10)의 내부에 친환경적인 접착재료를 이용하여 통나무 벽면 등의 판넬(21)을 시공하고, 벽면 사이에 넝클등을 삽입하고, 일정조명을 위한 조명장치(14)를 내관(10) 천정 일측에 설치하며, 야생동물의 이동시 내관(1)의 바닥에서 오는 위화감을 줄이기 위해 토양(흙바닥)(16)을 설치한 다음,In order not to give environmental discomfort to wild animals, construct panels 21 such as log walls using eco-friendly adhesive materials inside the inner tube 10, insert a shank between the walls, and illuminate for constant lighting. The device 14 is installed on one side of the ceiling of the inner tube 10, and the soil (dirt) 16 is installed to reduce the discomfort coming from the bottom of the inner tube 1 when the wildlife moves. 제5공정(이동로접속 연결통로 조성)5th Process (Establishment of Mobile Passage Connection) 도로의 하단에 매설된 외관(1)의 양선단부에서 삼림지역으로 약 20m 정도의 방음벽(22)을 설치하고, 야생동물을 상기와 같이 시공된 이동로(내관(10))로 유도하기 위하여 도로의 측면에서 삼림안으로 20m 떨어져 설치한 상기 이동로 (내관(10))의 선단부와 도로측면을 완만한 경사로 연결하는 유도철책(13)을 설치함을 특징으로 하는 대구경 강관 압입추진공법을 이용한 생태계 이동로 시공방법.The soundproof wall 22 of about 20m is installed from the both ends of the exterior (1) buried at the bottom of the road into the forest area, and the road is used to guide the wildlife to the moving path (inner tube 10) constructed as described above. Ecological movement using large diameter steel pipe indentation and thrust method, characterized in that the guide rail 13 is installed to connect the front end of the moving path (inner pipe 10) and the side of the road with a gentle slope installed 20m away from the side of the forest. Construction method
KR10-2002-0011899A 2002-03-06 2002-03-06 The method for construction using pressure-input propulsion of ecosystem travel load KR100442523B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0011899A KR100442523B1 (en) 2002-03-06 2002-03-06 The method for construction using pressure-input propulsion of ecosystem travel load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0011899A KR100442523B1 (en) 2002-03-06 2002-03-06 The method for construction using pressure-input propulsion of ecosystem travel load

Publications (2)

Publication Number Publication Date
KR20020028967A KR20020028967A (en) 2002-04-17
KR100442523B1 true KR100442523B1 (en) 2004-07-30

Family

ID=19719627

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0011899A KR100442523B1 (en) 2002-03-06 2002-03-06 The method for construction using pressure-input propulsion of ecosystem travel load

Country Status (1)

Country Link
KR (1) KR100442523B1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100515189B1 (en) * 2002-09-27 2005-09-16 건양씨엔이 (주) The facility of river in the civil center and method restoration of it
KR100759504B1 (en) * 2006-02-16 2007-09-18 강성택 The eco-corridor for small earth animal
KR100790547B1 (en) * 2006-08-02 2008-01-02 (주)동양엠티 Method for constructing propulsion base for the construction method for propulsion steelpipe
CN105804756A (en) * 2016-05-16 2016-07-27 江苏宇隧通隧道装备有限公司 Disturbance-resistant pipe jacking construction scheme

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03110296A (en) * 1989-09-22 1991-05-10 Fujita Corp Excavation work and double-tube type preceding pipe therefor
JPH05280281A (en) * 1992-03-31 1993-10-26 Tokyo Gas Co Ltd Double steel pipe for propulsion
JPH0889122A (en) * 1994-09-28 1996-04-09 Maeda Seikan Kk Block for guiding animal and method for guiding animal
JPH08199517A (en) * 1995-01-20 1996-08-06 Landes Kk Intrusion preventive structure and intrusion preventive wall block to motorway of animal and crossing culvert block and installation structure thereof
JP2000073440A (en) * 1998-08-28 2000-03-07 Yamato Concrete Kogyo Kk Side ditch-tunnel system for protection of small animal and side ditch for protection of small animal
KR200222405Y1 (en) * 2000-11-22 2001-05-02 주식회사유신코퍼레이션 U-shaped water-channel having a passage for amphibia to move through
KR200236021Y1 (en) * 2001-03-20 2001-10-08 윤쾌로 Flume Duct Having Exit Channel for Wildlife
KR200238751Y1 (en) * 2001-04-02 2001-10-10 오부영 Concrete waterway

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03110296A (en) * 1989-09-22 1991-05-10 Fujita Corp Excavation work and double-tube type preceding pipe therefor
JPH05280281A (en) * 1992-03-31 1993-10-26 Tokyo Gas Co Ltd Double steel pipe for propulsion
JPH0889122A (en) * 1994-09-28 1996-04-09 Maeda Seikan Kk Block for guiding animal and method for guiding animal
JPH08199517A (en) * 1995-01-20 1996-08-06 Landes Kk Intrusion preventive structure and intrusion preventive wall block to motorway of animal and crossing culvert block and installation structure thereof
JP2000073440A (en) * 1998-08-28 2000-03-07 Yamato Concrete Kogyo Kk Side ditch-tunnel system for protection of small animal and side ditch for protection of small animal
KR200222405Y1 (en) * 2000-11-22 2001-05-02 주식회사유신코퍼레이션 U-shaped water-channel having a passage for amphibia to move through
KR200236021Y1 (en) * 2001-03-20 2001-10-08 윤쾌로 Flume Duct Having Exit Channel for Wildlife
KR200238751Y1 (en) * 2001-04-02 2001-10-10 오부영 Concrete waterway

Also Published As

Publication number Publication date
KR20020028967A (en) 2002-04-17

Similar Documents

Publication Publication Date Title
US7775738B2 (en) Vehicle barrier system
CN108868778B (en) Non-excavation construction method for large underground structure
CN105735354B (en) A kind of city underground engineering lid digs full-reverse construction method
CN210031842U (en) Combined supporting system for adjacent deep foundation pit based on row piles, connecting beams and counter-pulling anchor cables
CN108252329A (en) The assembled pipe gallery and its construction method of building enclosure load
KR100538272B1 (en) The methods of trenchless underway construction using pre-cast assembly concrete box
CN105926422B (en) The monolithic construction of bridge and underground pipe gallery and its construction method
CN103334452A (en) Underground engineering mixed construction method
KR100442523B1 (en) The method for construction using pressure-input propulsion of ecosystem travel load
CN207512777U (en) Assembled underground pipe gallery
KR20200024519A (en) Solar panel installing structure using linear site
Macaulay Underground
CN107190630A (en) Road changes the new cap excavation method of stealthy bridge type
CN113216249B (en) Method for constructing underground space under narrow road condition
CN214302989U (en) Build assembled garage parking on ground additional
CN111663815A (en) Tunnel type stereo garage under road and construction method thereof
CN207260185U (en) A kind of road changes stealthy lid and digs bridge type structure
CN103615008B (en) Overlength superelevation difference single span formula cableway terminal foundations the stone base of a column side cuts excavation construction engineering method open
KR20070105950A (en) Floting land by wire
CN100491696C (en) Method and device for structuring tunnel by propulsion of underground box
CN110644520A (en) Creation and application of lattice foundation pile net represented by specific model
CN109914473A (en) A kind of high molecule plastic assembled piping lane and its construction method
KR102225104B1 (en) Open shield method
CN110331739B (en) Cover-excavation sequential construction method
CN212983922U (en) Prefabricated construction of wisdom street lamp basis, inspection shaft complex

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20080722

Year of fee payment: 5

LAPS Lapse due to unpaid annual fee