JPS642726B2 - - Google Patents
Info
- Publication number
- JPS642726B2 JPS642726B2 JP4760583A JP4760583A JPS642726B2 JP S642726 B2 JPS642726 B2 JP S642726B2 JP 4760583 A JP4760583 A JP 4760583A JP 4760583 A JP4760583 A JP 4760583A JP S642726 B2 JPS642726 B2 JP S642726B2
- Authority
- JP
- Japan
- Prior art keywords
- sand
- ground
- soil
- piles
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 239000004576 sand Substances 0.000 claims description 61
- 238000010276 construction Methods 0.000 claims description 34
- 239000002689 soil Substances 0.000 claims description 25
- 238000000034 method Methods 0.000 claims description 18
- 238000005056 compaction Methods 0.000 claims description 10
- 230000035515 penetration Effects 0.000 claims description 8
- 230000000149 penetrating effect Effects 0.000 claims description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 1
- 235000011941 Tilia x europaea Nutrition 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 239000004571 lime Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000007935 neutral effect Effects 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 239000013589 supplement Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/10—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
- E02D3/106—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains by forming sand drains containing only loose aggregates
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4760583A JPS59173416A (ja) | 1983-03-22 | 1983-03-22 | 砂杭による軟弱地盤改良工法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4760583A JPS59173416A (ja) | 1983-03-22 | 1983-03-22 | 砂杭による軟弱地盤改良工法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59173416A JPS59173416A (ja) | 1984-10-01 |
| JPS642726B2 true JPS642726B2 (cs) | 1989-01-18 |
Family
ID=12779865
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP4760583A Granted JPS59173416A (ja) | 1983-03-22 | 1983-03-22 | 砂杭による軟弱地盤改良工法 |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59173416A (cs) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62211417A (ja) * | 1986-03-12 | 1987-09-17 | Fudo Constr Co Ltd | 土層に応じた砂杭の施工法 |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS55105149U (cs) * | 1979-01-17 | 1980-07-22 | ||
| JPS5820332B2 (ja) * | 1979-01-19 | 1983-04-22 | マップエンジニアリング株式会社 | 砂杭の造成装置 |
-
1983
- 1983-03-22 JP JP4760583A patent/JPS59173416A/ja active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59173416A (ja) | 1984-10-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110080194B (zh) | 勘探压注仪及其应用 | |
| CN111735493A (zh) | 水运工程大面积复杂场地地基动力固结智能化施工控制方法及设备 | |
| Brenner et al. | Shear strength behaviour and the measurement of shear strength in residual soils | |
| NeSmith | Static capacity analysis of augered, pressure-injected displacement piles | |
| JPS642726B2 (cs) | ||
| CN105926594A (zh) | 一种静压沉管载体灌注桩的双管施工方法 | |
| Brown | The rapid load testing of piles in fine grained soils. | |
| JP2005009170A (ja) | 締め固め杭造成工法 | |
| CN108239985A (zh) | 人工挖孔桩超前小导管注浆预加固施工方法 | |
| CN113153272B (zh) | Cfg桩钻孔施工深度检测及施工控制系统和方法 | |
| Brettmann et al. | Advances in auger pressure grouted piles: design, construction and testing | |
| CN106869194B (zh) | 运用重型圆锥动力触探法评价桩底注浆效果的检测方法 | |
| JPS5857573B2 (ja) | 土壌締固め方法と装置 | |
| CN106836320B (zh) | 预留管底激振旁孔接收波速测试桩底注浆测试装置及方法 | |
| CN213173663U (zh) | 一种水运工程大面积复杂场地地基动力固结施工系统 | |
| JP2005009169A (ja) | 締め固め杭造成工法 | |
| Liang et al. | Wave equation parameters from driven-rod test | |
| JPH02292409A (ja) | 地盤改良杭造成工法における品質管理方法 | |
| CN206873512U (zh) | 一种预留管底激振旁孔接收波速测试桩底注浆测试装置 | |
| JPS6125859B2 (cs) | ||
| JPS642725B2 (cs) | ||
| DE3434565A1 (de) | Verfahren zur messung der deformation von versenkten ramm- und bohrkoerpern | |
| JPH10252053A (ja) | 砂杭の強度測定方法 | |
| Likins et al. | Construction Control for Augercast Piling | |
| Leary | Experience with Relative Density as |