JPS6355572B2 - - Google Patents

Info

Publication number
JPS6355572B2
JPS6355572B2 JP8299582A JP8299582A JPS6355572B2 JP S6355572 B2 JPS6355572 B2 JP S6355572B2 JP 8299582 A JP8299582 A JP 8299582A JP 8299582 A JP8299582 A JP 8299582A JP S6355572 B2 JPS6355572 B2 JP S6355572B2
Authority
JP
Japan
Prior art keywords
unit
steel plates
concrete
building
units
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP8299582A
Other languages
Japanese (ja)
Other versions
JPS58199951A (en
Inventor
Haruo Morishige
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP8299582A priority Critical patent/JPS58199951A/en
Publication of JPS58199951A publication Critical patent/JPS58199951A/en
Publication of JPS6355572B2 publication Critical patent/JPS6355572B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Greenhouses (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 本発明は原子力発電所等の大型建屋の構築方法
に係るものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a large building such as a nuclear power plant.

従来この種の大型建屋の構築においては、躯体
の施工と機器配管の据付のための各種の作業が狭
隘な個所で行なわれ、労働環境が悪く、壁厚一床
厚が極めて大で大口径鉄筋が密に配筋され、コン
クリート面を直接露出することのないように入念
に壁面、床面に塗装を行なつたのち建屋の区画毎
に機械側に引渡され配管工事が開始されるので能
率が悪く、また配管のサポートを壁面、床面に取
付けるのに際し、コンクリート部に直接サポート
を取付けると、コンクリートは配管重量によつて
破壊する惧れがあり、このため従来前記鉄筋の配
筋と型枠引起しの間にコンクリート中にスタツド
付きの鉄板を埋設し、この鉄板にサポートを取付
けている。しかもこの埋込鉄板の数は尨大な数に
なり、限られた期間内に精度よく配設することが
要求される。しかしコンクリート打設中に埋込鉄
板の位置がずれてしまうこともあり、同鉄板の取
付工事は手間がかかり、その上精度が悪い。
Conventionally, when constructing large buildings of this type, various works for constructing the frame and installing equipment piping were carried out in narrow spaces, resulting in poor working conditions, extremely thick walls and floors, and large-diameter reinforcing bars. After the walls and floors are carefully painted so as not to directly expose the concrete surface, each section of the building is handed over to the machinery and piping work begins, increasing efficiency. Moreover, when installing piping supports on walls or floors, if the supports are installed directly on concrete, the concrete may break due to the weight of the pipes. An iron plate with studs is buried in the concrete between the lifts, and supports are attached to this iron plate. Moreover, the number of embedded iron plates is extremely large, and it is required to arrange them with high precision within a limited period of time. However, the position of the embedded steel plate may shift during concrete pouring, making installation of the steel plate time-consuming and inaccurate.

本発明はこのような欠点を除去するために提案
されたものであつて、内側面にシヤコネクタの配
設された一双の鋼板を中間連結材を介して平行に
連結するとともに、前記鋼板に予め機器取付金具
を固定してなる壁ユニツト並に床ユニツトを箱状
に組立てて建屋の一区画を構成し、同各ユニツト
における前記鋼板間にコンクリートを打設し、前
記ユニツトの組立と同ユニツトに対するコンクリ
ート打設とを交互に繰返して建屋の全区画を構築
することを特徴とする大型建屋の構築方法に係る
ものである。
The present invention has been proposed in order to eliminate such drawbacks, and involves connecting a pair of steel plates having shear connectors on their inner surfaces in parallel via an intermediate connecting member, and also connecting the steel plates in advance to the steel plates. A section of the building is constructed by assembling a wall unit and a floor unit in the form of a box to which equipment mounting brackets are fixed.Concrete is poured between the steel plates in each unit, and the assembly of the unit and the floor unit are performed. This relates to a method of constructing a large building, which is characterized by constructing all sections of the building by repeating concrete pouring and concrete pouring alternately.

本発明においては前記したように、中間連結材
を介して一双の鋼板を平行に連結して壁ユニツト
及び床ユニツトを構成し、同各ユニツトを箱状に
組立てて建屋の一区画を構成し、各ユニツトにお
ける一双の鋼板間にコンクリートを打設し、前記
ユニツトの組立と同ユニツトに対するコンクリー
ト打設とを交互に繰返して建屋の全区画を構築す
るようにしたので、建屋の区画の構成が既製の前
記ユニツトの組立作業によつて簡単迅速に行なわ
れ、しかも同各ユニツトにおける一双の鋼板がコ
ンクリート打設時の型枠の用を兼ねるので型枠建
込みの際の仮設作業が不要になり、建屋躯体の施
工が簡単迅速に行なわれ、しかも前記一双の鋼板
の内側面にはシヤコネクタが配設されているの
で、打設コンクリートが鋼板と一体化し、コンク
リート硬化後は同鋼板がコンクリートと一体とな
つて外力に抵抗するものであり、更に同鋼板によ
つて建屋躯体の表面が保護され、塗装作業が省略
され、工期が著しく短縮される。
In the present invention, as described above, a wall unit and a floor unit are constructed by connecting a pair of steel plates in parallel via an intermediate connecting member, and each unit is assembled into a box shape to constitute one section of a building. Concrete was poured between a pair of steel plates in each unit, and the assembly of the unit and the concrete pouring for the same unit were repeated alternately to construct all sections of the building, so the structure of the sections of the building was ready-made. The assembly work of the above-mentioned units can be easily and quickly carried out, and since the pair of steel plates in each unit also serve as formwork during concrete pouring, there is no need for temporary construction work when erecting formwork. Construction of the building frame is easy and quick, and since shear connectors are installed on the inner surfaces of the pair of steel plates, the poured concrete becomes integrated with the steel plates, and after the concrete hardens, the steel plates become integrated with the concrete. In addition, the steel plate protects the surface of the building frame, eliminates painting work, and significantly shortens the construction period.

また前記ユニツトにおける鋼板には予め機器取
付金具が固定されているので、コンクリート養生
後直ちに配管工事に移ることができ、配管工事の
ための足場、配管、配管ユニツト等を現場の大型
クレン等を利用して容易に搬入でき、この結果、
配管工事の工程を繰上げることができる。また前
記機器取付金具は予め前記ユニツトの鋼板に固定
されるので、精確に所定位置に取付けられ、コン
クリート打設中に移動することがなく、据付精度
が向上するものである。
In addition, since the equipment mounting brackets are fixed to the steel plates in the unit in advance, piping work can begin immediately after concrete curing, and the scaffolding, piping, piping units, etc. for piping work can be moved using a large crane on site. As a result,
The plumbing work process can be accelerated. Furthermore, since the equipment mounting bracket is fixed in advance to the steel plate of the unit, it can be accurately mounted at a predetermined position and will not move during concrete pouring, improving installation accuracy.

本発明によればこのように建屋躯体の大半が工
場で製作され、従来のような埋込金物が廃止さ
れ、現場における工数が大幅に削減され、工期が
大幅に縮減され、工費が節減されるものである
等、本発明は多くの利点を有するものである。
According to the present invention, most of the building frame is manufactured in a factory, eliminating the need for embedded hardware as in the past, significantly reducing the number of man-hours on site, the construction period, and construction costs. The present invention has many advantages.

以下本発明を図示の実施例について説明する。 The present invention will be described below with reference to the illustrated embodiments.

Aは工場製作された壁ユニツトで、一双の鋼板
1,1が中間連結材を構成するリブ2を介して平
行に連結され、また両鋼板1,1にはスリーブ3
の両端全周縁を溶接して、同スリーブ3自体を構
造部材として機能せしめるようにし、スリーブ3
廻りの補強鉄筋を不要ならしめている。また前記
鋼板1の対向面には打設コンクリートと一体化す
るためのシヤコネクタ4が植立されている。更に
両鋼板1間にはボツクスアウト5その他所要の金
具類が取付けられ、更に鋼板外側面には配管用サ
ポート6が固定されている。
A is a factory-manufactured wall unit in which a pair of steel plates 1 and 1 are connected in parallel via a rib 2 that constitutes an intermediate connecting member, and a sleeve 3 is attached to both steel plates 1 and 1.
The sleeve 3 itself is made to function as a structural member by welding the entire periphery of both ends of the sleeve 3.
This eliminates the need for surrounding reinforcing steel bars. Furthermore, a shear connector 4 is planted on the opposite surface of the steel plate 1 to be integrated with the poured concrete. Further, a box out 5 and other necessary metal fittings are attached between both steel plates 1, and a piping support 6 is fixed to the outer surface of the steel plate.

Bは工場製作された床ユニツトで、一双の鋼板
7,7がリブ8を介して平行に連結され、同鋼板
7にはアンカボルト9、ドレン管10等が固定さ
れ、また図示せぬシヤコネクタが植立されてい
る。なお前記各ユニツトA,Bの鋼板1,7には
工場において所要の塗装を施され、更に断熱、耐
熱を必要とする場合、前記各ユニツトの床面、天
井面、壁面に耐熱タイル等が張設される。
B is a factory-manufactured floor unit in which a pair of steel plates 7, 7 are connected in parallel via ribs 8, anchor bolts 9, drain pipe 10, etc. are fixed to the steel plate 7, and a shear connector (not shown) is fixed to the steel plate 7. has been planted. The steel plates 1 and 7 of each unit A and B are coated with the required coating at the factory, and if further heat insulation and heat resistance are required, heat-resistant tiles, etc. are placed on the floor, ceiling, and wall surfaces of each unit. will be established.

前記各ユニツトは海上輸送等によつて現地に送
られ、この際塩害を防止するためにビニルシート
が床面、天井面及び壁面に張設される。
Each of the above-mentioned units is sent to the site by sea transportation or the like, and at this time, vinyl sheets are stretched over the floor, ceiling, and walls to prevent salt damage.

現地に海上輸送された前記各ユニツトは陸揚
後、大型クレンで所定位置並に吊込まれる。
After the units are transported to the site by sea and landed, they are hoisted into their predetermined positions using a large crane.

かくして壁ユニツトAを順次所定位置に搬入し
て、相隣る壁ユニツトAの鋼板1の接合面を高張
力ボルト11で緊締して接合して箱状に組立て、
建屋躯体の区画を構成する。(第2図乃至第6図
及び第11図参照) 次いで同区画に納まるタンク、ポンプ、脱塩塔
等の各種装置12を搬入して据付けるとともに、
配管工事のための足場を先入れし、その空いた個
所に配管を仮置きする。
In this way, the wall units A are sequentially carried into a predetermined position, and the joint surfaces of the steel plates 1 of adjacent wall units A are tightened and joined with the high-tensile bolts 11, and assembled into a box shape.
Configure the sections of the building frame. (See Figures 2 to 6 and 11) Next, various equipment 12 such as tanks, pumps, and desalination towers to be accommodated in the same compartment are brought in and installed,
Scaffolding for piping work will be put in place first, and piping will be temporarily placed in the empty space.

次いで天井ユニツトを兼用する床ユニツトBを
前記区画上に架乗し、その鋼板7と壁ユニツトA
の鋼板1とを高張力ボルト13で緊締接合して、
床ユニツトBを据付け、(第7図及び第12図参
照)各ユニツトの鋼板間にコンクリート14を打
設し、同打設コンクリート養生後、本来の配管工
事を開始するとともに、隣接区画の作業を開始す
る。(第8図参照) かくして当該階床の施工を完了すると、(第9
図参照)上階の工事を開始する。(第10図参照) 以上の工程を反覆して大型建屋の施工を完了す
るものである。
Next, a floor unit B which also serves as a ceiling unit is mounted on the partition, and its steel plate 7 and wall unit A are connected to each other.
and the steel plate 1 are tightened together using high-tensile bolts 13,
Floor unit B was installed (see Figures 7 and 12), concrete 14 was poured between the steel plates of each unit, and after the poured concrete had cured, the actual piping work began, and work in the adjacent section was started. Start. (See Figure 8) When the construction of the relevant floor is completed, (9th
(See diagram) Start construction on the upper floor. (See Figure 10) The above steps are repeated to complete the construction of the large building.

以上本発明を実施例について説明したが、本発
明は勿論このような実施例にだけ局限されるもの
ではなく、本発明の精神を逸脱しない範囲内で
種々の設計の改変を施しうるものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の方法に使用される壁ユニツト
及び床ユニツトの斜面図、第2図乃至第10図は
本発明に係る大型建屋の構築方法の一実施例の工
程を示す斜面図、第11図は壁ユニツトの接合部
の横断平面図、第12図は壁ユニツトと床ユニツ
トとの接合部を示す縦断面図である。 A……壁ユニツト、B……床ユニツト、1……
鋼板、2……リブ、3……スリーブ、4……シヤ
コネクタ、7……鋼板、8……リブ、9……アン
カボルト。
FIG. 1 is a perspective view of a wall unit and a floor unit used in the method of the present invention, and FIGS. FIG. 11 is a cross-sectional plan view of the joint between the wall unit and FIG. 12 is a longitudinal sectional view showing the joint between the wall unit and the floor unit. A... Wall unit, B... Floor unit, 1...
Steel plate, 2...rib, 3...sleeve, 4...shear connector, 7...steel plate, 8...rib, 9...anchor bolt.

Claims (1)

【特許請求の範囲】[Claims] 1 内側面にシヤコネクタの配設された一双の鋼
板を中間連結材を介して平行に連結するととも
に、前記鋼板に予め機器取付用金具を固定してな
る壁ユニツト並に床ユニツトを箱状に組立てて建
屋の一区画を構成し、同各ユニツトにおける前記
鋼板間にコンクリートを打設し、前記ユニツトの
組立と同ユニツトに対するコンクリート打設とを
交互に繰返して建屋の全区画を構築することを特
徴とする大型建屋の構築方法。
1 A wall unit or a floor unit is made into a box shape by connecting a pair of steel plates with shear connectors arranged on the inner surfaces in parallel via an intermediate connecting member, and fixing the equipment mounting brackets to the steel plates in advance. The units are assembled to form one section of the building, concrete is poured between the steel plates in each unit, and the assembly of the units and the concrete pouring for the same units are alternately repeated to construct all sections of the building. A distinctive method of constructing large buildings.
JP8299582A 1982-05-19 1982-05-19 Construction of large house Granted JPS58199951A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8299582A JPS58199951A (en) 1982-05-19 1982-05-19 Construction of large house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8299582A JPS58199951A (en) 1982-05-19 1982-05-19 Construction of large house

Publications (2)

Publication Number Publication Date
JPS58199951A JPS58199951A (en) 1983-11-21
JPS6355572B2 true JPS6355572B2 (en) 1988-11-02

Family

ID=13789800

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8299582A Granted JPS58199951A (en) 1982-05-19 1982-05-19 Construction of large house

Country Status (1)

Country Link
JP (1) JPS58199951A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0261239A (en) * 1988-08-26 1990-03-01 Kajima Corp Steel plate concrete form block method
JP5520281B2 (en) * 2011-12-12 2014-06-11 株式会社日立製作所 Module structure

Also Published As

Publication number Publication date
JPS58199951A (en) 1983-11-21

Similar Documents

Publication Publication Date Title
US2160225A (en) Building construction
CN108005265B (en) Multilayer prefabricated steel reinforced concrete shear wall structure and preparation and construction methods thereof
JP6842881B2 (en) Duct construction method
KR19980080404A (en) Method of construction of plant buildings and modular structures used in the construction thereof
AU2020264333B2 (en) A Construction System and Method of Use Thereof
EP0065793B1 (en) Reinforcement structure for reinforced-concrete buildings
CN112482559A (en) Assembled steel structure building system and construction method
JPS6139469B2 (en)
CN111042573A (en) Construction method and structure for additionally arranging lift apartment sandwich floor without dehumidification operation
GB2131849A (en) Structural framework
JPS6355572B2 (en)
JPS6137692Y2 (en)
JPH0270848A (en) Floor slab
JP4872301B2 (en) Construction method of RC structure
JP3009298B2 (en) Method of manufacturing PCa slab
JPS6025576B2 (en) Building construction method
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JP3281972B2 (en) Reinforcing unit and method of constructing reinforced concrete building using the same
JPS63308B2 (en)
JPS6319661B2 (en)
JPH08239807A (en) Composite column base structure
JP2531045B2 (en) Construction method for reinforced concrete structure
JP2972956B2 (en) Column and beam joining method and its structure
KR20230109982A (en) PC half-slab construction method for quick construction of precast concrete apartment house
JPH11247449A (en) Building construction method