JPS6335997A - Tunnel lining method - Google Patents

Tunnel lining method

Info

Publication number
JPS6335997A
JPS6335997A JP61176761A JP17676186A JPS6335997A JP S6335997 A JPS6335997 A JP S6335997A JP 61176761 A JP61176761 A JP 61176761A JP 17676186 A JP17676186 A JP 17676186A JP S6335997 A JPS6335997 A JP S6335997A
Authority
JP
Japan
Prior art keywords
concrete
lining
air
water
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP61176761A
Other languages
Japanese (ja)
Inventor
津浦 謙一
山本 征彦
木全 一雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP61176761A priority Critical patent/JPS6335997A/en
Publication of JPS6335997A publication Critical patent/JPS6335997A/en
Pending legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、コンクリートによるトンネルの覆工方法に
関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of lining a tunnel with concrete.

〔従来技術〕[Prior art]

セグメント特に金属製セグメントあるいは中子式コンク
リートセグメントによる一次!!工の内側に覆工用内面
型枠を配置し、その内面型枠と一次覆工との間に、下部
から頂部に向かって順次コンクリートを打設して二次覆
工を施工する場合、コンクリート打設の進行に伴って、
−次覆工と内面型枠との間の空気が下側から頂部に向か
って追われ、逃げ場を失なった空気は一次覆工の頂部の
セグメントの四部に滞留し、そのためコンクリートが前
記凹部内の隅々まで行き渡らず、頂部に空胴を有する二
次覆工が形成される。この空胴は、トンネル覆工の強度
を低下させ、かつセグメント継手からの地下水の漏水を
招き、特に−次覆工用セグメントとして潤製セグメント
継手用した場合は、銅製セグメントが早期に腐食し耐久
性が短かくなる。
Primary with segments, especially metal segments or cored concrete segments! ! When constructing a secondary lining by placing an internal formwork for lining inside the construction and placing concrete between the internal formwork and the primary lining from the bottom to the top, concrete As pouring progresses,
- The air between the secondary lining and the inner formwork is chased from the bottom towards the top, and the air that has no place to escape stays in the four segments at the top of the primary lining, causing the concrete to fall inside the recess. A secondary lining is formed that does not reach every corner of the area and has a cavity at the top. This cavity reduces the strength of the tunnel lining and causes leakage of groundwater from the segment joints. Especially when using Junsei segment joints as segments for the next lining, the copper segments corrode early and become durable. sex becomes shorter.

この問題を解決する方法として、特開昭61−2479
8号公報により公表されているように、二次覆工コンク
リート打設予定区域内の頂部に多数の枝管を備えている
空気抜き管を配置し、各枝管の先端部を一次覆工におけ
る鋼製セグメントの周囲方向リプ間に配置し、かつ前記
空気抜き管の端部を二次覆工コンクリート打設予定区域
の外側に導出し、次にそのコンクリート打設予定区域に
二次覆工コンクリートを打設する方法が知られている。
As a method to solve this problem, Japanese Patent Application Laid-Open No. 61-2479
As announced in Publication No. 8, an air vent pipe with a large number of branch pipes is placed at the top of the area where secondary lining concrete is planned to be placed, and the tip of each branch pipe is connected to the steel used in the primary lining. The air vent pipe is placed between the circumferential lips of the manufactured segment, and the end of the air vent pipe is guided outside the area where the secondary lining concrete is planned to be placed, and then the secondary lining concrete is placed in the area where the secondary lining concrete is planned to be placed. There are known methods for setting

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかしながら、二次覆工コンクリートを二次覆工コンク
リート打設予定区域の下側から頂部に向かって打設して
いく場合、その区域の頂面に接近するにしたがって、コ
ンクリートの自由面積が減少していくので、一般のコン
クリート打設の場合と比較すると、ブリージング水の厚
さが極めて厚くなり、そのためコンクリート打設予定区
域内に滞留する空気を全量排除したとしても、結果的に
は、所要厚さの覆工コンクリートを打設したことにはな
らない。また二次覆工コンクリートの頂部(クラウン)
のコンクリートには多量の余剰水が含まれているので、
所要のコンクリート強度を確保することができない。
However, when pouring secondary lining concrete from the bottom to the top of the area where secondary lining concrete is to be placed, the free area of the concrete decreases as it approaches the top of the area. As a result, the thickness of the breathing water is extremely thick compared to the case of ordinary concrete pouring, and even if all the air stagnant in the area where concrete is to be poured is removed, the required thickness will not be as high as the required thickness. This does not mean that concrete lining has been poured. Also, the top of the secondary lining concrete (crown)
Since concrete contains a large amount of excess water,
It is not possible to secure the required concrete strength.

したがって、二次覆工コンクリートにおける頂部(クラ
ウン)の強度は他の部分よりも低く、その頂部にひび割
れが発生することが多い。
Therefore, the strength of the crown of the secondary lining concrete is lower than other parts, and cracks often occur at the crown.

〔発明の目的、構成〕[Purpose and structure of the invention]

この発明は前述の問題を有利に解決できるトンネル覆工
方法を提供することを目的とするものであって、この発
明の要旨とするところは、トンネル内に設けられた覆工
コンクリート用内面型枠1とトンネル周壁または一次覆
工との間の覆工コンクリート打設予定区域の頂部に、周
壁に気水通過性を有する気水浸透排出管2′5c、トン
ネル長手方向に延長するように配置し、かつその気水浸
透排出管2の端部を覆工コンクリート打設予定区域から
突出させてトンネル内に開放させ、次に前記覆工コンク
リート打設予定区域に覆工コンクリートを下部から頂部
に向かって順次打設し、覆工コンクリート打設部の頂部
の空気と覆工コンクリートの頂部のプリーソングによる
浮き水とコンクリート中の余剰水とを、前記気水浸透排
出管2の内部に侵入させて、その気水浸透排出管2によ
り覆工コンクリート打設部から排出することを特徴とす
るトンネル覆工方法にある。
The purpose of this invention is to provide a tunnel lining method that can advantageously solve the above-mentioned problems, and the gist of the invention is to provide an inner formwork for lining concrete provided in a tunnel. At the top of the area where lining concrete is planned to be placed between 1 and the tunnel peripheral wall or primary lining, an air/water infiltration discharge pipe 2'5c having air/water permeability is placed in the peripheral wall so as to extend in the longitudinal direction of the tunnel. , and the end of the air/water infiltration discharge pipe 2 is made to protrude from the area where lining concrete is to be placed and opened into the tunnel, and then lining concrete is poured into the area where lining concrete is to be placed from the bottom to the top. The air at the top of the lining concrete is poured, the floating water due to the pleat song at the top of the lining concrete, and the excess water in the concrete are allowed to enter the inside of the air-water permeation discharge pipe 2. , a tunnel lining method characterized in that air and water are discharged from a concrete lining part through the permeation discharge pipe 2.

〔実施例〕〔Example〕

次にこの発明を図示の例によって詳細に説明する。 Next, the present invention will be explained in detail using illustrated examples.

第1図および第2図は、シールドトンネルにおける一次
覆工10の内側の上部に気水浸透排出管2を配置すると
共に、前記−次覆工10の内側に二次覆工コンクリート
用内面型枠を配置した状態を示すものであって、多数の
鋼製セグメント6がトンネル周囲方向およびトンネル長
手方向に並べて配置されると共に、各鋼製セグメント6
のスキンプレート4が地山5に当接され、かつトンネル
周囲方向に隣り合う鋼製セグメント6の継手板6が、そ
の継手板6の貫通孔に挿通されたボルト7により結合さ
れてセグメントリングが構成され、さらにトンネル長手
方向に隣り合う鋼製セグメント6の継手板8が、その継
手板8の貫通孔に挿通されたボルト9により結合され、
ボルト7,9により結合された各鋼製セグメント乙によ
ってトンネルの周囲の地山5を被覆する一次覆工10が
構成され、各調製セグメント3におけるトンネル長手方
向に延長する補強リプ11におけるスキンプレート側の
両隅部が切り欠かれて流通孔12が設けられている。
1 and 2 show that an air/water infiltration discharge pipe 2 is arranged at the upper part of the inside of the primary lining 10 in a shield tunnel, and an inner formwork for the secondary lining concrete is placed inside the secondary lining 10. This figure shows a state in which a large number of steel segments 6 are arranged in the tunnel circumferential direction and in the tunnel longitudinal direction, and each steel segment 6
The skin plate 4 of is in contact with the ground 5, and the joint plates 6 of adjacent steel segments 6 in the circumferential direction of the tunnel are connected by bolts 7 inserted through the through holes of the joint plates 6 to form a segment ring. The joint plates 8 of the steel segments 6 adjacent in the longitudinal direction of the tunnel are connected by bolts 9 inserted through the through holes of the joint plates 8,
The primary lining 10 that covers the ground 5 around the tunnel is constructed by each steel segment B connected by bolts 7 and 9, and the skin plate side of the reinforcing lip 11 extending in the tunnel longitudinal direction in each prepared segment 3 is A communication hole 12 is provided by cutting out both corners of the hole.

周壁に多数の細孔を有する金属または合成樹脂の管体、
全長にわたって延長するスリットヲ有する金属または合
成樹脂の管体等からなる複数本の気水浸透排出管2は、
−次覆工10内の頂部においてトンネル周囲方向に間隔
をおいて配置されると共に、トンネル長手方向に延長す
るように配置され、かつ各気水浸透排出管2は鋼製セグ
メント5における継手板8に設けられた貫通孔13に挿
通され、さらに−次覆工10の内側には覆工コンクリー
ト用内面型枠1が配置され、その内面型枠1の上部には
コンクリート打設口14が設けられている。
A metal or synthetic resin tube with many pores on the peripheral wall,
A plurality of air/water infiltration/discharge pipes 2 are made of metal or synthetic resin pipes having slits extending over the entire length.
- The air/water infiltration discharge pipes 2 are arranged at intervals in the circumferential direction of the tunnel at the top of the next lining 10 and extend in the longitudinal direction of the tunnel, and each air/water permeation discharge pipe 2 is connected to the joint plate 8 in the steel segment 5. Further, an inner formwork 1 for lining concrete is arranged inside the second lining 10, and a concrete pouring opening 14 is provided at the upper part of the inner formwork 1. ing.

前記内面型枠1と一次覆工10と内面型枠1の端部およ
び一次覆工10の間に設けられた端部型枠15とにより
二次覆工コンクリート打設予定区域16が構成され、前
記気水浸透排出管2は端部型枠15に貫通され、その気
水浸透排出管2の開口端部17はトンネル内に配置され
ている。
The inner formwork 1, the primary lining 10, and the end formwork 15 provided between the end of the inner formwork 1 and the primary lining 10 constitute a secondary lining concrete placement area 16, The air/water infiltration/discharge pipe 2 is passed through the end formwork 15, and the open end 17 of the air/water infiltration/discharge pipe 2 is arranged in the tunnel.

前記内面型枠1に設けたコンクリート打設口14からコ
ンクリートポンプ等(図示を省略した)により、コンク
リートを前記二次覆工コンクリート打設予定区域16に
連続的に注入すると、注入されたコンクリートは、二次
覆工コンクリート打設予定区域16内を下方から上方に
向かって徐々に上昇して頂部に到達する。
When concrete is continuously poured into the area 16 where secondary lining concrete is to be placed through the concrete pouring port 14 provided in the inner formwork 1 using a concrete pump or the like (not shown), the poured concrete , gradually rises from the bottom to the top in the area 16 where secondary lining concrete is to be poured, and reaches the top.

二次覆工コンクリート打設予定区域16内に打設されて
いくコンクリートが二次覆工コンクリート打設予定区域
16の頂部(クラウン)に達するとき、二次覆工コンク
リート打設予定区域16の頂部の空気が、気水浸透排出
管20周壁の細孔またはスリットを通過して気水浸透排
出管2内に侵入し、その気水浸透排出管2内を通ってト
ンネル内に放出されるので、二次覆工コンクリート打設
予定区域16の頂部における鋼製セグメント6の凹部に
もコンクリートが完全に充填される。第6図は二次覆工
コンクIJ −) 18を打設した状態を示している。
When the concrete being poured into the secondary lining concrete placement area 16 reaches the top (crown) of the secondary lining concrete placement area 16, the top of the secondary lining concrete placement area 16 is reached. The air passes through the pores or slits in the peripheral wall of the air-water permeation discharge pipe 20, enters the air-water permeation discharge pipe 2, passes through the air-water permeation discharge pipe 2, and is released into the tunnel. The concave portion of the steel segment 6 at the top of the area 16 where secondary lining concrete is to be placed is also completely filled with concrete. Figure 6 shows the state in which the secondary lining concrete IJ-) 18 has been cast.

二次覆工コンクIJ −) 18の頂部においては、プ
リーソングによる浮き水が発生し、かつ水セメント比の
極めて高くなったコンクリートが存在するのでコンクリ
ート中に余剰水が存在するが、前記ツリーソングによる
浮き水および余剰水も、気水浸透排出管2の周壁におけ
る細孔またはスリットを通過して気水浸透排出管2内に
侵入し、その気水浸透排出管2内を通ってトンネル内に
排出される。
At the top of the secondary lining concrete IJ-) 18, floating water occurs due to the tree song, and there is concrete with an extremely high water-to-cement ratio, so there is surplus water in the concrete. Floating water and surplus water also pass through the pores or slits in the peripheral wall of the air-water permeation discharge pipe 2, enter the air-water permeation discharge pipe 2, pass through the air-water permeation discharge pipe 2, and enter the tunnel. be discharged.

次に二次覆工コンクIJ −トi F3の養生期間を経
過したのち、気水浸透排出管2の端部から、モルタルそ
の他の凝固性充填材料が気水浸透排出管2内に注入充填
される。
Next, after the secondary lining concrete IJ-i F3 has undergone a curing period, mortar or other coagulable filling material is injected into the air-water permeation discharge pipe 2 from the end of the air-water permeation discharge pipe 2. Ru.

第4図および第5図は二次覆工コンクリートの打設準備
を完了した山岳トンネルを示すものであって、トンネル
内に多数の鋼製支保枠19がトンネル長手方向に間隔を
おいて設置され、各鋼製支保枠19の外側にわたって金
網20が配置され、かつトンネルの地山5にコンクリー
ト吹付けによる一次覆工21が形成され、前記鋼製支保
枠19における外周側部分と金網20とは一次覆工21
に埋込まれ、さらに前記各鋼製支保枠19の頂部のウェ
ブに貫通孔13が設けられ、気水浸透排出管2は各鋼製
支保枠19の貫通孔13にわたって挿通され、前記鋼製
支保枠19および一次覆工λの内側に、コンクリート打
設口14を有する内面型枠1が配置され、その内面型枠
1の端部と一次覆工21との間に端部型枠15が設けら
れ、気水浸透排出管2の端部は端部型枠15から突出し
ている。
Figures 4 and 5 show a mountain tunnel in which preparations for pouring secondary lining concrete have been completed, and a number of steel supporting frames 19 are installed at intervals in the longitudinal direction of the tunnel. A wire mesh 20 is placed over the outside of each steel support frame 19, and a primary lining 21 is formed by spraying concrete on the ground 5 of the tunnel. Primary lining 21
Further, a through hole 13 is provided in the top web of each steel support frame 19, and the air/water permeation discharge pipe 2 is inserted across the through hole 13 of each steel support frame 19. An inner formwork 1 having a concrete pouring opening 14 is arranged inside the frame 19 and the primary lining λ, and an end formwork 15 is provided between the end of the inner formwork 1 and the primary lining 21. The end of the air/water infiltration and discharge pipe 2 protrudes from the end formwork 15.

第6図および第7図は一次覆工のみを行なう山岳トンネ
ルにおいて一次覆工コンクリートの打設準備を完了した
状態を示すものであって、トンネル内に多数の鋼製支保
枠19がトンネル長手方向に間隔をおいて設置され、か
つ各鋼製支保枠19の頂部のウェブに貫通孔16が設け
られ、気水浸透排出管2は各鋼製支保枠19の貫通孔1
3にわたって挿通され、さらに前記鋼製支保枠19の内
側に、コンクリート打設口14を有する覆工コンクリー
ト用内面型枠1が配置され覆工コンクリート用内面型枠
1の端部と地山5との間に端部型枠15が設けられ、気
水浸透排出管2の端部は端部型枠15から突出し、覆工
コンクリート用内面型枠1と地山5と端部型枠15とに
より一次覆工コンクリート打設予定区域24が形成され
ている。
Figures 6 and 7 show the state in which preparations for placing primary lining concrete have been completed in a mountain tunnel where only primary lining is performed, and a large number of steel supporting frames 19 are installed in the tunnel in the longitudinal direction of the tunnel. A through hole 16 is provided in the web at the top of each steel support frame 19, and the air/water infiltration discharge pipe 2 is installed in the through hole 1 of each steel support frame 19.
Further, an inner formwork 1 for lining concrete having a concrete pouring opening 14 is placed inside the steel supporting frame 19, and the end of the inner formwork 1 for lining concrete and the ground 5 An end form 15 is provided between them, and the end of the air/water infiltration and discharge pipe 2 protrudes from the end form 15. A primary lining concrete placement planned area 24 has been formed.

第4図および第5図において二次器エコンクリートヲ打
設した場合および第6図および第7図において一次覆工
コンクリートを打設した場合も、前述のように覆工コン
クリート打設部の頂部の空気、ブリージング水、余剰水
が気水浸透排出管2全通って排出される。
When secondary concrete is placed in Figures 4 and 5, and when primary lining concrete is placed in Figures 6 and 7, the top of the lining concrete is placed as described above. The air, breathing water, and excess water are discharged through the entire air/water permeation discharge pipe 2.

この発明を実施する場合、第8図および第9図に示すよ
うに、鋼製セグメントによる一次覆工における隣り合う
鋼製セグメント6の継手板の間にシール材22を介在さ
せてもよい。また第10図に示すように、継手板8の貫
通孔13に挿通された気水浸透排出管2を、その継手板
8の近くでスキンプレー)4に;向かって屈曲させ、継
手板8から離れた位置では、気水浸透排出管2をスキン
プレート4に接触または近接して延長させてもよい。
When carrying out this invention, a sealing material 22 may be interposed between the joint plates of adjacent steel segments 6 in the primary lining made of steel segments, as shown in FIGS. 8 and 9. Furthermore, as shown in FIG. At a remote location, the air/water infiltration drain tube 2 may extend into contact with or close to the skin plate 4.

また第11図に示すように、−次覆工の上側の鋼製セグ
メント乙におけるトンネル周囲方向の継手板に貫通孔2
3を設け、空気、浮き水、余剰水等を、その貫通孔23
を通ってキーセグメントの内側まで上昇させたのち、前
記気水浸透排出管2により覆工コンクリート打設部から
排出してもよい。
In addition, as shown in Figure 11, there are two through holes in the joint plate in the tunnel circumferential direction of the upper steel segment B of the secondary lining.
3 is provided, and air, floating water, surplus water, etc. are provided through the through hole 23.
After passing through and rising to the inside of the key segment, it may be discharged from the concrete lining area through the air/water permeation discharge pipe 2.

前記気水浸透排出管2としては、金属帯板を螺旋状に巻
回すると共に金属帯板の側部を折り曲げて弛く噛み合わ
せた螺旋管を使用してもよく、また気水浸透排出管2と
しては、剛性の高いものまたは柔軟性を有するものの何
れを使用してもよい。
As the air/water infiltration/discharge pipe 2, a spiral tube in which a metal band plate is wound spirally and the sides of the metal band plate are bent and loosely engaged may be used. As the material 2, either a material having high rigidity or a material having flexibility may be used.

さらにまた、空気、プリーソングによる浮き水およびコ
ンクリ−、ト中の余剰水の排出効果を高めるために、気
水浸透排出管2の端部に真空ポンプ(図示を省略した)
を接続して、積極的に吸引排出してもよい。
Furthermore, a vacuum pump (not shown) is installed at the end of the air-water permeation discharge pipe 2 in order to enhance the discharge effect of air, floating water caused by pre-songs, and surplus water in the concrete.
You may also connect it to actively suck and discharge.

この発明は、内側に四部を有しないセグメントすなわち
内側が平滑になっているセグメントを使用して一次覆工
を施工し、その内側に二次覆工を施工する場合にも実施
することができる。
The present invention can also be implemented when a primary lining is constructed using a segment that does not have four parts on the inside, that is, a segment whose inside is smooth, and a secondary lining is constructed inside the primary lining.

〔発明の効果〕〔Effect of the invention〕

この発明によれば、覆工コンクリート用内面型枠1とト
ンネル周壁または一次覆工との間の覆工コンクリート打
設予定区域に、覆工コンクリートを下部から頂部に向か
って順次打設し、覆工コンクリート打設部の頂部の空気
を周壁に気水通過性を有する気水浸透排出管2の内部に
侵入させ、その気水浸透排出管2により覆工コンクリー
ト打設部から排出するので、覆工コンクリートを隙間な
く充填して、設計コンクリート厚を確保することができ
、かつ覆工コンクリートの頂部のブリーソング水をも、
気水浸透排出管2の内部に侵入させて、その気水浸透排
出管2により覆工コンクIJ−ト打設部から排出するの
で、確実に設計コンクリート厚を確保することができ、
さらに覆工コンクリートの頂部における水セメント比の
高いコンクリートの余剰水をも、気水浸透排出管2の内
部に侵入させて、気水浸透排出管2により覆工コンクリ
ート打設部から排出するので、覆工コンクIJ−トの頂
部のコンクリート強度を充分に確保することができ、ま
た前述の空気排出、プリーソング水排出および余剰水の
排出により、覆工コンクリートの頂部の強度を大きくす
ると共にひび割れを低減あるいは防止することができる
等の効果が得られる。
According to this invention, lining concrete is sequentially poured from the bottom toward the top in the area where lining concrete is planned to be placed between the inner formwork 1 for lining concrete and the tunnel peripheral wall or the primary lining. The air at the top of the lining concrete placement area is allowed to enter the inside of the air/water infiltration discharge pipe 2 that has air/water permeability in the surrounding wall, and is discharged from the lining concrete placement area through the air/water infiltration discharge pipe 2. The design concrete thickness can be ensured by filling the concrete lining without any gaps, and the breather song water at the top of the lining concrete can also be absorbed.
Since it is allowed to enter the inside of the air and water infiltration discharge pipe 2 and discharged from the lining concrete IJ-casting part through the air and water infiltration and discharge pipe 2, the designed concrete thickness can be ensured.
Furthermore, surplus water from the concrete with a high water-to-cement ratio at the top of the lining concrete is also allowed to enter the inside of the air-water infiltration discharge pipe 2, and is discharged from the concrete lining area by the air-water infiltration discharge pipe 2. Sufficient concrete strength can be ensured at the top of the lining concrete IJ-t, and the above-mentioned air discharge, pre-song water discharge, and excess water discharge increase the strength of the top of the lining concrete and prevent cracks. Effects such as reduction or prevention can be obtained.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はシールドトンネルにおいて二次覆工コンクリー
トの打設準備を完了した状態を示す縦断側面図、第2図
はその縦断正面図、第6図は二次覆工コンクリートを打
設した状態を示す縦断正面図、第4図は二次覆工コンク
リートの打設準備を完了した山岳トンネルを示す縦断側
面図、第5図はその縦断正面図、第6図は一次覆工のみ
を行なう山岳トンネルにおいて一次覆工コンクリートの
打設準備を完了した状態を示す縦断側面図、第7図はそ
の縦断正面図、第8図はトンネル長手方向に隣り合う鋼
製セグメントの間にシール材ヲ介在させた状態を示す縦
断側面図、第9図はトンネル周囲方向に隣り合う鋼製セ
グメントの間にシール材を介在させた状態を示す縦断正
面図、第10図は気水浸透排出管の配置の変形例を示す
縦断側面図、第11図は潤製セグメントにおけるトンネ
ル周囲方向の継手板に貫通孔を設けた例を示す縦断正面
図である。 図において、1は覆工コンクリート用内面型枠、2は気
水浸透排出管、3は鋼製セグメント、5は地山、10は
一次覆工、12は流通孔、13は貫通孔、14はコンク
リート打設口、15は端部型枠、16は二次覆工コンク
リート打設予定区域、18は二次覆工コンクリートであ
る。 第6図 箪7図
Figure 1 is a longitudinal side view showing the state in which preparations for pouring the secondary lining concrete have been completed in a shield tunnel, Figure 2 is its longitudinal front view, and Figure 6 is the state in which the secondary lining concrete has been poured. Figure 4 is a vertical side view of a mountain tunnel that has completed preparations for placing the secondary lining concrete, Figure 5 is its vertical front view, and Figure 6 is a mountain tunnel with only the primary lining constructed. Figure 7 is a longitudinal side view showing the state in which preparations for pouring the primary lining concrete have been completed, Figure 8 is a longitudinal front view of the tunnel, and Figure 8 is a sealing material interposed between adjacent steel segments in the longitudinal direction of the tunnel. A longitudinal side view showing the condition, Fig. 9 is a longitudinal front view showing a state in which a sealing material is interposed between adjacent steel segments in the circumferential direction of the tunnel, and Fig. 10 is a modification of the arrangement of the air/water permeation discharge pipe. FIG. 11 is a longitudinal sectional side view showing an example in which a through hole is provided in a joint plate in the circumferential direction of a tunnel in a lubrication segment. In the figure, 1 is the inner formwork for lining concrete, 2 is the air/water infiltration discharge pipe, 3 is the steel segment, 5 is the ground, 10 is the primary lining, 12 is the circulation hole, 13 is the through hole, and 14 is the 15 is an end formwork, 16 is an area where secondary lining concrete is to be placed, and 18 is secondary lining concrete. Figure 6: Figure 7

Claims (1)

【特許請求の範囲】[Claims] トンネル内に設けられた覆工コンクリート用内面型枠1
とトンネル周壁または一次覆工との間の覆工コンクリー
ト打設予定区域の頂部に、周壁に気水通過性を有する気
水浸透排出管2を、トンネル長手方向に延長するように
配置し、かつその気水浸透排出管2の端部を覆工コンク
リート打設予定区域から突出させてトンネル内に開放さ
せ、次に前記覆工コンクリート打設予定区域に覆工コン
クリートを下部から頂部に向かつて順次打設し、覆工コ
ンクリート打設部の頂部の空気と覆工コンクリートの頂
部のブリージングによる浮き水とコンクリート中の余剰
水とを、前記気水浸透排出管2の内部に侵入させて、そ
の気水浸透排出管2により覆工コンクリート打設部から
排出することを特徴とするトンネル覆工方法。
Inner formwork 1 for lining concrete installed inside the tunnel
An air/water infiltration discharge pipe 2 having air/water permeability through the surrounding wall is arranged at the top of the area where lining concrete is planned to be placed between the tunnel surrounding wall or the primary lining so as to extend in the longitudinal direction of the tunnel, and The end of the air/water infiltration discharge pipe 2 is made to protrude from the area where the lining concrete is to be placed and opened into the tunnel, and then the lining concrete is sequentially poured into the area where the lining concrete is to be placed from the bottom to the top. The air at the top of the concrete lining area, the floating water caused by breathing at the top of the concrete lining, and the excess water in the concrete are allowed to enter the inside of the air-water permeation discharge pipe 2, and the air is discharged. A tunnel lining method characterized in that water is discharged from a concrete lining area through a water infiltration discharge pipe 2.
JP61176761A 1986-07-29 1986-07-29 Tunnel lining method Pending JPS6335997A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61176761A JPS6335997A (en) 1986-07-29 1986-07-29 Tunnel lining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61176761A JPS6335997A (en) 1986-07-29 1986-07-29 Tunnel lining method

Publications (1)

Publication Number Publication Date
JPS6335997A true JPS6335997A (en) 1988-02-16

Family

ID=16019347

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61176761A Pending JPS6335997A (en) 1986-07-29 1986-07-29 Tunnel lining method

Country Status (1)

Country Link
JP (1) JPS6335997A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5589136B1 (en) * 2013-12-10 2014-09-10 株式会社竹中土木 Concrete filling method and strip sheet used for the same method
JP2015090031A (en) * 2013-11-06 2015-05-11 清水建設株式会社 Tunnel lining construction method
JP2015090030A (en) * 2013-11-06 2015-05-11 清水建設株式会社 Tunnel lining construction method and management method for tunnel lining concrete placing

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS552156U (en) * 1978-06-22 1980-01-09
JPS57172100A (en) * 1981-04-15 1982-10-22 Nihon Rotsukuraapipe Kk Degassing and dehydrating pouring method of cement filler

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS552156U (en) * 1978-06-22 1980-01-09
JPS57172100A (en) * 1981-04-15 1982-10-22 Nihon Rotsukuraapipe Kk Degassing and dehydrating pouring method of cement filler

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015090031A (en) * 2013-11-06 2015-05-11 清水建設株式会社 Tunnel lining construction method
JP2015090030A (en) * 2013-11-06 2015-05-11 清水建設株式会社 Tunnel lining construction method and management method for tunnel lining concrete placing
JP5589136B1 (en) * 2013-12-10 2014-09-10 株式会社竹中土木 Concrete filling method and strip sheet used for the same method

Similar Documents

Publication Publication Date Title
JPS6335999A (en) Tunnel lining method
JPS6335997A (en) Tunnel lining method
JPS6335998A (en) Tunnel lining method
JP3625204B2 (en) Tunnel lining device and tunnel lining method
CN214272138U (en) Precast concrete cable shaft
JP4143794B2 (en) Filling method of filling material
US2224419A (en) Method of making concrete pipe
CN205741954U (en) A kind of box culvert in large size using steel plate water stopper
JP3933986B2 (en) Sheath with exhaust port
JP2942253B1 (en) Joint section gutter installation method
CN109371957A (en) Braced wall and two wall combined structure of structural wall
JP2826775B2 (en) Concrete casting method of closed structure
JP3052946B2 (en) Air release device and air release method in shield method
JP3902828B2 (en) Connection method between underwater structure and shield tunnel
US4554772A (en) Boot guard for sewer manhole construction
CN113463689B (en) Basement bottom plate structure
CN216276223U (en) Steel plate waterstop and construction joint waterproof structure
JPS5851518B2 (en) Floating box joining method at sea
JPS5936719Y2 (en) Concrete casing of large vertical shaft pump
AU634778B2 (en) Improvements relating to precast sewage pumping chambers
JPS6124798A (en) Secondary covering construction method of shield construction
JPH0354215B2 (en)
JPH04315660A (en) Inner mold structure and drain method for cast-in-place lining construction method
FI74099B (en) GOLVBRUNN.
JPS6334921B2 (en)