JPS6124798A - Secondary covering construction method of shield construction - Google Patents

Secondary covering construction method of shield construction

Info

Publication number
JPS6124798A
JPS6124798A JP14578584A JP14578584A JPS6124798A JP S6124798 A JPS6124798 A JP S6124798A JP 14578584 A JP14578584 A JP 14578584A JP 14578584 A JP14578584 A JP 14578584A JP S6124798 A JPS6124798 A JP S6124798A
Authority
JP
Japan
Prior art keywords
concrete
air vent
vent pipe
segment
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14578584A
Other languages
Japanese (ja)
Inventor
大林 重埴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ASAKAWAGUMI KK
Original Assignee
ASAKAWAGUMI KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ASAKAWAGUMI KK filed Critical ASAKAWAGUMI KK
Priority to JP14578584A priority Critical patent/JPS6124798A/en
Publication of JPS6124798A publication Critical patent/JPS6124798A/en
Pending legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は、主に鋼製のセグメントの内 周にコンクリートを巻上げるシールド工事等における2
次覆工の施工方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention is mainly used for shield work, etc. in which concrete is rolled up around the inner circumference of steel segments.
Regarding the construction method of next lining.

従来、2次覆工を行う場合、1次層ニーのセグメント1
′の縦リブ2°が障害となってコンクリートCの打上り
のときには天端においてコンクリート投入側が上昇しく
イで示す)、順次妻側部6′へ移動しく口で示す)、最
後に妻側部6゛が上昇する(ハで示す)。然しこのまま
の工法だとセグメント1゛の天端の縦リブ2゛間に空隙
Aが出来、この結果セグメントl°の腐食によって地盤
Bの沈下。
Conventionally, when performing secondary lining, segment 1 of the primary layer knee
When pouring concrete C, the vertical rib 2° of ′ becomes an obstacle, and when concrete C is cast, the concrete input side rises at the top (indicated by A), then moves to the gable side 6′ (indicated by mouth), and finally the gable side. 6゛ rises (indicated by C). However, if the construction method continues as it is, a gap A will be created between the vertical ribs 2° at the top of segment 1°, and as a result, ground B will sink due to corrosion of segment 1°.

管体の破損、漏水等の障害が生じるという問題があった
。8゛は横リブである。
There were problems such as pipe damage and water leakage. 8゛ is the horizontal rib.

本発明は上記の点に鑑みて為されたも のであって、その目的とするところは工程が複雑化する
ことなく、然もセグメントに空隙の生しるのを防ぐこと
の出来るシールド工事等における2次覆工の施工方法を
提供するにある。
The present invention has been made in view of the above points, and its purpose is to prevent the formation of voids in the segments without complicating the process. The present invention provides a construction method for secondary lining.

以下、本発明を図示の実施例に基づい て詳述する。The present invention will be described below based on the illustrated embodiments. This will be explained in detail.

1は鋼製のセグメントであって、内周 には格子状にリブ2,8が設けられ、周方向に縦リブ2
が、且つ軸方向に横リブ8が各々形成されている。3は
空気抜き管であって、分枝管9の先端を各縦リブ2間に
開口させてあり、空気抜き管3の他端はセグメントの妻
側部6から外に導出しである。10は内枠、11ばコン
クリート投入口である。しかしてコンクリート投入口1
1からセグメント1のコンクリート巻上げ部4にコンク
リートを打設した場合に、セグメント1の天端の縮リブ
2間に溜ろうとする空気は空気抜き管3から逐次に排出
されることになる。また図示の実施例は大径の空気抜き
管3aと小径の空気抜き管3bの二本が配されており、
天端の中央部分で各空気抜き管3a、3bの分枝管9a
、9bを重複させて排気量を多くしである。
Reference numeral 1 denotes a steel segment, and ribs 2 and 8 are provided in a grid pattern on the inner periphery, and vertical ribs 2 and 8 are provided in the circumferential direction.
However, horizontal ribs 8 are formed in the axial direction. Reference numeral 3 denotes an air vent pipe, and the tip of the branch pipe 9 is opened between each vertical rib 2, and the other end of the air vent pipe 3 is led out from the end side 6 of the segment. 10 is an inner frame, and 11 is a concrete inlet. However, concrete input port 1
When concrete is poured from 1 to the concrete rolling part 4 of the segment 1, air that tends to accumulate between the shrinking ribs 2 at the top end of the segment 1 is successively discharged from the air vent pipe 3. In addition, in the illustrated embodiment, two air vent pipes 3a and 3b are arranged, a large diameter air vent pipe 3a and a small diameter air vent pipe 3b.
Branch pipe 9a of each air vent pipe 3a, 3b in the center part of the top
, 9b are overlapped to increase the displacement.

したがってコンクリートを投入する場 合に従来例の第2図に示すように中央部分に空気が多く
溜る傾向にあっても空気をスムーズに外に排出できるよ
うになる。12は線材で形成される吊り具である。
Therefore, when pouring concrete, even if a large amount of air tends to accumulate in the center as shown in FIG. 2 of the conventional example, the air can be smoothly discharged to the outside. Reference numeral 12 denotes a hanging tool made of wire.

次にコンクリートの充填と空気の排出 との関連を述べると、先ずコンクリートの充填に伴なっ
て大径及び小径の空気抜き管3a、3bがら空気が排出
される。更に充填を続けると小径の空気抜き管3bから
の排気が停止し、次に大径の空気抜き管3aからの排気
が停止して充填を完了させる。尚、大径の空気抜き管3
aは例えば直径を161富、小径の空気抜き管3bは例
えば直径を131としである。また分枝管9の先端を第
5図のようにVカ・ツトすると空隙を確実に除くことが
できる。
Next, the relationship between filling concrete and discharging air will be described. First, as concrete is being filled, air is discharged from the large and small diameter air vent pipes 3a and 3b. When the filling is continued further, the exhaust from the small diameter air vent pipe 3b is stopped, and then the exhaust from the large diameter air vent pipe 3a is stopped to complete the filling. In addition, large diameter air vent pipe 3
For example, a has a diameter of 161mm, and the small diameter air vent pipe 3b has a diameter of 131mm, for example. Moreover, if the tip of the branch pipe 9 is V-shaped as shown in FIG. 5, the void can be reliably removed.

本発明は上述のように、セグメントの 天端の縦リブ間に空気抜き管の一端を開口させるととも
に、この空気抜き管の他端がわをセグメントのコンクリ
ート巻上げ部に導出し、然るのちセグメントのコンクリ
ート巻上げ部にコンクリートを打設するので、セグメン
トの天端の縦リブ間と外ネとは空気抜き管を介して連通
ずることとなり、したがってセグメントの内周にコンク
リートを打設する際に天端の縦リブ間に溜ろうとする空
気はコンクリートの投入とともに逐次外に排気でき、こ
の結果2次覆工において天端部分に空隙ができず構造上
の欠陥が生じるのを防げると云う効果を奏し、然も空気
抜き管を一旦配設すれば、あとはコンクリートの投入峠
よって空気が自然流出するので従来の工法に比べて複雑
化することもないと云う利点がある。
As described above, the present invention opens one end of the air vent pipe between the vertical ribs at the top end of the segment, and guides the other end of the air vent pipe to the concrete rolling part of the segment. Since concrete is placed in the rolled-up part, the vertical ribs at the top of the segment communicate with the outside wall through the air vent pipe. The air that tends to accumulate between the ribs can be gradually exhausted to the outside as concrete is poured, and as a result, the secondary lining has the effect of preventing voids from forming at the top and structural defects from occurring. Once the air vent pipe is installed, the air will flow out naturally through the concrete injection pass, so it has the advantage of being less complicated than conventional construction methods.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は従来の工法による施工後の縦 断面図、第2図は第1図のX−X断面図、第3図は本発
明の工法によるコンクリート投入前の断面図、第4図は
第3図のY−Y断面図、第5図は空気抜き管の他の実施
例を示す図、第6図はセグメントの全体斜視図である。 l−セグメント、2−縦リブ、3−空気抜き管、4−コ
ンクリート巻上げ部。
Figure 1 is a longitudinal sectional view after construction using the conventional construction method, Figure 2 is a sectional view taken along line X-X in Figure 1, Figure 3 is a sectional view before concrete is poured using the method of the present invention, and Figure 4 is 3 is a sectional view taken along line YY in FIG. 3, FIG. 5 is a view showing another embodiment of the air vent pipe, and FIG. 6 is a perspective view of the entire segment. l-segment, 2-vertical rib, 3-air vent pipe, 4-concrete hoist.

Claims (1)

【特許請求の範囲】[Claims] (1)セグメントの天端の縦リブ間に空気抜き管の一端
を開口させるとともに、この 空気抜き管の他端がわをセグメントの間 のコンクリート巻上げ部の外に導出し、 然るのちセグメントのコンクリート巻上 げ部にコンクリートを打設することを特 徴とするシールド工事等における2次覆 工の施工方法。
(1) One end of the air vent pipe is opened between the vertical ribs at the top of the segment, and the other end of this air vent pipe is led out of the concrete rolling part between the segments, and then concrete rolling of the segment is performed. A construction method for secondary lining in shield construction, etc., which is characterized by pouring concrete into the area.
JP14578584A 1984-07-12 1984-07-12 Secondary covering construction method of shield construction Pending JPS6124798A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14578584A JPS6124798A (en) 1984-07-12 1984-07-12 Secondary covering construction method of shield construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14578584A JPS6124798A (en) 1984-07-12 1984-07-12 Secondary covering construction method of shield construction

Publications (1)

Publication Number Publication Date
JPS6124798A true JPS6124798A (en) 1986-02-03

Family

ID=15393100

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14578584A Pending JPS6124798A (en) 1984-07-12 1984-07-12 Secondary covering construction method of shield construction

Country Status (1)

Country Link
JP (1) JPS6124798A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55558A (en) * 1979-02-28 1980-01-05 Canon Inc Non-mydriasis type fundus camera

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55558A (en) * 1979-02-28 1980-01-05 Canon Inc Non-mydriasis type fundus camera

Similar Documents

Publication Publication Date Title
CN107587584A (en) Drainpipe leakage-resistant device and its construction method
CN108560560A (en) A kind of method for dismounting of foundation pit enclosure structure
JPS58598A (en) Method of control construction of crack of wall-shaped concrete structure
JPS6124798A (en) Secondary covering construction method of shield construction
CN208966025U (en) A kind of flooring is vertically without reserved holes of pipes mouth pre-embedded device
CN108798011A (en) A kind of flooring is vertically without reserved holes of pipes mouth pre-embedded device and its application method
CN108397211B (en) A kind of section of jurisdiction that can be removed inside subway tunnel and construction method
CN207727733U (en) The spliced gutter that can be had enough to meet the need
JPS6041269B2 (en) How to repair old pipes
JPS6335999A (en) Tunnel lining method
JPS6124799A (en) Secondary construction method in shield construction
US2224419A (en) Method of making concrete pipe
JPS6335997A (en) Tunnel lining method
JPS5817916B2 (en) Floor slab construction method
JPS6335998A (en) Tunnel lining method
CN209760271U (en) Precipitation well head shaping protection plugging device
JPS6032200Y2 (en) sand pile guide pipe
JPH0538198Y2 (en)
JPS6256478B2 (en)
CN105863676B (en) A kind of underground loop cast-in-place concrete air passage construction method
JPS5943627B2 (en) Concrete pouring chute
JPS58124000A (en) Method of executing tunnel secondary covering work concrete
JPS597266Y2 (en) Large underground concrete tank
JPS587062A (en) Construction of corner drain
JPH08260445A (en) Method and equipment for forming joint weep hole in method of rcd construction