JP3625204B2 - Tunnel lining device and tunnel lining method - Google Patents

Tunnel lining device and tunnel lining method Download PDF

Info

Publication number
JP3625204B2
JP3625204B2 JP2002065257A JP2002065257A JP3625204B2 JP 3625204 B2 JP3625204 B2 JP 3625204B2 JP 2002065257 A JP2002065257 A JP 2002065257A JP 2002065257 A JP2002065257 A JP 2002065257A JP 3625204 B2 JP3625204 B2 JP 3625204B2
Authority
JP
Japan
Prior art keywords
lining
lining concrete
branch pipes
gap
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002065257A
Other languages
Japanese (ja)
Other versions
JP2003262096A (en
Inventor
仁志 小倉
肇 長政
喬一 佐藤
靖幸 臼井
洋司 石井
匡博 岩瀬
克史 梅田
直哉 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nishimatsu Construction Co Ltd
Original Assignee
Nishimatsu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nishimatsu Construction Co Ltd filed Critical Nishimatsu Construction Co Ltd
Priority to JP2002065257A priority Critical patent/JP3625204B2/en
Publication of JP2003262096A publication Critical patent/JP2003262096A/en
Application granted granted Critical
Publication of JP3625204B2 publication Critical patent/JP3625204B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、トンネルを覆工するためのトンネル覆工装置およびトンネルの覆工方法に関する。
【0002】
【従来の技術】
山岳トンネルを覆工する方法として、従来から、断面アーチ形状のセントルを用いたトンネルの覆工方法が知られている。この方法は、地山を掘削して形成された掘削孔の内面に、この掘削孔よりも径が小さく設定されたセントルを挿入する。次いで、セントルに予め設けられた複数の開口部の一つから、覆工コンクリートが流通する圧送管を挿入して、掘削孔の内面とセントルの外面との間の間隙に覆工コンクリートを流し込む方法である。
【0003】
しかしながら、前記した方法では、打設位置を中心に山状に覆工コンクリートが打設されるので、覆工コンクリートが均等の高さに打設されるまでの横移動距離が長くなり、材料分離やブリージングが発生してコンクリートの品質が悪くなってしまう欠点があった。
また、バイブレータを覆工コンクリートを締め固めるのみならず、覆工コンクリートを間隙内部に均等に広げるために用いているので、バイブレータの操作に手間がかかる欠点もあった。
【0004】
このため、本出願人は鋭意検討した結果、特開2001−280094号公報に示すトンネル覆工装置およびトンネル覆工方法を提案した。前記公報記載の技術においては、圧送管から分岐した各分岐管の先端部が、水平方向に複数の開口部にそれぞれ挿入されている。これにより、各分岐管から覆工コンクリートを同時に打設できるため、覆工コンクリートが均等の高さに打設されるまでの横移動距離を短くして材料分離やブリージングを防止できるとともに、バイブレータで覆工コンクリートを間隙内部に均等に広げる手間が省ける。
【0005】
【発明が解決しようとする課題】
ところで、前記公報記載の技術においては、各分岐管が水平方向にのみ複数となる開口部にそれぞれ挿入されている。したがって、下方に位置する略同高さの複数の開口部に各分岐管を挿入して覆工コンクリートを打設し、所定の高さまで打設された後に、前記開口部より上部に位置する開口部に各分岐管を挿入して再び打設する、という方法が採用されている。すなわち、垂直方向の分岐管の盛り替え作業が必要であり、この作業に時間がかかると覆工コンクリートにコールドジョイントが発生し、品質が劣化してしまうことが指摘されてきた。
本発明の課題は、覆工コンクリートのコールドジョイントの発生を確実に防止することを可能とするトンネル覆工装置およびトンネルの覆工方法を提供することである。
【0006】
【課題を解決するための手段】
上記課題を解決するため、請求項1に記載の発明は、例えば図1〜図3に示すように、地山1を掘削することで形成される掘削孔2の内壁面に覆工コンクリート3を打設してトンネル4を覆工するために用いられ、
掘削孔2の内壁面との間に間隙5を形成するように設けられ、縦横に複数の開口部11aを有するセントル11と、このセントル11を型枠として前記間隙5に打設される覆工コンクリート3を圧送する圧送管12とを備えたトンネル覆工装置10であって、
前記圧送管12は、
水平方向に複数に分岐された水平分岐管(第1分岐管12a、第2分岐管12b)と、
これら水平分岐管における覆工コンクリートの流量を調整する調整手段(第1シャッタバルブ12d1、第2シャッタバルブ12e1)と、
さらに前記水平分岐管に接続し、垂直方向に複数に分岐され、前記開口部11aのうち垂直方向の複数の開口部11aにそれぞれ挿入する垂直分岐管(第3分岐管12c)と、
これら垂直分岐管における覆工コンクリート3の流量を調整する調整手段(第3シャッタバルブ12f1)と、
を備えることを特徴としている。
【0007】
請求項1に記載の発明によれば、複数の垂直分岐管を、水平方向の複数の開口部にそれぞれ挿入して覆工コンクリートを打設することができるため、覆工コンクリートが均等の高さに打設されるまでの横移動距離を短くして材料分離、ブリージングを防止できるとともに、バイブレータで覆工コンクリートを間隙内部に均等に広げる手間を省くことができる。
その上、垂直分岐管を垂直方向の複数の開口部にそれぞれ挿入することができる。そして、前記調整手段を調整することにより、最下部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートを打設し、順次、上部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートを打設することができる。したがって、垂直方向に分岐管の盛り替えを行うことなく覆工コンクリートの打設を効率良く行ってコールドジョイントの発生を確実に防止することができる。
【0008】
ここで、前記圧送管を複数の分岐管に分岐させる方法としては、例えば、前記圧送管に複数方向に開口する管状の連結継手を設け、これら連結継手それぞれに分岐管を連結する方法がある。
また、前記圧送管をトンネルの両側壁部に向けて分岐させ、それぞれの側壁部において覆工コンクリートを同時に打設することが好ましい。
【0009】
前記分岐管としては、金属製や、樹脂製のフレキシブルな管を用いることが好ましい。
また、前記圧送管には、この圧送管から上方に伸びて掘削孔の天井部に位置するセントルの開口部から前記間隙に覆工コンクリートを打設するための天井部圧送管を前記圧送管に連結するための継手を設けてもよい。
【0010】
ここで、前記調整手段としては、例えば、前記圧送管の流路断面積を調整可能なバルブや、前記圧送管の流路を途中で仕切るストッパ等がある。
【0013】
請求項2に記載の発明は、例えば図1〜図4に示すように、請求項1に記載のトンネル覆工装置10において、
前記間隙5に打設される覆工コンクリート3を締め固めるバイブレータ14と、
前記間隙5内で前記バイブレータ14を昇降させる昇降装置(ウィンチ13)とを備えることを特徴としている。
【0014】
請求項2に記載の発明によれば、前記昇降装置を操作することで、覆工コンクリートの打設高さに対応して、バイブレータを容易に昇降させることができるため、覆工コンクリートの締め固めを容易に行うことができる。
【0015】
ここで、前記昇降装置としては、例えば、ワイヤ等のバイブレータに接続される接続部材を備え、この接続部材を適宜巻き取ることができるウィンチを用いることができる。このウィンチおよび前記バイブレータを前記トンネル覆工装置に設けるには、前記接続部材に接続されたバイブレータを、前記開口部を挿通させて前記間隙内に設けるとともに、前記ウィンチを前記セントルの内部側に設置すればよい。
【0016】
請求項3に記載の発明は、例えば図1〜図4に示すように、請求項2に記載のトンネル覆工装置10において、
前記バイブレータ14を周囲から覆うフレーム部材(鋼製フレーム14a)を備えることを特徴としている。
【0017】
請求項3に記載の発明によれば、前記フレーム部材によってバイブレータが直接セントルに接触しないため、覆工コンクリートを打設する際のセントルの振動を低減して施工性を向上させることができる。
【0018】
請求項4に記載の発明は、例えば図1〜図4に示すように、請求項1〜3のいずれか一項に記載のトンネル覆工装置10を用いたトンネルの覆工方法であって、
前記圧送管12から分岐した複数の垂直分岐管(第3分岐管12c)を、前記複数の開口部11aにそれぞれ挿入し、
前記圧送管12に覆工コンクリート3を圧送するとともに、前記調整手段(第1シャッタバルブ12d1、第2シャッタバルブ12e1、第3シャッタバルブ12f1)を調整して、最下部の同じ高さに位置する複数の垂直分岐管(第3分岐管12c)から前記間隙5に覆工コンクリート3を打設し、
順次、上部の同じ高さに位置する複数の垂直分岐管(第3分岐管12c)から前記間隙5に覆工コンクリート3を打設することを特徴としている。
【0019】
請求項4に記載の発明によれば、複数の垂直分岐管を、水平方向の複数の開口部にそれぞれ挿入して覆工コンクリートを打設することができるため、覆工コンクリートが均等の高さに打設されるまでの横移動距離を短くして材料分離、ブリージングを防止できるとともに、バイブレータで覆工コンクリートを間隙内部に均等に広げる手間を省くことができる。
その上、垂直分岐管が垂直方向の複数の開口部に挿入された後、前記調整手段を調整することにより、最下部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートが打設される。そして、覆工コンクリートが前記間隙に下方から打設されることに対応しながら、前記調整手段を調整することにより、順次、上部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートが打設される。したがって、分岐管の盛り替えを行うことなく覆工コンクリートの打設を効率良く行ってコールドジョイントの発生を確実に防止することがことができる。
【0020】
【発明の実施の形態】
以下、図を参照して本発明の実施の形態を詳細に説明する。
【0021】
先ず、トンネル覆工装置10の構成を図1〜図4に基づいて説明する。
トンネル覆工装置10は、図1および図2に示すように、門型構11bを備えるセントル11、第1分岐管(水平分岐管)12a、第2分岐管(水平分岐管)12b、第3分岐管(垂直分岐管)12cを備える圧送管12、ワイヤ13a、滑車13bを備えるウィンチ13(昇降装置)、鋼製フレーム14aを備えるバイブレータ14等によって概略構成されている。
【0022】
セントル11は、掘削孔2の内壁面との間に間隙5を形成するように設けられ、覆工コンクリート3を打設する際の型枠となるものであり、縦横に所定間隔で形成された複数の開閉可能な開口部11aを備え、内側から門型構11bによって支持されている。
【0023】
門型構11bは、その下端部に設けられている複数の台車11b1によって、掘削孔2内部に施設されたレール上を移動可能である。
【0024】
圧送管12は、その基端部が覆工コンクリートを供給するコンクリートポンプ車に連結されるとともに、門型構11bの上面部に掘削孔2の軸方向に沿って設置されており、覆工コンクリート3を打設位置まで圧送する。圧送管12には、後述する天井部圧送管15を連結するための継手16が設けられている。
【0025】
圧送管12は2本の第1分岐管12aに横方向に分岐しており、これら第1分岐管12aはそれぞれ掘削孔2の両側壁部に向かって伸びている。そして、これら第1分岐管12aは3本の第2分岐管12bに横方向に分岐しており、これら第2分岐管12bの先端部は、2本の第3分岐管12cが下方に分岐しており、これら第3分岐管12cの先端部は、垂直方向に複数となる開口部11aに挿入されている。
【0026】
第1分岐管12aの分岐元には、2方向に分岐する管状の第1連結継手12dが設けられており、この第1連結継手12dにそれぞれ第1分岐管12aが連結されている。また、第1連結継手12dの2方向に分岐した部分には、流路面積を調整可能な第1シャッタバルブ12d1(調整手段)がそれぞれ設けられている。
【0027】
また、第2分岐管12bの分岐元には、3方向に分岐する管状の第2連結継手12eが設けられており、この第2連結継手12eにそれぞれ第2分岐管12bが連結されている。また、第2連結継手12eの3方向に分岐した部分には、流路面積を調整可能な第2シャッタバルブ12e1(調整手段)がそれぞれ設けられている。
【0028】
さらに、第3分岐管12cの分岐元には、2方向に分岐する管状の第3連結継手12fが設けられており、この第3連結継手12fにそれぞれ第3分岐管12cが連結されている。また、第3連結継手12fの2方向に分岐した部分には、流路面積を調整可能な第3シャッタバルブ12f1(調整手段)がそれぞれ設けられている。
【0029】
ウィンチ13は、門型構11bの上端部に複数設置されており、ワイヤ13aと滑車13bとを備えている。
【0030】
ワイヤ13aは、図3にも示すように、セントル11に形成された開口部11aを挿通するように設けられており、その基端側の所定長さをウィンチ13に巻き取られており、開口部11aから先端側は後述するバイブレータ14に接続されている。
【0031】
滑車13bは、ウィンチ13と前記開口部11aとの間となる門型構11bの上端部に、ワイヤ13aを掛けた状態で設置されている。
【0032】
バイブレータ14は、棒状の本体部の先端に、高周波により振動する振動部が設けられた構成となっているとともに、図4にも示すように、バイブレータ14を周囲から覆う鋼製フレーム14aを備える。
【0033】
鋼製フレーム14aはワイヤ13aの周囲を囲む第1リング部14a1と、バイブレータ14の周囲を囲む2つの第2リング部14a2と、第1リング部14a1および2つの第2リング部14a2を接続する複数の接続部14a3とで構成されている。
また、第2リング部14a2は、外周リング14a4と、バイブレータ14に固定されている内周リング14a5と、外周リング14a4と内周リング14a5とを接続している複数の接続部14a6とで構成されている。
なお、内周リング14a5とバイブレータ14との間には、図示しないゴム等の緩衝材が設けられており、バイブレータ14の振動が直接鋼製フレーム14aに伝わることが防止されている。
【0034】
次に、このトンネル覆工装置10によってトンネル4を覆工する方法について図1〜図4を参照して説明する。
【0035】
先ず、一次覆工がなされた掘削孔2の内壁面との間に間隙5が形成されるようにセントル11を配する。
【0036】
覆工コンクリート3の打設は、掘削孔2の両側壁部2a、2aと天井部2bとに分けて行う。
掘削孔2の両側壁部2a、2aに覆工コンクリート3を打設するには、左右の側壁部2aを交互に打設するか、両側壁部2a、2aを同時に打設する。本実施の形態では後者の方法で両側壁部2a、2aを覆工するが、分岐管の挿入については、以下に示すように一方の側壁部2aにおいて説明する。
【0037】
先ず、図1および図2に示すように、セントル11の一方の側壁部2aに形成されている開口部11aのうち、下方に略均等間隔で水平に位置する適当な開口部11aを3つ選択し、これら選択した開口部11aに、下方に位置する3本の第3分岐管12cを挿入する。同時に、前記3つの開口部11aより上方に略均等間隔で位置する開口部11aに、上方に位置する3本の第3分岐管12cの先端部を挿入する。
【0038】
なお、2つの第1シャッタバルブ13d1を調整して2本の第1分岐管12aを開放し、一方の(以下、一方の側壁部2aにおける説明)第1分岐管12aにおける3つの第2シャッタバルブ13e1を調整して3本の第2分岐管12bを開放しておく。また、各第2分岐管12bにおける計3つの第3シャッタバルブ12f1を調整して、下方に位置する3本の第3分岐管12cのみを開放して上方に位置する3本の第3分岐管12cを閉塞しておく。また、上方に位置する3本の第3分岐管12cの先端部より下方に位置する開口部11aは予め閉塞しておく。
【0039】
また、各ウィンチ13のワイヤ13aにそれぞれバイブレータ14を接続し、各ウィンチ13と略同高さに位置する開口部11aから間隙5内部に吊下げる。
【0040】
次いで、コンクリートポンプ車を操作して、覆工コンクリート3を圧送管12に圧送し、下方に位置する3本の第3分岐管12cから間隙5に同時に覆工コンクリート3を打設していく。
【0041】
なお、図3にも示すように、ウィンチ13を適宜操作して、バイブレータ14を、打設される覆工コンクリート3の上部付近に常に位置させて締め固める。
【0042】
そして、第2分岐管12bの先端部付近まで覆工コンクリート3が打設されたら、3つの第2シャッタバルブ12e1を調整して、下方に位置する3本の第3分岐管12cを閉塞して上方に位置する3本の第3分岐管12cを閉塞する。そして、上方に位置する3本の第3分岐管12cから同時に覆工コンクリート3を打設していく。
【0043】
同様にして、他方の側壁部2aに覆工コンクリートを打設する。以上により、掘削孔2の両側壁部2a、2aに覆工コンクリート3を打設することができる。
【0044】
次いで、図1に示すように、掘削孔2の天井部2bに覆工コンクリート3を打設する。先ず、2つの第1シャッタバルブ12d1を調整して2本の第1分岐管12aを閉塞しておくとともに、天井部圧送管15を継手16に連結し、この天井部圧送管15を、掘削孔2の天井部2b近傍の開口部11aに挿入する。さらに、バイブレータ14を天井部2b近傍の開口部11aを挿通させて間隙5に設ける。
【0045】
次いで、コンクリートポンプ車を操作して、覆工コンクリート3を圧送管12に圧送し、天井部圧送管15から間隙5に覆工コンクリート3を打設するとともに、バイブレータ14を駆動させて覆工コンクリート3を締め固める。覆工コンクリート3の打設および締め固めが終了したら、天井部圧送管15およびバイブレータ14を間隙5から取り出す。
以上により、掘削孔2の天井部2bに覆工コンクリート3を打設することができる。
【0046】
本実施の形態によれば以下のような効果を得ることができる。
(1)(一方の側壁部2aにおいて)6本の第3分岐管12cが、前記開口部11aのうち、垂直方向に2列、水平方向に3列の6個の開口部11aに挿入された後、3つの第3シャッタバルブ12f1を調整することにより、最下部に位置する3本の第3分岐管12cから覆工コンクリート3が打設される。そして、覆工コンクリート3が前記間隙5に下方から打設されることに対応しながら、3つの第3シャッタバルブ12f1を調整することにより、順次、上部に位置する3本の第3分岐管12cから覆工コンクリート3が打設される。したがって、分岐管の盛り替えを行うことなく覆工コンクリート3の打設を効率良く行ってコールドジョイントの発生を確実に防止することがことができる。
【0047】
(2)また、前記したように、上部に位置する3本の第3分岐管12cと下部に位置する3本の第3分岐管12cとが、前記開口部11aのうち水平方向に3列の開口部11aに挿入された後に覆工コンクリート3が打設されるので、覆工コンクリート3が均等の高さに打設されるまでの横移動距離を短くして、材料分離、ブリージングを防止できるとともに、バイブレータ14で覆工コンクリート3を間隙内部に均等に広げる手間を省くことができる。
【0048】
▲3▼ウィンチ13を操作することで、覆工コンクリート3の打設高さに対応して、バイブレータ14を容易に昇降させることができるため、覆工コンクリート3の締め固めを容易に行うことができる。
【0049】
▲4▼鋼製フレーム14aによってバイブレータ14が直接セントル11に接触しないため、覆工コンクリート3を打設する際のセントル11の振動を低減して施工性を向上させることができる。
【0050】
▲5▼掘削孔2の両側壁部2a、2aに同時に覆工コンクリート3が打設されるので、セントル11に作用する荷重の左右のバランスが良くなり、覆工コンクリート3の打設を安定的に行うことができる。
【0051】
本実施の形態においては、掘削孔2の両側壁部2a、2aに同時に覆工コンクリート3を打設しているが、両側壁部2a、2aに交互に覆工コンクリート3を打設する場合には、先ず、2本の第1分岐管12aのうち、一方の側壁部2aに向かう第1分岐管12aのみを開放し、開放された第1分岐管12aから分岐する第2分岐管12bおよび第3分岐管12cから一方の側壁部2aに打設を行う。一方の側壁部2aの打設が完了したら、前記一方の側壁部2aに向かう第1分岐管12aを閉塞するとともに他方の第1分岐管12aを開放し、開放された第1分岐管12aから分岐する第2分岐管12bおよび第3分岐管12cから他方の側壁部2aに打設を行えばよい。
【0052】
また、本実施の形態においては、圧送管12から2本の第1分岐管12aが横方向に分岐し、各第1分岐管12aからそれぞれ3本の第2分岐管12bが横方向に分岐し、さらに各第2分岐管12bからそれぞれ2本の第3分岐管12cが縦方向に分岐する構成としている。しかし、本発明は前記構成に限定されるものではなく、分岐管の数や分岐する方向は任意である。
【0053】
【発明の効果】
請求項1に記載の発明によれば、複数の垂直分岐管を、水平方向の複数の開口部にそれぞれ挿入して覆工コンクリートを打設することができるため、覆工コンクリートが均等の高さに打設されるまでの横移動距離を短くして材料分離、ブリージングを防止できるとともに、バイブレータで覆工コンクリートを間隙内部に均等に広げる手間を省くことができる。
その上、垂直分岐管を垂直方向の複数の開口部にそれぞれ挿入することができる。そして、前記調整手段を調整することにより、最下部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートを打設し、順次、上部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートを打設することができる。したがって、分岐管の盛り替えを行うことなく覆工コンクリートの打設を効率良く行ってコールドジョイントの発生を確実に防止することができる。
【0055】
請求項2に記載の発明によれば、請求項1に記載の発明と同様の効果を得ることができることは勿論のこと、覆工コンクリートの締め固めを容易に行うことができる。
【0056】
請求項3に記載の発明によれば、請求項2に記載の発明と同様の効果を得ることができることは勿論のこと、覆工コンクリートを打設する際のセントルの振動を低減して施工性を向上させることができる。
【0057】
請求項4に記載の発明によれば、複数の垂直分岐管を、水平方向の複数の開口部にそれぞれ挿入して覆工コンクリートを打設することができるため、覆工コンクリートが均等の高さに打設されるまでの横移動距離を短くして材料分離、ブリージングを防止できるとともに、バイブレータで覆工コンクリートを間隙内部に均等に広げる手間を省くことができる。
その上、垂直分岐管が垂直方向の複数の開口部に挿入された後、前記調整手段を調整することにより、最下部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートが打設される。そして、覆工コンクリートが前記間隙に下方から打設されることに対応しながら、前記調整手段を調整することにより、順次、上部の同じ高さに位置する複数の垂直分岐管から覆工コンクリートが打設される。したがって、分岐管の盛り替えを行うことなく覆工コンクリートの打設を効率良く行ってコールドジョイントの発生を確実に防止することがことができる。
【図面の簡単な説明】
【図1】本発明の実施の形態例において、トンネル覆工装置の全体構成を示す、掘削孔の軸と直交方向の断面図である。
【図2】本発明の実施の形態例において、トンネル覆工装置の全体構成を示す、掘削孔の平断面図である。
【図3】同、バイブレータを順次上昇させていく状況を示す、掘削孔の側断面図である。
【図4】同、バイブレータを周囲から覆う鋼製フレームを示す斜視図である。
【符号の説明】
1 地山
2 掘削孔
3 覆工コンクリート
4 トンネル
5 間隙
10 トンネル覆工装置
11 セントル
11a 開口部
11b 門型構
12 圧送管
12a 第1分岐管(水平分岐管)
12b 第2分岐管(水平分岐管)
12c 第3分岐管(垂直分岐管)
12d1 第1シャッタバルブ
12e1 第2シャッタバルブ
12f1 第3シャッタバルブ
13 ウィンチ
14 バイブレータ
14a フレーム(フレーム部材)
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a tunnel lining device and a tunnel lining method for lining a tunnel.
[0002]
[Prior art]
As a method for lining a mountain tunnel, conventionally, a tunnel lining method using a centle having a cross-sectional arch shape is known. In this method, a centle having a diameter smaller than that of the excavation hole is inserted into the inner surface of the excavation hole formed by excavating the natural ground. Next, a method of inserting a pressure feed pipe through which the lining concrete flows from one of a plurality of openings provided in advance in the centle, and pouring the lining concrete into a gap between the inner surface of the excavation hole and the outer surface of the centle. It is.
[0003]
However, in the above-described method, since the lining concrete is cast in a mountain shape around the placement position, the lateral movement distance until the lining concrete is placed at a uniform height is increased, and the material separation is performed. There is a drawback that the quality of concrete deteriorates due to the occurrence of bleeding.
Moreover, since the vibrator is used not only to compact the lining concrete but also to spread the lining concrete evenly in the gap, there is a drawback that it takes time to operate the vibrator.
[0004]
For this reason, as a result of intensive studies, the present applicant has proposed a tunnel lining apparatus and a tunnel lining method disclosed in Japanese Patent Application Laid-Open No. 2001-280094. In the technique described in the above publication, the distal ends of the branch pipes branched from the pressure feeding pipe are respectively inserted into the plurality of openings in the horizontal direction. As a result, lining concrete can be poured from each branch pipe at the same time, so the lateral movement distance until the lining concrete is cast to a uniform height can be shortened to prevent material separation and breathing. This saves you the trouble of spreading the lining concrete evenly inside the gap.
[0005]
[Problems to be solved by the invention]
By the way, in the technique described in the publication, each branch pipe is inserted into a plurality of openings only in the horizontal direction. Therefore, after inserting each branch pipe into a plurality of openings at substantially the same height located below and placing the lining concrete, the openings located above the openings after being placed to a predetermined height. The method of inserting each branch pipe into the part and placing it again is adopted. That is, it has been pointed out that it is necessary to replace the branch pipe in the vertical direction, and if this operation takes time, a cold joint is generated in the lining concrete and the quality deteriorates.
An object of the present invention is to provide a tunnel lining device and a tunnel lining method that can reliably prevent the occurrence of a cold joint of lining concrete.
[0006]
[Means for Solving the Problems]
In order to solve the above-mentioned problem, the invention according to claim 1, for example, as shown in FIG. 1 to FIG. 3, lining concrete 3 is applied to the inner wall surface of the excavation hole 2 formed by excavating the natural ground 1. Used to cast and lining the tunnel 4,
A centle 11 that is provided so as to form a gap 5 between the inner wall surface of the excavation hole 2 and has a plurality of openings 11a vertically and horizontally, and a lining that is placed in the gap 5 by using the centle 11 as a mold. A tunnel lining device 10 including a pressure feeding pipe 12 for feeding concrete 3 by pressure,
The pressure feeding pipe 12 is
A horizontal branch pipe (first branch pipe 12a, second branch pipe 12b) branched in a plurality in the horizontal direction;
Adjusting means (first shutter valve 12d1, second shutter valve 12e1) for adjusting the flow rate of the lining concrete in these horizontal branch pipes;
Furthermore, a vertical branch pipe (third branch pipe 12c) connected to the horizontal branch pipe, branched into a plurality of vertical directions, and respectively inserted into the plurality of vertical openings 11a among the openings 11a,
Adjusting means (third shutter valve 12f1) for adjusting the flow rate of the lining concrete 3 in these vertical branch pipes;
It is characterized by having.
[0007]
According to the first aspect of the present invention, since the lining concrete can be placed by inserting a plurality of vertical branch pipes into the plurality of horizontal openings, respectively, the lining concrete has a uniform height. In addition to shortening the lateral movement distance until it is placed on the material, it is possible to prevent material separation and breathing, and it is possible to save time and effort to evenly spread the lining concrete inside the gap with a vibrator.
In addition, the vertical branch pipes can be respectively inserted into the plurality of openings in the vertical direction. And by adjusting the adjusting means, the lining concrete is placed from the plurality of vertical branch pipes located at the same height in the lowermost part, and sequentially from the plurality of vertical branch pipes located at the same height in the upper part. Lined concrete can be cast. Therefore, it is possible to efficiently prevent the occurrence of a cold joint by efficiently placing the lining concrete without changing the branch pipe in the vertical direction.
[0008]
Here, as a method of branching the pressure feed pipe into a plurality of branch pipes, for example, there is a method in which a tubular connection joint that opens in a plurality of directions is provided in the pressure feed pipe, and a branch pipe is connected to each of the connection joints.
Moreover, it is preferable to branch the said pressure feeding pipe toward the both-sides wall part of a tunnel, and to cast lining concrete simultaneously in each side wall part.
[0009]
As the branch pipe, it is preferable to use a flexible pipe made of metal or resin.
In addition, the pumping pipe has a ceiling pumping pipe extending upward from the pumping pipe for placing lining concrete in the gap from an opening of a centle located at the ceiling of the excavation hole. You may provide the coupling for connecting.
[0010]
Here, examples of the adjusting means include a valve capable of adjusting the flow path cross-sectional area of the pressure feed pipe, a stopper that partitions the flow path of the pressure feed pipe in the middle, and the like.
[0013]
The invention according to claim 2 is the tunnel lining apparatus 10 according to claim 1, for example, as shown in FIGS.
A vibrator 14 for compacting the lining concrete 3 placed in the gap 5;
An elevating device (winch 13) for elevating the vibrator 14 in the gap 5 is provided.
[0014]
According to the second aspect of the present invention, the vibrator can be easily moved up and down in accordance with the placement height of the lining concrete by operating the lifting device. Can be easily performed.
[0015]
Here, as the lifting device, for example, a winch that includes a connecting member connected to a vibrator such as a wire and can wind up the connecting member as appropriate can be used. In order to provide the winch and the vibrator in the tunnel lining device, a vibrator connected to the connection member is provided in the gap through the opening, and the winch is provided on the inner side of the centle. do it.
[0016]
The invention according to claim 3 is the tunnel lining apparatus 10 according to claim 2, for example, as shown in FIGS.
A frame member (steel frame 14a) that covers the vibrator 14 from the periphery is provided.
[0017]
According to invention of Claim 3, since a vibrator does not contact a centle directly with the said frame member, the vibration of the centle at the time of placing covering concrete can be reduced, and workability | operativity can be improved.
[0018]
The invention according to claim 4 is a tunnel lining method using the tunnel lining device 10 according to any one of claims 1 to 3, for example, as shown in FIGS.
A plurality of vertical branch pipes (third branch pipes 12c) branched from the pressure feed pipe 12 are respectively inserted into the plurality of openings 11a,
The lining concrete 3 is pumped to the pumping pipe 12, and the adjusting means (the first shutter valve 12d1, the second shutter valve 12e1, and the third shutter valve 12f1) are adjusted to be positioned at the same height at the bottom. Placing the lining concrete 3 into the gap 5 from a plurality of vertical branch pipes (third branch pipes 12c),
The lining concrete 3 is sequentially placed in the gap 5 from a plurality of vertical branch pipes (third branch pipes 12c) positioned at the same height in the upper part.
[0019]
According to the invention described in claim 4, since the lining concrete can be placed by inserting the plurality of vertical branch pipes into the plurality of horizontal openings, respectively, the lining concrete has a uniform height. In addition to shortening the lateral movement distance until it is placed on the material, it is possible to prevent material separation and breathing, and it is possible to save time and effort to evenly spread the lining concrete inside the gap with a vibrator.
In addition, after the vertical branch pipes are inserted into the plurality of vertical openings, the adjusting means is adjusted so that the lining concrete is cast from the plurality of vertical branch pipes located at the same height at the bottom. Is done. Then, by adjusting the adjusting means while corresponding to the fact that the lining concrete is placed in the gap from below, the lining concrete is sequentially removed from the plurality of vertical branch pipes located at the same height on the upper part. It is cast. Therefore, it is possible to efficiently prevent the occurrence of a cold joint by efficiently placing the lining concrete without replacing the branch pipe.
[0020]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
[0021]
First, the structure of the tunnel lining apparatus 10 is demonstrated based on FIGS. 1-4.
As shown in FIGS. 1 and 2, the tunnel lining apparatus 10 includes a center 11 having a portal structure 11b, a first branch pipe (horizontal branch pipe) 12a, a second branch pipe (horizontal branch pipe) 12b, a third A pressure feed pipe 12 having a branch pipe (vertical branch pipe) 12c, a wire 13a, a winch 13 (elevating device) having a pulley 13b, a vibrator 14 having a steel frame 14a, and the like are schematically configured.
[0022]
The center 11 is provided so as to form a gap 5 with the inner wall surface of the excavation hole 2 and serves as a formwork for placing the lining concrete 3 and is formed at predetermined intervals in the vertical and horizontal directions. It has a plurality of openable and closable openings 11a and is supported from the inside by a gate structure 11b.
[0023]
The gate-type structure 11b is movable on a rail provided inside the excavation hole 2 by a plurality of carriages 11b1 provided at the lower end thereof.
[0024]
The pressure-feed pipe 12 is connected to a concrete pump truck whose base end portion supplies lining concrete, and is installed along the axial direction of the excavation hole 2 on the upper surface portion of the portal structure 11b. 3 is pumped to the placement position. The pressure feed pipe 12 is provided with a joint 16 for connecting a ceiling part pressure feed pipe 15 described later.
[0025]
The pressure feeding pipe 12 branches laterally into two first branch pipes 12 a, and these first branch pipes 12 a extend toward both side walls of the excavation hole 2. These first branch pipes 12a branch laterally into three second branch pipes 12b. At the tip of these second branch pipes 12b, two third branch pipes 12c branch downward. The distal ends of the third branch pipes 12c are inserted into a plurality of openings 11a in the vertical direction.
[0026]
A branching source of the first branch pipe 12a is provided with a tubular first connecting joint 12d that branches in two directions, and the first branch pipe 12a is connected to the first connecting joint 12d. A first shutter valve 12d1 (adjusting means) capable of adjusting the flow path area is provided at a portion branched in two directions of the first coupling joint 12d.
[0027]
In addition, a tubular second coupling joint 12e that branches in three directions is provided at the branching source of the second branch pipe 12b, and the second branch pipe 12b is coupled to the second coupling joint 12e. A second shutter valve 12e1 (adjusting means) capable of adjusting the flow path area is provided at each of the portions of the second coupling joint 12e branched in three directions.
[0028]
Further, a branching source of the third branch pipe 12c is provided with a tubular third connecting joint 12f that branches in two directions, and the third branch pipe 12c is connected to the third connecting joint 12f. A third shutter valve 12f1 (adjusting means) capable of adjusting the flow path area is provided at a portion branched in two directions of the third coupling joint 12f.
[0029]
A plurality of winches 13 are installed at the upper end of the gate structure 11b, and include a wire 13a and a pulley 13b.
[0030]
As shown in FIG. 3, the wire 13 a is provided so as to pass through the opening 11 a formed in the center 11, and a predetermined length on the base end side is wound around the winch 13. The tip side from the portion 11a is connected to a vibrator 14 described later.
[0031]
The pulley 13b is installed in a state where a wire 13a is hung on an upper end portion of a gate-type structure 11b between the winch 13 and the opening portion 11a.
[0032]
The vibrator 14 has a structure in which a vibration part that vibrates by high frequency is provided at the tip of a rod-shaped main body part, and also includes a steel frame 14a that covers the vibrator 14 from the periphery as shown in FIG.
[0033]
The steel frame 14a includes a first ring portion 14a1 surrounding the wire 13a, two second ring portions 14a2 surrounding the vibrator 14, and a plurality of first ring portions 14a1 and two second ring portions 14a2. The connecting portion 14a3.
The second ring portion 14a2 includes an outer peripheral ring 14a4, an inner peripheral ring 14a5 fixed to the vibrator 14, and a plurality of connection portions 14a6 connecting the outer peripheral ring 14a4 and the inner peripheral ring 14a5. ing.
A cushioning material such as rubber (not shown) is provided between the inner ring 14a5 and the vibrator 14, so that vibration of the vibrator 14 is not directly transmitted to the steel frame 14a.
[0034]
Next, a method for lining the tunnel 4 by the tunnel lining device 10 will be described with reference to FIGS.
[0035]
First, the centle 11 is arranged so that the gap 5 is formed between the inner wall surface of the excavation hole 2 subjected to the primary lining.
[0036]
Placing the lining concrete 3 is performed separately on both side walls 2a, 2a of the excavation hole 2 and the ceiling 2b.
In order to place the lining concrete 3 on both side walls 2a, 2a of the excavation hole 2, the left and right side walls 2a are alternately placed or both side walls 2a, 2a are placed simultaneously. In this embodiment, the both side walls 2a and 2a are covered by the latter method, but the insertion of the branch pipe will be described in one side wall 2a as described below.
[0037]
First, as shown in FIG. 1 and FIG. 2, among the openings 11 a formed on one side wall 2 a of the centle 11, three appropriate openings 11 a positioned horizontally at substantially equal intervals are selected below. Then, the three third branch pipes 12c positioned below are inserted into the selected openings 11a. At the same time, the tip portions of the three third branch pipes 12c located above are inserted into the openings 11a located at substantially equal intervals above the three openings 11a.
[0038]
It should be noted that the two first shutter valves 13d1 are adjusted to open the two first branch pipes 12a, and the three second shutter valves in one of the first branch pipes 12a (hereinafter, explanation on one side wall portion 2a). 13e1 is adjusted to open the three second branch pipes 12b. In addition, a total of three third shutter valves 12f1 in each second branch pipe 12b are adjusted, and only the three third branch pipes 12c located below are opened and three third branch pipes located above are opened. 12c is closed. Moreover, the opening part 11a located below the front-end | tip part of the three 3rd branch pipes 12c located above is obstruct | occluded beforehand.
[0039]
Further, the vibrator 14 is connected to the wire 13 a of each winch 13, and is hung inside the gap 5 from the opening 11 a located at substantially the same height as each winch 13.
[0040]
Next, the concrete pump car is operated to pressure-feed the lining concrete 3 to the pressure-feeding pipe 12, and the lining concrete 3 is simultaneously placed in the gap 5 from the three third branch pipes 12 c located below.
[0041]
As shown in FIG. 3, the winch 13 is appropriately operated so that the vibrator 14 is always positioned near the upper portion of the lining concrete 3 to be placed and compacted.
[0042]
Then, when the lining concrete 3 is placed up to the vicinity of the tip of the second branch pipe 12b, the three second shutter valves 12e1 are adjusted to close the three third branch pipes 12c located below. The three third branch pipes 12c located above are closed. Then, the lining concrete 3 is poured simultaneously from the three third branch pipes 12c located above.
[0043]
Similarly, lining concrete is placed on the other side wall 2a. As described above, the lining concrete 3 can be placed on the both side walls 2a, 2a of the excavation hole 2.
[0044]
Next, as shown in FIG. 1, lining concrete 3 is placed on the ceiling 2 b of the excavation hole 2. First, the two first shutter valves 12d1 are adjusted to close the two first branch pipes 12a, and the ceiling part pressure feed pipe 15 is connected to the joint 16, and the ceiling part pressure feed pipe 15 is connected to the excavation hole. 2 is inserted into the opening 11a in the vicinity of the ceiling 2b. Further, the vibrator 14 is provided in the gap 5 through the opening 11a in the vicinity of the ceiling 2b.
[0045]
Next, the concrete pump car is operated to pump the lining concrete 3 to the pressure feeding pipe 12, and the lining concrete 3 is placed in the gap 5 from the ceiling pressure feeding pipe 15 and the vibrator 14 is driven to cover the concrete. 3 is tightened. When the placing and compacting of the lining concrete 3 is finished, the ceiling portion pressure feeding pipe 15 and the vibrator 14 are taken out from the gap 5.
Thus, the lining concrete 3 can be placed on the ceiling 2b of the excavation hole 2.
[0046]
According to the present embodiment, the following effects can be obtained.
(1) Six third branch pipes 12c (in one side wall 2a) are inserted into six openings 11a in two rows in the vertical direction and three rows in the horizontal direction among the openings 11a. Thereafter, by adjusting the three third shutter valves 12f1, the lining concrete 3 is driven from the three third branch pipes 12c located at the lowermost part. Then, the three third branch pipes 12c positioned in the upper part are sequentially adjusted by adjusting the three third shutter valves 12f1 while the lining concrete 3 is placed in the gap 5 from below. The lining concrete 3 is laid. Therefore, it is possible to efficiently prevent the occurrence of a cold joint by efficiently placing the lining concrete 3 without replacing the branch pipe.
[0047]
(2) Further, as described above, the three third branch pipes 12c located in the upper part and the three third branch pipes 12c located in the lower part are arranged in three rows in the horizontal direction in the opening 11a. Since the lining concrete 3 is placed after being inserted into the opening portion 11a, the lateral movement distance until the lining concrete 3 is placed at a uniform height can be shortened to prevent material separation and breathing. At the same time, it is possible to save the labor of spreading the lining concrete 3 evenly in the gap with the vibrator 14.
[0048]
(3) By operating the winch 13, the vibrator 14 can be easily raised and lowered in accordance with the placement height of the lining concrete 3, so that the lining concrete 3 can be compacted easily. it can.
[0049]
(4) Since the vibrator 14 is not in direct contact with the centle 11 by the steel frame 14a, it is possible to reduce the vibration of the centle 11 when placing the lining concrete 3 and improve the workability.
[0050]
(5) Since the lining concrete 3 is simultaneously placed on the both side walls 2a and 2a of the excavation hole 2, the right and left balance of the load acting on the centle 11 is improved and the placement of the lining concrete 3 is stable. Can be done.
[0051]
In the present embodiment, the lining concrete 3 is simultaneously placed on both side walls 2a and 2a of the excavation hole 2, but when the lining concrete 3 is alternately placed on both side walls 2a and 2a. First, of the two first branch pipes 12a, only the first branch pipe 12a toward the one side wall portion 2a is opened, and the second branch pipe 12b branched from the opened first branch pipe 12a and the second branch pipe 12a are opened. The three branch pipes 12c are driven into one side wall 2a. When the placement of the one side wall 2a is completed, the first branch pipe 12a toward the one side wall 2a is closed, the other first branch pipe 12a is opened, and the first branch pipe 12a is branched. The second branch pipe 12b and the third branch pipe 12c to be placed may be placed on the other side wall 2a.
[0052]
In the present embodiment, two first branch pipes 12a branch from the pressure feed pipe 12 in the horizontal direction, and three second branch pipes 12b branch from the first branch pipes 12a in the horizontal direction. Furthermore, two third branch pipes 12c are branched from each second branch pipe 12b in the vertical direction. However, the present invention is not limited to the above configuration, and the number of branch pipes and the branching direction are arbitrary.
[0053]
【The invention's effect】
According to the first aspect of the present invention, since the lining concrete can be placed by inserting a plurality of vertical branch pipes into the plurality of horizontal openings, respectively, the lining concrete has a uniform height. In addition to shortening the lateral movement distance until it is placed on the material, it is possible to prevent material separation and breathing, and it is possible to save time and effort to evenly spread the lining concrete inside the gap with a vibrator.
In addition, the vertical branch pipes can be respectively inserted into the plurality of openings in the vertical direction. And by adjusting the adjusting means, the lining concrete is placed from the plurality of vertical branch pipes located at the same height in the lowermost part, and sequentially from the plurality of vertical branch pipes located at the same height in the upper part. Lined concrete can be cast. Therefore, it is possible to efficiently prevent the occurrence of a cold joint by efficiently placing the lining concrete without replacing the branch pipe.
[0055]
According to the second aspect of the invention, the same effect as that of the first aspect of the invention can be obtained, and the lining concrete can be easily compacted.
[0056]
According to the invention described in claim 3, the same effect as that of the invention described in claim 2 can be obtained. Can be improved.
[0057]
According to the invention described in claim 4, since the lining concrete can be placed by inserting the plurality of vertical branch pipes into the plurality of horizontal openings, respectively, the lining concrete has a uniform height. In addition to shortening the lateral movement distance until it is placed on the material, it is possible to prevent material separation and breathing, and it is possible to save time and effort to evenly spread the lining concrete inside the gap with a vibrator.
In addition, after the vertical branch pipes are inserted into the plurality of vertical openings, the adjusting means is adjusted so that the lining concrete is cast from the plurality of vertical branch pipes located at the same height at the bottom. Is done. Then, by adjusting the adjusting means while corresponding to the fact that the lining concrete is placed in the gap from below, the lining concrete is sequentially removed from the plurality of vertical branch pipes located at the same height on the upper part. It is cast. Therefore, it is possible to efficiently prevent the occurrence of a cold joint by efficiently placing the lining concrete without replacing the branch pipe.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view perpendicular to an axis of an excavation hole showing the overall configuration of a tunnel lining apparatus in an embodiment of the present invention.
FIG. 2 is a plan sectional view of an excavation hole showing the overall configuration of the tunnel lining device in the embodiment of the present invention.
FIG. 3 is a side sectional view of the excavation hole showing a situation where the vibrator is sequentially raised.
FIG. 4 is a perspective view showing a steel frame that covers the vibrator from the periphery.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Ground mountain 2 Excavation hole 3 Covering concrete 4 Tunnel 5 Crevice 10 Tunnel lining apparatus 11 Centle 11a Opening part 11b Gate type structure 12 Pumping pipe 12a 1st branch pipe (horizontal branch pipe)
12b Second branch pipe (horizontal branch pipe)
12c 3rd branch pipe (vertical branch pipe)
12d1 first shutter valve 12e1 second shutter valve 12f1 third shutter valve 13 winch 14 vibrator 14a frame (frame member)

Claims (4)

地山を掘削することで形成される掘削孔の内壁面に覆工コンクリートを打設してトンネルを覆工するために用いられ、
掘削孔の内壁面との間に間隙を形成するように設けられ、縦横に複数の開口部を有するセントルと、このセントルを型枠として前記間隙に打設される覆工コンクリートを圧送する圧送管とを備えたトンネル覆工装置であって、
前記圧送管は、
水平方向に複数に分岐された水平分岐管と、
これら水平分岐管における覆工コンクリートの流量を調整する調整手段と、
さらに前記水平分岐管に接続し、垂直方向に複数に分岐され、前記開口部のうち垂直方向の複数の開口部にそれぞれ挿入する垂直分岐管と、
これら垂直分岐管における覆工コンクリートの流量を調整する調整手段と、
を備えることを特徴とするトンネル覆工装置。
Used to lining the tunnel by placing concrete lining on the inner wall of the excavation hole formed by excavating the natural ground,
A centle that is provided so as to form a gap between the inner wall surface of the excavation hole and has a plurality of openings in the vertical and horizontal directions, and a pressure feed pipe that pressure-feeds the lining concrete placed in the gap by using the centle as a mold. A tunnel lining device comprising:
The pressure feeding pipe is
A horizontal branch pipe branched into a plurality of horizontal directions;
Adjusting means for adjusting the flow rate of lining concrete in these horizontal branch pipes;
A vertical branch pipe connected to the horizontal branch pipe, branched into a plurality in the vertical direction, and respectively inserted into a plurality of vertical openings in the openings;
Adjusting means for adjusting the flow rate of the lining concrete in these vertical branch pipes,
A tunnel lining device comprising:
前記間隙に打設される覆工コンクリートを締め固めるバイブレータと、
このバイブレータを前記間隙内で昇降させる昇降装置とを備えることを特徴とする請求項1に記載のトンネル覆工装置。
A vibrator for compacting the lining concrete placed in the gap;
The tunnel lining device according to claim 1, further comprising a lifting device that lifts and lowers the vibrator in the gap.
前記バイブレータを周囲から覆うフレーム部材を備えることを特徴とする請求項2に記載のトンネル覆工装置。The tunnel lining apparatus according to claim 2, further comprising a frame member that covers the vibrator from the periphery. 請求項1〜3のいずれか一項に記載のトンネル覆工装置を用いたトンネル覆工方法であって、
前記圧送管から分岐した複数の垂直分岐管を、前記複数の開口部にそれぞれ挿入し、
前記圧送管に覆工コンクリートを圧送するとともに、前記調整手段を調整して、最下部の同じ高さに位置する複数の垂直分岐管から前記間隙に覆工コンクリートを打設し、
順次、上部の同じ高さに位置する垂直分岐管から前記間隙に覆工コンクリートを打設することを特徴とするトンネル覆工方法。
A tunnel lining method using the tunnel lining device according to any one of claims 1 to 3,
A plurality of vertical branch pipes branched from the pressure feed pipe are respectively inserted into the plurality of openings,
While pumping the lining concrete to the pumping pipe, adjusting the adjusting means, placing the lining concrete into the gap from a plurality of vertical branch pipes located at the same height at the bottom,
A tunnel lining method characterized by sequentially placing lining concrete in the gap from a vertical branch pipe located at the same height in the upper part.
JP2002065257A 2002-03-11 2002-03-11 Tunnel lining device and tunnel lining method Expired - Fee Related JP3625204B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002065257A JP3625204B2 (en) 2002-03-11 2002-03-11 Tunnel lining device and tunnel lining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002065257A JP3625204B2 (en) 2002-03-11 2002-03-11 Tunnel lining device and tunnel lining method

Publications (2)

Publication Number Publication Date
JP2003262096A JP2003262096A (en) 2003-09-19
JP3625204B2 true JP3625204B2 (en) 2005-03-02

Family

ID=29197652

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002065257A Expired - Fee Related JP3625204B2 (en) 2002-03-11 2002-03-11 Tunnel lining device and tunnel lining method

Country Status (1)

Country Link
JP (1) JP3625204B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106499410A (en) * 2016-11-13 2017-03-15 中铁十局集团第工程有限公司 Tunnel-liner side wall concrete is by window placement layer by layer method
CN106761828A (en) * 2016-12-29 2017-05-31 中铁十九局集团第工程有限公司 A kind of lining trolley

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009127229A (en) * 2007-11-21 2009-06-11 Okumura Corp Tunnel lining concrete placing method
JP4931777B2 (en) * 2007-11-21 2012-05-16 株式会社奥村組 Tunnel lining concrete placement management method
JP4863308B2 (en) * 2008-10-24 2012-01-25 飛島建設株式会社 Tunnel lining concrete placement switching device and placement switching method
JP5945436B2 (en) * 2012-03-16 2016-07-05 前田建設工業株式会社 Vibrator for concrete compaction and concrete compaction method
CN103032082A (en) * 2012-12-14 2013-04-10 中铁隧道集团一处有限公司 Tunnel lining trolley material distribution mechanism
JP5843293B2 (en) * 2013-09-26 2016-01-13 テクノプロ株式会社 Lined concrete placing apparatus and method, and mobile centle
JP7241339B2 (en) * 2019-01-29 2023-03-17 株式会社奥村組 Arrangement structure of plate members for joint formation
CN110566231B (en) * 2019-08-08 2024-07-30 福建祝融工程机械有限公司 Trolley distributing system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106499410A (en) * 2016-11-13 2017-03-15 中铁十局集团第工程有限公司 Tunnel-liner side wall concrete is by window placement layer by layer method
CN106499410B (en) * 2016-11-13 2018-08-14 中铁十一局集团第一工程有限公司 Tunnel-liner side wall concrete is by window placement layer by layer method
CN106761828A (en) * 2016-12-29 2017-05-31 中铁十九局集团第工程有限公司 A kind of lining trolley
CN106761828B (en) * 2016-12-29 2018-07-13 中铁十九局集团第一工程有限公司 A kind of lining trolley

Also Published As

Publication number Publication date
JP2003262096A (en) 2003-09-19

Similar Documents

Publication Publication Date Title
JP3625204B2 (en) Tunnel lining device and tunnel lining method
JP4931777B2 (en) Tunnel lining concrete placement management method
CN108505448A (en) Pier cap beam anchor ear girder steel template system and its construction method
JP5826350B2 (en) Concrete placement method
JP2020023864A (en) Tunnel lining concrete placement method
JP2001280094A (en) Tunnel lining device and tunnel lining method
JP5726496B2 (en) Concrete placement equipment and concrete placement method
JP2020023797A (en) Method for placing concrete used for lining on upper end portion of tunnel
JP2008088696A (en) Tunnel lining construction method
CN208668279U (en) Pier cap beam anchor ear girder steel template system
CN106217639A (en) Ladder-type sleepers prefabricated construction device and method
CN107882337A (en) It is limited for working space, the concrete in close packed structure region synthesis makes method firm by ramming
JP4799453B2 (en) Tunnel lining concrete placement method
JP4524756B2 (en) Side wall construction method for underground tank
JP7241336B2 (en) Placement method of tunnel lining concrete
JP6942025B2 (en) How to compact construction seams in tunnel lining
JP4904072B2 (en) Manufacturing method of pretension member
CN115434518A (en) Auxiliary vibrating device and internal corner concrete vibrating method
CN207847694U (en) A kind of tunnel drainage device and tunnel solid concrete roabed
JP4566891B2 (en) Tunnel lining concrete placement method
JP7182176B2 (en) Tunnel lining method
JP2007291791A (en) Lining construction method for tunnel and form device
JP2007291792A (en) Pipe for bleeding air used for forming lining on wall surface of structure
CN108131162A (en) A kind of tunnel drainage device and tunnel solid concrete roabed
JP7261409B2 (en) Tunnel lining method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040517

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040525

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040726

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040817

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041015

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20041124

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20041125

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101210

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111210

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111210

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121210

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141210

Year of fee payment: 10

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees