JPS63236833A - Building construction method - Google Patents
Building construction methodInfo
- Publication number
- JPS63236833A JPS63236833A JP7097787A JP7097787A JPS63236833A JP S63236833 A JPS63236833 A JP S63236833A JP 7097787 A JP7097787 A JP 7097787A JP 7097787 A JP7097787 A JP 7097787A JP S63236833 A JPS63236833 A JP S63236833A
- Authority
- JP
- Japan
- Prior art keywords
- frame
- construction method
- column
- lifted
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title description 3
- 238000009435 building construction Methods 0.000 title 1
- 238000010276 construction Methods 0.000 claims description 5
- 238000010586 diagram Methods 0.000 description 4
- 239000004744 fabric Substances 0.000 description 3
- 101150054854 POU1F1 gene Proteins 0.000 description 2
- 241001070941 Castanea Species 0.000 description 1
- 235000014036 Castanea Nutrition 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は高所作業と、部材の荷上げ作業をなくした新し
い建築工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a new construction method that eliminates work at heights and lifting work of members.
木造あるいはプレハゲ等の住宅建築に際してはまず地面
を少し掘り下げて布基礎を設け、この布基礎上に一階部
分から二階、三階へと上層階へ組み立てている。しかし
地上より高くなればなる程、すなわち高所での作業では
それだけ危険が増す。When constructing a wooden or pre-hewn house, the ground is first dug a little and a cloth foundation is laid out, and the upper floors are built from the first floor to the second and third floors on this cloth foundation. However, the higher you are above the ground, the more dangerous it becomes when working at heights.
さらには高所で部材の組み立てるため、部材を所望階ま
で荷上げする作業が必要となる。Furthermore, since the parts are assembled at a high place, it is necessary to lift the parts to the desired floor.
本発明ではこのような荷上げ作業や高所での作業を可能
な限り減少させ危険性をなくすことを目的とする。The present invention aims to reduce such loading work and work at high places as much as possible and eliminate danger.
柱を設ける位置の地面に垂直方向に穿設された坑内に、
所要長の柱を挿入立設し、この柱の上部に地面上にて梁
その他の架構体を組み立てた鐘、この架構体全体を扛上
させ、次に二P1浬以上の場合はさらに下層階の柱を前
記坑内に挿入立設して前記扛上した柱下端部に継合し、
さらにド層011架構体を組み立て、これを所t!階層
繰り返した徨、前記坑内にコンクリート等を打設して基
礎を構築し、前記架構体を支持せしめる。A hole is drilled vertically into the ground at the location where the pillar will be installed.
A pillar of the required length is inserted and erected, beams and other frame structures are assembled on the ground on top of the pillars, the entire frame is lifted up, and then, if the length is 2 P1 or more, a lower floor is built. inserting a column into the pit and erecting it and joining it to the lower end of the lifted column;
Furthermore, assemble the layer 011 frame structure and place it! After repeating the layers, a foundation is constructed by pouring concrete or the like in the tunnel to support the frame structure.
第】図乃至第4図は本発明の建築工法をその作業順序に
従って示11、またもので、以下図示の実施例1mもと
づいて説明する。11 to 4 show the construction method of the present invention according to its working order, and will be explained below based on the illustrated embodiment 1m.
まず地面GLに予め設計した位置にほぼ垂直方向に坑l
を複数箇所掘削する。この坑lは柱2を挿入するのに必
要な径と長さとを有するようにし、望ましくは坑1の深
さを一階分の柱2の長さと等しいかもしくはこれより少
し短いものとする。そして必要に応じてこの坑内底面に
て架構体組み立て時の柱及び梁等の荷重を支持できるよ
う栗石等を敷設して基礎とすることもある。First, a hole is placed in a pre-designed position on the ground GL in an almost vertical direction.
excavate in multiple locations. The hole 1 has a diameter and length necessary for inserting the column 2, and preferably the depth of the hole 1 is equal to or slightly shorter than the length of the column 2 for one floor. If necessary, chestnut stones or the like may be laid as a foundation at the bottom of the mine to support the loads of columns and beams when assembling the frame.
次にこの各坑1内に所望の柱2をそれぞれ挿入立設し、
この柱2の坑1より上方に突出する柱上部に隣接する柱
間に梁3その他の架構体を架設し、この梁3等を介して
各柱1,1間を連結固定する。Next, the desired columns 2 are inserted and erected into each of the pits 1,
Beams 3 and other frame structures are installed between the columns adjacent to the upper part of the column that protrudes upward from the shaft 1 of the column 2, and the columns 1 and 1 are connected and fixed via the beams 3 and the like.
この状態を第2図に示す。This state is shown in FIG.
このようにして最上階部分の架構体A、を組み立てた壕
、ジヤツキ等の扛上機4を複数台用いて架構体A1の全
体を平均して持ち上げる。このとき坑1内に挿入立設さ
れた柱は垂直あるいは垂直に近い状態であるので、架構
体A1の扛上時にも柱1は重直になるようにする。はぼ
柱長分を扛上させた状態で、架構体A、の扛上を停止し
、かつその状態を扛上機4にて維持しつつ、次に前記各
坑1内に次階層分の柱2.2・・・を挿入立設し、扛上
された前記柱2の下端に下層階の柱2を突き合せ、その
池の方法にて継合する。勿論上下両社の継合には図示省
略したが所望強度を有するよう継手板、その池の継合具
を用いるものである。Using a plurality of lifting machines 4 such as trenches, jacks, etc., in which the frame A1 on the top floor is assembled in this way, the entire frame A1 is lifted up evenly. At this time, the pillars inserted and erected in the pit 1 are in a vertical or nearly vertical state, so the pillars 1 are made to be vertical even when the frame structure A1 is lifted up. With the length of the pillars lifted up, the lifting of the frame structure A is stopped, and while this state is maintained by the lifting machine 4, the next floor is placed in each of the mines 1. The pillars 2, 2, etc. are inserted and erected, and the lower end of the pillar 2 that has been lifted up is butted against the lower end of the pillar 2, and the pillars 2, 2, and so on are joined using the method. Of course, although not shown in the drawings, the upper and lower parts are joined together using a joint plate and a joint tool for achieving the desired strength.
また柱2の継白峰、次に下層階分の梁3その池の架構体
を組み立て最上階より2番目の階層分の架橋t4hA
aを組み立てる。そして次に前回作業と同様に扛上機4
にて所要高さまで持ち上げる。この扛上時にも架構体A
2及びA、が均一に扛上されるようになす。この作業を
順次繰り返して2階層にの階層部分を組み立てていくも
のである。In addition, assemble the structure of the pond for pillar 2, Keihakumine, and then the beam 3 for the lower floor, and build the bridge t4hA for the second floor from the top floor.
Assemble a. Next, as in the previous work, the lifting machine 4
lift it to the required height. During this lifting, frame structure A
2 and A are lifted up evenly. This work is repeated in sequence to assemble the two-layered parts.
そして最佳に扛上されている架構体A□の柱1の下部す
なわち坑1内にコンクリートを打設して基礎5とする。Then, concrete is poured into the bottom of the pillar 1 of the frame structure A□ that has been lifted up, that is, into the pit 1 to form the foundation 5.
また従来−触に行なわれている布基礎を構築して架構体
A、、A、を支持せしめるものである。In addition, a cloth foundation, which is conventionally done, is constructed to support the frame structures A, .
本発明建築工法は地面に穿設された坑内に柱を挿入立設
し、上部の架構体を組み立てた濠、上方に持ち上げ、次
に下部の架構体を同様にして組み立てるように地面上で
組み立てたものを順次上方へ持ち上げるようにしている
ため、高所で作業が減少せしめて危険性をなくし、かつ
部材の荷上げ作業がなく一箇所にて部材を集約でき、作
業の合理化が行なえる等の利点を有する。The construction method of the present invention involves inserting and erecting columns into a pit drilled in the ground, lifting the upper frame into the assembled moat, and then assembling the lower frame on the ground in the same manner. Since the items are lifted upward one by one, work at heights is reduced and danger is eliminated, and there is no need to unload parts, so parts can be collected in one place, streamlining work, etc. It has the following advantages.
図面は本発明建築工法の過程を示すものであって、第1
図は坑内に柱を挿入立設する状態の説明図、第2図は架
構体組立時の説明図、第3図は架構体扛上時の説明図、
第4図は架構体下部に基礎を構築した状態の説明図であ
る。
1は坑、2は柱、3は梁、4は扛上機、5は基礎
ばか1名The drawings show the process of the construction method of the present invention.
The figure is an explanatory diagram of a state in which a column is inserted and erected in a mine, Figure 2 is an explanatory diagram when the frame is assembled, and Figure 3 is an explanatory diagram when the frame is lifted.
FIG. 4 is an explanatory diagram of a state in which a foundation has been constructed at the bottom of the frame. 1 is a pit, 2 is a pillar, 3 is a beam, 4 is a hoisting machine, 5 is a foundation idiot
Claims (1)
内に、所要長の柱を挿入立設し、この柱の上部に地面上
にて梁その他の架構体を組み立てた後、この架構体全体
を扛上させ、次に坑内にコンクリート等を打設して基礎
を構築し、前記架構体を支持せしめるようになしたこと
を特徴とする建築工法。(1) A column of the required length is inserted and erected into a pit drilled vertically into the ground at the location where the column will be installed, and a beam or other frame structure is assembled on the ground on top of this column. A construction method characterized in that the entire frame is lifted up, and then a foundation is constructed by pouring concrete or the like into a pit to support the frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7097787A JPS63236833A (en) | 1987-03-25 | 1987-03-25 | Building construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP7097787A JPS63236833A (en) | 1987-03-25 | 1987-03-25 | Building construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS63236833A true JPS63236833A (en) | 1988-10-03 |
Family
ID=13447092
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP7097787A Pending JPS63236833A (en) | 1987-03-25 | 1987-03-25 | Building construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS63236833A (en) |
-
1987
- 1987-03-25 JP JP7097787A patent/JPS63236833A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2596798B2 (en) | Existing building seismic isolation method | |
JPS63236833A (en) | Building construction method | |
JPH0684690B2 (en) | Building basement extension method | |
JPH08270081A (en) | Construction method of frame structure | |
JP2004176434A (en) | Method for constructing structure and underground skeleton | |
JP2946372B2 (en) | Construction method of structure | |
JPH06101348A (en) | Method for constructing tower | |
JPS5942155B2 (en) | Building extension method | |
JP2894217B2 (en) | Building structural frame | |
JPH0874278A (en) | Construction method for large underground space | |
JPS63312437A (en) | Construction of underground structure | |
JPH02266014A (en) | Constructing underground structure eliminating use of temporary material | |
JPH0742179A (en) | Modified inversion placing construction method | |
JP3416759B2 (en) | Underground structure frame building equipment | |
JP3060191B2 (en) | Building push-up construction method | |
JPS58195652A (en) | Hanging-up construction of roof enclosure | |
JPH0874279A (en) | Construction method for large underground space | |
JPS6259766A (en) | Method for disassembling building | |
JP2022066705A (en) | Construction method | |
JPH0485427A (en) | Composite building construction of medium-high-building and low building | |
JP2508931B2 (en) | Lift slab method | |
JPH05255944A (en) | Skeleton construction method for underground structure | |
JPS6272822A (en) | Construction work of underground structure | |
JPS63315768A (en) | Method for constructing pillar, beam and cross reinforcing bar | |
CN115198649A (en) | Steel trestle construction method for deep foundation pit engineering by cover-excavation top-down construction method |