JPS6314903A - Arch ring execution method in concrete arch bridge - Google Patents

Arch ring execution method in concrete arch bridge

Info

Publication number
JPS6314903A
JPS6314903A JP61157793A JP15779386A JPS6314903A JP S6314903 A JPS6314903 A JP S6314903A JP 61157793 A JP61157793 A JP 61157793A JP 15779386 A JP15779386 A JP 15779386A JP S6314903 A JPS6314903 A JP S6314903A
Authority
JP
Japan
Prior art keywords
arch
formwork
arch ring
frame
center
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP61157793A
Other languages
Japanese (ja)
Other versions
JPH0364003B2 (en
Inventor
甲本 敏行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ORIENTAL CONCRETE CO
ORIENTAL CONCRETE KK
Original Assignee
ORIENTAL CONCRETE CO
ORIENTAL CONCRETE KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ORIENTAL CONCRETE CO, ORIENTAL CONCRETE KK filed Critical ORIENTAL CONCRETE CO
Priority to JP61157793A priority Critical patent/JPS6314903A/en
Publication of JPS6314903A publication Critical patent/JPS6314903A/en
Publication of JPH0364003B2 publication Critical patent/JPH0364003B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明はコンクリートアーチ橋におけるアーチリング
の施工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] This invention relates to a method of constructing an arch ring in a concrete arch bridge.

〔従来技術〕[Prior art]

河川上に架設されるヌノン50m〜100mの比較的中
規模のコンクリートアーチ橋のアーチリングを施工する
際に、アーチリング下に接地式の支保工を組立てること
ができない場合、従来は。
Conventionally, when constructing an arch ring for a relatively medium-sized concrete arch bridge of 50 to 100 m over a river, it is not possible to assemble ground-type shoring under the arch ring.

アーチセントルをアーチアバツト間に架設した後。After installing the arch center between the arch abutments.

そのアーチセントル上に型枠を建込み1次いでコンクリ
ートを打設して、アーチリングを形成していた。
Formwork was erected over the arch center and concrete was then poured to form the arch ring.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

上記従来の方法によれば、アーチリングが形成されてし
まうと、アーチセントルがアーチリングの下になってし
まうため、タワークレーン等によって、アーチリングの
上からアーチセントルを解体、撤去する作業が極めて複
雑なため1作業日数を多く要し、°コンクリートアーチ
橋の建設コストを増加させる要因となっていた。コンク
リートア−チ橋は、使用材料が少なく、半径間長大橋に
適した構造型式とされながらも、実用例が少ないという
理由は、このように架設費の全体工費に占める割合が大
きいところにあると云われている。
According to the above conventional method, once an arch ring is formed, the arch center will be under the arch ring, so it is extremely difficult to dismantle and remove the arch center from above the arch ring using a tower crane, etc. Due to its complexity, it took many days to complete the work, which was a factor in increasing the construction cost of concrete arch bridges. Although concrete arch bridges use less materials and are considered to be a structural type suitable for long-radius bridges, the reason why there are few practical examples is that the construction cost accounts for a large proportion of the overall construction cost. It is said that

〔発明の目的、構成〕[Purpose and structure of the invention]

この発明は、前記の欠点を有利に解決し、建設費の安い
コンクリートアーチ橋を施工できるコンクリートアーチ
橋におけるアーチリング施工法を提供することを目的と
するものであって、この発明の要旨とするところは、ア
ーチリング施工予定位置の上部に予めアーチセントル1
を組立架設し、そのアーチセントル1の両岸側に載架し
た型枠移動支持装置2によりアーチリングブロック施工
用型枠を支持し、その型枠内にコンクリートを打設して
アーチリングブロック6を施工する工程と、コンクリー
ト硬化後に脱型した前記型枠を移動支持装置2により移
動する工程とを反復して行ない、かつアーチリング架設
途中のアーチリングブロック6をアーチセントル1によ
りアーチリング吊材4を介して支持し、アーチリング5
が完成したのち。
The object of the present invention is to provide an arch ring construction method for a concrete arch bridge that advantageously solves the above-mentioned drawbacks and can construct a concrete arch bridge at low construction cost. However, the arch center 1 was placed in advance at the top of the arch ring construction location.
The arch ring block construction formwork is supported by the formwork moving support device 2 mounted on both sides of the arch center 1, concrete is poured into the formwork, and the arch ring block 6 is assembled and erected. and the step of moving the formwork, which has been removed from the mold after the concrete has hardened, using the movable support device 2 are repeated, and the arch ring block 6 in the middle of the arch ring erection is moved by the arch center 1 to the arch ring hanging material. Support through 4 and arch ring 5
After it is completed.

アーチリング吊S4.*撤去しかつアーチセントル1を
解体撤去することを特徴とするコン7クリートアーテ橋
におけるアーチリング施工法にある。
Arch ring hanging S4. *An arch ring construction method for a concrete arte bridge that is characterized by removing and dismantling arch center 1.

〔実施例〕〔Example〕

次にこの発明を図示の例によって詳細に説明する。 Next, the present invention will be explained in detail using illustrated examples.

第7図ないし第12図はこの発明の実施例において用い
られる型枠移動支持装置2を示すものであって、中間桁
材6とその左右両側に配置された側部桁材7と各桁材を
連結する多数の連結梁8とからなる鋼製アーチセントル
1における前記側部桁材7の上面に多数の枕木9が載置
されて固定され、かつ桁長子方向に延長するレール10
は各枕木9にわたって載置されて固定され、車体フレー
ム11とその前部および後部の左右両側に取付けられた
車輪12とからなる車体16における前記車輪12はレ
ール10に載置され、さらにアーチセントル1および型
枠移動支持装置2の下方において型枠支持フレーム14
が配置され、前記車体フレーム11は、左右方向に延長
すると共に前後方向に間隔をおいて配置された複数の下
部枠材15と、前後方向に延長すると共に左右方向に間
隔をおいて配置されて下部枠材15に対しボルト等によ
り着脱自在に固定された上部枠材16とによシ構成され
、また前記型枠支持フレーム14は1前後方向に延長す
ると共に左右方向に間隔をおいて配置された多数の下部
枠材17と、左右方向に延長すると共に前後方向に間隔
をおいて配置されて下部枠材17に対しボルト等により
着脱自在に固定された複数の中間枠材18と、@後方向
に延長すると共に左右方向に小間隔で配置されて中間枠
材18に対しボルト等により着脱自在に固定された多数
の上部枠材19とにより構成されている。
7 to 12 show a formwork moving support device 2 used in an embodiment of the present invention, in which an intermediate girder 6, side girders 7 disposed on both left and right sides of the intermediate girder 6, and each girder A large number of sleepers 9 are placed and fixed on the upper surface of the side girder members 7 of the steel arch center 1, which consists of a large number of connecting beams 8 connecting
are placed and fixed across each sleeper 9, and the wheels 12 of a car body 16 consisting of a car body frame 11 and wheels 12 attached to both the left and right sides of the front and rear parts of the car body frame 11 are placed on the rails 10, and the wheels 12 are placed on the rails 10. 1 and the formwork support frame 14 below the formwork movement support device 2.
The body frame 11 includes a plurality of lower frame members 15 extending in the left-right direction and spaced apart in the front-rear direction, and a plurality of lower frame members 15 extending in the front-rear direction and spaced apart in the left-right direction. An upper frame member 16 is detachably fixed to a lower frame member 15 with bolts or the like, and the formwork support frame 14 extends in the front-rear direction and is arranged at intervals in the left-right direction. a plurality of lower frame members 17, a plurality of intermediate frame members 18 extending in the left-right direction, spaced apart in the front-rear direction, and removably fixed to the lower frame members 17 with bolts or the like; The upper frame member 19 extends in the upper frame member 18 and is arranged at small intervals in the left-right direction, and is detachably fixed to the intermediate frame member 18 with bolts or the like.

全長にわたってねじを有する鋼棒からなるフレーム吊材
20が前後方向および左右方向に間隔をおいて配置され
、かつフレーム吊材20の上部は。
Frame hanging members 20 made of steel rods having threads over the entire length are arranged at intervals in the front-rear direction and left-right direction, and the upper part of the frame hanging members 20 is.

小間隔で配置された上部枠材16の間に挿通され。It is inserted between the upper frame members 16 arranged at small intervals.

左右方向に延長する半円筒状上部凸面および上方に向か
って拡開する吊材挿通孔21を有する支承金具22は、
@記フレーム吊材20の上部に嵌挿されて隣り合う上部
枠材16の上面にわたって載置され、さらに左右方向に
延長する円弧状下部凹面を有する可動支持金具26は、
フレーム吊材λの上部に嵌挿されると共に支承金具22
に対し傾動自在に嵌合載置され、またフレーム吊材20
の上部に螺合されたナツト24は前記可動支持金具26
により支持されている。
The support fitting 22 has a semi-cylindrical upper convex surface extending in the left-right direction and a hanging material insertion hole 21 expanding upward.
The movable support fitting 26 is fitted into the upper part of the frame hanging material 20 and placed over the upper surface of the adjacent upper frame material 16, and has an arcuate lower concave surface extending in the left-right direction.
The supporting metal fitting 22 is fitted onto the upper part of the frame hanging material λ.
The frame hanging member 20
The nut 24 screwed onto the upper part of the movable support fitting 26
Supported by

前記フレーム吊材20の下部は、小間隔で配置された下
部枠材17の間に挿通され、左右方向に延長する半円筒
状下部凸面および下方に向かって拡開する吊材挿通孔2
5を有する支承金具26は、前記フレーム吊材20の下
部に嵌挿されて隣シ合う下部枠材17の下面にわたって
当接され、かつ左右方向に延長する円弧状上部凹面を有
する可動支持金具27は、フレーム吊材20の下部に嵌
挿されると共に支承金具26に対し傾動自在に嵌合され
、さらにフレーム吊材20の下部に螺合されたナツト2
8により前記可動支持金具27が支持されている。
The lower part of the frame hanging material 20 is inserted between the lower frame materials 17 arranged at small intervals, and has a semi-cylindrical lower convex surface extending in the left-right direction and a hanging material insertion hole 2 expanding downward.
5 is a movable support fitting 27 that is fitted into the lower part of the frame hanging member 20 and abuts across the lower surface of the adjacent lower frame member 17, and has an arcuate upper concave surface extending in the left-right direction. The nut 2 is fitted into the lower part of the frame hanging material 20 and is fitted to the support fitting 26 so as to be tiltable, and is further screwed into the lower part of the frame hanging material 20.
The movable support fitting 27 is supported by 8.

前記各上部枠材19の上面にわたって底部型枠29が載
置されてボルト等により着脱自在に固定され、かつ底部
型枠29の左右両側の上面には、支持フレーム60を備
えている側部型枠61が載置されてボルト等により着脱
自在に固定され、さらに底部型枠29の前部の上面には
、支持フレーム62を備えている前端型枠66が載置さ
れてボルト等により着脱自在に固定され、前記底部型枠
29と側部型枠61と前部型枠66とによりアーチリン
グブロック施工用型枠が構成されている。
A side mold includes a bottom formwork 29 placed over the upper surface of each of the upper frame members 19 and removably fixed with bolts or the like, and support frames 60 provided on the left and right upper surfaces of the bottom formwork 29. A frame 61 is placed and removably fixed with bolts or the like, and furthermore, a front end formwork 66 having a support frame 62 is placed on the upper surface of the front part of the bottom formwork 29 and is removably attached with bolts or the like. The bottom formwork 29, the side formwork 61, and the front formwork 66 constitute a formwork for constructing the arch ring block.

左右方向に延長する多数の上部枠材64が前後方向に間
隔をおいて配置され、各上部枠材64の左右両端部にお
いて、それぞれ2本の下部枠材65が小間隔を保って前
後方向に延長するように配置され、かつ各上部枠材34
と下部枠材65とはボルト等により着脱自在に固定され
、足場板66は各上部枠材64にわたって載置されてボ
ルト等により着脱自在に固定され、@記上部枠材64.
下部枠材65および足場板66からなる足場67は前記
型枠支持フレーム14の下方に配置され、さらに前記側
部桁材7の外fjにあるフレーム吊材20の下部は小間
隔で配置された左右の下部枠材65の間に挿通され、型
枠支持フレーム14を支持する場合と同様に、フレーム
吊材20に螺合されたナツト28により可動支持金具2
7および支承金具26を介して足場67の下部枠材65
が支持されている。
A large number of upper frame members 64 extending in the left-right direction are arranged at intervals in the front-rear direction, and at both left and right ends of each upper frame member 64, two lower frame members 65 are arranged at small intervals in the front-rear direction. Each upper frame member 34 is arranged to extend.
and the lower frame member 65 are removably fixed with bolts or the like, and the scaffold board 66 is placed across each upper frame member 64 and removably fixed with bolts or the like, and the upper frame member 64.
Scaffolding 67 consisting of a lower frame member 65 and a scaffold board 66 is arranged below the formwork support frame 14, and the lower parts of the frame hanging members 20 located outside fj of the side girder member 7 are arranged at small intervals. The movable support metal fitting 2 is inserted between the left and right lower frame members 65 and is screwed onto the frame hanging material 20 in the same way as when supporting the formwork support frame 14.
7 and the lower frame member 65 of the scaffolding 67 via the support fittings 26
is supported.

前記車体13の後端に液圧ジヤツキからなるクライミン
グ用ジヤツキ68の前端部がビンにより連結され、その
クライミング用ジヤツキ68の後端部には、レールクラ
ンプ39がピンにより連結され、さらに車体16の前端
部にはレバー手動操作式牽引機40が連結され、その牽
引機40のロードシーブに巻掛けられたチェーン41の
端部にレールクランプ42が連結されている。
The front end of a climbing jack 68 made of a hydraulic jack is connected to the rear end of the vehicle body 13 by a pin, and a rail clamp 39 is connected to the rear end of the climbing jack 68 by a pin. A manually operated lever traction machine 40 is connected to the front end, and a rail clamp 42 is connected to the end of a chain 41 wrapped around a load sheave of the traction machine 40.

このように構成された型枠移動支持装置2をアーチセン
トル1の低レベル側から高レベル側に移動する場合は、
クライミング用ジヤツキ68に付属スるレールクランゾ
ロ9によりレール10を把持して、そのレールクランプ
39をレール10に固定した状態で、フライばング用ツ
ヤツキ68を伸長して型枠移動支持装置2をアーチセン
トル1に沿って上昇移動させる。この場合、車体16が
浮き上がるのを防止するために、前記チェーン41に取
付けられている支承金具22によりレール10を把持し
、型枠移動支持装置2の前進移動とともにレバー手動操
作式牽引機40を操作してチェーン41を常時緊張状態
に保持しておく。
When moving the formwork moving support device 2 configured in this way from the lower level side of the arch center 1 to the higher level side,
Grip the rail 10 with the rail clamp 9 attached to the climbing jack 68, and with the rail clamp 39 fixed to the rail 10, extend the fly bang jack 68 and move the formwork moving support device 2. Move upward along arch center 1. In this case, in order to prevent the vehicle body 16 from floating up, the rail 10 is gripped by the support metal fittings 22 attached to the chain 41, and the lever manually operated traction machine 40 is moved as the formwork moving support device 2 moves forward. The chain 41 is kept under tension at all times.

前記型枠移動支持装置2をアーチセントル1に沿って移
動した場合、アーチセントル1上の型枠移動支持装置2
の位置によって水平面に対する型枠9動支持装置2の角
度が変化するが、前記実施例の場合は、半円筒状上部凸
面を有する支承金具22、円弧状下部凹面を有する可動
支持金具26およびナツト24を介してフレーム吊材2
0の上部が吊下支持されているので、そのフレーム吊材
20を常に垂直状態になるように垂下させることができ
る。
When the formwork movement support device 2 is moved along the arch center 1, the formwork movement support device 2 on the arch center 1
Although the angle of the formwork 9 movable support device 2 with respect to the horizontal plane changes depending on the position of the support device 2, in the case of the above embodiment, the support metal fitting 22 having a semi-cylindrical upper convex surface, the movable support metal fitting 26 having an arcuate lower concave surface, and the nut 24 Frame hanging material 2 through
Since the upper part of 0 is suspended and supported, the frame hanging material 20 can be hung so that it is always in a vertical state.

またフレーム吊材20に対し型枠支持フレーム14およ
び足場67が傾斜していても、可動支持金具27が支承
金具26に対し前後方向に回動することかできるので、
下部枠材17および下部枠材65に対し支承金具26を
常に面妾触させることができる。
Furthermore, even if the formwork support frame 14 and the scaffolding 67 are inclined with respect to the frame hanging material 20, the movable support fittings 27 can be rotated in the front and rear directions relative to the support fittings 26, so that
The support metal fitting 26 can always be brought into contact with the lower frame member 17 and the lower frame member 65.

この発明を利用してコンクリートアーチ橋におけるアー
チリングを施工する場合は、まず第1図に示すように、
地盤43にアバツト44およびアーチアバツト45を築
造したのち、そのアーチアバツト45の上部にエンドポ
スト46を構築し。
When constructing an arch ring for a concrete arch bridge using this invention, first, as shown in Figure 1,
After constructing an abutment 44 and an arch abutment 45 on the ground 43, an end post 46 is constructed on top of the arch abutment 45.

かつエンドポスト46の上端部とアバツト44とにわた
って端部上床版47を架設する。
In addition, an upper end slab 47 is constructed across the upper end of the end post 46 and the abutment 44.

次にアーチリング5が架設される位置よりもやや高い位
置において、′両岸のアーチアバツト45間に鋼製アー
チセントル1を架設する。このアーチセントル1を架設
する場合、例えばアーチセントル1を多数のアーチセン
トルブロック48に分割し、そのアーチセントルブロッ
ク48を、両岸から公知の張出工法により継手板49お
よびボルトを使用して連結しなから張出架設してもよく
、あるいはアーチセントル1を2ブロツクに分割し、両
岸のアーチアバツト45上でアーチセントルの半分を組
立てたのち、この半アーチセントルを所定の位置まで降
下し1次いで各半アーチセントルの対向端部を連結して
アーチセントルを架設してもよい。
Next, at a position slightly higher than the position where the arch ring 5 is installed, the steel arch center 1 is installed between the arch abutments 45 on both banks. When constructing this arch center 1, for example, the arch center 1 is divided into a large number of arch center blocks 48, and the arch center blocks 48 are connected from both banks using joint plates 49 and bolts by a known overhang method. Alternatively, the arch center 1 may be constructed by overhanging it into two blocks, and after assembling half of the arch center on the arch abutments 45 on both banks, this half arch center is lowered to a predetermined position. The arch center may then be constructed by connecting the opposite ends of each half arch center.

次にアーチセントル1の端部の下方において。Next, below the end of arch center 1.

多数の支柱50と支柱連結部材51とからなる支柱式支
保工52をアーチリング付根のレベルに達するように組
立設置し、かつその支柱式支保工52の上に、多数の支
保枠の組立連結した枠組式支保工55をアーチリング5
の端部下面に達する高さまで組立設置する。
A column type shoring 52 consisting of a large number of columns 50 and a column connecting member 51 is assembled and installed so as to reach the level of the root of the arch ring, and on top of the column type shoring 52, a large number of supporting frames are assembled and connected. Arch ring 5 for frame type shoring 55
Assemble and install it to a height that reaches the bottom surface of the end.

次に枠組式支保工56の上に型枠(図示を省略した)を
載置し、その型枠内に、鉄筋と全長にわたってねじを有
する宗棒からなるアーチリング吊材4の下部とを配置し
、かつそのアーチリング吊材4の上端部に螺合されたナ
ツト56を、アーチセントル1の上面に架設された支持
ビーム54により支持し、次いで型枠内にコンクリート
を打設して、アーチリング端部ブロック55を形成する
Next, a formwork (not shown) is placed on the frame type shoring 56, and within the formwork, the lower part of the arch ring hanging material 4, which is made of reinforcing bars and a rod having threads over its entire length, is placed. A nut 56 screwed onto the upper end of the arch ring hanging member 4 is supported by a support beam 54 installed on the upper surface of the arch center 1, and then concrete is poured into the formwork to complete the arch. A ring end block 55 is formed.

アーチリング端部ブロック55のコンクリートが硬化し
て所定の強度に達したのち、センターホールジヤツキ等
の緊張用ジヤツキ(図示を省略した)を、アーチリング
吊材4の上部に挿通すると共に支持ビーム54に載置し
、次いでアーチリング吊材4の上端に螺合したジヤツキ
保合用ナツト(図示を省略した)を、前記緊張用ジヤツ
キの上端部に係合し、その緊張用ジヤツキによりアーチ
リング吊材4を緊張した状態で、アーチリング吊材4の
上部に螺合されているナツト56を緊締して。
After the concrete of the arch ring end block 55 hardens and reaches a predetermined strength, a tensioning jack (not shown) such as a center hole jack is inserted into the upper part of the arch ring hanging material 4 and the support beam is inserted. 54, and then a jack retaining nut (not shown) screwed onto the upper end of the arch ring suspension material 4 is engaged with the upper end of the tensioning jack, and the arch ring is suspended by the tensioning jack. With the material 4 under tension, tighten the nut 56 screwed onto the upper part of the arch ring hanging material 4.

アーチリング吊材4の上部を定着し1次いで前記緊張用
ジヤツキ、型枠および前記枠組式支保工56を撤去する
。    ″ 次にアーチセントル1の分割長さとほぼ同じ長さにアー
チリングの未施工区間を分割し、アーチリング端部ブロ
ック55に続いてアーチリングブロック3を頑次施工し
ていく。
The upper part of the arch ring hanging member 4 is fixed, and then the tensioning jack, the formwork, and the frame support 56 are removed. ``Next, the unfinished section of the arch ring is divided into lengths that are approximately the same as the divided length of the arch center 1, and the arch ring block 3 is stubbornly constructed following the arch ring end block 55.

アーチリングブロック3を施工する場合は、まず前記型
枠移動支持装置2の構成部材をトラッククレーン64等
により運搬してアーチセントル1および支柱式支保工5
2の上に載置し、第2図。
When constructing the arch ring block 3, first, the constituent members of the formwork movement support device 2 are transported by a truck crane 64 or the like, and the arch center 1 and the post-type shoring 5 are installed.
Figure 2.

第7図および第8図に示すように型枠移動支持装置2を
組立てる。
As shown in FIGS. 7 and 8, the formwork moving support device 2 is assembled.

次にセンターホールツヤツキ等の昇降用ツヤツキ(図示
を省略した)をフレーム吊材2oの上部に挿通すると共
に上部枠材16に載置し、かつフレーム吊材20の上端
に螺合したジヤツキ保合用ナツト(図示を省略した)を
昇降用ジヤツキの上端部に係合し、次いで前記昇降用ジ
ヤツキにより。
Next, a lifting gloss (not shown) such as a center hole gloss is inserted into the upper part of the frame hanging material 2o, and placed on the upper frame material 16, and a jack retainer screwed onto the upper end of the frame hanging material 20 is inserted into the upper part of the frame hanging material 2o. A combination nut (not shown) is engaged with the upper end of the lifting jack, and then by the lifting jack.

各フレーム吊材20とこれにより支持されている各部分
とを引上げて、第5図に示すように、底部型枠29の後
端部をアーチリング端部ブロック55の前端部の下面に
密着させ、この状態で、ナツト24を緊締して、フレー
ム吊材20の上部を上部枠材16により支承金具22.
可動支持金具23およびナツト24を介して支持する。
Pull up each frame hanging material 20 and each part supported thereby, and bring the rear end of the bottom formwork 29 into close contact with the lower surface of the front end of the arch ring end block 55, as shown in FIG. In this state, the nut 24 is tightened, and the upper part of the frame hanging material 20 is attached to the supporting metal fitting 22 by the upper frame material 16.
It is supported via a movable support fitting 23 and a nut 24.

次に側部型枠61の後端部をアーチリング端部ブロック
55の前端部側面に当接した状態で、その側部型枠61
を底部型枠29に固定し、かつ左−右の側部型枠61の
前端部間に配置された前端型枠33を底部型枠29およ
び側部型枠61に固定し、さらに第6図に示すように、
アーチセントル1における中間桁材6および側部桁材7
にわたって架設された支持ビーム54に、全長にわたっ
てねじを有する鋼棒からなる複数のアーチリング吊材4
の上部を挿通し、そのアーチリング吊材4の上端部に螺
合されたナツト56を支持ビーム54により支持する。
Next, with the rear end of the side formwork 61 in contact with the front end side surface of the arch ring end block 55, the side formwork 61
is fixed to the bottom formwork 29, and the front end formwork 33 disposed between the front ends of the left and right side formworks 61 is fixed to the bottom formwork 29 and the side formworks 61, and further, as shown in FIG. As shown in
Intermediate girder material 6 and side girder material 7 in arch center 1
A plurality of arch ring suspension members 4 made of steel rods having threads over the entire length are attached to a support beam 54 that is constructed across the entire length of the support beam 54.
The support beam 54 supports a nut 56 which is inserted through the upper part of the arch ring hanging material 4 and screwed onto the upper end of the arch ring hanging material 4.

またアーチリング中空部成形用内部型枠57に前記アー
チリング吊材4の下部を挿通し、そのアーチリング吊材
4の下部に螺合したナツト58によシ前記内部型枠57
を支持し、前記型枠により凹まれた部分に鉄筋を配置し
てコンクリート59を打設する。
Further, the lower part of the arch ring hanging material 4 is inserted into the internal form 57 for forming the arch ring hollow part, and the internal form 57 is inserted through the nut 58 screwed into the lower part of the arch ring hanging material 4.
is supported, reinforcing bars are placed in the recessed portion of the formwork, and concrete 59 is poured.

コンクリート59が硬化して所定の強度に達したのち、
側部型枠61.前端型枠36およびアーチリング中空部
成形用内部型枠57を脱型し、次いでアーチリング吊材
4の下端部に螺合されているナンド58を緊締してアー
チリング吊材4を緊張する。なおコンクリートを打設す
る場合、打設コンク’J −) 59の重量が相当大き
いので、このコンクリート重量を車輪12に作用させな
いために、アーチセントル1における中間桁材6および
側部桁材7に載置した複数の楔60および支承ブロック
61により車体13を支承するのが好ましい。
After the concrete 59 hardens and reaches a predetermined strength,
Side formwork 61. The front end form 36 and the internal form 57 for molding the arch ring hollow part are removed, and then the arch ring hanger 4 is tightened by tightening the nand 58 screwed onto the lower end of the arch ring hanger 4. When pouring concrete, since the weight of the concrete 59 is quite large, in order to prevent this concrete weight from acting on the wheels 12, the middle girder 6 and side girder 7 of the arch center 1 are Preferably, the vehicle body 13 is supported by a plurality of mounted wedges 60 and support blocks 61.

次にセンタホールジヤツキ等の昇降用ジヤツキ(図示を
省略した)をフレーム吊材20の上部に押通するき共に
上部枠材16に載置し、かつフレーム吊材20の上端に
螺合したジヤツキ保合用ナツト(図示を省略した)を昇
降用ジヤツキの上端部に係合し1次いでナツト24を弛
めながら、前記昇降用ジヤツキにより、各フレーム吊材
20とこれにより支持されている各部分とを下降して、
底部型枠29を脱型したのち、クライミング用ジヤツキ
68およびレバー手動操作式牽引機40を使用して、型
枠移動支持装置2を次のアーチリングブロック施工予定
位置まで前進移動する。以下同様の作業を両岸から中央
のアーチリングブロック(クラウン)に隣接するアーチ
リングブロックまで繰返して行なう。
Next, a lifting jack such as a center hole jack (not shown) was pushed through the upper part of the frame hanging material 20, placed on the upper frame material 16, and screwed onto the upper end of the frame hanging material 20. A jack retaining nut (not shown) is engaged with the upper end of the lifting jack, and then, while loosening the nut 24, each frame hanging member 20 and each part supported by the lifting jack is connected to the upper end of the lifting jack. descending and
After demolding the bottom form 29, the climbing jack 68 and the manually operated lever traction machine 40 are used to move the form moving support device 2 forward to the position where the next arch ring block is to be constructed. Thereafter, the same operation is repeated from both banks to the arch ring block adjacent to the central arch ring block (crown).

次に何れか一方の型枠移動支持装置2をアーチ付根まで
撤退させたのち、その型枠移動支持装置2を解体して撤
去し、他方の型枠移動支持装置2を、第3図に示すよう
にアーチセントル1の中央まで移動して、前述のように
して中央のアーチリングブロックを施工し、アーチリン
グ全体の施工を完了する。なお中央のアーチリングブロ
ックを施工する場合は、前記内部型枠57.アーチリン
グ吊材4および前端型枠66を使用しない。
Next, after withdrawing one of the formwork moving and supporting devices 2 to the base of the arch, that formwork moving and supporting device 2 is dismantled and removed, and the other formwork moving and supporting device 2 is replaced as shown in FIG. Move to the center of the arch center 1 and construct the central arch ring block as described above, completing construction of the entire arch ring. When constructing the central arch ring block, the internal formwork 57. Arch ring hanging material 4 and front end formwork 66 are not used.

次ニセンターホールジャッキ等の緊張用ジヤツキを、ア
ーチリング吊材4の上部に挿通すると共に支持ビーム5
4に載置し、次いでアーチリング吊材4の上端に螺合し
たジヤツキ保合用ナツトを、前記緊張用ジヤツキの上端
部に係合し、その緊張用レヤソキによりアーチリング吊
材4を緊張した状態で、アーチリング吊材4の上部に螺
合されているナツト56を弛緩し、次いでアーチリング
吊材4を撤去し、このようにして全数のアーチリング吊
材4を順次撤去したのち、アーチセントル1を解体して
撤去し、次にM4図に示すようにアーチリング5の上に
支保工を組立てて、支柱62および残りの上床板66を
施工し、アーチ橋を完成する。
Next, insert a tensioning jack such as a center hole jack into the upper part of the arch ring hanging material 4 and
4, and then the jack retaining nut screwed onto the upper end of the arch ring hanging material 4 is engaged with the upper end of the tensioning jack, and the arch ring hanging material 4 is tensioned by the tensioning bolt. Then, loosen the nut 56 screwed onto the upper part of the arch ring hanging material 4, and then remove the arch ring hanging material 4. After removing all the arch ring hanging materials 4 one after another in this way, the arch center 1 is dismantled and removed, and then, as shown in Fig. M4, shoring is assembled on top of the arch ring 5, and the pillars 62 and the remaining upper floor board 66 are constructed to complete the arch bridge.

この発明を実施する場合、レバー手動操作式牽引機40
のチェーン41をレール10に固定シないでアーチセン
トル1に対し適当な手段により固定してもよい。また型
枠移動支持装置2を前進移動する際は、中間桁材6と側
部桁材7との間に、フレーム吊材20の移動の障害とな
る連結梁8が存在するので、中間桁材6と側部桁材7と
の間のフレーム吊材20を外して型枠移動支持装置2を
前進移動させる。
When carrying out this invention, the lever manually operated traction machine 40
The chain 41 may not be fixed to the rail 10, but may be fixed to the arch center 1 by suitable means. In addition, when moving the formwork moving support device 2 forward, since there is a connecting beam 8 between the intermediate girder 6 and the side girder 7 that becomes an obstacle to the movement of the frame hanging material 20, the intermediate girder 6 and the side beam members 7 are removed, and the formwork moving support device 2 is moved forward.

〔発明の効果〕〔Effect of the invention〕

この発明によれば、アーチリング施工予定位置の上部に
予めアーチセントル1を組立架設し、そのアーチセント
ル1の両岸圓に載架した型枠移動支持装置2によりアー
チリングブロック施工用型枠を支持し、その型枠内にコ
ンクIJ −トを打設してアーチリングブロック6を施
工する工程と、コンクリート硬化後に、脱型した前記型
枠を移動支持装置2により移動する工程とを反復して行
ない1かつアーチリング架設途中のアーチリングブロッ
ク6をアーチセントル1によりアーチリング吊材4を介
して支持するので、短かいアーチリングブロック施工用
型枠を反復使用してアーチリング5を分割施工すること
ができ、そのため少人数でかつ一定の施工サイクルでア
ーチリング5を施工することができ、さらに短かい型枠
を反復使用するのでアーチリング架設費を節減すること
ができ、またアーチセントル1はアーチリング5の上に
架設されているので、アーチリング5の施工が完了した
後のアーチセントル1の解体、撤去を容易にかつ短時間
で行なうことができる等の効果が得られる。
According to this invention, the arch center 1 is assembled and erected in advance above the location where the arch ring is to be constructed, and the formwork for arch ring block construction is moved by the formwork moving support device 2 mounted on both banks of the arch center 1. The process of supporting the arch ring block 6 by pouring concrete IJ-t into the formwork, and the process of moving the demolded formwork by the movable support device 2 after the concrete has hardened are repeated. Since the arch ring block 6 is supported by the arch center 1 via the arch ring hanging material 4, the arch ring 5 is constructed in parts by repeatedly using the short arch ring block construction formwork. Therefore, the arch ring 5 can be constructed by a small number of people and in a fixed construction cycle, and since short formwork is used repeatedly, arch ring erection costs can be reduced. Since it is constructed on the arch ring 5, the arch center 1 can be dismantled and removed easily and in a short time after the construction of the arch ring 5 is completed.

【図面の簡単な説明】[Brief explanation of drawings]

図面はこの発明の一実施例を示すものであって。 第1図はアーチセントルを架設すると共にアーチリング
端部ブロックを施工した状態を示す概略側面図、第2図
は枠組式支保工を撤去してアーチセントルに型枠移動支
持装置を組立設置した状態を示す概略側面図、第3図は
中央アーチリングブロックを施工している状態を示す概
略側面図、第4図はアーチリングの施工を完了してアー
チセントルを撤去した状態を示す概略側面図である。M
5図はアーチリングブロック施工位置に型枠移動支持装
置を設置した状態を示す側面図、第6図はアーチリング
ブロックのコノクリートを打設した状態を示す縦断正面
図である。 第7図は型枠移動支持装置の側面図、第8図はその縦断
正面図、第9図はフレーム吊材の上端部の支持構造を示
す側面図、第10図はその平面図、第11図は型枠支持
フレームおよび足場における下部枠材の支持構造を示す
側面図、第12図はその底面図である。 図において、1はアーチセントル、2は型枠移動支持装
置、6はアーチリングブロック、4はアーチリング吊材
、5はアーチリング、10はレール、11は車体フレー
ム、16は車体、14は型枠支持フレーム、20はフレ
ーム吊材、21は吊材挿通孔、22は支承金具、25は
可動支持金具。 24はナツト、25は吊材挿通孔、26は支承金具、2
7は可動支持金具、28はナンド、29は底部型枠、5
1は側部型枠、63は前端型枠、37は足場、38はク
ライミング用ツヤツキ、69はレールクランプ540は
レバー手動操作式牽引機、41はチェーン、42はレー
ルクランプ、44は、アバツト、45はアーチアバツト
、48はアーチセントルブロック、52は支柱式支保工
、56は枠組式支保工、54は支持ビーム、55はアー
チリング端部ブロック、56はナツトである。
The drawings show one embodiment of the invention. Figure 1 is a schematic side view showing the state in which the arch center has been erected and the arch ring end blocks have been constructed, and Figure 2 is the state in which the frame support has been removed and the formwork moving support device has been assembled and installed on the arch center. Figure 3 is a schematic side view showing the state in which the center arch ring block is being constructed, and Figure 4 is a schematic side view showing the state in which the arch ring construction has been completed and the arch center has been removed. be. M
FIG. 5 is a side view showing the formwork moving support device installed at the arch ring block construction position, and FIG. 6 is a longitudinal sectional front view showing the arch ring block with conocrete cast. Fig. 7 is a side view of the formwork moving support device, Fig. 8 is a longitudinal sectional front view thereof, Fig. 9 is a side view showing the support structure for the upper end of the frame hanging material, Fig. 10 is a plan view thereof, and Fig. 11 is a side view of the formwork moving support device. The figure is a side view showing the formwork support frame and the support structure of the lower frame member in the scaffolding, and FIG. 12 is a bottom view thereof. In the figure, 1 is an arch center, 2 is a formwork movement support device, 6 is an arch ring block, 4 is an arch ring hanging material, 5 is an arch ring, 10 is a rail, 11 is a car body frame, 16 is a car body, and 14 is a mold A frame support frame, 20 a frame hanging material, 21 a hanging material insertion hole, 22 a supporting metal fitting, and 25 a movable supporting metal fitting. 24 is a nut, 25 is a hanging material insertion hole, 26 is a support metal fitting, 2
7 is a movable support metal fitting, 28 is a nand, 29 is a bottom formwork, 5
1 is a side formwork, 63 is a front end formwork, 37 is a scaffold, 38 is a climbing gloss, 69 is a rail clamp 540 is a lever manually operated traction machine, 41 is a chain, 42 is a rail clamp, 44 is an abutment, 45 is an arch abutment, 48 is an arch center block, 52 is a post type shoring, 56 is a frame type shoring, 54 is a support beam, 55 is an arch ring end block, and 56 is a nut.

Claims (1)

【特許請求の範囲】[Claims] アーチリング施工予定位置の上部に予めアーチセントル
1を組立架設し、そのアーチセントル1の両岸側に載架
した型枠移動支持装置2によりアーチリングブロック施
工用型枠を支持し、その型枠内にコンクリートを打設し
てアーチリングブロック3を施工する工程と、コンクリ
ート硬化後に脱型した前記型枠を移動支持装置2により
移動する工程とを反復して行ない、かつアーチリング架
設途中のアーチリングブロック3をアーチセントル1に
よりアーチリング吊材4を介して支持し、アーチリング
5が完成したのち、アーチリング吊材4を撤去しかつア
ーチセントル1を解体撤去することを特徴とするコンク
リートアーチ橋におけるアーチリング施工法。
An arch center 1 is assembled and erected in advance above the planned arch ring construction position, and the formwork for arch ring block construction is supported by the formwork moving support device 2 mounted on both sides of the arch center 1. The process of pouring concrete into the arch ring block 3 and moving the formwork, which has been removed from the mold after the concrete has hardened, using the movable support device 2 is repeated, and A concrete arch characterized in that a ring block 3 is supported by an arch center 1 via an arch ring hanging material 4, and after the arch ring 5 is completed, the arch ring hanging material 4 is removed and the arch center 1 is dismantled and removed. Arch ring construction method for bridges.
JP61157793A 1986-07-07 1986-07-07 Arch ring execution method in concrete arch bridge Granted JPS6314903A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61157793A JPS6314903A (en) 1986-07-07 1986-07-07 Arch ring execution method in concrete arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61157793A JPS6314903A (en) 1986-07-07 1986-07-07 Arch ring execution method in concrete arch bridge

Publications (2)

Publication Number Publication Date
JPS6314903A true JPS6314903A (en) 1988-01-22
JPH0364003B2 JPH0364003B2 (en) 1991-10-03

Family

ID=15657409

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61157793A Granted JPS6314903A (en) 1986-07-07 1986-07-07 Arch ring execution method in concrete arch bridge

Country Status (1)

Country Link
JP (1) JPS6314903A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2208088A1 (en) * 2002-07-09 2004-06-01 R & C RESEARCH AND CONCRETE, S.A. Construction system for precast arch bridge for movement of both vehicles and people, includes preliminary phase performed on ground foundation for correct placement of structure manufactured in different phases on ground to bridge
CN107119584A (en) * 2017-05-08 2017-09-01 中建三局基础设施工程有限公司 A kind of method for dismounting of concrete rigid frame arch bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2208088A1 (en) * 2002-07-09 2004-06-01 R & C RESEARCH AND CONCRETE, S.A. Construction system for precast arch bridge for movement of both vehicles and people, includes preliminary phase performed on ground foundation for correct placement of structure manufactured in different phases on ground to bridge
CN107119584A (en) * 2017-05-08 2017-09-01 中建三局基础设施工程有限公司 A kind of method for dismounting of concrete rigid frame arch bridge
CN107119584B (en) * 2017-05-08 2019-07-05 中建三局基础设施工程有限公司 A kind of method for dismounting of concrete rigid frame arch bridge

Also Published As

Publication number Publication date
JPH0364003B2 (en) 1991-10-03

Similar Documents

Publication Publication Date Title
US4036466A (en) Flying deck-type concrete form installation
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
JP3804883B2 (en) Concrete high structure construction apparatus and concrete oblique column construction method
CN112726411B (en) Integral dragging construction method for single-hole large cantilever steel truss girder
JP3125652B2 (en) Bridge girder erection equipment
JPH0959932A (en) Construction method of column head of overhanging erection girder bridge
JP3125653B2 (en) Bridge girder construction method
JP2632922B2 (en) Bridge construction method
JPS6314903A (en) Arch ring execution method in concrete arch bridge
CN114414354A (en) Temporary support test device for large-span box girder erection
CN111794074B (en) Arch bridge concrete beam and beam forming method thereof
JPH05311617A (en) Construction method for elevated structure
JP2653644B2 (en) Formwork support structure and construction method
CN218027222U (en) Box girder forming template
JPH0380202B2 (en)
JPH11117226A (en) Form device for forming overhang part at head of bridge pier
JP3171676B2 (en) Construction method of cast-in-place concrete horizontal member
JPH0681314A (en) Construction method for concrete main tower
JPH0352811Y2 (en)
AU746805B2 (en) A structural element
JPH07102524A (en) Method for building concrete cable-stayed bridge and form supporting truck using the same
CN113481851A (en) Tied rod arch type fast splicing support and erection method thereof
JP2000160834A (en) Step-up construction of concrete caisson
JPH0376366B2 (en)
JP2002038422A (en) Lifting and lowering movable scaffold for arch construction for arch bridge