JPH0380202B2 - - Google Patents

Info

Publication number
JPH0380202B2
JPH0380202B2 JP12571187A JP12571187A JPH0380202B2 JP H0380202 B2 JPH0380202 B2 JP H0380202B2 JP 12571187 A JP12571187 A JP 12571187A JP 12571187 A JP12571187 A JP 12571187A JP H0380202 B2 JPH0380202 B2 JP H0380202B2
Authority
JP
Japan
Prior art keywords
arch ring
arch
block
work vehicle
suspension cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP12571187A
Other languages
Japanese (ja)
Other versions
JPS63293203A (en
Inventor
Motohiko Suzuki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ORIENTAL KENSETSU KK
Original Assignee
ORIENTAL KENSETSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ORIENTAL KENSETSU KK filed Critical ORIENTAL KENSETSU KK
Priority to JP12571187A priority Critical patent/JPS63293203A/en
Publication of JPS63293203A publication Critical patent/JPS63293203A/en
Publication of JPH0380202B2 publication Critical patent/JPH0380202B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明はRCアーチ橋のアーチリングの施工
法に関するものである。
[Detailed Description of the Invention] [Industrial Field of Application] This invention relates to a method of constructing an arch ring for an RC arch bridge.

〔従来技術〕[Prior art]

従来、RCアーチ橋のアーチリングを施工する
に当たつて、アーチリングの下方に接地式の支保
工を組立設置することができない場合は、アーチ
セントルをアーチアバツト間に架設したのち、そ
のアーチセントル上に型枠を建込み、次いでコン
クリートを打設して、アーチリングを形成する方
法が採用されていた。また他の方法として、アー
チリング基部からアーチクラウンに向かつて、カ
ンチレバー工法によりアーチリングを分割してコ
ンクリートを打設して、アーチリングを形成する
方法も採用されていた。
Conventionally, when constructing an arch ring for an RC arch bridge, if it is not possible to assemble and install ground-type shoring below the arch ring, an arch center is erected between the arch abutments, and then the arch center is placed above the arch center. The method used was to erect formwork and then pour concrete to form an arch ring. Another method has been to form an arch ring by dividing the arch ring using the cantilever method and pouring concrete from the base of the arch ring toward the arch crown.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかるに、前記アーチセントルを用いる方法の
場合は、アーチスパンが大きくなるにつれて、架
設費が割高になるので、最近では、カンチレバー
工法による架設方法が主流になつている。
However, in the case of the method using the arch center, the construction cost increases as the arch span increases, so recently, the cantilever construction method has become mainstream.

カンチレバー工法による架設方法の場合は、橋
桁の施工方法を応用したもので、大型のアーチセ
ントルを必要とせず、小規模の移動作業車を利用
して、アーチリングを分割施工するので、これに
より架設費を低減することができるという利点が
ある。
The cantilever construction method is an application of the bridge girder construction method, and does not require a large arch center, but uses a small-scale mobile work vehicle to construct the arch ring in sections. This has the advantage that costs can be reduced.

しかしながら、カンチレバー工法による架設方
法を採用する場合、橋桁はほぼ水平な部材である
のに対し、アーチリングは曲線部材であるので、
アーチリング基部からアーチクラウンまで分割施
工する際に、部材の傾斜角が遂一変化し、そのた
め移動作業車はこの傾斜角の変化に対応できる機
能を持たねばならないので、橋桁の施工に利用し
た移動作業車を、そのままカンチレバー工法によ
る架設方法に利用することができないという問題
がある。
However, when using the cantilever construction method, the bridge girder is a nearly horizontal member, whereas the arch ring is a curved member.
When constructing parts from the base of the arch ring to the arch crown, the angle of inclination of the members changes, and the mobile work vehicle must have the ability to handle this change in angle of inclination. There is a problem in that the work vehicle cannot be used as is for the cantilever construction method.

第11図は橋桁の施工に使用される従来の移動
作業車8の例を示すものであつて、橋桁の上部に
固定されたレール10に、移動フレーム11に取
付けられた前部車輪12および後部車輪13が載
置され、かつ前記移動フレーム11の後部に、レ
ール10の頭部下面に係合されるアンカージヤツ
キ14が取付けられると共にレール10の頭部上
面に対向するスクリユウジヤツキ15が取付けら
れ、さらに前記移動フレーム11に、前部車輪1
2付近でレール10に係合される主ジヤツキ16
と、上部型枠受け部材17および下部型枠受け部
材18と、足場19,20とが取付けられ、また
前記移動フレーム11の後側部分に、移動作業車
8を前進移動させるためのレバー揺動式牽引具ま
たはチエーンブロツク等の小型牽引装置21を係
止し、その小型牽引装置21におけるチエーン2
2をレール10の前端に係合した状態で、小型牽
引装置21を手動操作することにより、移動作業
車8を前進移動させるように構成している。
FIG. 11 shows an example of a conventional mobile work vehicle 8 used in the construction of bridge girders, in which front wheels 12 and rear wheels are mounted on rails 10 fixed to the upper part of the bridge girder, front wheels 12 attached to a movable frame 11, Wheels 13 are mounted, and an anchor jack 14 that engages with the lower surface of the head of the rail 10 is attached to the rear of the moving frame 11, and a screw jack 15 that faces the upper surface of the head of the rail 10 is attached. furthermore, front wheels 1 are attached to the moving frame 11.
The main jack 16 is engaged with the rail 10 near 2
, an upper formwork receiving member 17 , a lower formwork receiving member 18 , and scaffolds 19 , 20 are attached, and a swinging lever for moving the mobile work vehicle 8 forward is attached to the rear portion of the moving frame 11 . A small-sized traction device 21 such as a type traction device or a chain block is locked, and the chain 2 of the small-sized traction device 21 is
2 is engaged with the front end of the rail 10, and by manually operating the small traction device 21, the mobile work vehicle 8 is moved forward.

また第12図はアーチリング施工のために改造
された移動作業車23の一部を示すものであつ
て、急勾配車のアーチリングに沿つて移動作業車
23を押上げるための大型の推進用ジヤツキ24
とねじ式伸縮装置からなる角度調整装置25とを
装備している。
Moreover, FIG. 12 shows a part of the mobile work vehicle 23 modified for arch ring construction, and shows a large propulsion vehicle for pushing the mobile work vehicle 23 up along the arch ring of a steep slope vehicle. Jyatsuki 24
and an angle adjustment device 25 consisting of a screw type telescopic device.

そのため第12図に示す移動作業車23の場合
は、第11図に示す移動作業車8に比べて製作費
が相当高くなる。
Therefore, the manufacturing cost of the mobile work vehicle 23 shown in FIG. 12 is considerably higher than that of the mobile work vehicle 8 shown in FIG. 11.

また傾斜したコンクリート部材を施工する場合
は、斜面で配筋作業やコンクリート打設作業を行
なわねばならないので、ほぼ水平な部材を施工す
る場合に比べて、施工性が極めて悪いという問題
がある。
Furthermore, when constructing an inclined concrete member, reinforcement work and concrete pouring work must be performed on the slope, so there is a problem that the workability is extremely poor compared to when constructing a substantially horizontal member.

〔発明の目的、構成〕[Purpose and structure of the invention]

この発明は、前記従来のカンチレバー工法によ
つてアーチリングを形成する際に生じる前記問題
点を解決したRCアーチ橋のアーチリング施工法
を提供することを目的とするものであつて、この
発明の要旨とするところは、基礎地盤にアーチア
バツト1とアンカーブロツク2とを築造し、かつ
前記アーチアバツト1にピン支承3のベース部材
4を固定し、そのピン支承3の可動部材5に連結
されたアーチリング基部ブロツク6Aをほぼ水平
状態で施工したのち、第2アーチリングブロツク
をほぼ水平状態で施工できるように、前記アンカ
ーブロツク2により第1吊ケーブル7を介して前
記アーチリング基部ブロツク6Aを吊上支持し、
次にそのアーチリング基部ブロツク6Aの上に移
動作業車8を組立設置したのち、前記アーチリン
グ基部ブロツク6Aに連結された第2アーチリン
グブロツク6Bをほぼ水平状態で施工し、次いで
第3アーチリングブロツクをほぼ水平状態で施工
できるように、前記アンカーブロツク2により第
2吊ケーブル9を介して第2アーチリングブロツ
ク6Bを吊上支持したのち、アーチリング基部ブ
ロツク6Aから第1吊ケーブル7を離脱し、かつ
移動作業車8を第2アーチブロツク6B上に移動
し次に第3以降のアーチリングブロツクのほぼ水
平状態での施工と第1吊ケーブル7および第2吊
ケーブル9の交互使用による新設アーチリングブ
ロツクの吊上支持と移動作業車8の移動とを交互
に行なうことを特徴とするRCアーチ橋のアーチ
リング施工法にある。
An object of the present invention is to provide an arch ring construction method for an RC arch bridge that solves the problems described above that occur when forming an arch ring using the conventional cantilever construction method. The gist is that an arch abutment 1 and an anchor block 2 are constructed on the foundation ground, a base member 4 of a pin support 3 is fixed to the arch abutment 1, and an arch ring is connected to a movable member 5 of the pin support 3. After constructing the base block 6A in a substantially horizontal state, the arch ring base block 6A is suspended and supported by the anchor block 2 via the first suspension cable 7 so that the second arch ring block can be constructed in a substantially horizontal state. death,
Next, after assembling and installing the mobile work vehicle 8 on the arch ring base block 6A, the second arch ring block 6B connected to the arch ring base block 6A is constructed in a substantially horizontal state, and then the third arch ring is constructed. After the second arch ring block 6B is suspended and supported by the anchor block 2 via the second suspension cable 9 so that the block can be constructed in a substantially horizontal state, the first suspension cable 7 is removed from the arch ring base block 6A. Then, the mobile work vehicle 8 is moved onto the second arch ring block 6B, and the third and subsequent arch ring blocks are constructed in a substantially horizontal state, and the first suspension cable 7 and the second suspension cable 9 are used alternately to construct the new construction. This is an arch ring construction method for an RC arch bridge, which is characterized by alternately carrying out lifting support of arch ring blocks and moving a mobile work vehicle 8.

〔実施例〕〔Example〕

次にこの発明を図示の例によつて詳細に説明す
る。
Next, the present invention will be explained in detail using illustrated examples.

この発明を実施してRCアーチ橋のアーチリン
グを施工する場合は、第1図および第2図に示す
ように、まず基礎地盤上に、コンクリートのアー
チアバツト1およびコンクリートのアバツト26
を築造したのち、そのアーチアバツト1の上部に
エンドポスト27を構築し、かつエンドポスト2
7の上端部とアバツト26とにわたつて側径間の
上床版28を架設し、さらにアーチリングの支持
点となる位置に予めピン支承3を配置し、そのピ
ン支承3におけるベース部材4をアーチアバツト
1に対しアンカーボルト29により固定してお
く。
When constructing an arch ring for an RC arch bridge by carrying out this invention, first, as shown in Figs. 1 and 2, concrete arch abutments 1 and 26 are placed on the foundation ground.
After constructing the arch abutment 1, an end post 27 is constructed on top of the arch abutment 1, and an end post 2 is constructed.
7 and the abutment 26, a pin support 3 is placed in advance at a position that will serve as a support point for the arch ring, and the base member 4 of the pin support 3 is attached to the arch abutment. 1 with anchor bolts 29.

次にアーチアバツト1の前部の基礎地盤上に多
数の支柱と支柱連結部材とからなる支柱式支保工
30を組立設置し、その支柱式支保工30の上
に、アーチリング基部ブロツクを施工するための
溝形型枠31をほぼ水平になるように設置し、そ
の型枠31内に鉄筋を配置してコンクリートを打
設する。
Next, a column type support 30 consisting of a large number of columns and column connecting members is assembled and installed on the foundation ground in front of the arch abutment 1, and an arch ring base block is constructed on top of the column type support 30. A groove-shaped formwork 31 is installed so as to be almost horizontal, reinforcing bars are placed inside the formwork 31, and concrete is poured.

一方、第3図ないし第5図に示すように、アバ
ツト26の後方にコンクリートのアンカーブロツ
ク2を築造し、必要に応じてそのアンカーブロツ
ク2をロツクアンカー32により地盤に繋止し
て、アーチリング吊上時のアンカーブロツク2の
浮上がりを防止する。また前記アンカーブロツク
2に埋込繋止される定着ケーブル33の一端部を
アンカーブロツク2のコンクリート打設前に予め
所定の位置において鉄筋等に固定しておき、かつ
エンドポスト27の上部または上床版28の上に
仮支柱34を設置し、その仮支柱34の天端の左
右両側に、それぞれ第一吊ケーブル7の中間部を
摺動自在に支承するためサドル35と第2吊ケー
ブル9の中間部を摺動自在に支承するためのサド
ル36とを固定しておく。
On the other hand, as shown in Figs. 3 to 5, a concrete anchor block 2 is constructed behind the abutment 26, and if necessary, the anchor block 2 is anchored to the ground with a lock anchor 32, and an arch ring is constructed. To prevent floating of an anchor block 2 during lifting. Furthermore, one end of the fixing cable 33 to be embedded and connected to the anchor block 2 is fixed to a reinforcing bar or the like at a predetermined position in advance before concrete pouring of the anchor block 2, and the anchor cable 33 is fixed to the upper part of the end post 27 or the upper deck slab. A temporary strut 34 is installed on top of the temporary strut 34, and on both left and right sides of the top end of the temporary strut 34, the intermediate portion of the first suspension cable 7 is slidably supported. A saddle 36 for slidably supporting the part is fixed.

前記アーチリング基部ブロツクのコンクリート
が硬化したのち脱型し、次いで第6図ないし第8
図に示すように、左右方向に間隔をおいて配置さ
れたワイヤロープまたはパラレルワイヤストラン
ドからなる一対の第一吊ケーブル7を、連結金具
37に取付けられたセンターホールジヤツキ38
に挿通し、かつそのセンターホールジヤツキ38
の中空ピストン杆に係合されるクランプ39によ
り前記第一吊ケーブル7を把持すると共に、連結
金具37の左右両側に定着ケーブル33の他端部
を連結し、さらに前記第1吊ケーブル7を、サド
ル35の溝に嵌入すると共に中空のアーチリング
基部ブロツク6Aの上面版およびセンターホール
ジヤツキ40に順次挿通し、そのセンターホール
ジヤツキ40の中空ピストン杆に係合されるクラ
ンプ41により第1吊ケーブル7を把持する。
After the concrete of the arch ring base block has hardened, it is removed from the mold, and then
As shown in the figure, a pair of first suspension cables 7 made of wire ropes or parallel wire strands arranged at intervals in the left and right direction are connected to a center hole jack 38 attached to a connecting fitting 37.
and its center hole jack 38.
The first suspension cable 7 is held by a clamp 39 that is engaged with the hollow piston rod, and the other end of the fixing cable 33 is connected to both left and right sides of the connecting fitting 37, and the first suspension cable 7 is It is fitted into the groove of the saddle 35 and sequentially inserted into the top plate of the hollow arch ring base block 6A and the center hole jack 40, and is suspended by the clamp 41 which is engaged with the hollow piston rod of the center hole jack 40. Grip the cable 7.

次にアンカーブロツク側のセンターホールジヤ
ツキ38とアーチリング基部側のセンターホール
ジヤツキ40とを使用して、第2アーチリングブ
ロツクをほぼ水平状態で施工できるように前記ア
ーチリング基部ブロツク6Aを吊り上げたのち、
前記上床版28上からクレーン等の揚重機により
移動作業車構成用の各部品をアーチリング基部ブ
ロツク6A上に吊り降ろし、そのアーチリング基
部ブロツク6A上で移動作業車8の組立作業を行
なう。
Next, using the center hole jack 38 on the anchor block side and the center hole jack 40 on the arch ring base side, lift the arch ring base block 6A so that the second arch ring block can be constructed in a substantially horizontal state. Later,
Each part constituting the mobile work vehicle is lifted onto the arch ring base block 6A from above the upper floor slab 28 using a lifting machine such as a crane, and the mobile work vehicle 8 is assembled on the arch ring base block 6A.

次に第2アーチリングブロツク用の型枠31を
建込み、その型枠31内に配置した鉄筋と前記ア
ーチリング基部ブロツク6Aの鉄筋とを連結した
のち、前記型枠31内にコンクリートを打設す
る。この打設コンクリートは、アーチリングの上
方に張設したケーブルクレーン(図示を省略し
た)により打設位置まで運搬される。
Next, a formwork 31 for the second arch ring block is erected, and after connecting the reinforcing bars placed in the formwork 31 and the reinforcing bars of the arch ring base block 6A, concrete is poured into the formwork 31. do. This poured concrete is transported to the pouring position by a cable crane (not shown) placed above the arch ring.

次に前記コンクリートが硬化したのち脱型し、
次いで前記第1吊ケーブル7の場合と同様の手順
によつて、第2吊ケーブル9をアンカーブロツク
2、サドル36および第2アーチリングブロツク
6B間に張設し、続いて施工される第3アーチリ
ングブロツクがほぼ水平状態になる高さまで、前
記第2アーチリングブロツク6Bをアーチリング
基部ブロツク6Aと共にセンターホールジヤツキ
38,40により吊り上げる。これにより既設ア
ーチリングの重量および移動作業車8の重量等は
第1吊ケーブル7から第2吊ケーブル9に移行
し、第1吊ケーブル7から荷重が解放される。そ
してこの第1吊ケーブル7は第3アーチリングブ
ロツクの吊り上げに使用される。
Next, after the concrete has hardened, it is demolded,
Next, by the same procedure as for the first suspension cable 7, the second suspension cable 9 is stretched between the anchor block 2, the saddle 36 and the second arch ring block 6B, and then the third arch to be constructed is The second arch ring block 6B is lifted together with the arch ring base block 6A by the center hole jacks 38 and 40 until the ring block is in a substantially horizontal state. As a result, the weight of the existing arch ring, the weight of the mobile work vehicle 8, etc. are transferred from the first suspension cable 7 to the second suspension cable 9, and the load is released from the first suspension cable 7. This first suspension cable 7 is used to lift the third arch ring block.

前述のようにして、第3以降のアーチリングブ
ロツクをほぼ水平状態で順次施工すると共に、第
1吊ケーブル7および第2吊ケーブル9を交互に
使用して新設アーチリングブロツクを吊上支持し
て、アーチクラウンに向かつてアーチリングを施
工していく。第9図はアーチリングブロツク6A
〜6Fを施工した状態を示している。
As described above, the third and subsequent arch ring blocks are successively constructed in a substantially horizontal state, and the first and second suspension cables 7 and 9 are used alternately to suspend and support the newly installed arch ring blocks. , construct the arch ring towards the arch crown. Figure 9 shows arch ring block 6A.
This shows the state in which floors 6 to 6 have been constructed.

既設アーチリングの長さが長くなるにつれて、
アーチリングの下縁に作用する曲げ引張応力が増
大し、設計荷重に対応するように配置された鉄筋
のみでは、鉄筋に作用する引張応力度が許容値を
越えることがある。この場合は、アーチリングの
下縁にアウトケーブル(図示を省略した)を配置
し、そのアウトケーブルを緊張して、アーチリン
グの下縁に圧縮応力を与えることにより対処でき
る。
As the length of the existing arch ring increases,
The bending tensile stress acting on the lower edge of the arch ring increases, and if only the reinforcing bars are placed to accommodate the design load, the tensile stress acting on the reinforcing bars may exceed the allowable value. This case can be dealt with by arranging an out cable (not shown) at the lower edge of the arch ring and tensioning the out cable to apply compressive stress to the lower edge of the arch ring.

アーチクラウン部分のコンクリートを打設する
場合は、移動作業車を撤去したのち、第10図に
示すように、アーチクラウン部分の両側のアーチ
リングブロツクにわたつて吊支保工42を架設
し、その吊支保工42によりアーチクラウン部分
の型枠を支持し、その型枠内に鉄筋を配置してコ
ンクリートを打設する。
When pouring concrete for the arch crown part, after removing the mobile work vehicle, as shown in Figure 10, suspending supports 42 are erected across the arch ring blocks on both sides of the arch crown part. The formwork of the arch crown portion is supported by the shoring 42, reinforcing bars are placed within the formwork, and concrete is poured.

アーチリングが完成したのち、アーチ基部(ア
ーチスプリンギング)が固定構造の場合には、前
記ピン支承3を撤去することなく、アーチアバツ
ト1およびアーチリング43の下端から鉄筋を突
出させると共にそれらの鉄筋を結合したのち、ア
ーチアバツト1とアーチリング43との間にコン
クリートを打設するか、あるいはピン支承を撤去
したのち、アーチアバツト1とアーチリング43
の下端との間に鉄筋を配置してコンクリートを打
設する。
After the arch ring is completed, if the arch base (arch springing) has a fixed structure, the reinforcing bars are made to protrude from the lower ends of the arch abutment 1 and the arch ring 43 without removing the pin support 3, and those reinforcing bars are removed. After joining, concrete is poured between the arch abutment 1 and the arch ring 43, or after the pin support is removed, the arch abutment 1 and the arch ring 43 are connected.
Place reinforcing bars between the bottom edge and pour concrete.

アーチリング基部からアーチクラウンに向かつ
てブロツクの形成が進むにつれて、吊ケーブル
7,9の長さを長くする必要があるので、この場
合は、クランプ39を弛緩してセンターホールジ
ヤツキ38に対し吊ケーブル7,9を移動し、次
いで再びクランプ39により吊ケーブル7,9を
把持する。
As the block progresses from the arch ring base toward the arch crown, it is necessary to increase the length of the suspension cables 7 and 9. In this case, loosen the clamp 39 and suspend the suspension from the center hole jack 38. The cables 7, 9 are moved, and then the hanging cables 7, 9 are held again by the clamp 39.

〔発明の効果〕〔Effect of the invention〕

この発明によれば、アーチアバツト1にピン支
承3のベース部材4を固定し、そのピン支承3の
可動部材5に連結されたアーチリング基部ブロツ
ク6Aをほぼ水平状態で施工したのち、第2アー
チリングブロツクをほぼ水平状態で施工できるよ
うに、前記アンカーブロツク2により第1吊ケー
ブル9を介して前記アーチリング基部ブロツク6
Aを吊上支持し、次にそのアーチリング基部ブロ
ツク6Aの上に移動作業車8を組立配置したの
ち、前記アーチリング基部ブロツク6Aに連結さ
れた第2アーチリングブロツク6Bをほぼ水平状
態で施工し、次いで第3アーチリングブロツクを
ほぼ水平状態で施工できるように、前記アンカー
ブロツク2により第2吊ケーブル9を介して第2
アーチリングブロツク6Bを吊上支持したのち、
アーチリング基部ブロツク6Aから第1吊ケーブ
ル7を離脱し、かつ移動作業車8を第2アーチリ
ングブロツク6B上に移動し次に第3以降のアー
チリングブロツクのほぼ水平状態での施工と第1
吊ケーブル7および第2吊ケーブル9の交互使用
による新設アーチリングブロツクの吊上支持と移
動作業車8の移動とを交互に行なうので、RCア
ーチ橋のアーチリングを構成する各コンクリート
ブロツクを常にほぼ水平状態で施工することがで
き、そのため移動作業車8の設置および移動、配
筋作業、コンクリート打設作業等を容易にかつ迅
速に行なうことができると共に、アーチリングの
架設コストを低減することができ、さらに移動作
業車8としては、従来の橋桁施工に使用していた
ものをそのまま使用できるので、従来の移動作業
車を改造したり特殊で高価な移動作業車を新規に
製作する等の必要がなく、したがつて経済的であ
る等の効果が得られる。
According to this invention, after fixing the base member 4 of the pin support 3 to the arch abutment 1 and constructing the arch ring base block 6A connected to the movable member 5 of the pin support 3 in a substantially horizontal state, the second arch ring The anchor block 2 connects the arch ring base block 6 via the first suspension cable 9 so that the block can be constructed in a substantially horizontal state.
After lifting and supporting the arch ring base block 6A, and then assembling and arranging the mobile work vehicle 8 on the arch ring base block 6A, the second arch ring block 6B connected to the arch ring base block 6A is constructed in a substantially horizontal state. Then, the anchor block 2 connects the second arch ring block through the second suspension cable 9 so that the third arch ring block can be constructed in a substantially horizontal state.
After suspending and supporting arch ring block 6B,
The first suspension cable 7 is removed from the arch ring base block 6A, and the mobile work vehicle 8 is moved onto the second arch ring block 6B. Next, the third and subsequent arch ring blocks are constructed in a substantially horizontal state, and the first
Since the suspension cables 7 and the second suspension cables 9 are used alternately to lift and support the newly installed arch ring block, and the mobile work vehicle 8 is moved, each concrete block that makes up the arch ring of the RC arch bridge is always almost always lifted. Construction can be carried out in a horizontal state, so installation and movement of the mobile work vehicle 8, reinforcing work, concrete pouring work, etc. can be performed easily and quickly, and the cost of erecting the arch ring can be reduced. Moreover, as the mobile work vehicle 8, the one used for conventional bridge girder construction can be used as is, so there is no need to modify the conventional mobile work vehicle or manufacture a new special and expensive mobile work vehicle. Therefore, effects such as being economical can be obtained.

【図面の簡単な説明】[Brief explanation of drawings]

第1図ないし第10図はこの発明の一実施例を
示すものであつて、第1図はアーチリング基部ブ
ロツクの施工準備を完了した状態を示す縦断側面
図、第2図はアーチアバツトに対するピン支承の
取付状態を示す縦断側面図、第3図はアーチリン
グ基部ブロツクを吊ケーブルにより支持すると共
に移動作業車を設置した状態を示す縦断側面図、
第4図は仮支柱上のサドルにより支持された吊ケ
ーブルを示す正面図、第5図はその側面図、第6
図はアンカーブロツクに繋止された定着ケーブル
と吊ケーブルとの連結状態を示す縦断側面図、第
7図はその平面図、第8図はアーチリング基部ブ
ロツクと吊ケーブルとの連結状態を示す縦断側面
図、第9図はアーチリング施工途中の状態を示す
縦断側面図、第10図はアーチクラウン部分を施
工するときの状態を示す縦断側面図である。第1
1図は従来の橋桁施工用移動作業車を示す側面
図、第12図はアーチリング施工用に改造された
従来の移動作業車を示す側面図である。 図において、1はアーチアバツト、2はアンカ
ーブロツク、3はピン支承、4はベース部材、5
は可動部材、6はアーチリング基部ブロツク、7
は第1吊ケーブル、8は移動作業車、9は第2吊
ケーブル、26はアバツト、27はエンドポス
ト、28は上床版、29はアンカーボルト、30
は支柱式支保工、31は型枠、32はロツクアン
カー、33は定着ケーブル、34は仮支柱、35
および36はサドル、37は連結金具、38はセ
ンターホールジヤツキ、39はクラウン、40は
センターホールジヤツキ、41はクランプ、42
は吊支保工、43はアーチリングである。
Figures 1 to 10 show one embodiment of the present invention, in which Figure 1 is a vertical cross-sectional side view showing the completed construction preparation of the arch ring base block, and Figure 2 is a pin support for the arch abutment. Fig. 3 is a vertical side view showing the arch ring base block supported by a suspension cable and a mobile work vehicle installed;
Figure 4 is a front view showing the suspension cable supported by the saddle on the temporary support, Figure 5 is its side view, and Figure 6
The figure is a longitudinal side view showing the connection state between the fixing cable and the suspension cable connected to the anchor block, Figure 7 is a plan view thereof, and Figure 8 is a longitudinal section showing the connection state between the arch ring base block and the suspension cable. A side view, FIG. 9 is a longitudinal sectional side view showing a state in the middle of construction of an arch ring, and FIG. 10 is a longitudinal sectional side view showing a state when an arch crown portion is being constructed. 1st
FIG. 1 is a side view showing a conventional mobile work vehicle for constructing bridge girders, and FIG. 12 is a side view showing a conventional mobile work vehicle modified for arch ring construction. In the figure, 1 is an arch abutment, 2 is an anchor block, 3 is a pin support, 4 is a base member, and 5 is a
is a movable member, 6 is an arch ring base block, and 7 is a movable member.
is the first suspension cable, 8 is the mobile work vehicle, 9 is the second suspension cable, 26 is the abutment, 27 is the end post, 28 is the upper floor slab, 29 is the anchor bolt, 30
31 is the formwork, 32 is the lock anchor, 33 is the anchoring cable, 34 is the temporary support, 35
36 is a saddle, 37 is a connecting fitting, 38 is a center hole jack, 39 is a crown, 40 is a center hole jack, 41 is a clamp, 42
is a suspension support, and 43 is an arch ring.

Claims (1)

【特許請求の範囲】[Claims] 1 基礎地盤にアーチアバツト1とアンカーブロ
ツク2とを築造し、かつ前記アーチアバツト1に
ピン支承3のベース部材4を固定し、そのピン支
承3の可動部材5に連結されたアーチリング基部
ブロツク6Aをほぼ水平状態で施工したのち、第
2アーチリングブロツクをほぼ水平状態で施工で
きるように、前記アンカーブロツク2により第1
吊ケーブル7を介して前記アーチリング基部ブロ
ツク6Aを吊上支持し、次にそのアーチリング基
部ブロツク6Aの上に移動作業車8を組立設置し
たのち、前記アーチリング基部ブロツク6Aに連
結された第2アーチリングブロツク6Bをほぼ水
平状態で施工し、次いで第3アーチリングブロツ
クをほぼ水平状態で施工できるように、前記アン
カーブロツク2により第2吊ケーブル9を介して
第2アーチリングブロツク6Bを吊上支持したの
ち、アーチリング基部ブロツク6Aから第1吊ケ
ーブル7を離脱し、かつ移動作業車8を第2アー
チリングブロツク6B上に移動し次に第3以降の
アーチリングブロツクのほぼ水平状態での施工と
第1吊ケーブル7および第2吊ケーブル9の交互
使用による新設アーチリングブロツクの吊上支持
と移動作業車8の移動とを交互に行なうことを特
徴とするRCアーチ橋のアーチリング施工法。
1 Construct an arch abutment 1 and an anchor block 2 on the foundation ground, fix the base member 4 of the pin support 3 to the arch abutment 1, and approximately After the construction is carried out in a horizontal state, the anchor block 2 is attached to the first arch ring block so that the second arch ring block can be constructed in a substantially horizontal state.
The arch ring base block 6A is suspended and supported via the suspension cable 7, and then the mobile work vehicle 8 is assembled and installed on the arch ring base block 6A. The second arch ring block 6B is suspended by the anchor block 2 via the second suspension cable 9 so that the second arch ring block 6B can be constructed in a substantially horizontal state, and then the third arch ring block can be constructed in a substantially horizontal state. After the upper support, the first suspension cable 7 is removed from the arch ring base block 6A, and the mobile work vehicle 8 is moved onto the second arch ring block 6B, and then the third and subsequent arch ring blocks are placed in a substantially horizontal state. Arch ring construction for an RC arch bridge characterized by alternately performing construction, lifting support of a newly installed arch ring block by alternately using a first suspension cable 7 and a second suspension cable 9, and moving a mobile work vehicle 8. Law.
JP12571187A 1987-05-25 1987-05-25 Arch ring execution method of rc arch bridge Granted JPS63293203A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12571187A JPS63293203A (en) 1987-05-25 1987-05-25 Arch ring execution method of rc arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12571187A JPS63293203A (en) 1987-05-25 1987-05-25 Arch ring execution method of rc arch bridge

Publications (2)

Publication Number Publication Date
JPS63293203A JPS63293203A (en) 1988-11-30
JPH0380202B2 true JPH0380202B2 (en) 1991-12-24

Family

ID=14916851

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12571187A Granted JPS63293203A (en) 1987-05-25 1987-05-25 Arch ring execution method of rc arch bridge

Country Status (1)

Country Link
JP (1) JPS63293203A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2208088B2 (en) * 2002-07-09 2005-10-01 R & C RESEARCH AND CONCRETE, S.A. PREFABRICATED ARCH BRIDGE CONSTRUCTION SYSTEM.
JP4522941B2 (en) * 2005-11-04 2010-08-11 三井住友建設株式会社 How to dismantle and remove the arch bridge

Also Published As

Publication number Publication date
JPS63293203A (en) 1988-11-30

Similar Documents

Publication Publication Date Title
JP5059491B2 (en) Assembly method of mobile suspension support
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
JPH0841826A (en) Erection method of bridge and equipment thereof and main girder unit
JP3110985B2 (en) Construction method of column capital of overhang girder bridge
EP1111135A2 (en) Method of building viaducts
JP2967874B1 (en) How to build an overhead suspension bridge
KR102477955B1 (en) Bridge pier and the construction method using maintained concrete mold
JPH02503099A (en) Cable supported bridge and construction method
US6412132B1 (en) Methods for constructing a bridge utilizing in-situ forms supported by beams
JPH07233508A (en) Pier, and pier-constructing method by means of self-climbing form installation
JP2006207209A (en) Construction method of deck type suspended floor slab bridge
JP3877995B2 (en) How to build a string string bridge
JPH0380202B2 (en)
CN111877127B (en) Construction method of continuous arch bridge
JP3197234B2 (en) Moving scaffold for floor slab assembly
JP7134133B2 (en) Bridge railing construction method
JP4375788B2 (en) Construction method of upper-floor type suspension floor slab bridge
KR100507597B1 (en) Formwork supporting apparatus for hanging type formwork system and formwork using the same
JPS6041164B2 (en) Cable-stayed bridge construction method
JPS6314903A (en) Arch ring execution method in concrete arch bridge
JP2977243B2 (en) Removal method of formwork support for arch concrete construction
JP3171676B2 (en) Construction method of cast-in-place concrete horizontal member
JPS6135325B2 (en)
JP2734985B2 (en) Cantilever shed and its construction method
JP4838329B2 (en) Construction method of upper-floor type suspension floor slab bridge