JPS627329B2 - - Google Patents

Info

Publication number
JPS627329B2
JPS627329B2 JP56065555A JP6555581A JPS627329B2 JP S627329 B2 JPS627329 B2 JP S627329B2 JP 56065555 A JP56065555 A JP 56065555A JP 6555581 A JP6555581 A JP 6555581A JP S627329 B2 JPS627329 B2 JP S627329B2
Authority
JP
Japan
Prior art keywords
wall
water
concrete
piles
reference piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP56065555A
Other languages
Japanese (ja)
Other versions
JPS57180715A (en
Inventor
Kimihiko Terada
Takekazu Baba
Kenji Nakane
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP6555581A priority Critical patent/JPS57180715A/en
Publication of JPS57180715A publication Critical patent/JPS57180715A/en
Publication of JPS627329B2 publication Critical patent/JPS627329B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、水中に連続壁を構築する方法に関
し、特に、水中に建込んだ基準杭をガイドにして
壁板体を建込み、基準杭と壁板体とで囲まれる空
間の水を駆逐してその水底を堀り下げ、ここに、
コンクリートを打設して水中の連続壁となす。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method for constructing a continuous wall underwater, and in particular, a method of constructing a wall plate using reference piles erected underwater as a guide, and The water in the space surrounded by the wall and the wall board was expelled and the bottom of the water was dug down, and here,
Concrete will be poured to create a continuous underwater wall.

〔従来例〕 従来の水上で連続壁を構築する工事には、ま
ず、埋立てによつて人工地盤を作り、次にこの人
工地盤上に連続壁を作るという方法を採用してい
た。
[Conventional example] Conventional construction work for constructing continuous walls over water involves first creating artificial ground by reclaiming land, and then building continuous walls on top of this artificial ground.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかしながら、この方法によれば、人工地盤を
造成するための埋立て工事に時間と手間、費用が
かかること、埋立層の崩落防止工事が必要であ
り、これが面倒であること、さらに、連続壁を橋
脚の基礎等に使う場合には、埋立層を再び撤去し
なくてはならないこと、等々工程上あるいはコス
ト上の大きな無駄があつた。
However, according to this method, the reclamation work to create the artificial ground takes time, effort, and cost, and work to prevent the reclaimed layer from collapsing is required, which is troublesome. When using it for the foundations of bridge piers, etc., the reclaimed layer had to be removed again, which was a huge waste in terms of process and cost.

この発明は、従来方法のかかる問題を解決する
ものであつて、その目的は、水中に連続壁を構築
するにおいて埋立て工事を必要としない工法を提
供するにあり、またこの発明の目的は、簡単に水
中連続壁を構築する方法を提供するにあり、さら
この発明の目的は、工期、手間、コストを大幅に
節減できる水中連続壁の構築方法を提供するにあ
る。
This invention solves the problems of the conventional methods, and its purpose is to provide a construction method that does not require reclamation work when constructing a continuous wall underwater; It is an object of the present invention to provide a method for easily constructing an underwater continuous wall, and a further object of the present invention is to provide a method for constructing an underwater continuous wall that can significantly reduce construction period, labor, and cost.

〔問題点を解決するための手段及び作用〕[Means and actions for solving problems]

すなわち、この発明は、連続壁の厚さ方向両側
に夫々ガイドを有する基準杭を、水中に適宜間隔
で建込み、2つの基準杭のガイドに左右端を係合
案内させながら、相対向する2つの壁板体を前記
2つの基準杭間に建込み、この2つの壁板体を適
宜地中に進入させた状態で壁板体間の水を、泥水
と置換するなどして排除し、壁板体間の水底を堀
り下げて溝を形成し、こ溝内と、2つの壁板体及
び2つの基準杭に囲まれた区域内とにコンクリー
トを打設し、これを硬化させることにより両基準
杭間を所定厚みのコンクリートで直接に連結し、
前記コンクリートの硬化後に壁板体を撤去するこ
とを特徴とする、水中で連続壁を構築する方法に
係る。
That is, in this invention, reference piles having guides on both sides in the thickness direction of a continuous wall are erected in water at appropriate intervals, and while the left and right ends are engaged and guided by the guides of the two reference piles, two Two wall plates are erected between the two standard piles, and while these two wall plates are properly penetrated into the ground, the water between the wall plates is removed by replacing it with muddy water, etc. By digging down the bottom of the water between the plates to form a groove, pouring concrete into this groove and the area surrounded by the two wall plates and two reference piles, and allowing it to harden. Directly connect the two reference piles with concrete of a specified thickness,
The present invention relates to a method for constructing a continuous wall underwater, characterized in that the wall plate is removed after the concrete has hardened.

〔効 果〕〔effect〕

この発明においては、水中に建込んだ基準杭を
ガイドにして壁板を建込み、基準杭と壁板体とで
囲まれる空間の水を駆逐してその水底を堀り下
げ、ここに、コンクリートを打設して水中の連続
壁となすものであるから、壁板体が外部とエレメ
ントを構成する部分とを遮断し、それ自体および
これによつて保有される泥水圧力で溝の崩落を防
止する。したがつて、溝堀下げという単純な作業
によつて、水中の連続壁構築の主たる工事が遂行
できる。よつて、この発明によれば、水中の連続
壁が容易に、且つ低コストで行える。
In this invention, a wall plate is erected using reference piles erected in the water as guides, water is expelled from the space surrounded by the reference piles and the wall plate body, the bottom of the water is dug down, and concrete is placed here. Since the wall plate is cast to form a continuous wall underwater, the wall board blocks the outside from the parts that make up the element, and prevents the trench from collapsing due to the muddy pressure itself and the muddy water pressure held by it. do. Therefore, the main work of constructing an underwater continuous wall can be accomplished by the simple work of trenching and lowering. Therefore, according to the present invention, a continuous wall underwater can be formed easily and at low cost.

特にこの発明にあたつては、2つの基準杭間
に、相対向する2枚の壁板体を建込んでいるた
め、その間に打設されたコンクリートは、基準杭
に直接接して硬化する。このため打設コンクリー
トにより形成される壁体は、格別の工事を必要と
することなく両端の基準杭と一体に結合され、そ
のまま地中連続壁が出来上がる。さらにこの発明
にあつては、2つの基準杭の間に壁体を施工する
ものであるため、所定間隔で基準杭を多数建込ん
でおくことにより、基準杭の各間隔において並行
して施工することができる。このため、掘削機、
コンクリート打設機、クレーン等を遊ばせること
なく効率よく施工することができるほか、基準杭
を精度よく建込んでおくことにより、その間の壁
体の構築は基準杭に合わせて施工するだけでよい
から、壁体の施工の精度を確保することが容易に
可能になるという効果がある。
In particular, in this invention, since two wall plates facing each other are installed between two reference piles, the concrete placed between them hardens in direct contact with the reference piles. For this reason, the wall formed of poured concrete is integrally connected to the reference piles at both ends without the need for any special construction work, and an underground continuous wall is completed as is. Furthermore, in this invention, since the wall is constructed between two reference piles, by erecting a large number of reference piles at predetermined intervals, construction can be carried out in parallel at each interval between the reference piles. be able to. For this reason, excavators,
In addition to being able to perform construction efficiently without leaving concrete placing machines, cranes, etc. idle, by erecting reference piles with precision, the wall between them only needs to be constructed in line with the reference piles. This has the effect of easily ensuring the accuracy of wall construction.

〔実施例〕〔Example〕

第1図の如く、まず、円筒形のスタンドパイプ
6を一定の間隔で水底の地盤Bに根入れする。こ
の作業には、公知のバイブロハンマ(図示しな
い。)等を用いる。
As shown in FIG. 1, first, cylindrical stand pipes 6 are embedded in the ground B at the bottom of the water at regular intervals. A known vibrohammer (not shown) or the like is used for this work.

このスタンドパイプ6内の水(海水)を泥水と
置換してから、このスタンドパイプ6内にリバー
スサーキユレーシヨンドリル(図示しない。)を
設定し、これによつて所定の深さに基準穴7を掘
設する。この中に、H形鋼でなる基準杭2を建込
む。ここで用いられるH形鋼は、フランジ2a
が、これと一定の間隔で設けられた前記他のスタ
ンドパイプ6内の基準杭2のH形鋼フランジ2a
と対向するように建込まれる。そして、そのH形
鋼の構造は、単純なH形鋼であつてもよいが、こ
こでは、図の如く、フランジ2aを連結する連結
板2bが2枚である構造のものを採用した。第2
図は、上記の様子を明示している。第2図に見ら
れる如く、フランジ2aの外側には、フランジ先
端部を残してシート8が貼着してあり、基準穴7
の内周面とで区画空間を形成する。そして、第3
図の如く、シート8とフランジ2aの側面と基準
穴7の内周面とで画成される空間および基準杭2
の中空部に、斜線で示すコンクリートを打設し、
フランジ2aと連結板2bと基準穴7の内周面と
で画成される空間に砂利またはシルトモルタルを
充てんして基準杭2を基準穴7内に固定する。こ
の場合、泥水をそのまま固化することもあり得
る。燃る後、スタンドパイプ6は抜去する。この
様子は、第4図に示す。
After replacing the water (seawater) in this standpipe 6 with muddy water, a reverse circulation drill (not shown) is set in this standpipe 6, and thereby a reference hole is drilled at a predetermined depth. 7 is excavated. A reference pile 2 made of H-shaped steel is erected in this. The H-shaped steel used here has a flange 2a
However, the H-shaped steel flange 2a of the reference pile 2 in the other stand pipe 6 provided at a constant interval from this
It is built to face the. The structure of the H-shaped steel may be a simple H-shaped steel, but here, as shown in the figure, a structure in which there are two connecting plates 2b connecting the flanges 2a is adopted. Second
The figure clearly shows the above situation. As seen in FIG. 2, a sheet 8 is attached to the outside of the flange 2a, leaving the tip of the flange, and the reference hole 7
A partitioned space is formed with the inner circumferential surface of. And the third
As shown in the figure, the space defined by the sheet 8, the side surface of the flange 2a, and the inner peripheral surface of the reference hole 7 and the reference pile 2
Concrete shown with diagonal lines is poured into the hollow part of the
The space defined by the flange 2a, the connecting plate 2b, and the inner peripheral surface of the reference hole 7 is filled with gravel or silt mortar to fix the reference pile 2 in the reference hole 7. In this case, the muddy water may solidify as it is. After burning, the standpipe 6 is removed. This situation is shown in FIG.

次に第5図,第6図に示すように、基準杭2,
2の相対向する2組のフランジ2a,2aをガイ
ド1として、これを挾むように係合する凹形部9
を有する壁板体3を、2枚相対向して案内しなが
ら建込む。この壁板体3は、バイブロハンマ(図
示しない。)等を用いて水底Bに根入れさせる。
特に、第6図に見る如く、壁板体3の下端には、
この壁板体3に装着した注入パイプ(図示しな
い。)により、コンクリートを注し、以て、止水
を行うことも可能である。
Next, as shown in Figures 5 and 6, the reference pile 2,
A concave portion 9 that engages with the two sets of opposing flanges 2a, 2a as a guide 1 to sandwich them.
Two wall panels 3 having the same structure are installed while being guided so as to face each other. This wall plate body 3 is embedded in the water bottom B using a vibrohammer (not shown) or the like.
In particular, as shown in FIG. 6, at the lower end of the wall board 3,
It is also possible to pour concrete using a pouring pipe (not shown) attached to the wall plate 3 to stop water.

このようにして基準杭2と壁板体3とによつて
囲まれた空間内の水は、泥水によつて置換され
る。燃る後、壁板体3の間に、第8図に10で示
す連続地中壁用掘削機で、所定の深さまで溝4を
掘削する。溝4が所定深さまで掘削された後、第
9図に示す如く、鉄筋篭11を建込み、次に、ト
レミー管(図示しない。)により、コンクリート
5を打設する。
In this way, the water in the space surrounded by the reference pile 2 and the wall plate body 3 is replaced by muddy water. After burning, trenches 4 are excavated between the wall panels 3 to a predetermined depth using a continuous underground wall excavator shown at 10 in FIG. After the trench 4 is excavated to a predetermined depth, a reinforcing bar cage 11 is erected as shown in FIG. 9, and then concrete 5 is poured using a tremie pipe (not shown).

コンクリート5が固化した後、必要ならば、壁
板体3を上方に引上げることにより除去する。
After the concrete 5 has solidified, if necessary, it is removed by pulling the wall plate 3 upward.

かくして、基準杭2,2間に一エレメントの水
中壁が形成されるが、この作業を逐次くり返して
所定数のエレメントを連結させ、以て、必要長さ
に連続した水中の連続壁が水底下より立上るよう
に構築される。
In this way, an underwater wall of one element is formed between the reference piles 2 and 2, but by repeating this process one by one to connect a predetermined number of elements, a continuous underwater wall of the required length is created under the water. Built to stand up more.

この実施例によれば、埋立工事を先行させずに
水中に直接連続壁が水底下より立上る如く構築で
きる。
According to this embodiment, it is possible to construct a continuous wall directly underwater so that it rises from below the water bed without prior reclamation work.

したがつて、その工法はきわめて簡単であつ
て、工期、手間、コストの点で大幅に改善され
る。
Therefore, the construction method is extremely simple and can be greatly improved in terms of construction period, labor, and cost.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は基準杭建込み工程を示す縦断面図、第
2図は同平面図、第3図は基準穴に基準杭を固定
した状態を示す横断面図、第4図は同縦断面図、
第5図は基準杭に壁板体を係合した部分平面図、
第6図は同縦断面図、第7図は溝を掘削した状態
の平面図、第8図は同縦断面図、第9図はコンク
リートを打設した状態の一部切断平面図であり、
図中1はガイド、2は基準杭、3は壁板体、4は
溝、5はコンクリート、9は凹形部、2aはフラ
ンジである。
Figure 1 is a vertical cross-sectional view showing the standard pile erection process, Figure 2 is a plan view of the same, Figure 3 is a cross-sectional view showing the standard pile fixed in the standard hole, and Figure 4 is a vertical cross-sectional view of the same. ,
Figure 5 is a partial plan view of the wall plate engaged with the reference pile;
Fig. 6 is a longitudinal sectional view of the same, Fig. 7 is a plan view of the trench excavated, Fig. 8 is a longitudinal sectional view of the same, and Fig. 9 is a partially cutaway plan view of the concrete poured state.
In the figure, 1 is a guide, 2 is a reference pile, 3 is a wall board, 4 is a groove, 5 is concrete, 9 is a concave portion, and 2a is a flange.

Claims (1)

【特許請求の範囲】 1 連続壁の厚さ方向両側に夫々ガイトを有する
基準杭を、水中に適宜間隔で建込み、2つの基準
杭のガイドに左右端を係合案内させながら、相対
向する2つの壁板体を前記2つの基準杭間に建込
み、この2つの壁板体を適宜地中に進入させた状
態で壁板体間の水を、泥水と置換するなどして排
除し、壁板体間の水底を堀り下げて溝を形成し、
この溝内と、2つの壁板体及び2つの基準杭に囲
まれた区域内とにコンクリートを打設し、これを
硬化させることにより両基準杭間を所定厚みのコ
ンクリートで直接に連結し、前記コンクリートの
硬化後に壁板体を撤去することを特徴とする、水
中で連続壁を構築する方法。 2 基準杭のガイドは、H形鋼のフランジ部分で
なり、壁板体の左右端はこのフランジを挾むよう
に凹形部となつている特許請求の範囲第1項記載
の、水中で連続壁を構築する方法。
[Scope of Claims] 1. Reference piles having guides on both sides in the thickness direction of a continuous wall are erected in water at appropriate intervals, and the guides of the two reference piles engage and guide the left and right ends while facing each other. Two wall plates are erected between the two reference piles, and the water between the wall plates is removed by replacing it with muddy water while the two wall plates are properly penetrated into the ground. The bottom of the water between the wall panels is dug down to form a groove,
Concrete is placed in this groove and in the area surrounded by the two wall plates and the two reference piles, and by hardening it, the two reference piles are directly connected with concrete of a predetermined thickness, A method for constructing a continuous wall underwater, the method comprising removing the wall plate after the concrete has hardened. 2. The guide of the reference pile is made of a flange portion of H-beam steel, and the left and right ends of the wall plate are concave portions sandwiching the flange, as described in claim 1. How to build.
JP6555581A 1981-04-30 1981-04-30 Method of constructing continuous wall in water Granted JPS57180715A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6555581A JPS57180715A (en) 1981-04-30 1981-04-30 Method of constructing continuous wall in water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6555581A JPS57180715A (en) 1981-04-30 1981-04-30 Method of constructing continuous wall in water

Publications (2)

Publication Number Publication Date
JPS57180715A JPS57180715A (en) 1982-11-06
JPS627329B2 true JPS627329B2 (en) 1987-02-17

Family

ID=13290361

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6555581A Granted JPS57180715A (en) 1981-04-30 1981-04-30 Method of constructing continuous wall in water

Country Status (1)

Country Link
JP (1) JPS57180715A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56135625A (en) * 1980-03-25 1981-10-23 Tatsuo Morooka Construction of underwater structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56135625A (en) * 1980-03-25 1981-10-23 Tatsuo Morooka Construction of underwater structure

Also Published As

Publication number Publication date
JPS57180715A (en) 1982-11-06

Similar Documents

Publication Publication Date Title
KR101975297B1 (en) Multi-wall construction method using multi-wall construction supporting files and supporting files used for construction of harbors, rivers, dams and concrete that can prevent the inflow of soil and water
US4453366A (en) Process of forming a continuous wall in the ground
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
JP4410572B2 (en) Construction method of revetment for landfill
CN110359525B (en) Static pressure prefabricated assembled water pool and construction method thereof
JPS627329B2 (en)
JPS5936058B2 (en) How to construct a structure using underground continuous walls
CN218436906U (en) Underwater pouring solid bed sand blocking dam structure
KR102426192B1 (en) File fof retaining wall and construction method using file
JP2764482B2 (en) Construction method of large depth human hole
JPS62117911A (en) Setting of pipe for well
KR100543284B1 (en) The method of constructing support wall to use as pillar and slab
RU1818417C (en) Method for erection of underground structure
JP2581602B2 (en) Waste treatment method
SU844693A1 (en) Pile foundation constructing method
JPS6245368B2 (en)
JP2023102736A (en) Underground continuous wall in small section
JPH0261573B2 (en)
US1835665A (en) Method of installing sheet piling
JPS62111028A (en) Construction of underground structure
JPS63312417A (en) Water construction of continuous wall using steel caisson
JPS6313487B2 (en)
JP2000096976A (en) Vertical shaft constructing method
JPS5972319A (en) Underground continuous wall work utilizing soil pillar-row wall
JPH0612012B2 (en) Tsukishima construction method