JPS6245837A - Construction work for foundation of turbine generator - Google Patents

Construction work for foundation of turbine generator

Info

Publication number
JPS6245837A
JPS6245837A JP60183058A JP18305885A JPS6245837A JP S6245837 A JPS6245837 A JP S6245837A JP 60183058 A JP60183058 A JP 60183058A JP 18305885 A JP18305885 A JP 18305885A JP S6245837 A JPS6245837 A JP S6245837A
Authority
JP
Japan
Prior art keywords
concrete
foundation
plates
construction
turbine generator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP60183058A
Other languages
Japanese (ja)
Inventor
Junichiro Kono
河野 純一郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP60183058A priority Critical patent/JPS6245837A/en
Publication of JPS6245837A publication Critical patent/JPS6245837A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE:To shorten the period of construction by a method in which precast concrete plates are assembled into a formwork and concrete is placed into the formwork to form a turbine generator foundation using the concrete plates as outer walls. CONSTITUTION:Lower connecting metals 11 are welded to metals 1a buried when a foundation mat 1 is constructed, reinforcing bars 12 are set on the mat 1, and reinforced precast concrete plates 13 are assembled to be a concrete formwork. Bolts 14 buried in the plates 13 are inserted into the holes of the metals 11 and clamped with nuts 15 to erect the plates 13 on the mat 1. The recessed portion of the upper end of the plate 13 is fitted on a projection 16a of the lower end of the plate 16 for the next stage, and the upper and lower parts of a connecting metal 17 on the side of the jointed portion are clamped with bolts 14 and nuts 15 to connect the plates 13 and 16. After the plates 13 and 16 are assembled to a given height, concrete is placed and cured for hardening.

Description

【発明の詳細な説明】 〔発明の技術分野〕 本発明はタービンおよび発電機を載置させるタービン発
電F!1基礎台(以下、T/Gペディスタルという)を
)!設するタービン発電機基礎台建設工法の改良に関す
る。
DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a turbine power generator F! in which a turbine and a generator are installed. 1 foundation (hereinafter referred to as T/G pedestal)! Concerning improvements to construction methods for turbine generator foundations.

〔発明の技術的背景〕[Technical background of the invention]

まず、一般的なT/Gペディスタルの構成を第3図に基
いて説明する。
First, the configuration of a general T/G pedestal will be explained based on FIG. 3.

T/Gベディスタルはタービンおよび発t[1ilfi
を据付ける基礎台であり、基礎マット1上に立脚する複
数の柱部2と梁・床部3とを有する。
T/G pedestals are equipped with turbines and generators.
It is a foundation stand on which a foundation is installed, and has a plurality of pillar parts 2 and a beam/floor part 3 that stand on a foundation mat 1.

また、T/Gペディスタルは巨大な構築物Cあり、例え
ば110万KW級のタービンでは、長さ約707/L、
幅約15m、高さ約30 mに構築されている。そのた
めに、T/Gベディスタルの建設に際しては、全体を第
3図に示すように長さ方向を3ブロックA、B、Cに、
高さ方向を4ブロックW、X、Y、Zにそれぞれ区分し
て順次構築するようになっている。
In addition, the T/G pedestal is a huge structure C, for example, for a 1.1 million KW class turbine, the length is about 707/L,
It is built approximately 15m wide and 30m high. For this reason, when constructing the T/G pedestal, the entire length is divided into three blocks A, B, and C as shown in Figure 3.
The height direction is divided into 4 blocks W, X, Y, and Z and constructed sequentially.

次に、従来の建設工法について第3図のA−W部の施工
手順をもとに説明する。
Next, a conventional construction method will be explained based on the construction procedure shown in section A-W in FIG. 3.

第4図に示すようにまず、基礎マット1のコンクリート
の打設模、鉄筋4を配筋し、コククリート型枠5を組立
てる。次に、型枠押え6でコンクリート型枠5を固定し
、コンクリート7を打設する。このコンクリート7打設
後、約4週間の養生固化期間を経てから、型枠押え6を
取り外し、コンクリート型枠5の解体を行なう。引ぎ続
き同様手順にで第3図で示tA−X部、△・7部ど順次
立上工事を進める。8部および0部についても互いに干
渉しない範囲でA部と並行して作業を進める。
As shown in FIG. 4, first, a cast concrete model of the foundation mat 1, reinforcing bars 4 are arranged, and a coccrete formwork 5 is assembled. Next, the concrete formwork 5 is fixed with a formwork holder 6, and concrete 7 is poured. After pouring the concrete 7, the formwork holder 6 is removed and the concrete formwork 5 is dismantled after a curing period of approximately four weeks. Continuing with the same procedure, start-up work will be carried out sequentially for sections tA-X, △ and 7 as shown in Figure 3. The work on parts 8 and 0 will be carried out in parallel with part A as long as they do not interfere with each other.

こうして各7部のレベル迄コンクリート打設が完了した
後の各7部の施工時には、タービンおよび発電はの据付
のためのアンカーボルトを設定して、各7部のコンクリ
ート打設を並行して行ない、T/Gベディスタルを完成
ざゼる。
After completing the concrete pouring up to the level of each of the seven sections, when constructing each of the seven sections, anchor bolts for installing the turbine and power generator are set, and concrete pouring for each of the seven sections is carried out in parallel. , T/G Bedistal has been completed.

T/Gペディスタルの完成後はT/Gベディスタル−L
面8を鉄板9にて養生し、この鉄板9上に大型のりD−
ラフレーン10を搭載する。これにより、タービン建屋
の天井クレーンが稼動するまでの間、クローラクレーン
10をタービン建屋内の大型機器搬入・据付の作業時に
使用する。
After completion of T/G pedestal, T/G pedestal-L
The surface 8 is cured with an iron plate 9, and a large glue D- is placed on this iron plate 9.
Equipped with Rough Lane 10. As a result, the crawler crane 10 is used for carrying in and installing large equipment into the turbine building until the overhead crane of the turbine building starts operating.

このような従来のタービン発電機基礎台建設工法を含む
タービン建屋建設・機器据付の工程を第5図に示す。
FIG. 5 shows a process for constructing a turbine building and installing equipment including such a conventional turbine generator foundation construction method.

第5図に示丈ようにT/Gベデイスタルは、その構築箇
所のλ(礎マット1打設完了後に、建設工事が開始され
、タービン建屋1F床工事とほぼ並行して作業が進めら
れ、基礎マット1の着工から、例えば約16ケ月後に完
成し、クローラクレーン10の搭載が可能となる。この
クローラクレーン10はタービン建屋内の機器搬入・据
付に使用された後、タービン建屋の屋根工事とクレーン
ブームが干渉するのを避【)るために、基礎マツ1〜1
の着工から約20ケ月時点で解体される。
As shown in Fig. 5, the construction of the T/G Bedistal was started after the completion of laying the first foundation mat. It will be completed, for example, approximately 16 months after the start of construction on mat 1, and the crawler crane 10 will be able to be installed.This crawler crane 10 will be used to carry in and install equipment inside the turbine building, and then will be used for roof construction of the turbine building and the crane. To avoid the boom interfering with the base pine 1~1
It will be demolished approximately 20 months after construction began.

〔背慎技術の問題点〕[Problems with treachery technology]

しかしながら、ごのような従来のタービン発電機基礎台
建設工法では、次のような問題点があった。
However, the conventional turbine generator foundation construction method described above has the following problems.

すなわち、コンクリート打設後は必ず約4″i5間のコ
ンクリート養生固化期間をおいてから、上層部の工事へ
順次移行しなければならないために、T/Gペデイスタ
ル建設工事が長期化していた。
In other words, the T/G pedestal construction work was prolonged because after the concrete was poured, the concrete had to be allowed to cure and harden for approximately 4"i5, and then the work on the upper floors had to be started.

このために、T/Gペデイスタル建設工事以降の作業の
、例えば大型クローラクレーン10の搭載や機器搬入・
据付等が遅延し、タービン建屋建設工期長期化の最大の
原因となっていた。
For this purpose, work such as loading a large crawler crane 10, transporting equipment, etc. after T/G pedestal construction work is required.
This caused delays in installation and was the main reason for the prolongation of the turbine building construction period.

〔発明の目的〕[Purpose of the invention]

本発明は上記事情に鑑みてなされたもので、その目的は
タービン発′電機基礎台の建設1期の大幅短縮と工数の
低減とを図ることができるタービン発電機基礎台建設工
法を得ることにある1゜〔発明の概要〕 上記目的を達成するために本発明は、タービンおよび発
電機を載置させるタービン発電機基礎台を建設するター
ビン発電m基礎台i1設工法において、プレキャストコ
ンクリート板をコンクリート型枠として組み立てた後に
、コンクリート打設を行ない、このプレキャストコンク
リート板をタービン発電R基礎台の外壁となすことに特
徴がある。
The present invention has been made in view of the above circumstances, and its purpose is to provide a method for constructing a turbine generator foundation that can significantly shorten the first period of construction of a turbine generator foundation and reduce the number of man-hours. 1゜ [Summary of the Invention] In order to achieve the above object, the present invention provides a method for constructing a turbine generator foundation on which a turbine and a generator are mounted, using a method for constructing a turbine generator foundation on which a precast concrete plate is placed in concrete. The feature is that after assembling the formwork, concrete is poured, and this precast concrete plate is used as the outer wall of the turbine power generation R foundation.

〔発明の実施例〕[Embodiments of the invention]

以下、第1図および第2図を参照して本発明の一実施例
を説明する。
An embodiment of the present invention will be described below with reference to FIGS. 1 and 2.

第1図は本発明の一実施例を説明するための部分断面図
であり、第3図に示すように構成されたT/Gベデイス
タルのA−W部の施工手順を示す。
FIG. 1 is a partial cross-sectional view for explaining one embodiment of the present invention, and shows the construction procedure of the A-W section of a T/G bedstone constructed as shown in FIG. 3.

本実施例はまず、タービン建屋の基礎マット1の施工時
に埋設された埋込金物1aの所定位置に下部接続金具1
1の一端を溶接する。次に、鉄筋12を基礎マツ1〜1
上に組立でてから、鉄筋入りのPC板(プレキャストコ
ンクリ−1〜板)13をコンクリート型枠とし′C組立
てる。[−)C板13には予め植え込みボルト14を所
要数植設しでおり、これら植え込みボルト14を下部接
続金具11の孔に挿入してナツト15を締め句()、基
礎マット1上に立設する。
In this embodiment, first, a lower connecting metal fitting 1 is placed in a predetermined position of an embedded metal fitting 1a buried during construction of a foundation mat 1 of a turbine building.
Weld one end of 1. Next, attach the reinforcing bars 12 to the foundation pines 1 to 1.
After assembling on the top, a PC board (precast concrete 1 to board) 13 with reinforcing steel is used as a concrete formwork and assembled. [-) A required number of stud bolts 14 are installed in advance on the C plate 13, and these stud bolts 14 are inserted into the holes of the lower connection fitting 11, and the nuts 15 are tightened (), and the studs are placed on the base mat 1. Set up

これら基礎マット1上にX′l設されたPC板13の上
端部には四部13aが切欠き形成されて、13す、次段
のPC板16の下端部の凸部16aに嵌合される。これ
ら嵌合部の側部には接続金具17が添設され、接続金具
17の−F部と下部は植え込みボルト14を挿通して、
ナツト15を締め付け、両PC板13.16を上下方向
に接続する。
Four parts 13a are cut out at the upper end of the PC board 13 placed on the base mat 1, and are fitted into the convex part 16a at the lower end of the next PC board 16. . Connecting fittings 17 are attached to the sides of these fitting parts, and stud bolts 14 are inserted through the -F part and the lower part of the connecting fittings 17.
Tighten the nut 15 to connect both PC boards 13 and 16 in the vertical direction.

これらPC板13.16を所要高さに組立てた後に、コ
ンクリート18を打設し、これを養生固化する。これを
X、Y、Z部と上層部へ向けて順次繰り返して、Aブロ
ックを立ち上げて行く。このAブロックと並行して、B
、Cブロックについても同様の施工手順で立ら上ばて行
き、T/Gベディスタルを完成させる。
After these PC boards 13 and 16 are assembled to the required height, concrete 18 is placed and cured to harden. This is repeated sequentially toward the X, Y, and Z sections and toward the upper layer to start up the A block. In parallel with this A block, B
, Block C will also be erected using the same construction procedure to complete the T/G pedestal.

r/Gペディスタルの完成後は、第3図で示すようにペ
ディスタル上面8上に鉄板9を敷設してこれを養生する
と共に、この鉄板9上に大型のクローラクレーン10を
搭載し、これをタービン建屋内の機器搬入・据付等の際
に使用する。
After the r/G pedestal is completed, as shown in Fig. 3, a steel plate 9 is laid on the top surface 8 of the pedestal for curing, and a large crawler crane 10 is mounted on the steel plate 9 to carry the turbine. Used when transporting and installing equipment inside the building.

したがって、本実施例によれば、鉄筋入りPC板13を
コンクリート型枠として組立てるので、従来のコンクリ
ート型枠の仮設および解体作業が不要になるうえに、P
C板13自体がコンクリート型枠としての組立時に既に
強度を持っているために、打設したコンクリートの養生
固化期間を待たずに、直ちに上層部の施工へ順次移行す
ることができる。
Therefore, according to this embodiment, since the reinforcing PC board 13 is assembled as a concrete formwork, the temporary construction and dismantling work of the conventional concrete formwork is not necessary, and the P.S.
Since the C plate 13 itself already has strength when assembled as a concrete formwork, construction of the upper layer can be immediately started without waiting for the curing and hardening period of the poured concrete.

また、コンクリート型枠に組立てられるPC板13は工
場で予め製作されて、品質が均一であり、表面ら美しく
仕上げられているので、従来例で行なっていたコンクリ
ート打設面の仕上げ作業を省略することができる。
In addition, the PC board 13 that is assembled into the concrete formwork is prefabricated in a factory, has uniform quality, and has a beautifully finished surface, so the finishing work of the concrete pouring surface, which was done in the conventional example, can be omitted. be able to.

このために、本実施例ではT/Gベディスタルの完成が
第2図に示すように基礎マット1の着工から約12ケ月
後に達成され、第5図で示J従来例が約16ケ月程度要
していたのに比し、第2図の一点鎖線で示ず約4ケ月分
程度のti設工期の短縮を図ることかできる。
For this reason, in this embodiment, the T/G bedstone was completed approximately 12 months after the start of construction of the foundation mat 1, as shown in Figure 2, whereas the conventional example required approximately 16 months, as shown in Figure 5. Compared to the conventional method, it is possible to shorten the TI construction period by about four months, as shown by the dashed line in Fig. 2.

その結果、T/Gベディスタル立土工事後の各種工事の
石工が、その工期短縮分、順次繰り上げられる。例えば
クローラクレーン10のT / Gペディスタルへの搭
載時期も従来例に比して約4ケ月程早くなり、その後の
作業の終了も全て早められる。
As a result, the masonry work for various works after the T/G Bedistal erection work will be postponed one by one by the shortened construction period. For example, the time for loading the crawler crane 10 onto the T/G pedestal is approximately four months earlier than in the conventional example, and all subsequent work is also completed earlier.

〔発明の効果〕〔Effect of the invention〕

以上説明したように本発明は、タービンおよび発電間を
載置させるタービン発電機基礎台を建設するタービン発
電!1基礎台建設工法において、プレキャスト」ンクリ
ート板をコンクリート型枠として組み立てた後に、コン
クリート打設を行ない、このプレキャストコンクリート
板をタービン発電機基礎台の外壁となす。
As explained above, the present invention is a turbine generator for constructing a turbine generator foundation on which a turbine and a generator are placed. 1. In the foundation construction method, precast concrete plates are assembled as a concrete formwork, then concrete is poured, and the precast concrete plates are used as the outer wall of the turbine generator foundation.

したがって、本実施例によれば、ブリキ1ノストコンク
リート板をコンクリート型枠とし℃組立てるので、従来
のコンクリート型枠の仮設および解体作業が不要となる
うえに、プレキャストコンクリート板自体がコンクリー
ト型枠としての組立時に既に強度を持っているために、
打設した一1ンクリートの養生固化期間を持たずに、直
ちに上層部への施工へ順次移行することが(“きる。
Therefore, according to this embodiment, since the tin 1 nost concrete plate is used as the concrete formwork and assembled at °C, the conventional temporary construction and dismantling of the concrete formwork is not necessary, and the precast concrete plate itself can be used as the concrete formwork. Because it already has strength when assembled,
It is possible to immediately proceed to the construction of the upper layer without having to wait for curing and hardening of the poured concrete.

また、プレキャストコンクリート板は工場で製作されて
品質が均一であり、表面も美しく仕上げられているので
、従来例で行なっていたコンクリート打設面の仕上作業
を省略することかできる。
Furthermore, since precast concrete plates are manufactured in a factory and have uniform quality and a beautifully finished surface, it is possible to omit the finishing work of the concrete pouring surface, which is conventionally performed.

その結果、本実施例はタービン発電機基礎台の建設工数
の低減と建設工期の大幅な短縮を図ることができる。
As a result, this embodiment can reduce the number of man-hours for constructing the turbine generator foundation and significantly shorten the construction period.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に係るタービン発電i基礎台建設工法の
一実施例の施工手順を説明するためにタービン発電機基
礎台の一部を示す部分縦断面図、第2図は第1図で示す
一実施例の建設工程を示す矢線図、第3図は第1図で示
す実施例が適用される一般的なタービン発電m基礎台の
全体構成図、第4図は従来工法を説明するためのタービ
ン発電機基礎台の一部縦断面図、第5図は第4図で示す
従来工法の建設工程を示ず矢線図である。 1・・・基礎マット、2・・・柱部、3・・・梁・床部
、12・・・鉄筋、13・・・PC板(プレキャストコ
ンクリート板)、18・・・コンクリート。 代理人弁理士  則 近 憲 佑 同        三  俣  弘  文第4図
FIG. 1 is a partial longitudinal sectional view showing a part of a turbine generator foundation for explaining the construction procedure of an embodiment of the turbine generator i foundation construction method according to the present invention, and FIG. Fig. 3 is an overall configuration diagram of a general turbine power generation m foundation to which the embodiment shown in Fig. 1 is applied, and Fig. 4 explains the conventional construction method. FIG. 5 is a partial vertical cross-sectional view of a turbine generator foundation for the purpose of the present invention, and is an arrow diagram showing the construction process of the conventional construction method shown in FIG. 4. 1...Foundation mat, 2...Column section, 3...Beam/floor section, 12...Reinforcement bar, 13...PC board (precast concrete board), 18...Concrete. Representative Patent Attorney Noriyuki Chika Yudo Hirofumi Mimata Figure 4

Claims (1)

【特許請求の範囲】[Claims] タービンおよび発電機を載置させるタービン発電機基礎
台を建設するタービン発電機基礎台建設工法において、
プレキャストコンクリート板をコンクリート型枠として
組み立てた後に、コンクリート打設を行ない、このプレ
キャストコンクリート板をタービン発電機基礎台の外壁
となすことを特徴とするタービン発電機基礎台建設工法
In the turbine generator foundation construction method for constructing a turbine generator foundation on which the turbine and generator are mounted,
A method for constructing a foundation for a turbine generator, which comprises assembling precast concrete plates as a concrete formwork, then pouring concrete, and using the precast concrete plates as an outer wall of the turbine generator foundation.
JP60183058A 1985-08-22 1985-08-22 Construction work for foundation of turbine generator Pending JPS6245837A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60183058A JPS6245837A (en) 1985-08-22 1985-08-22 Construction work for foundation of turbine generator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60183058A JPS6245837A (en) 1985-08-22 1985-08-22 Construction work for foundation of turbine generator

Publications (1)

Publication Number Publication Date
JPS6245837A true JPS6245837A (en) 1987-02-27

Family

ID=16129002

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60183058A Pending JPS6245837A (en) 1985-08-22 1985-08-22 Construction work for foundation of turbine generator

Country Status (1)

Country Link
JP (1) JPS6245837A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2447025A1 (en) * 2009-06-24 2012-05-02 Mitsubishi Heavy Industries, Ltd. Method for producing concrete trestle, concrete trestle, and connecting member

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2447025A1 (en) * 2009-06-24 2012-05-02 Mitsubishi Heavy Industries, Ltd. Method for producing concrete trestle, concrete trestle, and connecting member
EP2447025A4 (en) * 2009-06-24 2013-07-03 Mitsubishi Heavy Ind Ltd Method for producing concrete trestle, concrete trestle, and connecting member
US8522507B2 (en) 2009-06-24 2013-09-03 Mitsubishi Heavy Industries, Ltd. Concrete platform production process, concrete platform, and connecting member

Similar Documents

Publication Publication Date Title
JP2001355246A (en) Pc(prestressed concrete) footing member and building construction method using it
CN109610707B (en) Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method
JP2915897B1 (en) Building construction method
CN108755938B (en) Steel core area node of assembled concrete frame
JPS6245837A (en) Construction work for foundation of turbine generator
JP3421298B2 (en) Internal stairs for buildings and method of construction
KR20130022656A (en) Hybrid building construction method combining dry type and wet type
JP3436104B2 (en) Steel pipe construction method
JP2002332645A (en) Foundation structure of rail for ground-traveling crane and laying method for foundation
JPH0657710A (en) Construction of concrete main tower
JP2000104220A (en) Erection of combined truss bridge
JP2864906B2 (en) Precast wall joining method
JPH101914A (en) Method of constructing floor slab of road
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JP2614000B2 (en) Basics of steel frame
JPS58173238A (en) Construction of wall body in reinforced concrete building
JPS63308B2 (en)
JPH04149365A (en) Construction method of beam
KR20230109982A (en) PC half-slab construction method for quick construction of precast concrete apartment house
JPH108725A (en) Constructing method for building frame
CN114412041A (en) Connecting structure of prefabricated parts
JPH07127174A (en) Method of unsupported construction of reinforced concrete slab
JPH058305B2 (en)
JP2004060340A (en) Full precast hollow floor slab and integral structure of the floor slab and building frame beam
JP3205467B2 (en) Translational construction of the building and the equipment stand, and advance loading of equipment into the building