CN109610707B - Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method - Google Patents
Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method Download PDFInfo
- Publication number
- CN109610707B CN109610707B CN201811519440.2A CN201811519440A CN109610707B CN 109610707 B CN109610707 B CN 109610707B CN 201811519440 A CN201811519440 A CN 201811519440A CN 109610707 B CN109610707 B CN 109610707B
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- flange
- reinforced concrete
- floor
- floor slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 85
- 239000010959 steel Substances 0.000 title claims abstract description 85
- 238000010276 construction Methods 0.000 title claims abstract description 32
- 239000004567 concrete Substances 0.000 claims abstract description 35
- 238000003466 welding Methods 0.000 claims abstract description 13
- 238000009415 formwork Methods 0.000 claims abstract description 8
- 239000002131 composite material Substances 0.000 claims abstract description 6
- 239000011150 reinforced concrete Substances 0.000 claims description 39
- 230000002787 reinforcement Effects 0.000 claims description 3
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims 1
- 238000005266 casting Methods 0.000 claims 1
- 230000006835 compression Effects 0.000 claims 1
- 238000007906 compression Methods 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 6
- 230000002708 enhancing effect Effects 0.000 abstract 1
- 230000000452 restraining effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 6
- 239000003351 stiffener Substances 0.000 description 4
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011010 flushing procedure Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/02—Load-carrying floor structures formed substantially of prefabricated units
- E04B5/14—Load-carrying floor structures formed substantially of prefabricated units with beams or girders laid in two directions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/02—Load-carrying floor structures formed substantially of prefabricated units
- E04B5/023—Separate connecting devices for prefabricated floor-slabs
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种应用在建筑工程结构中的预制装配式梁和楼板平齐装配的设计与快速施工方法,该发明尤其适用于现场焊接不易且对空间高度要求较高的建筑工程中。The invention relates to a design and rapid construction method for flush assembly of prefabricated beams and floor slabs used in construction engineering structures, and is especially suitable for construction projects where on-site welding is not easy and high space requirements are required.
背景技术Background technique
在建筑工程结构中,预制钢梁与楼板的连接方法至关重要,直接关系着空间利用、施工进度和工程造价。现阶段我国装配式梁板连接方式大多是将板通过不同的方式搭在梁的上方,进而完成楼盖体系的施工,造成了空间利用率一定程度上的降低,如上海前滩某建筑工程就提出了将楼板与钢梁上平面平齐的要求。此外,现行的装配式楼板连接方法多存在大量的现场焊接、现场支模、搭设脚手架等,容易影响施工质量并导致施工进度迟缓。In the construction engineering structure, the connection method between the prefabricated steel beam and the floor slab is very important, which is directly related to the space utilization, construction progress and project cost. At this stage, most of the prefabricated beam-slab connection methods in my country are to place the plate on the top of the beam in different ways to complete the construction of the floor system, which reduces the space utilization rate to a certain extent. For example, a construction project in Shanghai Qiantan has A requirement was put forward to make the floor slab flush with the upper plane of the steel beam. In addition, the current prefabricated floor connection method involves a large number of on-site welding, on-site formwork, and erecting scaffolding, which easily affects the construction quality and leads to a slow construction progress.
因此,需要一种新型的预制钢梁与楼板平齐设计及其快速施工方法,以提高空间利用率、缩短施工时间等。基于此,本发明提出了一种新型的预制钢梁与楼板平齐装配的设计及其快速施工方法,使楼板与钢梁顶面平齐,且可避免现场焊接,具有空间利用率高、施工质量更可控等优点;当使用预制装配混凝土楼板或钢板混凝土组合楼板时,无需现场支模和搭设脚手架,具有施工速度快等优点。Therefore, a new type of flush design of prefabricated steel beams and floor slabs and a rapid construction method are required to improve space utilization and shorten construction time. Based on this, the present invention proposes a new design of flush assembly of prefabricated steel beams and floor slabs and a rapid construction method thereof, so that the floor slabs are flush with the top surface of the steel beams, and on-site welding can be avoided. The quality is more controllable and other advantages; when using prefabricated concrete floor or steel plate concrete composite floor, there is no need for on-site formwork and scaffolding, and it has the advantages of fast construction.
发明内容SUMMARY OF THE INVENTION
本发明提出了一种预制钢梁与楼板平齐的装配结构及快速施工方法;该梁板体系具有空间利用率高、不施工快速、需要现场焊接、安装方便等优点。The invention proposes an assembly structure and a rapid construction method in which the prefabricated steel beam is flush with the floor slab; the beam-slab system has the advantages of high space utilization, fast construction, on-site welding, and convenient installation.
本发明的技术方案:Technical scheme of the present invention:
一种预制钢梁与楼板平齐的装配结构,主要针对预制装配式梁板子结构进行设计,预制装配式梁板子结构包括钢筋混凝土楼板1、预制型钢梁2、梁板间的现场浇筑混凝土3;An assembly structure in which a prefabricated steel beam is flush with a floor slab is mainly designed for a prefabricated assembled beam-slab substructure, and the prefabricated assembled beam-slab substructure includes a reinforced concrete floor slab 1, a
所述的钢筋混凝土楼板1端部的部分钢筋端头设置钢筋预制圆环4,用于连接预制型钢梁2的竖向预焊接栓钉5;Part of the end of the steel bar at the end of the reinforced concrete floor 1 is provided with a steel prefabricated ring 4 for connecting the vertical pre-welded
所述的预制型钢梁2的上翼缘为“几”字形,由水平翼缘6、竖直翼缘7和顶翼缘8共同组成,其中竖直翼缘7的高度与钢筋混凝土楼板1的厚度相同;水平翼缘6上布置梁加劲肋9,用于提高水平翼缘6的刚度及承载力,防止水平翼缘6出现局部变形;同时水平翼缘6上焊接有竖向预焊接栓钉5,竖向预焊接栓钉5位置与钢筋混凝土楼板1端部的钢筋预制圆环4一一对应;竖直翼缘7和顶翼缘8组成的内空间浇筑有翼缘内侧混凝土10,用于防止翼缘在受压状态下的变形;竖直翼缘7内侧设置水平向预焊接栓钉11,用于固定翼缘内侧混凝土10,防止其脱落。The upper flange of the described
一种预制钢梁与楼板平齐装配的快速施工方法,当楼板为钢筋混凝土楼板时,步骤如下:A rapid construction method for flush assembly of prefabricated steel beams and floor slabs. When the floor slab is a reinforced concrete floor slab, the steps are as follows:
步骤一、工厂预制钢筋混凝土楼板1,并在其端部的部分钢筋端头设置预制圆环4;Step 1: Prefabricate the reinforced concrete floor slab 1 in the factory, and set the prefabricated ring 4 at the end of the part of the steel bar at the end;
步骤二、在工厂预制型钢梁2,在其水平翼缘6上设置竖向预焊接栓钉5并设置加劲肋9,竖向预焊接栓钉5位置与钢筋混凝土楼板1端部的钢筋预制圆环4一一对应;在其竖直翼缘7内侧焊接水平向预焊接栓钉11;
步骤三、将预制型钢梁2倒置,以其竖直翼缘7和顶翼缘8为模板,完成工厂浇筑翼缘内侧混凝土10,其中水平向预焊接栓钉11用于固定翼缘内侧混凝土10;Step 3: Invert the
步骤四、现场装配,将钢筋混凝土楼板1搭在预制型钢梁2的水平翼缘6上,并使钢筋混凝土楼板1上的钢筋预制圆环4一一对应套在竖向预焊接栓钉5上;Step 4: On-site assembly, the reinforced concrete floor 1 is placed on the
步骤五、以预制型钢梁2的水平翼缘6、竖直翼缘7以及钢筋混凝土楼板1的侧面为模板,在预制型钢梁2和钢筋混凝土楼板1之间的空隙处现场浇筑混凝土3,完成梁板子结构的施工。
所述的楼板不限于预制钢筋混凝土楼板1,当楼板为其他形式的现浇楼板时,如果现场允许搭脚手架和支模板,支模后进行楼板钢筋施工时将楼板端部的钢筋预制圆环4一一对应套在竖向预焊接栓钉5上,然后现场浇筑混凝土;如果现场不搭脚手架,使用钢板混凝土组合楼板,即在工厂将钢板或压型钢板端部预先焊接钢筋预制圆环4,现场装配时将钢板端部的钢筋预制圆环4套在预制型钢梁2的竖向预焊接栓钉5上,然后以钢板为模板现场浇筑混凝土。The floor slab is not limited to the prefabricated reinforced concrete floor slab 1. When the floor slab is a cast-in-place floor slab of other forms, if scaffolding and formwork are allowed to be erected on site, the steel prefabricated ring 4 at the end of the floor slab will be prefabricated when the slab reinforcement construction is carried out after the formwork is supported. One-to-one set on the vertical pre-welded
本发明的有益效果在于,与现有技术相比,本发明提出的预制钢梁与楼板平齐装配方法:(1)既能满足梁板的承载力要求,还能提高建筑的空间利用率;(2)本发明的梁、板均可在工厂预制完成,施工时只需现场拼装并浇筑少量混凝土即可完成,避免了搭设脚手架和支模,实现了快速施工,大大节约了施工时间;(3)本发明避免了现场焊接,能更好地保障施工质量。The beneficial effect of the present invention is that, compared with the prior art, the method for flushing the prefabricated steel beams and the floor slabs proposed by the present invention: (1) not only can meet the bearing capacity requirements of the beams and slabs, but also improve the space utilization rate of the building; (2) The beams and slabs of the present invention can be prefabricated in factories, and only need to be assembled on site and pour a small amount of concrete to complete the construction, which avoids setting up scaffolding and formwork, realizes rapid construction, and greatly saves construction time; ( 3) The present invention avoids on-site welding and can better guarantee the construction quality.
附图说明Description of drawings
图1为本发明的预制装配式梁、板就位后待少量现场浇筑状态下的示意图。FIG. 1 is a schematic diagram of the prefabricated beams and slabs of the present invention in the state of a small amount of in-situ pouring after they are in place.
图2为本发明的预制装配式梁、板子结构平齐施工完成后的示意图。FIG. 2 is a schematic diagram of the prefabricated beam and slab structure of the present invention after the flush construction is completed.
图3为工厂浇筑混凝土前本发明的预制型钢梁示意图。FIG. 3 is a schematic diagram of the prefabricated steel beam of the present invention before concrete is poured in the factory.
图4为工厂浇筑混凝土后本发明的预制型钢梁示意图。FIG. 4 is a schematic diagram of the prefabricated steel beam of the present invention after concrete is poured in the factory.
图5为本发明的预制钢筋混凝土楼板及其端部预制钢筋圆环示意图。FIG. 5 is a schematic diagram of the prefabricated reinforced concrete floor slab of the present invention and its end prefabricated steel bars.
图6为本发明使用钢板作为模板浇筑钢板混凝土组合楼板时现场浇筑混凝土之前状态下的示意图。FIG. 6 is a schematic diagram of the state before the concrete is poured on site when a steel plate is used as a template to cast a steel plate-concrete composite floor according to the present invention.
图中:1钢筋混凝土楼板;2预制型钢梁;3混凝土;4钢筋预制圆环;5竖向预焊接栓钉;6水平翼缘;7竖直翼缘;8顶翼缘;9梁加劲肋;10梁翼缘内侧混凝土;11水平向预焊接栓钉;12当楼板为钢板混凝土组合楼板时的底钢板。In the picture: 1 reinforced concrete floor; 2 prefabricated steel beams; 3 concrete; 4 steel prefabricated rings; 5 vertical pre-welded studs; 6 horizontal flanges; 7 vertical flanges; 8 top flanges; 9 beam stiffening Rib; 10 Concrete on the inside of beam flange; 11 Horizontal pre-welded studs; 12 Bottom steel plate when the floor is a steel plate-concrete composite floor.
具体实施方式Detailed ways
为了让本发明的上述特征和优点更易懂,以预制钢筋混凝土楼板为例,下文结合附图对本发明的技术方案作详细说明:In order to make the above-mentioned features and advantages of the present invention easier to understand, taking prefabricated reinforced concrete floor slabs as an example, the technical solutions of the present invention are described in detail below in conjunction with the accompanying drawings:
如图1~5所示,钢筋混凝土楼板1端部的部分钢筋端头设置钢筋预制圆环4,用于连接预制型钢梁2的竖向预焊接栓钉5;预制型钢梁2的上翼缘为“几”字形,由水平翼缘6、竖直翼缘7和顶翼缘8共同组成,其中竖直翼缘7的高度与钢筋混凝土楼板1的厚度相同;水平翼缘6上布置梁加劲肋9,用于提高水平翼缘6的刚度及承载力,防止水平翼缘6出现局部变形;同时水平翼缘6上焊接有竖向预焊接栓钉5,竖向预焊接栓钉5位置与钢筋混凝土楼板1端部的钢筋预制圆环4一一对应;竖直翼缘7和顶翼缘8组成的内空间浇筑有翼缘内侧混凝土10,用于防止翼缘在受压状态下的变形;竖直翼缘7内侧设置水平向预焊接栓钉11,用于固定翼缘内侧混凝土10,防止其脱落。As shown in Figures 1 to 5, prefabricated steel rings 4 are provided at the ends of some steel bars at the ends of the reinforced concrete floor 1, which are used to connect the vertical pre-welded
其施工按照以下步骤进行:Its construction is carried out according to the following steps:
步骤一、工厂预制钢筋混凝土楼板1,并在其端部的部分钢筋端头设置预制圆环4;Step 1: Prefabricate the reinforced concrete floor slab 1 in the factory, and set the prefabricated ring 4 at the end of the part of the steel bar at the end;
步骤二、在工厂预制型钢梁2,在其水平翼缘6上设置竖向预焊接栓钉5并设置加劲肋9,竖向预焊接栓钉5位置与钢筋混凝土楼板1端部的钢筋预制圆环4一一对应;在其竖直翼缘7内侧焊接水平向预焊接栓钉11;
步骤三、将预制型钢梁2倒置,以其竖直翼缘7和顶翼缘8为模板,完成工厂浇筑翼缘内侧混凝土10,其中水平向预焊接栓钉11用于固定翼缘内侧混凝土10;Step 3: Invert the
步骤四、现场装配,将钢筋混凝土楼板1搭在预制型钢梁2的水平翼缘6上,并使钢筋混凝土楼板1上的钢筋预制圆环4一一对应套在竖向预焊接栓钉5上;Step 4: On-site assembly, the reinforced concrete floor 1 is placed on the
步骤五、以预制型钢梁2的水平翼缘6、竖直翼缘7以及钢筋混凝土楼板1的侧面为模板,在预制型钢梁2和钢筋混凝土楼板1之间的空隙处现场浇筑混凝土3,完成梁板子结构的施工。
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811519440.2A CN109610707B (en) | 2018-12-12 | 2018-12-12 | Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811519440.2A CN109610707B (en) | 2018-12-12 | 2018-12-12 | Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109610707A CN109610707A (en) | 2019-04-12 |
CN109610707B true CN109610707B (en) | 2020-10-20 |
Family
ID=66007442
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811519440.2A Active CN109610707B (en) | 2018-12-12 | 2018-12-12 | Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109610707B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110107006B (en) * | 2019-05-05 | 2020-10-16 | 湘潭大学 | A large-span composite structure floor |
CN111502033A (en) * | 2020-05-06 | 2020-08-07 | 无锡锡晟建设有限公司 | Quick mounting structure of full-prefabricated high strength PC floor and girder steel |
Family Cites Families (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS52101822A (en) * | 1976-02-21 | 1977-08-26 | Kumagai Gumi Co Ltd | Complex concrete floor molding method and complex concrete floor device by means of i beam and corrugated deck plate |
DE102005011817B4 (en) * | 2005-03-15 | 2007-12-13 | Werner Averkamp | Ceiling structure with filled or covered cavities |
JP5155776B2 (en) * | 2008-08-26 | 2013-03-06 | 大成建設株式会社 | Composite beam |
US8281534B2 (en) * | 2008-11-07 | 2012-10-09 | Korea Institute Of Construction Technology | Formed steel beam for steel-concrete composite beam and slab |
CN202200393U (en) * | 2011-08-01 | 2012-04-25 | 河北路桥集团有限公司 | Combined steel structure base and module thereof |
CN105089204A (en) * | 2015-05-12 | 2015-11-25 | 重庆大学 | Cold-formed thin-walled ribbed U-shaped steel-encased concrete laminated slab composite beam |
CN106284047A (en) * | 2016-08-04 | 2017-01-04 | 浙江工业大学 | Steel-concrete combined bridge beam slab |
CN107152088B (en) * | 2017-03-30 | 2020-08-18 | 西京学院 | Prefabricated double-dovetail type steel-concrete combined beam connected by adopting studs |
CN206859427U (en) * | 2017-06-14 | 2018-01-09 | 广州大学 | A kind of attachment structure of Fabricated Beam-Slab system |
CN108385884A (en) * | 2018-02-12 | 2018-08-10 | 北京工业大学 | A kind of bolted and welded connection steel reinforced concrete special-shape column-stealth beam floor assembly system |
CN108360721B (en) * | 2018-03-03 | 2020-04-14 | 北京工业大学 | Precast concrete ultra-thin two-way load-bearing prefabricated reinforced truss composite floor |
CN108360723B (en) * | 2018-03-03 | 2020-03-13 | 北京工业大学 | Assembly type large module semi-welded superposed beam plate structure with stereo truss temporary support |
CN108412100A (en) * | 2018-06-11 | 2018-08-17 | 青岛理工大学 | Fully assembled sunken floor and connection structure thereof |
-
2018
- 2018-12-12 CN CN201811519440.2A patent/CN109610707B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN109610707A (en) | 2019-04-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020118563A1 (en) | Design and rapid construction methods for flush assembly of prefabricated steel beams and floor | |
CN112900619B (en) | Fabricated concrete beam-column joint and construction method thereof | |
CN109339229B (en) | Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor | |
CN108385904B (en) | Roofing parapet wall and construction method thereof | |
CN105649360A (en) | Integral assembling type building system and installing method | |
CN108571071A (en) | Prefabricated PC beams of concrete column connected node and construction method | |
EA034805B1 (en) | Construction of the prefabricated column and beam type | |
CN107476470A (en) | Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method | |
CN105952060A (en) | Precast beam reinforcement cage component and assembling method thereof | |
CN110792164A (en) | Transverse assembling device and method for assembled shear wall | |
CN109610707B (en) | Assembly structure with parallel and level prefabricated steel beams and floor slab and rapid construction method | |
CN104294920B (en) | The node component of a kind of U-shaped steel-concrete combination beam and special-shaped steel pipe concrete post and preparation method | |
CN204570446U (en) | The T-shaped simply supported beam of a kind of precast assembly | |
CN108505655A (en) | Assembled floor connecting structure and construction method | |
CN110805144A (en) | Fully assembled high-rise/super high-rise concrete frame-supported structure system and its construction method | |
CN108316150B (en) | Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge | |
CN211421637U (en) | Connecting structure of prefabricated gutter | |
CN110439267A (en) | A kind of aluminum alloy mould plate applied to laminated floor slab construction | |
CN104989422A (en) | Tunnel half-prefabricated speeded-up middle-wall construction process | |
CN210421568U (en) | Assembled beam and plate structure | |
CN109653770B (en) | Middle plate construction method by utilizing original temporary support | |
CN104234418A (en) | Early removal formwork for fabrication of reinforced concrete beams and construction method thereof | |
CN108755938B (en) | Steel core area node of assembled concrete frame | |
CN113356882B (en) | Large-section tunnel wall bracket and construction method | |
CN215290759U (en) | a prefabricated wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |