CN106032705A - Integrated casting molding construction method of reinforced concrete floor system - Google Patents
Integrated casting molding construction method of reinforced concrete floor system Download PDFInfo
- Publication number
- CN106032705A CN106032705A CN201510752696.8A CN201510752696A CN106032705A CN 106032705 A CN106032705 A CN 106032705A CN 201510752696 A CN201510752696 A CN 201510752696A CN 106032705 A CN106032705 A CN 106032705A
- Authority
- CN
- China
- Prior art keywords
- floor
- reinforced concrete
- steel
- construction method
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
本发明公开了一种钢筋混凝土楼盖的一体式浇筑成型施工方法,此钢筋混凝土楼盖的一体式浇筑成型施工方法将形成钢筋混凝土梁和钢筋混凝土楼板的自平衡整体结构进行单独拼装,将单独拼装完成的自平衡结构进行吊装,并在拼装完成的楼盖自平衡模板结构内浇筑混凝土,形成一体浇筑的钢筋混凝土楼盖结构,此方法方便拼装完成后吊装至施工现场进行施工进行安装,并在安装完成后一体浇筑完成施工,此方法可简化现场施工流程,且施工完成结构的整体性好,此发明用于建筑施工领域。
The invention discloses a construction method for integral pouring and forming of a reinforced concrete floor. The integral pouring and forming construction method of a reinforced concrete floor separately assembles a self-balancing integral structure of a reinforced concrete beam and a reinforced concrete floor. The assembled self-balancing structure is hoisted, and concrete is poured in the assembled floor self-balancing formwork structure to form an integrally poured reinforced concrete floor structure. This method is convenient for hoisting to the construction site for installation after the assembly is completed, and After the installation is completed, the construction is completed by integral pouring. This method can simplify the on-site construction process, and the integrity of the completed structure is good. This invention is used in the field of building construction.
Description
技术领域 technical field
本发明涉及建筑施工领域,特别是涉及一种钢筋混凝土楼盖的一体式浇筑成型施工方法。 The invention relates to the field of building construction, in particular to an integrated pouring and forming construction method for a reinforced concrete floor.
背景技术 Background technique
普通钢筋混凝土楼盖在现场施工时,首先需要形成钢筋混凝土梁和钢筋混凝土楼板的结构,再将已成形的钢筋混凝土梁和钢筋混凝土楼板的结构进行搭设形成钢筋混凝土楼盖。 When ordinary reinforced concrete floors are constructed on site, it is first necessary to form the structure of reinforced concrete beams and reinforced concrete floors, and then erect the formed reinforced concrete beams and reinforced concrete floors to form reinforced concrete floors.
普通钢筋混凝土楼盖的现场施工步骤多,流程复杂,现场施工工期长。传统预制钢筋混凝土梁和楼板在工厂完成上述步骤,并将完全预制好的钢筋混凝土梁和楼板运输到施工现场后,再吊装安装,运输和吊装安装的重量较大,并且预制构件之间的连接构造复杂,结构的整体性欠佳。 The on-site construction steps of ordinary reinforced concrete floors are many, the process is complicated, and the on-site construction period is long. The traditional prefabricated reinforced concrete beams and slabs complete the above steps in the factory, and after transporting the fully prefabricated reinforced concrete beams and slabs to the construction site, they are hoisted and installed. The weight of transportation and hoisting and installation is relatively large, and the connection between prefabricated components The structure is complex and the integrity of the structure is not good.
发明内容 Contents of the invention
为解决上述问题,本发明提供一种可在模板整体拼装完成后通过浇筑直接成型的钢筋混凝土楼盖的一体式浇筑成型施工方法。 In order to solve the above problems, the present invention provides an integrated pouring and forming construction method of a reinforced concrete floor that can be directly formed by pouring after the overall assembly of the formwork is completed.
本发明解决其技术问题所采用的技术方案是: The technical solution adopted by the present invention to solve its technical problems is:
一种钢筋混凝土楼盖的一体式浇筑成型施工方法,包括以下步骤: An integrated pouring forming construction method for a reinforced concrete floor, comprising the following steps:
1)、通过沿混凝土梁长度方向设置的若干梁钢筋笼主筋连接若干沿混凝土梁长度方向平行设置的梁箍筋形成梁钢筋笼,各梁钢筋笼主筋的长度长于梁模板的长度并伸出梁模板的两端,各梁箍筋包括位于钢筋笼两侧和底部带外螺纹的梁骨架钢筋; 1) A beam reinforcement cage is formed by connecting several beam stirrups arranged in parallel along the length direction of the concrete beam through the main reinforcement of several beam reinforcement cages arranged along the length direction of the concrete beam. The length of the main reinforcement of each beam reinforcement cage is longer than the length of the beam formwork and extends out of the beam At both ends of the template, each beam stirrup includes beam skeleton reinforcement with external threads on both sides of the reinforcement cage and at the bottom;
2)、竖向设置的梁骨架钢筋的顶端高于侧面的梁模板的高度,在竖向设置的梁骨架钢筋间设置连接在两梁骨架钢筋顶端的梁连接部附加钢筋; 2) The top of the vertical beam skeleton reinforcement is higher than the height of the side beam formwork, and the additional reinforcement of the beam connection part connected to the top of the two beam skeleton reinforcement is arranged between the vertical beam skeleton reinforcement;
3)、在竖向设置的梁骨架钢筋底部安装梁模板,将带外螺纹的梁骨架钢筋底部穿过底部的梁模板; 3) Install the beam template at the bottom of the vertical beam skeleton reinforcement, and pass the bottom of the beam skeleton reinforcement with external threads through the beam template at the bottom;
4)、在两侧设置梁模板,将带外螺纹的梁骨架钢筋侧向穿透侧面的梁模板; 4) Set beam templates on both sides, and penetrate the beam skeleton reinforcement with external threads laterally through the beam templates on the side;
5)、在两对接的梁模板外侧设置呈直角设置的梁加劲型钢,梁加劲型钢的两侧分别穿入带外螺纹的梁骨架钢筋端头,并通过螺母与外螺纹间的连接实现梁模板和梁加劲型钢的固定; 5) On the outside of the two butted beam templates, beam stiffening steel is arranged at right angles. The two sides of the beam stiffening steel are respectively inserted into the end of the beam skeleton steel bar with external thread, and the beam template is realized through the connection between the nut and the external thread. and the fixing of beam stiffening steel;
6)、在两侧的梁模板顶端设置呈直角形的楼板支座型钢,楼板支座型钢的一直角边紧贴梁模板,并通过螺母与外螺纹连接实现与梁模板顶端的固定连接,楼板支座型钢的另一直角边水平悬空设置; 6) At the top of the beam formwork on both sides, a right-angled floor support section steel is arranged. The right-angled side of the floor support section steel is close to the beam formwork, and the fixed connection with the top of the beam formwork is realized through nuts and external threads. The other right-angle side of the support section steel is suspended horizontally;
7)、临时固定梁支座可移动面筋,混凝土梁自平衡整体式模板拼装成型; 7) Temporary fixed beam support movable gluten, concrete beam self-balancing integral formwork assembly;
8)、通过若干折弯筋纵横搭接的楼板骨架钢筋焊接连接形成楼板钢筋网; 8) The floor reinforcement mesh is formed by welding and connecting the floor skeleton steel bars overlapped vertically and horizontally by several bending bars;
9)、在楼板模板与楼板钢筋网、钢筋桁架的固定连接点位置安装矩形连接板; 9) Install a rectangular connection plate at the fixed connection point between the floor formwork, the floor reinforcement mesh and the reinforcement truss;
10)、通过与所述楼板模板上的各矩形连接板固定连接来安装楼板钢筋网和钢筋桁架,所述钢筋桁架位于楼板钢筋网的上方,且彼此平行设置,形成一体式的钢筋混凝土楼板模板拼装结构; 10) Install the floor reinforcement mesh and the reinforcement truss by fixed connection with each rectangular connecting plate on the floor formwork, the reinforcement trusses are located above the floor reinforcement mesh and arranged parallel to each other to form an integrated reinforced concrete floor formwork Assembled structure;
11)、将所述钢筋混凝土梁模板拼装结构和钢筋混凝土楼板模板拼装结构运输至施工现场,吊装就位钢筋混凝土梁模板拼装结构; 11), transport the reinforced concrete beam formwork assembly structure and the reinforced concrete floor formwork assembly structure to the construction site, and hoist the reinforced concrete beam formwork assembly structure in place;
12)、安装梁结构和楼板结构上的支承杆,安装梁与柱连接节点、梁与墙连接节点的箍筋网片; 12) Install the support rods on the beam structure and the floor structure, install the stirrup mesh at the connection node between the beam and the column, and the connection node between the beam and the wall;
13)、将梁支座可移动面筋移至预定位置,安装梁与柱连接节点区、梁与墙连接节点区的侧面模板; 13) Move the movable gluten of the beam support to the predetermined position, and install the side formwork in the joint area of the beam-column connection and the joint area of the beam-wall connection;
14)、吊装就位钢筋混凝土楼板模板拼装结构; 14), hoisting in place reinforced concrete floor formwork assembly structure;
15)、安装楼板搭接底筋和楼板面钢筋; 15) Install floor lap joint bottom reinforcement and floor surface reinforcement;
16)、整体浇筑梁和楼板混凝土,混凝土与梁和楼板模板凝结形成整体; 16) Integral pouring of beam and slab concrete, concrete and beam and slab formwork condense to form a whole;
17)、混凝土达到预定强度后,拆除模板临时加固角钢和支承杆,循环使用。 17) After the concrete reaches the predetermined strength, remove the formwork and temporarily reinforce the angle steel and support rods for recycling.
进一步作为本发明技术方案的改进,步骤1)中各梁箍筋通过若干梁骨架钢筋彼此纵横连接。 As a further improvement of the technical solution of the present invention, in step 1), the stirrups of the beams are vertically and horizontally connected to each other through several beam skeleton reinforcements.
进一步作为本发明技术方案的改进,各梁箍筋还包括搭接在各梁骨架钢筋间的另加梁箍筋或者另加梁箍筋圈。 As a further improvement of the technical solution of the present invention, each beam stirrup also includes an additional beam stirrup or an additional beam stirrup ring lapped between the steel bars of each beam skeleton.
进一步作为本发明技术方案的改进,各另加梁箍筋为纵横搭接在梁骨架钢筋间的钢筋条。 As a further improvement of the technical solution of the present invention, each additional beam stirrup is a steel bar vertically and horizontally lapped between the steel bars of the beam skeleton.
进一步作为本发明技术方案的改进,另加梁箍筋圈为一由钢筋弯折而成的钢筋圈,钢筋圈与各梁骨架钢筋错位固定,钢筋圈或者钢筋条与各梁骨架钢筋的连接点通过焊接或者绑扎固定。 Further as an improvement of the technical solution of the present invention, an additional beam stirrup ring is a steel ring formed by bending a steel bar, and the steel bar ring and each beam frame steel bar are dislocated and fixed, and the connection point between the steel bar ring or the steel bar and each beam frame steel bar Fix by welding or binding.
进一步作为本发明技术方案的改进,步骤15)中,通过梁顶两侧的所述楼板支座型钢实现楼板与混凝土梁安装的临时施工连接。 As a further improvement of the technical solution of the present invention, in step 15), the temporary construction connection between the floor and the concrete beam installation is realized through the floor support section steel on both sides of the beam top.
进一步作为本发明技术方案的改进,钢筋桁架包括两侧的桁架底筋以及在两桁架底筋中部的上方设置的桁架顶筋,各桁架底筋与桁架顶筋间通过呈波浪状弯折的折弯筋进行多点连接。 As a further improvement of the technical solution of the present invention, the steel bar truss includes truss bottom bars on both sides and truss top bars arranged above the middle of the two truss bottom bars, and each truss bottom bar and truss top bars pass through a wave-like bending fold Bend ribs for multi-point connections.
进一步作为本发明技术方案的改进,桁架底筋与折弯筋连接点与矩形连接板固定连接。 As a further improvement of the technical solution of the present invention, the connection point between the bottom reinforcement of the truss and the bending reinforcement is fixedly connected with the rectangular connection plate.
进一步作为本发明技术方案的改进,确认矩形连接板的安装位后,通过四个直角位的紧固螺栓实现矩形连接板与楼板模板间的连接。 As a further improvement of the technical solution of the present invention, after confirming the installation position of the rectangular connecting plate, the connection between the rectangular connecting plate and the floor formwork is realized through four fastening bolts at right angles.
进一步作为本发明技术方案的改进,梁模板与梁钢筋笼通过梁骨架钢筋对拉连接形成自平衡整体,楼板模板与楼板钢筋网和钢筋桁架固定连接形成一体,可在整体运输和吊装安装。 As a further improvement of the technical solution of the present invention, the beam formwork and the beam reinforcement cage are connected to form a self-balancing whole through the tension connection of the beam skeleton reinforcement, and the floor formwork is fixedly connected with the floor reinforcement mesh and the reinforcement truss to form a whole, which can be transported and hoisted as a whole.
本发明的有益效果:此钢筋混凝土楼盖的一体式浇筑成型施工方法将形成钢筋混凝土梁和钢筋混凝土楼板的自平衡整体结构进行单独拼装,将单独拼装完成的自平衡结构进行吊装,并在拼装完成的楼盖自平衡模板结构内浇筑混凝土,形成一体浇筑的钢筋混凝土楼盖结构,此方法方便拼装完成后吊装至施工现场进行施工进行安装,并在安装完成后一体浇筑完成施工,此方法可简化现场施工流程,且施工完成结构的整体性好。 Beneficial effects of the present invention: the integrated pouring and molding construction method of the reinforced concrete floor will separately assemble the self-balancing overall structure that forms the reinforced concrete beam and the reinforced concrete floor, hoist the self-balancing structure that has been assembled separately, and Concrete is poured into the completed floor self-balancing formwork structure to form an integrally poured reinforced concrete floor structure. This method is convenient for hoisting to the construction site for installation after the assembly is completed, and the integral pouring completes the construction after the installation. This method can The on-site construction process is simplified, and the integrity of the completed structure is good.
附图说明 Description of drawings
下面结合附图对本发明作进一步说明: The present invention will be further described below in conjunction with accompanying drawing:
图1是本发明实施例中梁整体模板结构整体结构俯视图; Fig. 1 is the top view of the overall structure of the beam integral formwork structure in the embodiment of the present invention;
图2是本发明实施例中梁整体模板结构整体结构侧视图; Fig. 2 is a side view of the overall structure of the overall formwork structure of the beam in the embodiment of the present invention;
图3是本发明实施例中梁整体模板结构主视面剖视图; Fig. 3 is a cross-sectional view of the front view of the integral formwork structure of the beam in the embodiment of the present invention;
图4是本发明实施例中楼板支承杆与建筑物横梁结构示意图; Fig. 4 is a structural schematic diagram of floor support rods and building beams in an embodiment of the present invention;
图5是本发明图4中A部分结构详细示意图; Fig. 5 is a detailed schematic diagram of the structure of part A in Fig. 4 of the present invention;
图6是本发明实施例中楼板整体模板结构整体结构示意图; Fig. 6 is a schematic diagram of the overall structure of the overall formwork structure of the floor slab in the embodiment of the present invention;
图7是本发明实施例中楼板整体模板结构钢筋桁架连接部分结构剖视图; Fig. 7 is a structural sectional view of the connection part of the steel bar truss of the overall formwork structure of the floor slab in the embodiment of the present invention;
图8是本发明实施例中楼板整体模板结构楼板钢筋网连接部分结构剖视图; Fig. 8 is a structural sectional view of the connection part of the floor slab integral formwork structure in the embodiment of the present invention;
图9是本发明实施例中楼板整体模板结构楼板钢筋网连接部分结构俯视图; Fig. 9 is a top view of the structure of the connection part of the floor's overall formwork structure in the embodiment of the present invention;
图10是本发明实施例中楼板整体模板结构楼板钢筋网整体结构示意图。 Fig. 10 is a schematic diagram of the overall structure of the floor reinforcement mesh in the integral formwork structure of the floor in the embodiment of the present invention.
具体实施方式 detailed description
参照图1~图10,本发明为一种钢筋混凝土楼盖的一体式浇筑成型施工方法,包括以下步骤: Referring to Figures 1 to 10, the present invention is an integrated pouring and forming construction method for a reinforced concrete floor, comprising the following steps:
1)、通过沿混凝土梁长度方向设置的若干梁钢筋笼主筋13连接若干沿混凝土梁长度方向平行设置的梁箍筋14形成梁钢筋笼,各梁钢筋笼主筋13的长度长于梁模板11的长度并伸出梁模板11的两端,各梁箍筋14包括位于梁钢筋笼两侧和底部带外螺纹的梁骨架钢筋141; 1) A beam reinforcement cage is formed by connecting several beam reinforcement cage main reinforcements 13 arranged along the length direction of the concrete beam to several beam stirrups 14 arranged in parallel along the length direction of the concrete beam, and the length of each beam reinforcement cage main reinforcement 13 is longer than the length of the beam template 11 And stretch out the two ends of beam formwork 11, each beam stirrup 14 comprises the beam skeleton reinforcing bar 141 that is positioned at the both sides of beam reinforcement cage and bottom band external thread;
2)、竖向设置的梁骨架钢筋141的顶端高于侧面的梁模板11的高度,在竖向设置的梁骨架钢筋141间设置连接在两梁骨架钢筋141顶端的梁连接部附加钢筋142; 2) The top of the vertically arranged beam skeleton reinforcing bars 141 is higher than the height of the side beam formwork 11, and the beam connecting portion additional reinforcing bars 142 connected to the tops of the two beam skeleton reinforcing bars 141 are arranged between the vertically arranged beam skeleton reinforcing bars 141;
3)、在竖向设置的梁骨架钢筋141底部安装梁模板11,将带外螺纹的梁骨架钢筋141底部穿过底部的梁模板11; 3) Install the beam template 11 at the bottom of the vertical beam skeleton reinforcement 141, and pass the bottom of the beam skeleton reinforcement 141 with external threads through the beam template 11 at the bottom;
4)、在两侧设置梁模板11,将带外螺纹的梁骨架钢筋141侧向穿透侧面的梁模板11; 4) Install beam formwork 11 on both sides, and penetrate the beam formwork 11 on the side with the beam skeleton reinforcement 141 with external threads;
5)、在两对接的梁模板11外侧设置呈直角设置的梁加劲型钢12,梁加劲型钢12的两侧分别穿入带外螺纹的梁骨架钢筋141端头,并通过螺母与外螺纹间的连接实现梁模板11和梁加劲型钢12的固定; 5) On the outside of the two butted beam templates 11, a beam stiffening section steel 12 arranged at right angles is arranged, and the two sides of the beam stiffening section steel 12 respectively penetrate into the end of the beam skeleton steel bar 141 with external thread, and pass through the nut and the external thread. The connection realizes the fixing of the beam template 11 and the beam stiffening section steel 12;
6)、在两侧的梁模板11顶端设置呈直角形的楼板支座型钢,楼板支座型钢的一直角边紧贴梁模板11,并通过螺母与外螺纹连接实现与梁模板11顶端的固定连接,楼板支座型钢的另一直角边水平悬空设置; 6) At the top of the beam formwork 11 on both sides, a right-angled floor support section steel is arranged, and the right-angled side of the floor support section steel is close to the beam formwork 11, and is fixed to the top of the beam formwork 11 through nuts and external threads. Connection, the other right-angled side of the floor support section steel is suspended horizontally;
7)、临时固定梁支座可移动面筋,混凝土梁自平衡整体式模板拼装成型; 7) Temporary fixed beam support movable gluten, concrete beam self-balancing integral formwork assembly;
8)、通过若干纵横搭接的楼板骨架钢筋21焊接连接形成楼板钢筋网; 8) A number of vertically and horizontally overlapped floor skeleton steel bars 21 are welded and connected to form a floor steel mesh;
9)、在楼板模板22与楼板钢筋网、钢筋桁架24的固定连接点位置安装矩形连接板25; 9) Install a rectangular connection plate 25 at the fixed connection point between the floor formwork 22 and the floor reinforcement mesh and reinforcement truss 24;
10)、通过与所述楼板模板22上的各矩形连接板25固定连接来安装楼板钢筋网和钢筋桁架24,所述钢筋桁架24位于楼板钢筋网的上方,且彼此平行设置,形成一体式的钢筋混凝土楼板模板22拼装结构; 10) Install the floor reinforcement mesh and the reinforcement truss 24 by fixedly connecting with each rectangular connecting plate 25 on the floor formwork 22. The reinforcement truss 24 is located above the floor reinforcement mesh and arranged parallel to each other to form an integrated Reinforced concrete floor formwork 22 assembly structure;
11)、将所述钢筋混凝土梁模板拼装结构和钢筋混凝土楼板模板22拼装结构运输至施工现场,吊装就位钢筋混凝土梁模板拼装结构; 11), transport the assembled structure of the reinforced concrete beam formwork and the assembled structure of the reinforced concrete floor formwork 22 to the construction site, and hoist the assembled structure of the reinforced concrete beam formwork in place;
12)、安装梁结构和楼板结构上的支承杆10,安装梁与柱连接节点、梁与墙连接节点的箍筋网片; 12) Install the support rods 10 on the beam structure and the floor structure, install the stirrup mesh at the connection node between the beam and the column, and the connection node between the beam and the wall;
13)、将梁支座可移动面筋移至预定位置,安装梁与柱连接节点区、梁与墙连接节点区的侧面模板; 13) Move the movable gluten of the beam support to the predetermined position, and install the side formwork in the joint area of the beam-column connection and the joint area of the beam-wall connection;
14)、吊装就位钢筋混凝土楼板模板22拼装结构; 14), hoisting in place reinforced concrete floor formwork 22 assembly structure;
15)、安装楼板搭接底筋和楼板面钢筋; 15) Install floor lap joint bottom reinforcement and floor surface reinforcement;
16)、整体浇筑梁和楼板混凝土,混凝土与梁和楼板模板22凝结形成整体; 16) Integral pouring of beam and floor concrete, concrete and beam and floor formwork 22 condense to form a whole;
17)、混凝土达到预定强度后,拆除模板临时加固角钢和支承杆10,循环使用。 17) After the concrete reaches the predetermined strength, the formwork is removed to temporarily reinforce the angle steel and support rod 10 for recycling.
此钢筋混凝土楼盖的一体式浇筑成型施工方法将形成钢筋混凝土梁和钢筋混凝土楼板的自平衡整体结构进行单独拼装,将单独拼装完成的自平衡结构进行吊装,并在拼装完成的楼盖自平衡模板结构内浇筑混凝土,形成一体浇筑的钢筋混凝土楼盖结构,此方法方便拼装完成后吊装至施工现场进行施工进行安装,并在安装完成后一体浇筑完成施工,此方法可简化现场施工流程,且施工完成结构的整体性好。 The integrated pouring and forming construction method of the reinforced concrete floor will form the self-balancing overall structure of the reinforced concrete beam and the reinforced concrete floor to be assembled separately, and the self-balancing structure that has been assembled separately will be hoisted, and the assembled floor will be self-balancing. Concrete is poured into the formwork structure to form an integrally poured reinforced concrete floor structure. This method is convenient for hoisting to the construction site for installation after the assembly is completed, and the construction is completed by integral pouring after the installation. This method can simplify the construction process on site, and The integrity of the structure after construction is good.
作为本发明优选的实施方式,步骤1)中各梁箍筋14通过若干梁骨架钢筋141彼此纵横连接。 As a preferred embodiment of the present invention, in step 1), each beam stirrup 14 is vertically and horizontally connected to each other by several beam skeleton steel bars 141 .
作为本发明优选的实施方式,各梁箍筋14还包括搭接在各梁骨架钢筋141间的另加梁箍筋或者另加梁箍筋圈。 As a preferred embodiment of the present invention, each beam stirrup 14 also includes an additional beam stirrup or an additional beam stirrup ring lapped between each beam skeleton steel bar 141 .
作为本发明优选的实施方式,各另加梁箍筋为纵横搭接在梁骨架钢筋141间的钢筋条。 As a preferred embodiment of the present invention, each additional beam stirrup is a steel bar overlapping vertically and horizontally between the steel bars 141 of the beam skeleton.
作为本发明优选的实施方式,另加梁箍筋圈为一由钢筋弯折而成的钢筋圈,钢筋圈与各梁骨架钢筋141错位固定,钢筋圈或者钢筋条与各梁骨架钢筋141的连接点通过焊接或者绑扎固定。 As a preferred embodiment of the present invention, the additional beam stirrup ring is a steel ring formed by bending steel bars, the steel ring is fixed with each beam frame steel bar 141 in dislocation, and the connection between the steel bar ring or the steel bar and each beam frame steel bar 141 Points are secured by welding or tying.
作为本发明优选的实施方式,所述步骤15)中,通过梁顶两侧的所述楼板支座型钢实现楼板与混凝土梁安装的临时施工连接。 As a preferred embodiment of the present invention, in the step 15), the temporary construction connection between the floor and the concrete beam is realized through the floor support section steel on both sides of the beam top.
作为本发明优选的实施方式,钢筋桁架24包括两侧的桁架底筋241以及在两桁架底筋241中部的上方设置的桁架顶筋243,各桁架底筋241与桁架顶筋243间通过呈波浪状弯折的折弯筋242进行多点连接。 As a preferred embodiment of the present invention, the steel bar truss 24 includes truss bottom bars 241 on both sides and truss top bars 243 arranged above the middle of the two truss bottom bars 241, and each truss bottom bar 241 and truss top bars 243 pass through in waves. The bending ribs 242 bent in the same shape are used for multi-point connection.
作为本发明优选的实施方式,桁架底筋241与折弯筋242连接点与矩形连接板25固定连接。 As a preferred embodiment of the present invention, the connecting points of the truss bottom rib 241 and the bending rib 242 are fixedly connected with the rectangular connecting plate 25 .
作为本发明优选的实施方式,确认矩形连接板25的安装位后,通过四个直角位的紧固螺栓实现矩形连接板25与楼板模板22间的连接。 As a preferred embodiment of the present invention, after the installation position of the rectangular connecting plate 25 is confirmed, the connection between the rectangular connecting plate 25 and the floor formwork 22 is realized through four fastening bolts at right angles.
作为本发明优选的实施方式,梁模板与梁钢筋笼通过梁骨架钢筋对拉连接形成自平衡整体,楼板模板22与楼板钢筋网和钢筋桁架24固定连接形成一体,可在整体运输和吊装安装。 As a preferred embodiment of the present invention, the beam formwork and the beam reinforcement cage are connected to form a self-balancing whole through the tension connection of the beam skeleton reinforcement, and the floor formwork 22 is fixedly connected with the floor reinforcement mesh and the reinforcement truss 24 to form a whole, which can be transported and hoisted as a whole.
在钢筋笼与两侧和底部的梁模板11固定形成自平衡结构后,通过梁钢筋笼主筋13和两侧的楼板制作型钢与侧面的墙板间连接,可将拼装完成的混凝土梁自平衡整体梁模板结构与侧面的墙板等固定连接,通过在自平衡结构的上方倒入混凝土即可形成钢筋混凝土梁。 After the reinforcement cage is fixed to the beam formwork 11 on both sides and bottom to form a self-balancing structure, the steel reinforcement cage 13 and the floor slabs on both sides are connected to the side wall panels to make the assembled concrete beam self-balancing as a whole. The beam formwork structure is fixedly connected to the side wall panels, etc., and the reinforced concrete beam is formed by pouring concrete above the self-balancing structure.
形成钢筋混凝土梁上部的梁骨架钢筋141露出钢筋混凝土梁的上表面,并通过梁连接部附加钢筋142连接,露出的梁骨架钢筋141部分和梁连接部附加钢筋142方便后期与其他结构相连,利于提高整体强度及抗震能力。 The beam skeleton steel bar 141 forming the upper part of the reinforced concrete beam exposes the upper surface of the reinforced concrete beam, and is connected by the additional steel bar 142 of the beam connection part. Improve the overall strength and earthquake resistance.
根据钢筋混凝土墙制作宽度的不同,可在各梁箍筋14上搭设另加梁箍筋和另加梁箍筋圈来增强各梁箍筋14的强度。 According to the difference in the width of the reinforced concrete wall, additional beam stirrups and additional beam stirrup circles can be set up on each beam stirrup 14 to enhance the strength of each beam stirrup 14 .
附加箍筋17间隔设置在相邻的梁箍筋14之间,各附加箍筋17包括若干纵横搭接且均与梁钢筋笼主筋13相连的钢筋条或者环绕在竖直钢筋外的钢筋圈,可增强钢筋笼结构的整体强度。 Additional stirrups 17 are arranged at intervals between adjacent beam stirrups 14, and each additional stirrup 17 includes a number of vertically and horizontally overlapping reinforcing bars that are all connected to the main reinforcement 13 of the beam reinforcing cage or surrounding reinforcing rings outside the vertical reinforcing bars. It can enhance the overall strength of the steel cage structure.
可在梁模板11上设置螺孔,螺栓15设置内螺纹,穿过螺孔实现与梁骨架钢筋141端头的外螺纹固定连接。通过从外侧调整螺栓15,可调整梁模板11的连接牢固程度,使得整体式梁模板11达到较好的连接牢固性。 A screw hole can be set on the beam template 11, and the bolt 15 is set with an internal thread, and the external thread fixed connection with the end of the beam skeleton steel bar 141 is realized through the screw hole. By adjusting the bolts 15 from the outside, the connection firmness of the beam formwork 11 can be adjusted, so that the integral beam formwork 11 can achieve better connection firmness.
梁加劲型钢12设置在两相邻的梁模板11间,并与两侧的梁模板11均固定连接,可使得整体式梁模板形成一个四周密封的整体,防止混凝土浇筑过程中混凝土泄露,同时,能增强整体式梁模板的连接牢固性。 Beam stiffening steel 12 is arranged between two adjacent beam formworks 11, and is fixedly connected with the beam formworks 11 on both sides, so that the integral beam formwork can form a whole with a seal around it, preventing concrete from leaking during the concrete pouring process. At the same time, The connection firmness of the integral beam formwork can be enhanced.
梁模板11为永久式梁模板,混凝土浇筑完成后与混凝土结合为一体,不用拆除,可节省施工工序。 The beam formwork 11 is a permanent beam formwork, which is combined with concrete after the concrete pouring is completed, and does not need to be dismantled, which can save construction procedures.
钢筋桁架24的设置可增加楼板钢筋网立面空间,便于在混凝土浇筑过程中,增强混凝土楼板内楼板钢筋网的承力效果。 The setting of the steel bar truss 24 can increase the space of the facade of the floor steel mesh, which is convenient to enhance the load-bearing effect of the floor steel mesh in the concrete floor during the concrete pouring process.
矩形连接板25可通过焊接等工艺与楼板钢筋网或者钢筋桁架24相连,随后通过紧固螺栓251实现矩形连接板25与楼板模板22间的连接,从而形成一体化的整体式楼板模板结构。 The rectangular connecting plate 25 can be connected with the floor steel mesh or steel bar truss 24 by welding or other processes, and then the connection between the rectangular connecting plate 25 and the floor formwork 22 can be realized by fastening bolts 251, thereby forming an integrated integral floor formwork structure.
当然,本发明创造并不局限于上述实施方式,熟悉本领域的技术人员在不违背本发明精神的前提下还可作出等同变形或替换,这些等同的变型或替换均包含在本申请权利要求所限定的范围内。 Of course, the present invention is not limited to the above-mentioned embodiments. Those skilled in the art can also make equivalent modifications or replacements without violating the spirit of the present invention. These equivalent modifications or replacements are all included in the claims of this application. within a limited range.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510752696.8A CN106032705B (en) | 2015-11-06 | 2015-11-06 | A kind of integral type pouring molding construction method of reinforced concrete floor |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510752696.8A CN106032705B (en) | 2015-11-06 | 2015-11-06 | A kind of integral type pouring molding construction method of reinforced concrete floor |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106032705A true CN106032705A (en) | 2016-10-19 |
| CN106032705B CN106032705B (en) | 2018-01-09 |
Family
ID=57149032
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510752696.8A Active CN106032705B (en) | 2015-11-06 | 2015-11-06 | A kind of integral type pouring molding construction method of reinforced concrete floor |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106032705B (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110863608A (en) * | 2019-11-20 | 2020-03-06 | 中国十七冶集团有限公司 | Construction method of large-span space section beam |
| CN110919151A (en) * | 2019-10-30 | 2020-03-27 | 中民筑友有限公司 | Complete equipment for producing reinforcement cage |
| CN113565139A (en) * | 2021-07-07 | 2021-10-29 | 深圳市中地建设工程有限公司 | Construction method for easy demoulding of floor beam and floor formwork |
| CN113756425A (en) * | 2021-09-23 | 2021-12-07 | 广州容联建筑科技有限公司 | A building structure with integrated decorative structure and its construction method |
| CN114000634A (en) * | 2021-12-10 | 2022-02-01 | 广州容联建筑科技有限公司 | Assembly type fold line type top cover and construction method thereof |
| CN116641483A (en) * | 2023-06-15 | 2023-08-25 | 广州市鲁班建筑结构设计事务所有限公司 | Assembled building structure |
| CN119332864A (en) * | 2024-12-09 | 2025-01-21 | 南京粲宛喏建筑有限公司 | A modular steel frame floor structure for building |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20090165399A1 (en) * | 2006-03-03 | 2009-07-02 | Alejandro Campos Gines | Prefabricated reinforced-concrete single-family dwelling and method for erecting said dwelling |
| CN101806095A (en) * | 2010-03-15 | 2010-08-18 | 中山市快而居房屋预制件有限公司 | Full-fabricated assembly overall reinforced concrete house and building method thereof |
| CN202831296U (en) * | 2012-08-08 | 2013-03-27 | 沈阳建筑大学 | Assembled spliced connecting structure of concrete frame-shear wall and structure constructed |
| CN103422672A (en) * | 2013-08-29 | 2013-12-04 | 杜新智 | Construction method for reinforced concrete prefabricated house |
| CN104153576A (en) * | 2014-08-15 | 2014-11-19 | 袁建华 | Construction methods for building combined buildings |
| CN104234185A (en) * | 2014-07-24 | 2014-12-24 | 刘贻鹏 | Wire cage frame hollow concrete framework structure and assembling method thereof |
-
2015
- 2015-11-06 CN CN201510752696.8A patent/CN106032705B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20090165399A1 (en) * | 2006-03-03 | 2009-07-02 | Alejandro Campos Gines | Prefabricated reinforced-concrete single-family dwelling and method for erecting said dwelling |
| CN101806095A (en) * | 2010-03-15 | 2010-08-18 | 中山市快而居房屋预制件有限公司 | Full-fabricated assembly overall reinforced concrete house and building method thereof |
| CN202831296U (en) * | 2012-08-08 | 2013-03-27 | 沈阳建筑大学 | Assembled spliced connecting structure of concrete frame-shear wall and structure constructed |
| CN103422672A (en) * | 2013-08-29 | 2013-12-04 | 杜新智 | Construction method for reinforced concrete prefabricated house |
| CN104234185A (en) * | 2014-07-24 | 2014-12-24 | 刘贻鹏 | Wire cage frame hollow concrete framework structure and assembling method thereof |
| CN104153576A (en) * | 2014-08-15 | 2014-11-19 | 袁建华 | Construction methods for building combined buildings |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110919151A (en) * | 2019-10-30 | 2020-03-27 | 中民筑友有限公司 | Complete equipment for producing reinforcement cage |
| CN110919151B (en) * | 2019-10-30 | 2022-01-21 | 中民筑友有限公司 | Complete equipment for producing reinforcement cage |
| CN110863608A (en) * | 2019-11-20 | 2020-03-06 | 中国十七冶集团有限公司 | Construction method of large-span space section beam |
| CN113565139A (en) * | 2021-07-07 | 2021-10-29 | 深圳市中地建设工程有限公司 | Construction method for easy demoulding of floor beam and floor formwork |
| CN113756425A (en) * | 2021-09-23 | 2021-12-07 | 广州容联建筑科技有限公司 | A building structure with integrated decorative structure and its construction method |
| CN114000634A (en) * | 2021-12-10 | 2022-02-01 | 广州容联建筑科技有限公司 | Assembly type fold line type top cover and construction method thereof |
| CN116641483A (en) * | 2023-06-15 | 2023-08-25 | 广州市鲁班建筑结构设计事务所有限公司 | Assembled building structure |
| CN119332864A (en) * | 2024-12-09 | 2025-01-21 | 南京粲宛喏建筑有限公司 | A modular steel frame floor structure for building |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106032705B (en) | 2018-01-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106032705B (en) | A kind of integral type pouring molding construction method of reinforced concrete floor | |
| CN105569224B (en) | Concrete filled steel tube edge constraint overlaps monoblock type shear wall and preparation and installation method | |
| CN106032692B (en) | A kind of integral type pouring molding construction method of reinforced column | |
| CN106032706B (en) | A kind of integral type pouring molding construction method of reinforced concrete shear wall | |
| JP5620344B2 (en) | Construction method of pier | |
| CN105952061A (en) | Prefabricated shear wall reinforcement cage member and column reinforcement cage member as well as manufacturing and assembling methods thereof | |
| CN106013455A (en) | Prefabricated combination reinforcement cage member and reinforcement arrangement assembling method thereof | |
| US9422680B2 (en) | Deck | |
| CN206052964U (en) | Prefabricated composite steel reinforcement cage component and structure | |
| CN105952060A (en) | Precast beam reinforcement cage component and assembling method thereof | |
| KR20210004289A (en) | Transfer Structure Construction Method Using U-shaped Steel Girder | |
| CN102051931B (en) | Steel reinforcement cage for multi-ribbed composite wall and installation method of steel reinforcement cage | |
| CN205153536U (en) | Structure is assembled to self -balancing integral template of reinforced concrete roof beam | |
| CN106049719B (en) | A kind of self-balancing monoblock type template assembly structure of reinforced concrete shear wall | |
| KR101875015B1 (en) | Prefabricated src structure for column and the manufacturing method thereof | |
| US12523033B2 (en) | Composite frame having end-embedded girder joint structure | |
| CN106032702B (en) | A kind of self-balancing monoblock type template assembly structure of reinforced beam | |
| CN104032855B (en) | Assembled cross mixing coupled wall and construction method thereof | |
| CN205153530U (en) | Structure is assembled to integral template of reinforced concrete floor | |
| CN115977233A (en) | Fully assembled concrete building structure | |
| WO2015051551A1 (en) | Building and construction method thereof | |
| CN104032862B (en) | Assembled girder steel seam line L shape mixing coupled wall and construction method thereof | |
| CN116290767A (en) | Construction process of self-supporting cast-in-situ reinforced concrete frame with assembled rib mould | |
| JPH10102423A (en) | PCa formwork and pier construction method using this PCa formwork | |
| CN210288825U (en) | Assembled and cast-in-situ combined beam plate structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| PP01 | Preservation of patent right |
Effective date of registration: 20250928 Granted publication date: 20180109 |