JPS62291308A - Construction work of concrete dam - Google Patents

Construction work of concrete dam

Info

Publication number
JPS62291308A
JPS62291308A JP13371986A JP13371986A JPS62291308A JP S62291308 A JPS62291308 A JP S62291308A JP 13371986 A JP13371986 A JP 13371986A JP 13371986 A JP13371986 A JP 13371986A JP S62291308 A JPS62291308 A JP S62291308A
Authority
JP
Japan
Prior art keywords
aggregate
cement
concrete
dam
bulldozer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13371986A
Other languages
Japanese (ja)
Inventor
Satoru Oda
哲 小田
Toshiaki Kanai
金井 俊昭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Komatsu Ltd
Original Assignee
Komatsu Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Komatsu Ltd filed Critical Komatsu Ltd
Priority to JP13371986A priority Critical patent/JPS62291308A/en
Publication of JPS62291308A publication Critical patent/JPS62291308A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To cut down the cost of machinery and facilities as well as to shorten the period of construction by a method in which, aggregate carried to a dam site is uniformly laid, cement is spread over the aggregate and mixed with the aggregate, and they are compacted. CONSTITUTION:Aggregate 27 is carried into a dam sits by dump truck, etc., and uniformly laid by bulldozer, and cement 28 is spread over the aggregate 27 by using a spreader 20 attached to the bulldozer 21 having a spreading hopper 22 on its back side. The aggregate 27 and the cement 28 are mixed together by using a stabilizer 23 with a breaker 25 on the front of a traveling vehicle 24 and then compacted by a vibro-roller. The separation of the cement 28 can thus be prevented.

Description

【発明の詳細な説明】 λ発明の詳細な説明 産業上の利用分野 本発明はコンクリートダムの構築工法に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION λ Detailed Description of the Invention Field of Industrial Application The present invention relates to a method of constructing a concrete dam.

従来の技術 従来のこの種のコンクリートダムの構築工法としてRC
D工法がある。このRCD工法は、貧配合超硬練りコン
クリートをダンプトラック等で運搬し、ブルドーザで敷
均し振動目地切り機で目地を造成した後、振動ローラで
締固めてコンクリートダムを建設する一連の施ニジステ
ムである。
Conventional technology The conventional construction method for this type of concrete dam is RC.
There is method D. This RCD construction method is a series of construction systems in which poorly mixed cemented carbide concrete is transported by dump trucks, etc., leveled with a bulldozer, joints created with a vibrating joint cutter, and then compacted with vibrating rollers to construct a concrete dam. It is.

そしてとのRCD工法によるダムコンクリートの打設順
序は第す図及び第7図に示すよってコンクリートプラン
ト1→パケツト2(バンカー線)→固定ケーブルクレー
ン3→移動式ホッパー4→ダンプトラック5→ブルドー
ザ−6→ジヨイントカツター7→振動ローラ8→モータ
ースイーパ−9(グリーンカット)→散水養生10→モ
ルタル敷均し11→次層打設置2のようになる。
The order of placing dam concrete using the RCD method is shown in Figures 1 and 7: concrete plant 1 -> packet 2 (bunker line) -> fixed cable crane 3 -> mobile hopper 4 -> dump truck 5 -> bulldozer. 6 → joint cutter 7 → vibrating roller 8 → motor sweeper 9 (green cut) → watering curing 10 → mortar leveling 11 → next layer pouring installation 2.

上記したようにRC’ D工法は主としてコンクリート
プラント;で骨材とセメントとを混合してコンクリート
を作り、このコンク−リート?ダンプトラック等で運搬
し、このコンクリートをブルドーザbで敷均し次に振動
ロー28で締め固める工法である(第8図参照)。
As mentioned above, the RC'D method is mainly used in concrete plants; aggregate and cement are mixed to make concrete. This is a construction method in which the concrete is transported by a dump truck or the like, leveled with a bulldozer b, and then compacted with a vibrating row 28 (see Figure 8).

発明が解決しようとする問題点 RC’ D工法は、従来のブロック打設工法等と比較す
ると ■ 一般の大型機械による大量急速(連続)施工が可能 ■ 使用するセメント量が少ないので、温度上昇が少な
く、冷却作業が省略出来る。
Problems to be solved by the invention Compared to conventional block casting methods, etc., the RC'D construction method allows large-volume, rapid (continuous) construction using general large machinery.■ Because the amount of cement used is small, temperature rise is reduced. Cooling work can be omitted.

+I+  コンクリート打設直後に機械的に目地切りを
行うため型枠作業が不要 等の特長が有り、技術面を含めた総合評価として、効果
が認められている。しかし反面、セメント配合、管理゛
システムの改善や機械の効率的運用による工期短縮等の
課題が残っている。
+I+ Since the joints are mechanically cut immediately after concrete is poured, there is no need for formwork work, and the overall evaluation including technical aspects has shown that it is effective. However, on the other hand, issues remain, such as shortening the construction period through improvements in cement mixing and management systems and efficient use of machinery.

またRCD工法では、配合、混合されたコンクリートを
ダム現場へ運搬して敷均すため、ダンプトラックからの
ダンピング時やプルでの敷均し時、セメント材料の分離
が発生していた。
In addition, in the RCD method, the mixed concrete is transported to the dam site and leveled, so separation of cement materials occurs when dumping from a dump truck or leveling by pulling.

発明の目的 本発明は上記の本情に鑑み表されたもので、セメント材
料の分離がなくまた、コンクリートプラントが不要でプ
ラント設置工程及びプラントからダム現場へのコンクリ
ート運搬工程を削除することができて工期の短縮が計れ
しかも機械設備コストの低減を計ることが可能なコンク
リートダム構築工法を提供することを目的とする。
Purpose of the Invention The present invention has been developed in view of the above-mentioned circumstances, and there is no separation of cement materials, no concrete plant is required, and the plant installation process and the concrete transportation process from the plant to the dam site can be eliminated. The purpose of the present invention is to provide a concrete dam construction method that can shorten the construction period and reduce the cost of machinery and equipment.

問題点を解決するための手段及び作用 上記の目的を達成するために本発廚は、ダム現場に搬入
された骨材を敷均した後にこの骨材上にセメントを散布
し、骨材とセメントとを混合した後に締固めるようにし
たものである〇実  施  例 以下、本発明の実施例を図面に基づいて説明する。  
 一 本発明に係るコンクリートダムの構築工法(Stabi
Lizing RaLLar CmytpactatL
 Dam工法すなわち5pcn工法)はセメントの配合
、混合iダム現場で直接行うようにしたものである。
Means and action for solving the problem In order to achieve the above purpose, this plant spreads cement on the aggregate brought to the dam site after leveling it, and then mixes the aggregate and cement. Embodiment Embodiments of the present invention will be described below based on the drawings.
1. Concrete dam construction method according to the present invention (Stabi
Lizing RaLLar CmytpactatL
Dam construction method (5pcn construction method) is a method in which cement is blended and mixed directly at the dam site.

すなわち第1図に示すようにダム現場に骨材27をダン
プトラック等で運び入れてこの骨材27をブルドーザ−
で敷均し、次にこの敷均された骨材27にセメント28
を散布する。このセメント散布には第2図及び第3図に
示す散布機20が用いられる。この散布機20はブルド
ーザ−21の後部にセメント散布用ホッパ−22を取付
けた構造のものである。
That is, as shown in Fig. 1, aggregate 27 is brought to the dam site by a dump truck or the like, and this aggregate 27 is moved to a bulldozer.
Then, cement 28 is applied to this leveled aggregate 27.
Spread. A spreader 20 shown in FIGS. 2 and 3 is used for this cement spreading. This spreader 20 has a structure in which a cement spreading hopper 22 is attached to the rear of a bulldozer 21.

次に骨材27とセメント28とを混合する。Next, aggregate 27 and cement 28 are mixed.

この混合にはスタビライザ23が用いられる。A stabilizer 23 is used for this mixing.

このスタビライザ23は第4図に示すように走行車両2
4の前部にブレーカ25を備えたものであって、このブ
レーカ25は破砕ビット26aを射る回転体26を回転
して第5図のように骨材27上に散布されたセメント2
Bを混合するものである、 次に前記スタビライザ23により混合された骨材27と
セメント2gとを振動ローラを用いて締固める。
This stabilizer 23 is connected to the traveling vehicle 2 as shown in FIG.
The breaker 25 is equipped with a breaker 25 on the front part of the aggregate 27, and this breaker 25 rotates a rotary body 26 that shoots a crushing bit 26a to crush the cement 2 scattered on the aggregate 27 as shown in FIG.
Next, the aggregate 27 mixed by the stabilizer 23 and 2 g of cement are compacted using a vibrating roller.

発明の効果 以上詳述したように1本発明に係るコンクリートダムの
構築工法は、ダム現場に搬入された骨材を敷均した後に
この骨材上にセメントを散布し、骨材とセメントとを混
合した後に締固めるようにしたことを%徴とするもので
ある。
Effects of the Invention As detailed above, the method for constructing a concrete dam according to the present invention is to spread cement on the aggregate after leveling the aggregate carried to the dam site, and to mix the aggregate and cement. The percentage indicates that the material is compacted after mixing.

したがって、あらかじめ敷均した骨材上にセメントを散
布した後混合を行うためにセメント材料の分離が発生す
るととがない。
Therefore, it is inevitable that the cement material will separate because the cement is spread on the pre-leveled aggregate and then mixed.

また、コンクリートプラントが不要のためプラント設置
工程及びプラントからダム現場へのコンクリート運搬工
程を削除することが出来るので工期の短縮が計れるし、
コンクリートプラント及びケーブルクレーンが不要とな
り、機械設備コストの低減を計ることができる。
In addition, since a concrete plant is not required, the plant installation process and the concrete transport process from the plant to the dam site can be eliminated, reducing the construction period.
Concrete plants and cable cranes are no longer required, and machinery and equipment costs can be reduced.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係るコンクリートダム構築工法の説明
図、第2図は散T1機の平面図、第3図は同側面図、第
4図はスタビライザの側面図、第5図はブレーカの作動
説明図、第6図は従来のコンクリートダム構築工法によ
るダムコンクリートの打設順序の説明図、第7図は同コ
ンクリート打設説明図、第8図は従来のコンクリートダ
ム構築工法の説明図である。 20は散布機、21はブルドーザ、22は散布用ホッパ
ー、23はスタビライザ、25はブレーカ、27は骨材
、28はセメント。 第 4 図 第6図
Figure 1 is an explanatory diagram of the concrete dam construction method according to the present invention, Figure 2 is a plan view of the scatterer T1, Figure 3 is a side view of the same, Figure 4 is a side view of the stabilizer, and Figure 5 is the breaker. Fig. 6 is an explanatory diagram of the order of placing dam concrete using the conventional concrete dam construction method, Fig. 7 is an explanatory diagram of the same concrete pouring, and Fig. 8 is an explanatory diagram of the conventional concrete dam construction method. be. 20 is a spreader, 21 is a bulldozer, 22 is a spreading hopper, 23 is a stabilizer, 25 is a breaker, 27 is aggregate, and 28 is cement. Figure 4 Figure 6

Claims (1)

【特許請求の範囲】[Claims] ダム現場に搬入された骨材を敷均した後にこの骨材上に
セメントを散布し、骨材とセメントとを混合した後に締
固めるようにしたことを特徴とするコンクリートダム構
築工法。
A method of constructing a concrete dam, which is characterized in that after leveling the aggregate carried to the dam site, cement is spread on the aggregate, and the aggregate and cement are mixed and then compacted.
JP13371986A 1986-06-11 1986-06-11 Construction work of concrete dam Pending JPS62291308A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13371986A JPS62291308A (en) 1986-06-11 1986-06-11 Construction work of concrete dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13371986A JPS62291308A (en) 1986-06-11 1986-06-11 Construction work of concrete dam

Publications (1)

Publication Number Publication Date
JPS62291308A true JPS62291308A (en) 1987-12-18

Family

ID=15111303

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13371986A Pending JPS62291308A (en) 1986-06-11 1986-06-11 Construction work of concrete dam

Country Status (1)

Country Link
JP (1) JPS62291308A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010053598A (en) * 2008-08-28 2010-03-11 Kajima Corp Method of reusing green cut waste and concrete structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010053598A (en) * 2008-08-28 2010-03-11 Kajima Corp Method of reusing green cut waste and concrete structure

Similar Documents

Publication Publication Date Title
JP2020193557A (en) Bound dam and method for constructing the same
CN107117893A (en) The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration
EP0283225A2 (en) Apparatus for mixing, transporting and placing concrete
CN107287999A (en) Rigid pile composite foundation united drainage consolidation reinforces highway soft soil ground construction
ES8504302A1 (en) Mobile device for the in situ cold mixing and spreading of bitumen-coated products for road surfacings.
CN101886364B (en) Pavement paver capable of spanning central median for construction and construction method thereof
JPS62291308A (en) Construction work of concrete dam
JPH02263890A (en) Quick ground-preventing method and soil-coagulant
CN206092062U (en) Special protection device encircles at bottom of big circular tunnel flow surface of section
CN206127839U (en) Laying device of road base construction
JP2854427B2 (en) Road pavement method
Bass RCC construction–acceptable means and methods
JP4014448B2 (en) Solidifying material, solidifying material manufacturing equipment, solidifying material spraying equipment used for ground improvement work
JPH1072846A (en) Treatment method of soil
CN108755362A (en) Base cures cold regeneration construction method
JP2642258B2 (en) Concrete leveling method in RCD method
KR101139506B1 (en) Manufacturing method of rapidly hardening concrete by 2-step mixing with semi-remicon
JP2939552B2 (en) Joint structure
JPS5918804A (en) Construction of concrete cut-off wall for dam slope
CN110835903A (en) Bottom arch concrete protection device and method for water delivery tunnel in shape of horseshoe
RU2045605C1 (en) Concrete placing machine
JP3545641B2 (en) Backfill method
JPH0261590B2 (en)
JPH05306505A (en) Concrete paving construction method
JP3341541B2 (en) Backfilling method for buried objects