CN107117893A - The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration - Google Patents

The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration Download PDF

Info

Publication number
CN107117893A
CN107117893A CN201710215408.4A CN201710215408A CN107117893A CN 107117893 A CN107117893 A CN 107117893A CN 201710215408 A CN201710215408 A CN 201710215408A CN 107117893 A CN107117893 A CN 107117893A
Authority
CN
China
Prior art keywords
water
concrete
construction
pervious concrete
maintenance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710215408.4A
Other languages
Chinese (zh)
Inventor
姜允庆
赵新创
侯睿妮
崔传志
李永光
刘家亮
余艮乐
张仕龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical ANHUI XINLU CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201710215408.4A priority Critical patent/CN107117893A/en
Publication of CN107117893A publication Critical patent/CN107117893A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • C04B28/04Portland cements
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving
    • E01C7/142Mixtures or their components, e.g. aggregate
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00241Physical properties of the materials not provided for elsewhere in C04B2111/00
    • C04B2111/00284Materials permeable to liquids
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/0075Uses not provided for elsewhere in C04B2111/00 for road construction
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/20Resistance against chemical, physical or biological attack
    • C04B2111/29Frost-thaw resistance
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2201/00Mortars, concrete or artificial stone characterised by specific physical values
    • C04B2201/50Mortars, concrete or artificial stone characterised by specific physical values for the mechanical strength
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration, is related to technical field of building construction, it is characterised in that:Comprise the following steps, prepare construction, mix-design, stirring, transport, the shaping that paves, vibrate, conserve, joint-cutting, maintenance, maintenance.The inventive method is reasonable, easy to operate, work well.

Description

The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration
Technical field
The present invention relates to technical field of building construction, and in particular to the closely knit macrovoid pervious concrete pavement of plate vibration is applied The method of work.
Background technology
With the implementation and popularization of national sponge urban construction, many road engineering technical research mechanisms and designing unit are not Disconnected to carry out road surface dank material research and water-permeable pavement An attempt of design, strong construction enterprises are also to this progress tradition The innovation of construction technology, obtains a series of new results, plays a significant role in actual applications.In municipal engineering construction, with Cement concrete with water permeability is surface layer or the pavement of sub-surface and other pavement structures are applied based on cement concrete tradition The innovation and application of work technique, are the technological projects for putting forth effort in municipal engineering construction to study, promote.Anhui Province's Xin Lu construction projects Co., Ltd of group undertakes the construction of Fuyang City south of a city new district Fu Kanglu, Nanjing Road and appurtenant work and started, and constitutes know-how power Amount, carries out the research of pavement sub-surface permeable concrete material and construction technology, obtains innovative achievements and is applied to Multiple engineering projects, there is preferable economic benefit and social benefit.
Being built with reference to modern " sponge city " needs, and patent of the present invention can be widely applied to pavement surface layer and permeable face brick Formula pavement basis, square ground, parkway and parking lot etc., can also be used as major urban arterial highway dankness type sub-surface Deng.
The content of the invention
The technical problems to be solved by the invention be to overcome existing technological deficiency provide a kind of method rationally, operation side Just the method for the closely knit macrovoid pervious concrete pavement construction of plate vibration, worked well.
The technical problems to be solved by the invention are realized using following technical scheme:
The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration, it is characterised in that:Comprise the following steps,
Step 1: preparing construction:
I establishes and improve construction organization mechanism, and personnel, device configuration are in place;
II is familiar with construction drawing and relevant technical data, conscientiously carries out technical annotation in construction;
III march into the arena raw material by batch detection it is qualified;
Step 2: mix-design:Pervious concrete is to be used as coarse aggregate and cement, mineral admixture, additional by rubble The concrete with continuous pore structure and some strength that agent and water are formed after mix, hardening by a certain percentage;Reach strong Degree is high, the concrete of good water permeability, and match ratio wants multiple optimization design;
I design considerations:1)《Water-permeable cement concrete pavement technique code》CJJ/T135-2009
2)《Highway engineering cement and cement concrete testing regulations》JTG E42-2005
3)《Highway engineering is gathered materials testing regulations》JTG E30-2005
4) construction drawing requirement;
II mix-design:Design strength is C20.In mix-design, to ensure the strength grade of pervious concrete, From P.O42.5R class g cements, the mono- graded broken stones of particle diameter 5-10mm, the YY-I type high efficiency water reducing agents with gelling;
It is defined below by multi-scheme than choosing:
Water:Cement:Water reducer:Rubble=123:445:6.8:1720;
III analysis checking:The following form of analysis of experiments is carried out according to design mixture proportion,
Design requirement is met through analysis of experiments;
Step 3: stirring:
I according to quantities size and Design of Construction Organization requirement, using qualified forced mixer, mixer one Determine on the ground in scope, setting prevents the splicing equipment (the board-like bucket class of such as square) of water and material spilling, environmental protection and subtract Cleaning work after few work;Material is put into mixer respectively by with when feeding sequence during stirring;Using three feeding methods:First Mud stir about is added water after rubble after 1 minute, it is tentatively mixed, then puts into the YY-I types high efficiency water reducing agent progress of gelling fully Mix, mixing time 1.5 minutes, finally by the water of ormal weight, point 2-3 addition continues to stir 1.5-2 minutes;It is equal depending on stirring Even degree, can the proper extension mechanical agitation time, but no more than 2.5 minutes.Site inspection, compound should hold agglomerating, pine Hand vibration is bulk state;Compound will be timely used, and had isolation, air-dry and consolidated phenomenon and make waste disposal;
According to field measurement raw material water content in II construction, mix amount of water is adjusted;To ensure mix effect, moisture 2- 3 additions, it is strict to control the ratio of mud and add water the time, make into material quality and meet design requirement;Into material dry Site Detection, its Vigorous denseness control is tieed up in 25S between 35S;
III checks into material manual site, judges whether particles of aggregates wash cement slurry wraps up uniform, no cement mortar disengaging and Lower drop phenomenon, compound holding is agglomerating, and vibration of loosing one's grip, which dissipates, to be advisable;
Step 4: transport:Pervious concrete uses stiff mix, and initial set is fast, should not be using tank car transport.Scene can Transported using medium and small dump truck, and formulate the measure of mixture segregation in transportation that prevents, haul distance exceeds 500 meters or gas The temperature waterproof cloth of the application more than 15 DEG C is covered;Haulage time is short, maximum duration<Stirring during concrete initial set after m- input cement And discharging time-blanking, pave and the roller-compaction time, it must not be stopped in transportation;
Step 5: the shaping that paves:Pervious concrete is fast because of its initial set, and paving must be timely rapidly, to ensure consolidation effect, often Layer paving thickness 10cm-15cm, during multilayer pouring, when must not exceed bottom concrete initial set to the superiors' construction deadline Between, find flatness accurately with floating rule, then vibrated with plate vibrator;
Step 6: vibrating:Without vibrating or tamping strongly in paving process, first struck off after discharging with floating rule, then Gently shaken the compound after paving with plate vibrator low frequency;Without using large-tonnage high frequency rolling apparatus, concrete mistake otherwise can be made In closely knit, cause surface bleeding to reduce effective drainage porosity, influence permeable effect, high speed vibrator can also make cement slurry from thick bone Expect surface segregation, flow into bottom and form an impermeable stratum, material is lost water penetration;
Step 7: maintenance:Pervious concrete maintenance is link more important in work progress, is preferably taken after bedding felt-cloth Watering maintenance, felt-cloth keeps moistening in whole curing time, three main points is noted during watering:Water spray dynamics, spraying time and Infiltration degree;
Water spray dynamics:Water pipe can not be held high, and concrete surface must not be patted or hammered to water column, and current should be formed carefully during watering Rain shape, to ensure that concrete surface stone is not destroyed by powerful current;
Spraying time:Should not at noon pavement temperature highest when sprayed with cold water, prevent concrete from drastically shrinking formation and splitting Line, is preferably timed watering in daily morning and at dusk;
Infiltration degree:Aspect concrete keeps must not having current generation in moistening, structure sheaf, can take double-deck maintenance side Method, that is, descend paving plastic film, and upper lid felt-cloth covers health of sprinkling water again, and curing time is 14 days;
Step 8: joint-cutting:Pervious concrete joint-cutting, time interval is unsuitable long, 12 hours after general 15 DEG C of makings of temperature Left and right joint-cutting, temperature is reduced or increased, and the suitable proper extension of lancing time or postponement, design parameter are determined with field measurement, joint-cutting When to occur without flash and obscission as standard, spacing every 5m together, seam depth 40mm, slit width 6mm, the filler cementation of fissures;
Step 9: maintenance, maintenance:
I pavement road bed should have enough strength and stabilities;
(1) when being impervious stratum, if 1% to 2% slope is towards gutter, be easy to the discharge of water, basic top surface with it is permeable 3cm blotters are set between concrete layer, to ensure pervious concrete making quality;
(2) when intensity higher water penetration gravel soil property is in basis, longitudinal drainage ditch can not be set, road surface water directly penetrates into ground Pervious concrete layer construction can be carried out after lower recharge of groundwater, basic top surface grinding compacting and leveling;
II grading of aggregates meets design requirement, and its crush values, clay content and elongated particles should be detected before marching into the arena.Crush values With elongated particles are exceeded will directly affect pervious concrete intensity, clay content is excessive also to influence pervious concrete permeability rate;
III strict control feeding sequence;
Preferably covered in IV transport with waterproof cloth, prevent moisture loss and pellet from tumbling, the time should be controlled within 20 minutes;
V is not more than vibration force coverage, general single berth using the compacting of Small-scale Flat vibrator, a paving thickness Thickness is not more than 15cm;
VI maintenance process can not be accumulation of heat protection, prevent current to scatter and disappear, take saturating directly with felt-cloth covering watering maintenance After water coagulation soil surface is integrally covered with film, then in the method for film surface laying geotextiles, then maintenance of sprinkling water, structure sheaf Interior to keep moist, curing time is 14 days;
VII maintenance expires, and core detection its intensity, scene carry out water penetration detection;
Filler in the step 8 is 851 polyurethane.
Beneficial effects of the present invention are:1. dry plate vibration air-free concrete is used, construction technology is simple, and input is set Standby few, construction quality is preferably controlled.
2. identical with normal concrete production technology, coarse aggregate matches somebody with somebody particulate formula rubble, bill of material one, sorting side using single-stage Just, procedure quality is preferably controlled.
3. maintenance can be covered or be atomized after decking and rolling shaping, speed of application is fast, efficiency high.
Embodiment
In order that the technical means, the inventive features, the objects and the advantages of the present invention are easy to understand, enter below One step illustrates the present invention.
The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration, it is characterised in that:Comprise the following steps,
Step 1: preparing construction:
I establishes and improve construction organization mechanism, and personnel, device configuration are in place;
II is familiar with construction drawing and relevant technical data, conscientiously carries out technical annotation in construction;
III march into the arena raw material by batch detection it is qualified;
Step 2: mix-design:Pervious concrete is to be used as coarse aggregate and cement, mineral admixture, additional by rubble The concrete with continuous pore structure and some strength that agent and water are formed after mix, hardening by a certain percentage;Reach strong Degree is high, the concrete of good water permeability, and match ratio wants multiple optimization design;
I design considerations:1)《Water-permeable cement concrete pavement technique code》CJJ/T135-2009
2)《Highway engineering cement and cement concrete testing regulations》JTG E42-2005
3)《Highway engineering is gathered materials testing regulations》JTG E30-2005
4) construction drawing requirement;
II mix-design:Design strength is C20.In mix-design, to ensure the strength grade of pervious concrete, From P.O42.5R class g cements, the mono- graded broken stones of particle diameter 5-10mm, the YY-I type high efficiency water reducing agents with gelling;
It is defined below by multi-scheme than choosing:
Water:Cement:Water reducer:Rubble=123:445:6.8:1720;
III analysis checking:The following form of analysis of experiments is carried out according to design mixture proportion,
Design requirement is met through analysis of experiments;
Step 3: stirring:
I according to quantities size and Design of Construction Organization requirement, using qualified forced mixer, mixer one Determine on the ground in scope, setting prevents the splicing equipment (the board-like bucket class of such as square) of water and material spilling, environmental protection and subtract Cleaning work after few work;Material is put into mixer respectively by with when feeding sequence during stirring;Using three feeding methods:First Mud stir about is added water after rubble after 1 minute, it is tentatively mixed, then puts into the YY-I types high efficiency water reducing agent progress of gelling fully Mix, mixing time 1.5 minutes, finally by the water of ormal weight, point 2-3 addition continues to stir 1.5-2 minutes;It is equal depending on stirring Even degree, can the proper extension mechanical agitation time, but no more than 2.5 minutes.Site inspection, compound should hold agglomerating, pine Hand vibration is bulk state;Compound will be timely used, and had isolation, air-dry and consolidated phenomenon and make waste disposal;
According to field measurement raw material water content in II construction, mix amount of water is adjusted;To ensure mix effect, moisture 2- 3 additions, it is strict to control the ratio of mud and add water the time, make into material quality and meet design requirement;Into material dry Site Detection, its Vigorous denseness control is tieed up in 25S between 35S;
III checks into material manual site, judges whether particles of aggregates wash cement slurry wraps up uniform, no cement mortar disengaging and Lower drop phenomenon, compound holding is agglomerating, and vibration of loosing one's grip, which dissipates, to be advisable;
Step 4: transport:Pervious concrete uses stiff mix, and initial set is fast, should not be using tank car transport.Scene can Transported using medium and small dump truck, and formulate the measure of mixture segregation in transportation that prevents, haul distance exceeds 500 meters or gas The temperature waterproof cloth of the application more than 15 DEG C is covered;Haulage time is short, maximum duration<Stirring during concrete initial set after m- input cement And discharging time-blanking, pave and the roller-compaction time, it must not be stopped in transportation;
Step 5: the shaping that paves:Pervious concrete is fast because of its initial set, and paving must be timely rapidly, to ensure consolidation effect, often Layer paving thickness 10cm-15cm, during multilayer pouring, when must not exceed bottom concrete initial set to the superiors' construction deadline Between, find flatness accurately with floating rule, then vibrated with plate vibrator;
Step 6: vibrating:Without vibrating or tamping strongly in paving process, first struck off after discharging with floating rule, then Gently shaken the compound after paving with plate vibrator low frequency;Without using large-tonnage high frequency rolling apparatus, concrete mistake otherwise can be made In closely knit, cause surface bleeding to reduce effective drainage porosity, influence permeable effect, high speed vibrator can also make cement slurry from thick bone Expect surface segregation, flow into bottom and form an impermeable stratum, material is lost water penetration;
Step 7: maintenance:Pervious concrete maintenance is link more important in work progress, is preferably taken after bedding felt-cloth Watering maintenance, felt-cloth keeps moistening in whole curing time, three main points is noted during watering:Water spray dynamics, spraying time and Infiltration degree;
Water spray dynamics:Water pipe can not be held high, and concrete surface must not be patted or hammered to water column, and current should be formed carefully during watering Rain shape, to ensure that concrete surface stone is not destroyed by powerful current;
Spraying time:Should not at noon pavement temperature highest when sprayed with cold water, prevent concrete from drastically shrinking formation and splitting Line, is preferably timed watering in daily morning and at dusk;
Infiltration degree:Aspect concrete keeps must not having current generation in moistening, structure sheaf, can take double-deck maintenance side Method, that is, descend paving plastic film, and upper lid felt-cloth covers health of sprinkling water again, and curing time is 14 days;
Step 8: joint-cutting:Pervious concrete joint-cutting, time interval is unsuitable long, 12 hours after general 15 DEG C of makings of temperature Left and right joint-cutting, temperature is reduced or increased, and the suitable proper extension of lancing time or postponement, design parameter are determined with field measurement, joint-cutting When to occur without flash and obscission as standard, spacing every 5m together, seam depth 40mm, slit width 6mm, the filler cementation of fissures;
Step 9: maintenance, maintenance:
I pavement road bed should have enough strength and stabilities;
(2) when being impervious stratum, if 1% to 2% slope is towards gutter, be easy to the discharge of water, basic top surface with it is permeable 3cm blotters are set between concrete layer, to ensure pervious concrete making quality;
(2) when intensity higher water penetration gravel soil property is in basis, longitudinal drainage ditch can not be set, road surface water directly penetrates into ground Pervious concrete layer construction can be carried out after lower recharge of groundwater, basic top surface grinding compacting and leveling;
II grading of aggregates meets design requirement, and its crush values, clay content and elongated particles should be detected before marching into the arena.Crush values With elongated particles are exceeded will directly affect pervious concrete intensity, clay content is excessive also to influence pervious concrete permeability rate;
III strict control feeding sequence;
Preferably covered in IV transport with waterproof cloth, prevent moisture loss and pellet from tumbling, the time should be controlled within 20 minutes;
V is not more than vibration force coverage, general single berth using the compacting of Small-scale Flat vibrator, a paving thickness Thickness is not more than 15cm;
VI maintenance process can not be accumulation of heat protection, prevent current to scatter and disappear, take saturating directly with felt-cloth covering watering maintenance After water coagulation soil surface is integrally covered with film, then in the method for film surface laying geotextiles, then maintenance of sprinkling water, structure sheaf Interior to keep moist, curing time is 14 days;
VII maintenance expires, and core detection its intensity, scene carry out water penetration detection;
Filler in the step 8 is 851 polyurethane.
The material and equipment used:
Material:
Pervious concrete is similar to cement concrete construction, and no fine granules match somebody with somebody single-stage particle diameter 5mm-10mm high intensity Rubble mixes synthesis material as aggregate, incorporation cement and high performance additive;
Cement:Portland cement is preferably used, strength grade is not less than 42.5, and quality should meet existing national standards 《Common portland cement》GB175 requirement;
Additive:Using preferable YY-I types high efficiency water reducing agent (liquid) (the technical requirements reference of gelatinization results《Outside concrete Plus agent》GB8076-2008) manufacturer be Hefei Yong Yuan building materials Co., Ltd;
Specific Testing index see the table below:
Rubble:It is required that quality is hard, clean, meet cement concrete construction code requirement, particle diameter is 5mm-10mm, pin The poor pellet of sheet, specification see the table below:
Water:City domestic water;
Equipment:
Equipment such as following table need to be equipped with:
Establish Safety assurance measures:
Safety in production organization is set up, every production safety management system is established and improve, strengthens safety inspection and carries out Safety inspection is recorded, and every safety measure is fulfilled;
Carry out security incident response and Rescue Plan, it is ensured that fund input needed for safety in production;
Every safety regulation for operations is strictly observed, special equipment operating personnel is accomplished to take appointment with certificate;
The dangerous position such as job site gateway, along the line intersection, temporary electricity will set up safety protection facility, set bright Aobvious safety signses;
It is determined that environmentally friendly safeguard measure:
In residential block construction, night transport vehicle must not blow a whistle, be disturbed residents with reducing noise, it is ensured that construction noise meets《Building Construction site noise limit is put》(GB12523) require, 62 decibels are not more than between daytime, night is not more than 55 decibels;
Mixer surrounding sets sedimentation basin, gutter, and waste water is discharged after precipitation, and stirring personnel will wear protective mask;
To prevent concrete pickup construction site, the certain limit of mixer bottom need to use protective plate fortification measure;
When stirring slurry, stirring canopy is set, to prevent dust pollution;
Fine environment is created, building site Office Area, living area clean hygiene, daily personnel assigned are cleaned;
Building waste and house refuse clear up outward transport at any time, are stacked by appointed place.After the completion of construction, place is flattened, is done Clear, live net to the complete material of work, after construction completion, surplus material will be withdrawn in time;
Work responsibility system is established and improve, civilized construction responsibility is fulfilled.
The general principle and principal character and advantages of the present invention of the present invention has been shown and described above.The technology of the industry Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the simply explanation described in above-described embodiment and specification is originally The principle of invention, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these changes Change and improvement all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and its Equivalent thereof.

Claims (2)

1. the method for the closely knit macrovoid pervious concrete pavement construction of plate vibration, it is characterised in that:Comprise the following steps,
Step 1: preparing construction:
I establishes and improve construction organization mechanism, and personnel, device configuration are in place;
II is familiar with construction drawing and relevant technical data, conscientiously carries out technical annotation in construction;
III march into the arena raw material by batch detection it is qualified;
Step 2: mix-design:Pervious concrete be by rubble as coarse aggregate and cement, mineral admixture, additive and The concrete with continuous pore structure and some strength that water is formed after mix, hardening by a certain percentage;Reach intensity it is high, The concrete of good water permeability, match ratio wants multiple optimization design;
I design considerations:1)《Water-permeable cement concrete pavement technique code》CJJ/T135-2009
2)《Highway engineering cement and cement concrete testing regulations》JTG E42-2005
3)《Highway engineering is gathered materials testing regulations》JTG E30-2005
4) construction drawing requirement;
II mix-design:Design strength is C20.In mix-design, to ensure the strength grade of pervious concrete, select P.O42.5R class g cements, the mono- graded broken stones of particle diameter 5-10mm, the YY-I type high efficiency water reducing agents with gelling;
It is defined below by multi-scheme than choosing:
Water:Cement:Water reducer:Rubble=123:445:6.8:1720;
III is carried out after analysis checking, it is ensured that meet design requirement;
Step 3: stirring:
I according to quantities size and Design of Construction Organization requirement, using qualified forced mixer, the certain model of mixer On ground in enclosing, setting prevents the splicing equipment (the board-like bucket class of such as square) of water and material spilling, environmental protection and reduction work Cleaning work afterwards;Material is put into mixer respectively by with when feeding sequence during stirring;Using three feeding methods:First rubble After add water mud stir about after 1 minute, make it tentatively mix, then put into the YY-I type high efficiency water reducing agents of gelling fully to be mixed Close, mixing time 1.5 minutes, finally by the water of ormal weight, point 2-3 addition continues to stir 1.5-2 minutes;Depending on stirring Degree, can the proper extension mechanical agitation time, but no more than 2.5 minutes.Site inspection, compound should be held agglomerating, loose one's grip Vibration is bulk state;Compound will be timely used, and had isolation, air-dry and consolidated phenomenon and make waste disposal;
According to field measurement raw material water content in II construction, mix amount of water is adjusted;To ensure mix effect, moisture 2-3 times Add, it is strict to control the ratio of mud and add water the time, make into material quality and meet design requirement;Into material dry Site Detection, it is tieed up Vigorous denseness control is in 25S between 35S;
III checks into material manual site, judges whether particles of aggregates wash cement slurry wraps up uniform, and no cement mortar departs from and lower drop Phenomenon, compound holding is agglomerating, and vibration of loosing one's grip, which dissipates, to be advisable;
Step 4: transport:Pervious concrete uses stiff mix, and initial set is fast, should not be using tank car transport.Scene can be used Medium and small dump truck transport, and the measure of mixture segregation in transportation that prevents is formulated, haul distance is super beyond 500 meters or temperature 15 DEG C of application waterproof cloth are crossed to cover;Haulage time is short, maximum duration<During concrete initial set it is m- input cement after stirring and go out M- blanking during material, pave and the roller-compaction time, must not be stopped in transportation;
Step 5: the shaping that paves:Pervious concrete is fast because of its initial set, and paving must be timely rapidly, to ensure consolidation effect, every layer of stand Thickness 10cm-15cm is spread, during multilayer pouring, the bottom concrete initial set time must not be exceeded to the superiors' construction deadline, Find flatness accurately with floating rule, then vibrated with plate vibrator;
Step 6: vibrating:Without vibrating or tamping strongly in paving process, first struck off after discharging with floating rule, then with flat Deck vibrator low frequency gently shakes the compound after paving;Without using large-tonnage high frequency rolling apparatus, otherwise concrete can be made excessively close It is real, cause surface bleeding to reduce effective drainage porosity, influence permeable effect, high speed vibrator can also make cement slurry from coarse aggregate table Face is isolated, and is flowed into bottom and is formed an impermeable stratum, material is lost water penetration;
Step 7: maintenance:Pervious concrete maintenance is link more important in work progress, preferably takes and is sprinkled water after bedding felt-cloth Maintenance, felt-cloth keeps moistening in whole curing time, and three main points are noted during watering:Water spray dynamics, spraying time and infiltration Degree;
Water spray dynamics:Water pipe can not be held high, and concrete surface must not be patted or hammered to water column, and current should form drizzle during watering Shape, to ensure that concrete surface stone is not destroyed by powerful current;
Spraying time:Should not at noon pavement temperature highest when sprayed with cold water, prevent concrete from drastically shrinking to form crackle, preferably Watering is timed in daily morning and dusk;
Infiltration degree:Aspect concrete keeps must not having current generation in moistening, structure sheaf, can take double-deck maintenance process, i.e., Lower paving plastic film, upper lid felt-cloth covers health of sprinkling water again, and curing time is 14 days;
Step 8: joint-cutting:Pervious concrete joint-cutting, time interval is unsuitable long, 12 hours or so after general 15 DEG C of makings of temperature Joint-cutting, temperature reduction or increases, the suitable proper extension of lancing time or postponement, and design parameter is determined with field measurement, during joint-cutting with It is standard to occur without flash and obscission, and spacing together, stitches depth 40mm, slit width 6mm, the filler cementation of fissures every 5m;
Step 9: maintenance, maintenance:
I pavement road bed should have enough strength and stabilities;
(1) when being impervious stratum, if 1% to 2% slope is towards gutter, it is easy to the discharge of water, basic top surface and permeable coagulation 3cm blotters are set between soil layer, to ensure pervious concrete making quality;
(2) when intensity higher water penetration gravel soil property is in basis, longitudinal drainage ditch can not be set, road surface water directly permeates the ground benefit Underground water is filled, pervious concrete layer construction can be carried out after basic top surface grinding compacting and leveling;
II grading of aggregates meets design requirement, and its crush values, clay content and elongated particles should be detected before marching into the arena.Crush values and pin Sheet content overproof will directly affect pervious concrete intensity, and clay content is excessive also to influence pervious concrete permeability rate;
III strict control feeding sequence;
Preferably covered in IV transport with waterproof cloth, prevent moisture loss and pellet from tumbling, the time should be controlled within 20 minutes;
V using the compacting of Small-scale Flat vibrator, and a paving thickness is not more than vibration force coverage, and general single berth is thick not More than 15cm;
VI maintenance process can not be accumulation of heat protection, prevent current to scatter and disappear, take permeable mixed directly with felt-cloth covering watering maintenance After solidifying soil surface is integrally covered with film, then protected in the method for film surface laying geotextiles, then maintenance of sprinkling water, structure sheaf Humidity is held, curing time is 14 days;
VII maintenance expires, and core detection its intensity, scene carry out water penetration detection.
2. the method for the closely knit macrovoid pervious concrete pavement construction of plate vibration according to claim 1, its feature exists In:Filler in the step 8 is 851 polyurethane.
CN201710215408.4A 2017-04-03 2017-04-03 The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration Pending CN107117893A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710215408.4A CN107117893A (en) 2017-04-03 2017-04-03 The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710215408.4A CN107117893A (en) 2017-04-03 2017-04-03 The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration

Publications (1)

Publication Number Publication Date
CN107117893A true CN107117893A (en) 2017-09-01

Family

ID=59725572

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710215408.4A Pending CN107117893A (en) 2017-04-03 2017-04-03 The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration

Country Status (1)

Country Link
CN (1) CN107117893A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503266A (en) * 2017-09-09 2017-12-22 泰州市好友体育设施科技有限公司 Basis uses the plastic cement race track and its construction method of pervious concrete
CN107576781A (en) * 2017-09-15 2018-01-12 中国葛洲坝集团勘测设计有限公司 A kind of device and method for determining pervious concrete service behaviour
CN108505413A (en) * 2018-04-16 2018-09-07 黄河三角洲京博化工研究院有限公司 A kind of rapid constructing method of single layer pervious concrete
CN108585668A (en) * 2018-03-29 2018-09-28 重庆建工第七建筑工程有限责任公司 Creepage concrete construction technology
CN109629377A (en) * 2018-12-27 2019-04-16 江苏诚意工程技术研究院有限公司 A kind of pervious concrete construction method
CN110144790A (en) * 2019-05-05 2019-08-20 武汉开思新材料有限公司 A kind of construction method of water permeable concrete
CN110409245A (en) * 2019-06-14 2019-11-05 湖南交通国际经济工程合作有限公司 A kind of construction of cement concrete road surface variance control method
CN110747709A (en) * 2019-10-30 2020-02-04 广西壮族自治区城乡规划设计院 Maintenance treatment method for asphalt pavement of high-grade road
CN112726342A (en) * 2020-12-26 2021-04-30 杭州雷力信息科技有限公司 Construction method of municipal road surface pervious concrete
CN113320007A (en) * 2021-06-11 2021-08-31 江苏瑞皇新型建材有限公司 Preparation method, preparation device and application of colored pervious concrete
CN113943119A (en) * 2021-03-27 2022-01-18 西安科技大学 Construction method for paving pavement base course by adopting magnesium slag-based cementing material
CN115198693A (en) * 2022-07-18 2022-10-18 国网江苏省电力有限公司经济技术研究院 Construction method and construction equipment for water conservancy dike
CN115928525A (en) * 2022-09-21 2023-04-07 保利长大工程有限公司 Construction method of tunnel porous concrete permeable base layer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103304250A (en) * 2013-04-27 2013-09-18 重庆建工住宅建设有限公司 High water-storage concrete
CN106046979A (en) * 2016-06-28 2016-10-26 上海砼仁环保技术发展有限公司 Noctilucent finish coat protective agent for permeable concrete pavements, and pavement containing noctilucent finish coat protective agent and construction method thereof
CN106145830A (en) * 2016-08-08 2016-11-23 广州大学 A kind of pervious concrete and construction technology thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103304250A (en) * 2013-04-27 2013-09-18 重庆建工住宅建设有限公司 High water-storage concrete
CN106046979A (en) * 2016-06-28 2016-10-26 上海砼仁环保技术发展有限公司 Noctilucent finish coat protective agent for permeable concrete pavements, and pavement containing noctilucent finish coat protective agent and construction method thereof
CN106145830A (en) * 2016-08-08 2016-11-23 广州大学 A kind of pervious concrete and construction technology thereof

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
上海园林(集团)有限公司: "《上海世博会园区景观绿化建设》", 31 December 2010 *
姜成等: "透水混凝土路面透水性能的影响因素研究", 《浙江建筑》 *
李迁: "《现代混凝土技术应用研究》", 31 March 2016 *
谭碧清: "《新旧市政工程施工与质量验收规范对照详解》", 31 October 2010 *
透水混凝土性能及构造调控研究: "王啸夫等", 《山西建筑》 *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503266A (en) * 2017-09-09 2017-12-22 泰州市好友体育设施科技有限公司 Basis uses the plastic cement race track and its construction method of pervious concrete
WO2019047372A1 (en) * 2017-09-09 2019-03-14 朱志华 Plastic running track using permeable concrete as base and construction method therefor
CN107576781A (en) * 2017-09-15 2018-01-12 中国葛洲坝集团勘测设计有限公司 A kind of device and method for determining pervious concrete service behaviour
CN108585668A (en) * 2018-03-29 2018-09-28 重庆建工第七建筑工程有限责任公司 Creepage concrete construction technology
CN108505413A (en) * 2018-04-16 2018-09-07 黄河三角洲京博化工研究院有限公司 A kind of rapid constructing method of single layer pervious concrete
CN109629377A (en) * 2018-12-27 2019-04-16 江苏诚意工程技术研究院有限公司 A kind of pervious concrete construction method
CN110144790A (en) * 2019-05-05 2019-08-20 武汉开思新材料有限公司 A kind of construction method of water permeable concrete
CN110409245A (en) * 2019-06-14 2019-11-05 湖南交通国际经济工程合作有限公司 A kind of construction of cement concrete road surface variance control method
CN110747709A (en) * 2019-10-30 2020-02-04 广西壮族自治区城乡规划设计院 Maintenance treatment method for asphalt pavement of high-grade road
CN110747709B (en) * 2019-10-30 2021-09-21 广西壮族自治区城乡规划设计院 Maintenance treatment method for asphalt pavement of high-grade road
CN112726342A (en) * 2020-12-26 2021-04-30 杭州雷力信息科技有限公司 Construction method of municipal road surface pervious concrete
CN113943119A (en) * 2021-03-27 2022-01-18 西安科技大学 Construction method for paving pavement base course by adopting magnesium slag-based cementing material
CN113320007A (en) * 2021-06-11 2021-08-31 江苏瑞皇新型建材有限公司 Preparation method, preparation device and application of colored pervious concrete
CN115198693A (en) * 2022-07-18 2022-10-18 国网江苏省电力有限公司经济技术研究院 Construction method and construction equipment for water conservancy dike
CN115928525A (en) * 2022-09-21 2023-04-07 保利长大工程有限公司 Construction method of tunnel porous concrete permeable base layer

Similar Documents

Publication Publication Date Title
CN107117893A (en) The method of the closely knit macrovoid pervious concrete pavement construction of plate vibration
KR101444989B1 (en) Road surfacing, method of constructing road surfacing, and concrete form
CN101293763A (en) Water permeable concrete and pavement construction method
CN102776897B (en) Wash apron anti-settling anti-cracking construction method and structure
CN108101456A (en) A kind of big water absorption rate coarse aggregate high-performance marine concrete and its construction
CN107226648A (en) A kind of diamond dust mine tailing composite sand base ecological permeable bricks and preparation method thereof
CN107034767A (en) A kind of full pervious concrete pavement structure of regeneration aggregate and its construction method
CN106045399A (en) Water permeable brick and preparation method thereof
KR100957790B1 (en) Pavement material comprising loess and excution method using the same
CN107630395A (en) A kind of maize straw regenerates the permeable Footpath brick of lightweight aggregate concrete
CN108532401A (en) A kind of coral sand concrete road surface structure and its construction method
KR20190006233A (en) Construction method of water-permeable pavement with excellent properties of stability, economy and conduct ability for pavement and road
CN110041005A (en) A kind of pervious concrete reinforcing agent and preparation method thereof and construction technology
CN103553471A (en) Method for manufacturing water permeable brick from waste concrete, and pavement method of water permeable brick
CN104514217B (en) Expansive soil foundation modifying agent and improvement construction method
CN207362616U (en) A kind of paving structure of water-permeable brick
CN106278005A (en) Inorganic system pervious concrete and construction technology thereof and application
CN106677003A (en) Pervious concrete structure and preparation method thereof
CN207244376U (en) A kind of creepage concrete compression-resistance pavement structure
CN113755176A (en) In-situ hardened soil road and soil curing material and preparation and construction method thereof
JP4699081B2 (en) Water retentive pavement and its pavement method
CN206828912U (en) A kind of full pervious concrete pavement structure of regeneration aggregate
CN109056455A (en) A kind of sponge urban construction permeable side walk slab and method for paving
CN106587887B (en) Roadbed subbase course material and its preparation method made from a kind of solidification tailings and tail clay
KR101185626B1 (en) Environmentally-friendly construction method for mountain reservoir using solidified material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170901