JPS62160314A - Construction work of continuous underground wall - Google Patents

Construction work of continuous underground wall

Info

Publication number
JPS62160314A
JPS62160314A JP135786A JP135786A JPS62160314A JP S62160314 A JPS62160314 A JP S62160314A JP 135786 A JP135786 A JP 135786A JP 135786 A JP135786 A JP 135786A JP S62160314 A JPS62160314 A JP S62160314A
Authority
JP
Japan
Prior art keywords
piles
underground wall
pile
concrete
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP135786A
Other languages
Japanese (ja)
Inventor
Hiroshi Ooya
浩 大矢
Toshie Konno
紺野 勤衛
Hiroaki Sugiyama
浩章 杉山
Masatsune Ogawa
小川 正恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP135786A priority Critical patent/JPS62160314A/en
Publication of JPS62160314A publication Critical patent/JPS62160314A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To obtain an underground wall whose concrete is well adhered to master pile by a method in which chain materials are charged into the space in the surrounding of a master pile driven into a pit, and while the chain materials are pulled up, the ground between it and the master pile is excavated and soil on the surface of the master pile is removed by vertically moving the chain material. CONSTITUTION:In constructing a continuous underground wall, master piles 1 are driven into pits 3 excavated at a given interval, and chains 2 are charged into the surrounding of the piles 1. A solidifying agent 4 is then packed into the space between a flange 11 and the pit wall 4, the ground between the piles 1 is excavated by a bucket 7, etc., to form a trench 8. The chains 2 are pulled up as the excavation proceeds to avoid obstruction to the excavation. After the ending of the excavation between the piles 1, concrete is placed into the trench 8 to construct an underground wall. Soil adhered to the surfaces of the piles 1 is removed by vertically moving the chains 2 in order to improve the adhesion between the concrete and the piles 1.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明はH型抗、ボックス型杭等の親杭間を開削し、こ
の開削溝内にコンクリートを打設して連続したコンクリ
ート壁を114築する連続地中壁工法に関するものであ
る。
[Detailed Description of the Invention] <Industrial Application Field> The present invention involves excavating between parent piles such as H-type piles and box-type piles, and pouring concrete into the excavated grooves to form a continuous concrete wall of 114 mm. This relates to the continuous underground wall construction method.

〈従来の技術〉 ボックス杭やH型抗等からなる親杭を使用して連続した
地中壁を構築する方法が存在する。
<Prior Art> There is a method of constructing a continuous underground wall using parent piles such as box piles and H-shaped piles.

この構築方法は、まず地中にヘントナイト液等の泥水を
充満させて開設した孔内に親杭を建込む。
In this construction method, a parent pile is first built into a hole created by filling the ground with muddy water such as hentonite liquid.

次に、建込んだ親杭のフランジと孔壁との間にモルタル
等を打設する。
Next, mortar or the like is placed between the flange of the erected parent pile and the hole wall.

さらに親杭のリブ面が接する孔内空間にコンクリートや
砂利等を充填して親杭を固定する。
Furthermore, the space in the hole where the rib surface of the parent pile touches is filled with concrete, gravel, etc. to fix the parent pile.

次に親杭間を開削し、この開削溝内にコンクリートを連
続打設して地中壁を構築する方法である。
Next, an excavation is made between the main piles, and concrete is continuously poured into the excavated groove to construct an underground wall.

く本発明が解決しようとする問題点〉 上記した池中壁の構築方法には次のような問題点が存在
する。
Problems to be Solved by the Present Invention> The above-described method of constructing a pond wall has the following problems.

(イ)親杭間を開削する場合、親杭にぎりぎりまで接近
して掘削することは非常に困難である。
(b) When excavating between the parent piles, it is extremely difficult to excavate as close as possible to the parent piles.

そのため、親杭の周囲に未掘削の土砂がそのまま残存し
綺麗に取り除くことが困難である。
Therefore, unexcavated earth and sand remains around the parent pile and is difficult to remove cleanly.

(ロ)親杭の周囲には泥水および親杭固定用の貧配合モ
ルタルやシルトモルタル等が付着している。
(b) Muddy water, poorly mixed mortar for fixing the main pile, silt mortar, etc. are attached to the area around the main pile.

そのため親杭間に形成した開削溝内にコンクリートを打
設とき、親杭とコンクリートとの一体化が困難となり、
構造体としての強度が低下する。
Therefore, when pouring concrete into the trench formed between the main piles, it becomes difficult to integrate the main piles with the concrete.
The strength of the structure decreases.

く本発明の目的〉 本発明は以上のような問題点を解決するためになされた
もので、親杭とコンクリートとの付着性が良好で、コン
クリートと親杭の一体化が確実に行える、連続地中壁工
法を提供することを目的とする。
OBJECT OF THE INVENTION The present invention has been made to solve the above-mentioned problems. The purpose is to provide an underground wall construction method.

く本発明の構成〉 以下、図面を参照しながら本発明の一実施例について説
明する。
Configuration of the Present Invention> An embodiment of the present invention will be described below with reference to the drawings.

[本発明に使用する充填材] 本発明では、親杭1の周囲に充填する充填材として鎖材
2を使用する。
[Filler used in the present invention] In the present invention, the chain material 2 is used as a filler to be filled around the parent pile 1.

この鎖材2は多数の小形リング環を接続して形成した硬
質あるいは軟質の公知の部材を使用することができる。
This chain member 2 may be a known hard or soft member formed by connecting a large number of small rings.

[施工方法] 〈1〉穿孔 池中壁の構築方向に所定の間隔で孔3を開設する。[Construction method] <1> Perforation Holes 3 are opened at predetermined intervals in the construction direction of the pond wall.

く2〉親杭の建込み 次にこの孔3内に親杭1をクレーン等を使って建込む。2〉Erecting the main pile Next, the parent pile 1 is erected into this hole 3 using a crane or the like.

く3〉鎖材の投入(第1.2図) 次に親杭1の周囲に鎖材2を投入して親杭1を固定する
3> Inserting chain material (Fig. 1.2) Next, chain material 2 is introduced around the main pile 1 to fix the main pile 1.

さらに、ボックス型の親杭1内およびフランジ11の外
表面と孔壁との間にコンクリートやモルタル等の固結材
4を充填する。
Further, a consolidating material 4 such as concrete or mortar is filled inside the box-shaped main pile 1 and between the outer surface of the flange 11 and the hole wall.

鎖材2の投入作業と、固結材4の充填作業を並行して行
う場合には、固結材4の天端より鎖材2の天端が常に高
くなるように、鎖材2を投入すると親杭1の安定性を確
保できる。
When adding the chain material 2 and filling the consolidation material 4 in parallel, insert the chain material 2 so that the top of the chain material 2 is always higher than the top of the consolidation material 4. Then, the stability of the main pile 1 can be ensured.

また親杭1のフランジ11面と孔壁との間に固結材4を
充填しても、リブ12面側には鎖材2が存在するので固
結材4の回り込みが規制される。
Furthermore, even if the consolidation material 4 is filled between the flange 11 surface of the parent pile 1 and the hole wall, the presence of the chain material 2 on the rib 12 surface prevents the consolidation material 4 from going around.

く4〉親杭間の開削(第3図) 鎖材2の投入を完了したら、泥水5を充満させなから親
杭1間をパケット7等で開削して開削溝8を形成する。
4> Cutting between the main piles (Fig. 3) After completing the insertion of the chain material 2, cut the space between the main piles 1 with a packet 7 or the like to form the cut groove 8 without filling with muddy water 5.

この開削作業に際して、開削の障害とならないように開
削溝8の底面より低い位置に銀材2層が位置するよう、
開削の進行に応じて鎖材2を順次引き揚げる。
During this excavation work, so that the two layers of silver material are located at a position lower than the bottom surface of the excavation groove 8 so as not to become an obstacle to the excavation.
The chain members 2 are sequentially pulled up as the excavation progresses.

そのため、鎖材2の内部に入り込んだ掘削土砂等は、鎖
材2を引き揚げることによって容易に排出される。
Therefore, excavated soil and the like that have entered the inside of the chain material 2 can be easily discharged by pulling up the chain material 2.

また鎖材2を引き揚げるとき、鎖材2の凹凸が親杭1の
外表や親杭1の周辺に付着するモルタルや土砂等の付着
物を取り除いていく。
Further, when the chain material 2 is pulled up, the unevenness of the chain material 2 removes deposits such as mortar and earth and sand adhering to the outer surface of the parent pile 1 and the periphery of the parent pile 1.

く5〉コンクリートの打設 親杭1間の開削が完了したらこの開削溝8内にコンクリ
ートを打設して地中壁6を構築する。
5> Casting concrete Once the excavation between the main piles 1 is completed, concrete is poured into the excavated groove 8 to construct the underground wall 6.

鎖材2の上げ降ろしによって親杭1の外表やその周辺の
付着物がきれいに撤去されているので、打設したコンク
リートと親杭1との付着が良好に行われる。
By raising and lowering the chain members 2, the external surface of the parent pile 1 and its surroundings are cleanly removed, so that the cast concrete and the parent pile 1 are well adhered to each other.

従って、従来のように泥水5や貧配合モルタル、等が混
入することもなく、コンクリートと親杭1が強固に一体
化された地中壁が構築される。
Therefore, an underground wall in which the concrete and the parent pile 1 are firmly integrated can be constructed without mixing of muddy water 5, poorly mixed mortar, etc. as in the conventional case.

くその他の実施例〉 前記実施例では、ボックス型の親杭1を使用する場合に
ついて説明したが、H型鋼からなる親杭lを使用して行
うことも勿論可能である。
Other Examples> In the above embodiments, the case where a box-shaped main pile 1 is used has been described, but it is of course also possible to use a main pile 1 made of H-shaped steel.

本実施例の場合には、第4図に示すように親杭1のリブ
面に貫通鉄筋7を配置して施工する。
In the case of this embodiment, as shown in FIG. 4, penetrating reinforcing bars 7 are arranged on the rib surface of the parent pile 1 during construction.

また、コンクリートを打設して構築した地中壁6との境
界には隔絶部材9を配置する場合もある。
Further, an isolation member 9 may be placed at the boundary with the underground wall 6 constructed by pouring concrete.

く本発明の効果〉 本発明は以上説明したようになるから次のような効果を
得ることができる。
Effects of the Present Invention> Since the present invention is as described above, the following effects can be obtained.

(イ)銀材を孔内の親杭に密着させて出し入れすること
によって、親杭の外表およびその周囲に付着する土砂や
貧配合モルタル等を綺麗に除去できろ。
(b) By bringing the silver material in and out of the hole in close contact with the parent pile, dirt, poor mix mortar, etc. adhering to the outer surface of the parent pile and its surroundings can be thoroughly removed.

従って、開削溝内に打設したコンクリートと親杭との付
着が良好となり、構築された地中壁の信頼性が向上する
Therefore, the adhesion between the concrete placed in the trench and the parent pile is improved, and the reliability of the constructed underground wall is improved.

(ロ)銀材は砂利等のように一度使用したら廃棄する必
要はなく、再使用が可能である。
(b) Unlike gravel, silver materials do not need to be disposed of once used, and can be reused.

(ハ)連続性を有する銀材を使用するので銀材の投入作
業および撤去作業が容易である。
(c) Since a silver material having continuity is used, it is easy to insert and remove the silver material.

【図面の簡単な説明】[Brief explanation of drawings]

第1図:本発明に係る施工方法の説明図第2図:銀材の
投入時の説明図
Figure 1: An explanatory diagram of the construction method according to the present invention. Figure 2: An explanatory diagram when adding silver material.

Claims (1)

【特許請求の範囲】 所定の間隔で開設した孔内に親杭を建込み、前記親杭の
周囲に鎖材を投入して固定した後、鎖材を引き揚げなが
ら親杭間を開削して開削溝を形成し、 前記開削溝内にコンクリートを打設して地中壁を構築す
ることを特徴とする、 連続地中壁工法
[Claims] After erecting parent piles in holes opened at predetermined intervals and fixing them by inserting chain members around the parent piles, excavation is performed by cutting between the parent piles while pulling up the chain members. A continuous underground wall construction method characterized by forming a trench and pouring concrete into the trench to construct an underground wall.
JP135786A 1986-01-09 1986-01-09 Construction work of continuous underground wall Pending JPS62160314A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP135786A JPS62160314A (en) 1986-01-09 1986-01-09 Construction work of continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP135786A JPS62160314A (en) 1986-01-09 1986-01-09 Construction work of continuous underground wall

Publications (1)

Publication Number Publication Date
JPS62160314A true JPS62160314A (en) 1987-07-16

Family

ID=11499246

Family Applications (1)

Application Number Title Priority Date Filing Date
JP135786A Pending JPS62160314A (en) 1986-01-09 1986-01-09 Construction work of continuous underground wall

Country Status (1)

Country Link
JP (1) JPS62160314A (en)

Similar Documents

Publication Publication Date Title
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN109915167A (en) Shield tunnel backfill loopful section of jurisdiction Demolition Construction method
JPS62288218A (en) Settlement caisson
EP0136355A1 (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP3948655B2 (en) Construction method of retaining wall and underground structure
JPS62160314A (en) Construction work of continuous underground wall
JPH06306853A (en) Construction of underground structure
JPH0415878B2 (en)
JPH0721196B2 (en) Reverse construction method of underground structure
JPS6248011B2 (en)
JPS6018769B2 (en) Construction method of underground structure
JPH02300422A (en) Construction of underground structure
JP2007231641A (en) Collapse prevention construction method for dike
JPH04258410A (en) Constructing method of underground continuous wall in underground obstruction existing ground
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JP2603307B2 (en) Retaining method for the upper part of the continuous underground wall
JPH10121465A (en) Continuos underground wall engineering method
JPS609172B2 (en) How to build underground structures
JP2000178983A (en) Foundation construction method
JPH0442493B2 (en)
JP2003027885A (en) Construction method for underground tunnel and underground tunnel
JPS63219727A (en) Construction of water-stop sheet pile wall
JPH04269210A (en) Construction method for underground continuous wall
JPH06212648A (en) Foundation construction
JP2001323485A (en) Method of constructing underground structure