JPH04269210A - Construction method for underground continuous wall - Google Patents

Construction method for underground continuous wall

Info

Publication number
JPH04269210A
JPH04269210A JP5073291A JP5073291A JPH04269210A JP H04269210 A JPH04269210 A JP H04269210A JP 5073291 A JP5073291 A JP 5073291A JP 5073291 A JP5073291 A JP 5073291A JP H04269210 A JPH04269210 A JP H04269210A
Authority
JP
Japan
Prior art keywords
continuous wall
wall
underground continuous
underground
trench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5073291A
Other languages
Japanese (ja)
Inventor
Nobuhiro Tsuchiya
信洋 土屋
Noboru Kunugihara
昇 櫟原
Yasuo Iwane
岩根 保男
Hiroyuki Takahashi
裕行 高橋
Toshiya Otsuka
大塚 敏哉
Koichi Yamada
幸一 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP5073291A priority Critical patent/JPH04269210A/en
Publication of JPH04269210A publication Critical patent/JPH04269210A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To prevent the collapse of a groove wall by providing an excavation groove in a columnar continuous wall, arranging reinforcing bars in the excavation groove, and filling concrete in the excavation groove. CONSTITUTION:Many mortar piles 6 are continuously provided in line to form a nearly circular column continuous wall 7. A guide wall 8 is formed at the upper section of the continuous wall 7. The continuous wall 7 is excavated with an underground continuous excavator 9 while it is guided by the guide wall 8, and an excavation groove 10 is formed with only a surface layer section 7a left. A reinforcing bar cage is arranged in the excavation groove 10, then concrete is placed and hardened to form an underground continuous wall 3.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は地中連続壁の施工方法、
特に、上部が軟弱土層であり深層部が硬岩であるような
地盤に対して地中連続壁を設ける場合に採用して好適な
地中連続壁の施工方法に関する。
[Industrial Application Field] The present invention relates to a method for constructing an underground continuous wall,
In particular, the present invention relates to a method of constructing a continuous underground wall that is suitable for use when installing a continuous underground wall in the ground where the upper layer is a soft soil layer and the deeper layer is hard rock.

【0002】0002

【従来の技術】従来より広く用いられている汎用の地中
連続壁掘削機は硬岩に対する掘削が困難なものであるの
で、上記のように深層部が硬岩であるような地盤に地中
連続壁を設ける場合には、掘削孔内に安定液を満たして
孔壁を保護しつつたとえばオールケーシング掘削機を用
いて硬岩に至る柱列状の掘削を行い、その掘削溝の内部
に鉄筋かごを配してコンクリートを打設することによっ
て、鉄筋コンクリート造の連続壁を直接的に形成するこ
とが一般的である。
[Prior Art] Since it is difficult for general-purpose underground continuous wall excavators that have been widely used in the past to excavate into hard rock, it is difficult to excavate into hard rock, so as mentioned above, it is difficult to excavate into hard rock. When creating a continuous wall, the hole is filled with a stabilizing liquid to protect the hole wall, and an all-casing excavator is used to excavate in a row of columns into hard rock, and a reinforcing bar cage is installed inside the excavation trench. It is common to directly form a continuous reinforced concrete wall by arranging walls and pouring concrete.

【0003】0003

【発明が解決しようとする課題】ところが、その場合、
掘削溝内に鉄筋かごを配置する際には溝壁が開放される
ことになるため、溝内に満たした安定液のみでは溝壁の
安定が保持されないような軟弱土層に対しては、溝壁の
崩壊を防止するための何等かの対策が必要であり、その
ための有効な手段の提供が望まれていた。
[Problem to be solved by the invention] However, in that case,
When placing a reinforcing bar cage in an excavated trench, the trench wall is opened, so it is difficult to install the trench in a soft soil layer where the stability of the trench wall cannot be maintained with only the stabilizing liquid filled in the trench. Some kind of measure was needed to prevent the wall from collapsing, and it was desired to provide an effective means for that purpose.

【0004】0004

【課題を解決するための手段】本発明は上記の事情に鑑
みてなされたもので、地中連続壁を設けるにあたって、
まず、その地中連続壁より壁厚の大きい無筋の柱列連続
壁を貧配合モルタルを用いて場所打ち工法により形成し
、その柱列連続壁の表層部のみを残して内部を掘削する
ことにより掘削溝を設け、その掘削溝内に鉄筋を配する
とともにコンクリートを充填して地中連続壁を設けるこ
とを特徴とするものである。
[Means for Solving the Problems] The present invention has been made in view of the above circumstances, and when installing an underground continuous wall,
First, an unreinforced columnar continuous wall with a wall thickness greater than that of the underground continuous wall is formed using a cast-in-place method using poor mix mortar, and the interior of the columnar continuous wall is excavated, leaving only the surface layer. This method is characterized by creating an excavated trench, placing reinforcing bars in the trench, and filling it with concrete to provide an underground continuous wall.

【0005】[0005]

【作用】地中連続壁を形成するべき位置に、まず、貧配
合モルタルからなるぜい弱な仮設の柱列連続壁を形成し
、その柱列連続壁の表層部を残して内部に形成した掘削
溝内に鉄筋コンクリート造の強固な地中連続壁を最終的
に形成することにより、掘削されずに残された柱列連続
壁の表層部によって掘削溝内面が保護され、したがって
溝壁が崩壊してしまうようなことが防止される。
[Operation] At the location where the underground continuous wall is to be formed, we first form a weak temporary column continuous wall made of poorly mixed mortar, and then excavate a trench formed inside the column leaving the surface layer of the column continuous wall. By finally forming a strong underground continuous wall made of reinforced concrete, the inner surface of the excavated trench is protected by the surface layer of the column continuous wall that was left unexcavated, which prevents the trench wall from collapsing. Such things are prevented.

【0006】[0006]

【実施例】以下、本発明の一実施例を図面を参照して説
明する。以下に示す実施例の工法は、上部が軟弱土層で
あり深層部が硬岩であるような地盤1に、図5および図
6に示すようなシールド立坑(発進立坑あるいは到達立
坑)2の山留壁としての地中連続壁3を平面視略円形と
なるように設けるようにしたものである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. The construction method of the example shown below is based on the construction of a shield shaft (starting shaft or arrival shaft) 2 on the ground 1 where the upper part is a soft soil layer and the deeper part is hard rock. The underground continuous wall 3 as a retaining wall is provided so as to have a substantially circular shape in plan view.

【0007】この場合、まず、地中連続壁3を形成する
べき位置に、仮設の柱列連続壁を場所打ち工法により設
ける。すなわち、図1(a)に示すようにオールケーシ
ング掘削機5を用いて硬岩に至る掘削孔を形成してはそ
の内部をモルタルに置換していくことによってモルタル
杭6を設け、そのようなモルタル杭6を列をなすように
連続的に多数形成することによって図1(b)に示すよ
うな略円形の柱列連続壁7を設ける。その柱列連続壁7
の壁厚は形成するべき地中連続壁3の壁厚より大きくし
ておく。また、その柱列連続壁7は、後工程において容
易に掘削し得るようにぜい弱なものとしておく必要があ
り、したがって鉄筋は一切用いず、また、掘削孔内に充
填するモルタルとしては強度qu=5〜10Kgf/c
m2程度の貧配合モルタルを用いることとする。
[0007] In this case, first, a temporary column continuous wall is installed at the location where the underground continuous wall 3 is to be formed by a cast-in-place method. That is, as shown in FIG. 1(a), a mortar pile 6 is provided by forming an excavation hole reaching hard rock using an all-casing excavator 5 and replacing the inside with mortar. By continuously forming a large number of piles 6 in a row, a substantially circular column continuous wall 7 as shown in FIG. 1(b) is provided. The column continuous wall 7
The wall thickness is made larger than the wall thickness of the underground continuous wall 3 to be formed. In addition, the column continuous wall 7 needs to be weak so that it can be easily excavated in the subsequent process, so no reinforcing bars are used at all, and the mortar filled in the excavation hole has a strength qu= 5~10Kgf/c
A poorly mixed mortar of about m2 will be used.

【0008】次に、図2に示すように、上記で形成した
柱列連続壁7の上部にガイドウォール8を形成し、続い
て、そのガイドウォール8により案内しつつ、図3に示
すような地中連続壁掘削機9を用いて柱列連続壁7に対
して掘削を行い、その柱列連続壁7の表層部7a,7a
のみを残して内部に掘削溝10を形成していく。この際
、上記のように、柱列連続壁7は貧配合モルタルによる
無筋のものであるので、上記の地中連続壁掘削機9とし
てはたとえばバケット式等の汎用のものを用いることが
でき、そのような地中連続壁掘削機9により容易に掘削
溝10を形成することができる。
Next, as shown in FIG. 2, a guide wall 8 is formed on the upper part of the columnar continuous wall 7 formed above, and then, while being guided by the guide wall 8, as shown in FIG. The column continuous wall 7 is excavated using the underground continuous wall excavator 9, and the surface layer parts 7a, 7a of the column continuous wall 7 are excavated.
Excavation grooves 10 are formed inside, leaving only the holes. At this time, as mentioned above, since the columnar continuous wall 7 is unreinforced and made of poorly mixed mortar, a general purpose machine such as a bucket type can be used as the underground continuous wall excavator 9. , the excavation trench 10 can be easily formed using such an underground continuous wall excavator 9.

【0009】上記のようにして、柱列連続壁7の内部に
所定の深度まで掘削溝10を形成した後、その掘削溝1
0内に鉄筋かご(図示せず)を配し、続いてコンクリー
トを打設する。打設されたコンクリートが硬化すれば図
4に示すように鉄筋コンクリート造の強固な地中連続壁
3が完成するので、その内側を掘削して立坑2を完成さ
せる。なお、形成された地中連続壁3の内面側に残る柱
列連続壁7の表層部7aは立坑2の掘削に際して容易に
除去することができ、したがって地中連続壁3の内面を
平坦なものとできる。
After forming the excavated groove 10 to a predetermined depth inside the column continuous wall 7 as described above, the excavated groove 1
A reinforcing cage (not shown) is placed inside the container, and then concrete is poured. When the poured concrete hardens, a strong underground continuous wall 3 made of reinforced concrete is completed as shown in FIG. 4, and the inside of the wall 3 is excavated to complete the shaft 2. Note that the surface layer 7a of the columnar continuous wall 7 remaining on the inner surface side of the formed underground continuous wall 3 can be easily removed when excavating the shaft 2, so that the inner surface of the underground continuous wall 3 can be made flat. It can be done.

【0010】上記方法によれば、掘削されずに残された
柱列連続壁7の表層部7aにより掘削溝10の内面が保
護されるので、地盤が軟弱土層であっても溝壁の崩壊を
確実に防止することができるものである。また、汎用の
オールケーシング掘削機5や地中連続壁掘削機9を用い
ることのみで、深層部の硬岩および貧配合モルタルから
なる柱列連続壁7の掘削が可能であり、したがって、特
殊な掘削機械を必要とせず、工費の点でも有利である。
According to the above method, the inner surface of the excavated trench 10 is protected by the surface layer 7a of the column continuous wall 7 that remains unexcavated, so even if the ground is a soft soil layer, the trench wall will not collapse. It is possible to reliably prevent this. In addition, it is possible to excavate the columnar continuous wall 7 made of deep hard rock and poorly mixed mortar only by using the general-purpose all-casing excavator 5 or the underground continuous wall excavator 9. Therefore, special excavation is possible. It does not require any machinery and is advantageous in terms of labor costs.

【0011】なお、本発明は上記のような立坑の山留壁
としての地中連続壁を施工する場合にのみならず、一般
的な地中連続壁を施工する場合に広く採用し得ることは
いうまでもない。
[0011] The present invention can be widely adopted not only when constructing an underground continuous wall as a retaining wall for a shaft as described above, but also when constructing a general underground continuous wall. Needless to say.

【0012】0012

【発明の効果】以上で説明したように、本発明は、貧配
合モルタルからなるぜい弱な柱列連続壁を形成した後、
その柱列連続壁の表層部を残して内部を掘削し、その掘
削溝内に鉄筋コンクリート造の強固な地中連続壁を形成
するようにしたので、掘削されずに残された柱列連続壁
の表層部により掘削溝の内面が保護されて溝壁の崩壊を
確実に防止することができるとともに、汎用のオールケ
ーシング掘削機や地中連続壁掘削機を用いることのみで
硬岩および柱列連続壁の掘削が可能であり、したがって
、上部が軟弱土層であり深層部が硬岩であるような地盤
に対して地中連続壁を設ける場合に採用して好適である
[Effects of the Invention] As explained above, the present invention provides the following advantages: After forming a weak columnar continuous wall made of poorly mixed mortar,
We excavated the inside of the column continuous wall, leaving the surface layer intact, and formed a strong underground continuous wall made of reinforced concrete within the excavation groove. The inner surface of the excavated trench is protected by the surface layer, making it possible to reliably prevent the trench wall from collapsing.In addition, it is possible to reliably prevent the collapse of the trench wall. It is possible to excavate it, and therefore, it is suitable for use when providing an underground continuous wall in the ground where the upper layer is a soft soil layer and the deeper layer is hard rock.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本発明方法の実施例の手順を説明するための図
であって、このうち(a)は柱列連続壁を施工している
状態を示す立面図、(b)は施工された柱列連続壁の平
面図である。
FIG. 1 is a diagram for explaining the procedure of an embodiment of the method of the present invention, of which (a) is an elevation view showing a column continuous wall being constructed; FIG. 3 is a plan view of a column continuous wall.

【図2】本発明方法の実施例の手順を説明するための図
であって、このうち(a)はガイドウォールが施工され
た状態を示す立面図、(b)はその平面図である。
FIG. 2 is a diagram for explaining the procedure of an embodiment of the method of the present invention, of which (a) is an elevation view showing a state in which a guide wall has been constructed, and (b) is a plan view thereof. .

【図3】本発明方法の実施例の手順を説明するための図
であって、柱列連続壁に掘削溝を形成している状態を示
す立面図である。
FIG. 3 is a diagram for explaining the procedure of an embodiment of the method of the present invention, and is an elevational view showing a state in which excavated grooves are formed in a column continuous wall.

【図4】本発明方法の実施例の手順を説明するための図
であって、このうち(a)は柱列連続壁の内部に地中連
続壁が形成された状態を示す立面図、(b)はその平面
図である。
FIG. 4 is a diagram for explaining the procedure of an embodiment of the method of the present invention, of which (a) is an elevation view showing a state in which an underground continuous wall is formed inside a columnar continuous wall; (b) is a plan view thereof.

【図5】本発明方法により施工された地中連続壁を山留
壁とするシールド立坑の立面図である。
FIG. 5 is an elevational view of a shield shaft whose retaining wall is an underground continuous wall constructed by the method of the present invention.

【図6】本発明方法により施工された地中連続壁を山留
壁とするシールド立坑の平面図である。
FIG. 6 is a plan view of a shield shaft whose retaining wall is an underground continuous wall constructed by the method of the present invention.

【符号の説明】[Explanation of symbols]

1  地盤 3  地中連続壁 5  オールケーシング掘削機 6  モルタル杭 7  柱列連続壁 7a  柱列連続壁の表層部 8  ガイドウォール 9  地中連続壁掘削機 10  掘削溝。 1. Ground 3 Underground continuous wall 5 All casing excavator 6 Mortar pile 7 Column continuous wall 7a Surface layer of column continuous wall 8 Guide wall 9 Underground continuous wall excavator 10. Excavation trench.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  地中連続壁を設けるにあたって、まず
、その地中連続壁より壁厚の大きい無筋の柱列連続壁を
貧配合モルタルを用いて場所打ち工法により形成し、そ
の柱列連続壁の表層部のみを残して内部を掘削すること
により掘削溝を設け、その掘削溝内に鉄筋を配するとと
もにコンクリートを充填して地中連続壁を設けることを
特徴とする地中連続壁の施工方法。
Claim 1: When installing an underground continuous wall, first, an unreinforced column-row continuous wall with a wall thickness greater than that of the underground continuous wall is formed using a cast-in-place method using poor mix mortar, and the column row continuous wall is An underground continuous wall characterized by creating an excavated trench by excavating the inside of the wall leaving only the surface layer, and placing reinforcing bars in the excavated trench and filling it with concrete to provide an underground continuous wall. Construction method.
JP5073291A 1991-02-22 1991-02-22 Construction method for underground continuous wall Pending JPH04269210A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5073291A JPH04269210A (en) 1991-02-22 1991-02-22 Construction method for underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5073291A JPH04269210A (en) 1991-02-22 1991-02-22 Construction method for underground continuous wall

Publications (1)

Publication Number Publication Date
JPH04269210A true JPH04269210A (en) 1992-09-25

Family

ID=12867025

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5073291A Pending JPH04269210A (en) 1991-02-22 1991-02-22 Construction method for underground continuous wall

Country Status (1)

Country Link
JP (1) JPH04269210A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100494354B1 (en) * 2002-12-11 2005-06-13 손기택 Reinforcement structure for dike and constructing method thereof
CN109267565A (en) * 2018-11-02 2019-01-25 西南科技大学 For shield launching and receive the closure door structure and its construction method in construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100494354B1 (en) * 2002-12-11 2005-06-13 손기택 Reinforcement structure for dike and constructing method thereof
CN109267565A (en) * 2018-11-02 2019-01-25 西南科技大学 For shield launching and receive the closure door structure and its construction method in construction

Similar Documents

Publication Publication Date Title
KR100927186B1 (en) Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP2008231816A (en) Construction method of pile foundation structure
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JPH06228947A (en) Construction of landslide protection wall in ground filled up with wastes
JPH04269210A (en) Construction method for underground continuous wall
KR100654973B1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JPS582294B2 (en) Continuous basement wall construction method
JPH1060879A (en) Building foundation and construction method thereof
JPS6018769B2 (en) Construction method of underground structure
JPH02266015A (en) Constructing underground continuous wall
JPH0959984A (en) Simple subsurface construction structure
KR102570649B1 (en) Method of demolition of underground exterior walls
JPH02300422A (en) Construction of underground structure
JPH10121465A (en) Continuos underground wall engineering method
JP2007231641A (en) Collapse prevention construction method for dike
JPS62117911A (en) Setting of pipe for well
JPH062329A (en) Shoring and cut-off method by underground continuous wall
JPH10140557A (en) Construction method of cast-in-place diaphragm wall with hollow
JPH11280060A (en) Work execution method for continuous underground wall
JP2023102736A (en) Underground continuous wall in small section
CN115125962A (en) Construction method of river-crossing foundation pit support
JP2006161374A (en) Caisson connecting method
JPH0510084A (en) Execution method of deeper depth man hole
JP2002206239A (en) Earth retaining wall

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19991130