JPS6183769A - Mold frame moving construction method of slab of high bridge - Google Patents

Mold frame moving construction method of slab of high bridge

Info

Publication number
JPS6183769A
JPS6183769A JP20541984A JP20541984A JPS6183769A JP S6183769 A JPS6183769 A JP S6183769A JP 20541984 A JP20541984 A JP 20541984A JP 20541984 A JP20541984 A JP 20541984A JP S6183769 A JPS6183769 A JP S6183769A
Authority
JP
Japan
Prior art keywords
slab
concrete
formwork
pier
bogie
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP20541984A
Other languages
Japanese (ja)
Other versions
JPH0214507B2 (en
Inventor
信之 松ケ下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okabe Co Ltd
Original Assignee
Okabe Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okabe Co Ltd filed Critical Okabe Co Ltd
Priority to JP20541984A priority Critical patent/JPS6183769A/en
Publication of JPS6183769A publication Critical patent/JPS6183769A/en
Publication of JPH0214507B2 publication Critical patent/JPH0214507B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、高架橋等のスラブコンクリートを連続的に打
設することのできる型枠移動式1法に関するものである
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a formwork moving type method 1 that can continuously cast slab concrete for elevated bridges and the like.

「従来の技術」 鉄道や高速道路などにおける高架橋工事は、構築された
橋脚上に殆んど同じ形状をもつスラブを連続的に造る工
事であって、その一般的な工法は、まず地上から支保工
を組立て、この支保工を土台としてスラブの型枠を組立
ててコンクリートの打設を行なうものである。そして、
コンクリートの硬化後は型枠や支保工を取払い次の工事
区間に運んで再び前記のように組立てて使用するのであ
る。
``Conventional technology'' Construction of viaducts on railways, expressways, etc. involves constructing slabs with almost the same shape continuously on the piers that have been constructed. Using this shoring as a base, the slab formwork is assembled and concrete is poured. and,
After the concrete hardens, the forms and supports are removed, transported to the next construction section, and reassembled as described above for use.

このような従来工法においては、作業区間毎に型枠や支
保工の組立てと解体を行ない順次施工を進めて行くので
、作業が極めて繁雑となり、多くの人員と手間を要し、
作栗能寛が悪く多額の費用を要していた。また、このよ
うな問題点を解決するために、Jへν枠或いは支保工を
組立てたまま次の喝所に移動させる工法が開発されてき
たが、しかし、この工法においても、やはり支保工の組
立、解体が面倒であるばかりでなく、型枠の移動に大き
なりレーンを要する等、工事が犬がかりとなり施工費が
高くなるという問題がある。
In such conventional construction methods, the formwork and shoring are assembled and dismantled for each work section and construction proceeds sequentially, making the work extremely complicated and requiring a large number of people and effort.
Yoshihiro Kuri's work was poor and it cost a lot of money. In addition, in order to solve these problems, a construction method has been developed in which the ν frame or shoring is moved to the next shed while it is assembled at J. However, even with this construction method, the shoring Not only is it troublesome to assemble and dismantle, but also a large lane is required to move the formwork, making the construction process laborious and raising construction costs.

「本発明が解決しようとする問題点」 本発明は、前述のような従来工法における欠点を解決し
、走行及び高さ調節可能な移動型枠装置と、これをさら
に移動させる台車とを用いることにより、組立てた型枠
装置を解体することなく施工が継続して行なえるように
なり、工事が簡易化されて省力的、能嘉的、及び経済的
である型枠工法を提供しようとするものである。
"Problems to be Solved by the Present Invention" The present invention solves the drawbacks of the conventional construction method as described above, and uses a movable formwork device that can travel and adjust its height, and a trolley for further moving the formwork device. This aims to provide a formwork construction method that allows construction to be continued without dismantling the assembled formwork equipment, simplifies construction, and is labor-saving, efficient, and economical. It is.

「問題点を解決するための手段」 本発明は、各橋脚間毎において、施工するスラブの92
 VfT方向に沼って走行移動自在に設けた台車上に、
昇降刺部自在としたスラブ型枠装置をスラブの長手方向
に沿って移動自在として載置して、スラブコンクリート
の打設が行なえるようにし、コンブ1】−トの硬化後は
、台車を移動してスラブ型枠装置を橋脚の外方に引出し
、次の橋脚間に設けられた台車をさきの台車と併列させ
て両台本間に渡りレールを架設し、スラブ型枠装置を次
の台車に移動、載置させ、その台車を当該橋脚間に移動
してスラブコンクリートの打設が行なえるようにするこ
とを特徴とするものである。
"Means for Solving the Problems" The present invention provides 92 parts of the slab to be constructed between each pier.
On a trolley that can move freely in the VfT direction,
A slab formwork device with freely raised and lowered barbs is mounted so as to be movable along the longitudinal direction of the slab so that slab concrete can be poured. Then, the slab formwork device is pulled out to the outside of the pier, the bogie installed between the next pier is aligned with the previous bogie, a rail is constructed between both platforms, and the slab formwork device is moved to the next bogie. This system is characterized in that it is moved and placed, and the cart is moved between the piers so that slab concrete can be placed.

「実施例」 以下、本発明工法の実施例について図面を参照して説明
する。
"Example" Hereinafter, an example of the construction method of the present invention will be described with reference to the drawings.

図においてAは、所要間隔毎に並列に構築された橋脚で
、その各上端はほぼ面一となっている。各橋脚間B、、
B、・・・の地盤C上には、施工するスラブの横断方向
に沿って一対のレール1゜1が橋脚間B、 、 B、・
・・の外方にわたって敷設される。そして、このレール
1.1の上には、橋脚間B、、B2・・・に入る大きさ
の台車El 、′F4・・・が、車輪2.2−・・を介
して載置され、それぞれレール1.1に沿って橋脚B、
、B、・・・間からその外方に完全に引出される位置ま
で走行移動できるようになっている。各台車E、・・・
にはその上面に、施工するスラブの長手方向に溢う一対
のレール部材3.3が設けられ、その両婦部は台車の巾
より短かく切欠され、台車上に段載部4.4が形成され
ている。また、各台車E1・・・は、そのレール部材3
,3の上面が互に水平な面一となるようにされている。
In the figure, A is a bridge pier constructed in parallel at required intervals, and the upper ends of each are almost flush. Between each pier B...
On the ground C of B,..., a pair of rails 1°1 are installed between the piers B, , B,... along the transverse direction of the slab to be constructed.
...is laid out over the outside of... Then, on this rail 1.1, bogies El, 'F4..., which are large enough to fit between the piers B, B2..., are placed via wheels 2.2-... Pier B along rail 1.1, respectively.
, B, . . . can travel to a position where it is completely pulled out to the outside. Each trolley E...
A pair of rail members 3.3 are provided on the top surface of the rail member 3.3 extending in the longitudinal direction of the slab to be constructed, and both of the rail members 3.3 are cut out to be shorter than the width of the trolley, and a stepped portion 4.4 is mounted on the trolley. It is formed. Moreover, each trolley E1... has its rail member 3
, 3 are arranged so that their upper surfaces are horizontally flush with each other.

したがって、図示のように、地盤Cに起伏や傾斜があっ
て、地盤Cから施工するスラブまでの高さが一定となら
ない場所での施工にあたっては、各橋脚間Bt・・・に
設けられる台車E、・・・の高さはそれぞれ異ったもの
に形成されることになる。
Therefore, as shown in the diagram, when performing construction in a place where the ground C has undulations or slopes and the height from the ground C to the slab to be constructed is not constant, it is necessary to install the bogie E installed between each pier Bt... , . . . are formed to have different heights.

5は各台車E1・・・上に共通して載置されるスラブ型
枠装量で、下端に台車龜・・・のレール部材3に案内さ
れて走行する車輪6を設けた脚杆7を昇降調節機構8を
介して支持した走行脚体9゜9・・・を装着した架台1
0に、施工するスラブの下面形状に沼って形成したスラ
ブ型枠11を載設して槽底されている。
Reference numeral 5 denotes a slab formwork unit which is commonly placed on each bogie E1, and has a leg rod 7 provided with wheels 6 at the lower end that are guided by the rail member 3 of the bogie head... A pedestal 1 equipped with running legs 9°9... supported via a lifting adjustment mechanism 8
A slab formwork 11 formed in the shape of the lower surface of the slab to be constructed is placed on the bottom of the tank.

施工の当初においては、最初の台車盲は第4図の鎖線イ
で示したように、橋+1/IA、A間より外方に完全に
引出された位置にあり、この台車E、のレール部材3上
にスラブ型枠装ff5を車輪6を介して載置する。次に
、台車E1をレール1゜1に沿って橋脚A、A間へと移
動させ、所定の位置に固定する。そして、走行脚体9.
9・・・の昇降機構8を操作して、架台10の高さ調節
を行ない、スラブ型枠11を所定の高さ位置にセットす
るとともに、スラブコンクリートD、を打設するのに必
要な側部型枠(図示を略す)をセットし、スラブコンク
リートD、を打設するのである。
At the beginning of construction, the first bogie blind was in a position where it was completely pulled out from the bridge +1/IA, A, as shown by the chain line A in Figure 4, and the rail member of this bogie E A slab formwork apparatus ff5 is placed on 3 via wheels 6. Next, the cart E1 is moved along the rail 1°1 between the piers A and A, and is fixed at a predetermined position. And the running leg body 9.
Operate the lifting mechanism 8 of 9... to adjust the height of the pedestal 10, set the slab formwork 11 at a predetermined height position, and move the side necessary for pouring the slab concrete D. A partial formwork (not shown) is set and slab concrete D is poured.

打設したコンクリートが硬化したならば゛、走行脚体9
,9・・・の昇降機構8を操作して架台】0の高さを低
下させ、スラブ型枠11をコンクリートD、より剥離す
る。また、他の側部型枠も撤去する。スラブ型枠11の
剥離脱型ができたら、台車E1を移動して型枠装置5を
橋PIIA、Aの外方に引出すのである。そして、次の
橋脚間に設置された次の台車E、を、第4図のようにこ
の台車E、と併列した位置に揃え、両台車E1.F4の
それぞれの段載部4.4間に渡りレール12.12(第
2図、第4図)を架設し、側台車E1.F4の各レール
部材3.3を渡りレール12を介して連通させる。その
状態でスラブ型枠装置5を押進してやれば、第2図のよ
うにスラブ型枠装置5は当初の台車E、から次の台車島
へと渡りレール12を渡って移動し、@3図、第4図−
のような位置に#!置されることになる。
Once the poured concrete has hardened, the running leg body 9
, 9 . . . to lower the height of the frame [0], and the slab formwork 11 is further peeled off from the concrete D. The other side formwork will also be removed. Once the peel-off mold of the slab formwork 11 is completed, the trolley E1 is moved and the formwork device 5 is pulled out to the outside of the bridge PIIA,A. Then, the next bogie E installed between the next piers is aligned in parallel with this bogie E as shown in Fig. 4, and both bogies E1. A rail 12.12 (Fig. 2, Fig. 4) is constructed across each of the stepped portions 4.4 of F4, and the side bogie E1. Each rail member 3.3 of F4 is communicated via a crossing rail 12. If the slab formwork device 5 is pushed forward in this state, the slab formwork device 5 will move across the rail 12 from the original bogie E to the next bogie island as shown in Figure 2. , Figure 4-
# in a position like! will be placed.

このようにして、次の台車E、へのスラブ型枠装置5の
移し変えをすましたら、渡りレール12を取除き、台車
龜を次の橋脚間B、内に移動させ、さきの橋脚間B、に
おけると同様にスラブ型枠11を所定の状態にセ・ソト
し、スラブコンクリートD2を打設するのである。以上
の工程を繰返すことにより、各橋脚間におけるスラブコ
ンクリートの施工はIl!次行なわれることになる。
In this way, after transferring the slab formwork device 5 to the next bogie E, remove the crossing rail 12, move the bogie head to the next pier B, and move it to the next pier B. As in , the slab formwork 11 is set in a predetermined state and slab concrete D2 is poured. By repeating the above process, concrete slab construction between each pier is completed! It will be done next.

「発明の効果」 以上説明したように、本発明は、各橋脚間毎において、
施工するスラブの欅断方向に沿って走行移動自在に設け
た台車上に、昇降調節自在としたスラブ型枠装置をスラ
ブの長手方向に沿って移動自在として載置して、スラブ
コンクリートの打設が行なえるようにし、コンクリート
の硬化後は、台車を移動してスラブ型枠装置を橋IJ&
IIの外方に引出し、次の@脚間に設けられた台車をさ
きの台車と併列させて両台車間に渡りレールを架設し、
スラブ型枠装置を次の台車に移動、載置させ、その台車
を当該橋脚間に移動してスラブコンクリートの打設が行
なえるようにしたので、従来工法のように、スラブ型枠
を作秦区間毎に組立、解体することなく、当初組立てら
れた大きな状態の型枠をそのまま移動して繰返し使用す
ることができるばかりでなく、スラブ型枠を支持するた
めの各m脚間毎の支保工の組立、解体の複雑で多くの手
間を要する作業が解消され、各橋脚間毎に配設された走
行自在な台本によってスラブ型枠の支持と移動とが極め
て簡便に行なえることになるとともに、スラブ型枠の台
車から台車への移動も極めて円滑、簡易にでき、高架橋
等のスラブコンクリートの型枠施工が著しく簡易化され
、工事が省力的、能率的及び経済的に行なえることにな
るという伜れた効果を有するものである。
"Effects of the Invention" As explained above, the present invention provides the following effects between each bridge pier:
Slab concrete is poured by placing a slab formwork device that can be raised and lowered freely on a trolley that is movable along the longitudinal direction of the slab to be constructed. After the concrete has hardened, move the trolley and install the slab formwork equipment on the bridge IJ &
Pull it out to the outside of II, align the next trolley installed between the legs with the previous one, and build a rail across between the two trolleys.
The slab formwork device is moved and placed on the next trolley, and then the trolley is moved between the relevant piers to allow slab concrete to be poured. Not only can the initially assembled large formwork be moved and used repeatedly without assembling and dismantling each section, but it is also possible to install shoring between each leg to support the slab formwork. The complicated and labor-intensive assembly and dismantling of the slab formwork has been eliminated, and the support and movement of the slab formwork has become extremely easy thanks to the movable scripts placed between each pier. The movement of slab formwork from one trolley to another is extremely smooth and simple, and the construction of slab concrete formwork for viaducts, etc., is significantly simplified, and construction can be carried out labor-savingly, efficiently, and economically. It has an improved effect.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明工法の実施例を略示したもので、第1図は
当初の橋脚間にスラブ型枠装置をセットした状磨を示す
側面図、第2図はスラブ型枠装置を当初の台車より次の
台車に移動させる状態を示す側面図、第3図はスラブ型
枠装置を次の橋脚間にセットした状態を示す側面図、第
4図はスラブ型枠装置の移動工程を示した平面図である
。 A・・・・・・橋Pi     Bt 、Bt・・・橋
脚間C・・・・・・地p     、D、、D、・・・
スラブコンクリートE、 、 E2・・・台車   1
・・・・・・レール2・・・・・・本論    3・・
・・・・レール部材4・・・・・・8載部   5・・
・・・・スラブ型枠装置9・・・・・・走行脚体  1
0・・・架台11・・・スラブ型枠 12・・・渡りレ
ール第2図    −一−−−−−−−−−〜・g3図 第4図
The drawings schematically show an embodiment of the construction method of the present invention. Figure 1 is a side view showing the slab formwork device set between the original piers, and Figure 2 is a side view showing the slab formwork device set between the original bridge piers. Fig. 3 is a side view showing the state in which the slab formwork device is set between the next piers, and Fig. 4 is a plan view showing the movement process of the slab formwork device. It is a diagram. A...Bridge Pi Bt, Bt...Between piers C...Ground p, D,,D,...
Slab concrete E, , E2...Truck 1
...Rail 2...Main theory 3...
...Rail member 4...8 Mounting part 5...
... Slab formwork device 9 ... Traveling leg body 1
0... Frame 11... Slab formwork 12... Transition rail Fig. 2 -1-----------g3 Fig. 4

Claims (1)

【特許請求の範囲】[Claims] 各橋脚間毎において、施工するスラブの横断方向に沿つ
て走行移動自在に設けた台車上に、昇降調節自在とした
スラブ型枠装置をスラブの長手方向に沿つて移動自在と
して載置して、スラブコンクリートの打設が行なえるよ
うにし、コンクリートの硬化後は、台車を移動してスラ
ブ型枠装置を橋脚の外方に引出し、次の橋脚間に設けら
れた台車をさきの台車と併列させて両台車間に渡りレー
ルを架設し、スラブ型枠装置を次の台車に移動、載置さ
せ、その台車を当該橋脚間に移動してスラブコンクリー
トの打設が行なえるようにすることを特徴とする、高架
橋等スラブの型枠移動式工法。
Between each pier, a slab formwork device that can be raised and lowered is placed on a trolley that is movable along the transverse direction of the slab to be constructed, and is movable along the longitudinal direction of the slab. After the concrete has hardened, the slab concrete can be placed, and after the concrete has hardened, the cart is moved and the slab formwork device is pulled out to the outside of the pier, and the cart installed between the next pier is aligned with the previous one. A rail is constructed between both bogies, the slab formwork device is moved and placed on the next bogie, and that bogie is moved between the piers to enable pouring of slab concrete. A mobile formwork construction method for slabs such as elevated bridges.
JP20541984A 1984-09-28 1984-09-28 Mold frame moving construction method of slab of high bridge Granted JPS6183769A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20541984A JPS6183769A (en) 1984-09-28 1984-09-28 Mold frame moving construction method of slab of high bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20541984A JPS6183769A (en) 1984-09-28 1984-09-28 Mold frame moving construction method of slab of high bridge

Publications (2)

Publication Number Publication Date
JPS6183769A true JPS6183769A (en) 1986-04-28
JPH0214507B2 JPH0214507B2 (en) 1990-04-09

Family

ID=16506534

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20541984A Granted JPS6183769A (en) 1984-09-28 1984-09-28 Mold frame moving construction method of slab of high bridge

Country Status (1)

Country Link
JP (1) JPS6183769A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6988592B2 (en) 2000-07-17 2006-01-24 Kabushiki Kaisha Toshiba Door and door hanger device at elevator landing

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6988592B2 (en) 2000-07-17 2006-01-24 Kabushiki Kaisha Toshiba Door and door hanger device at elevator landing
US7143870B2 (en) 2000-07-17 2006-12-05 Kabushiki Kaisha Toshiba Elevator hall door and door hanger apparatus

Also Published As

Publication number Publication date
JPH0214507B2 (en) 1990-04-09

Similar Documents

Publication Publication Date Title
JPS6183769A (en) Mold frame moving construction method of slab of high bridge
JPS62233312A (en) Running truck for moving mold frame apparatus
JPH0143086B2 (en)
JPH0347363B2 (en)
KR20100013426A (en) Mold apparatus for forming concrete girder of bridge
JPS649407B2 (en)
JPS61146963A (en) Mold frame moving type construction method of slab concrete of high bridge
JPS62189255A (en) Running and moving mold frame apparatus for constructing high bridge slab
JPS62185905A (en) Moving type mold frame construction method of slab of high bridge
JPH0214508B2 (en)
CN219260758U (en) Trolley for cast-in-situ cover plate culvert wall construction
JPH0336362B2 (en)
JP3179710B2 (en) Structural slide erection method and its work system
JPH0745773B2 (en) Mobile formwork method for multiple viaducts in parallel
JPS62206162A (en) Moving type mold frame construction method of high bridge slab
JPS62206161A (en) Moving type mold frame construction method of high bridge slab
JPH049904B2 (en)
JPH07116832B2 (en) Mobile formwork method for multiple viaducts in parallel
JPS62197508A (en) Moving type mold frame construction method high bridge slab
JPS6370772A (en) Movable type mold frame construction method of plural high bridge slabs arranged in parallel
JPS62253872A (en) Running movement type mold frame apparatus
JPH049902B2 (en)
JPS61270407A (en) Apparatus for moving high bridge slab mold frame centle
JPH0511163B2 (en)
JPS6333557B2 (en)