JPS6370772A - Movable type mold frame construction method of plural high bridge slabs arranged in parallel - Google Patents

Movable type mold frame construction method of plural high bridge slabs arranged in parallel

Info

Publication number
JPS6370772A
JPS6370772A JP21550386A JP21550386A JPS6370772A JP S6370772 A JPS6370772 A JP S6370772A JP 21550386 A JP21550386 A JP 21550386A JP 21550386 A JP21550386 A JP 21550386A JP S6370772 A JPS6370772 A JP S6370772A
Authority
JP
Japan
Prior art keywords
formwork
viaduct
slab
slabs
piers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21550386A
Other languages
Japanese (ja)
Other versions
JPH07116833B2 (en
Inventor
信之 松ケ下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okabe Co Ltd
Original Assignee
Okabe Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okabe Co Ltd filed Critical Okabe Co Ltd
Priority to JP61215503A priority Critical patent/JPH07116833B2/en
Publication of JPS6370772A publication Critical patent/JPS6370772A/en
Publication of JPH07116833B2 publication Critical patent/JPH07116833B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、鉄道、通路等の高架橋スラブの移動式型枠工
法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for constructing movable formwork for elevated slabs for railways, passageways, etc.

(従来の技術) コンクリート高架橋等の工事は、殆ど同じ形状の構造物
を連続的に構築する工事であるため、その型枠施工にお
いては、工事の省力化と能率化の上から、移動式型枠に
よる工法が採用されるようになってきた。
(Conventional technology) Construction of concrete viaducts, etc. involves constructing structures of almost the same shape continuously, so in order to save labor and improve efficiency of construction, mobile molding is used to construct the formwork. Construction methods using frames have come to be adopted.

型枠の移動方式としては、クレーンによる吊移動り式と
走行移動方式とがあるが、吊移動方式による場合、従来
は一般に門望クレーン等のような大型なりレーンを使用
しており、を枠装]か大規模となるばかりでなく、その
クレーンの設置や移動のために広い専用敷地か必要とな
り、経費も莫大なものになる。また、山間部等では大型
クレーンの設置が極めて回動なため、移動式型枠の使用
ができないことになる。
There are two ways to move the formwork: a hanging type using a crane and a traveling type. Conventionally, when using the hanging type, a large lane such as a gate crane was used, and the frame was moved using a crane. Not only would the crane be large-scale, but a large dedicated site would be required to install and move the crane, and the cost would be enormous. Furthermore, in mountainous areas, large cranes must be installed in extremely rotating locations, making it impossible to use movable formwork.

本発明者は、かかる状況にかんがみ、走行移動方式によ
る型枠施工の実現に努め、これまでに多くの提案と実用
化を行ってきた。そして、例えば特願昭61−2549
5号のように、高架橋スラブの橋脚間に架設覆る型枠を
、高架橋スラブの巾方向の数分割巾に形成した小型の型
枠装置を並設するようにして、型枠の走行移動方式によ
る工法を完成した。
In view of this situation, the present inventor has endeavored to realize formwork construction using a traveling and moving method, and has so far made many proposals and put them into practical use. For example, patent application No. 61-2549
As in No. 5, small formwork devices formed in several width divisions in the width direction of the viaduct slab are installed in parallel to cover the formwork that is erected between the piers of the viaduct slab, and the formwork is moved by the traveling method of the formwork. Completed the construction method.

(発明が解決しようとする問題点) しかし。前記の走行移動式型枠工法は、申−な高架橋ス
ラブの施工を対象と覆るものであるため、一般の畠架道
路のように、8架橋スラブが複列している場合でも、一
方の高架橋スラブを施工後折り返して他方の高架橋スラ
ブの施工を行うことになるのであるが、型枠装置を高架
橋スラブの長さ方向に移動(縦移動)することは、それ
が走行式移動であってもかなりの作業量を要覆るもので
あるため、一層の加工能率と紅演性向上とを図ることが
要望されてきた。
(The problem that the invention seeks to solve) However. The above-mentioned mobile formwork construction method is intended for the construction of elevated bridge slabs, so even if eight bridge slabs are arranged in double rows, such as in a general field road, only one elevated bridge After constructing one slab, the other viaduct slab will be constructed by turning it back, but moving the formwork equipment in the length direction of the viaduct slab (vertical movement) is not possible even if it is a traveling movement. Since this requires a considerable amount of work, it has been desired to further improve processing efficiency and performance.

本発明は、隅接した複列の高架橋スラブの施工におCプ
る前記工法の技術的課題を解決J゛るためになされたも
ので、型枠装置を一方の橋脚間におCプる施工後、隣の
橋脚間(WL移動して、複列の高架橋スラブを各橋脚間
毎に続【プて施工できるようじし、型枠装置の縦移動の
作業を半減以下とし、施工の能率と経演竹を大巾に高め
ることのできる型枠工法を提供しようとするものである
The present invention was made in order to solve the technical problems of the above-mentioned method of constructing double-row viaduct slabs with corner-contacting corners. After construction, the double-row viaduct slabs can be moved between adjacent piers (WL) to continue construction between each pier, reducing the work of vertical movement of formwork equipment by more than half, and improving construction efficiency. The aim is to provide a formwork construction method that can greatly increase the height of bamboo.

(問題点を解決するための手段) 本発明の構成を実除例に対応する図面を参照【ノて説明
すると、本発明は、並列する高架橋スラブ2a、2bの
各長さ方向に所定の間隔をおいて各列設した橋脚1a、
1bに、高架橋スラブ2a、2bの巾方向に沿って長く
形成した型枠横動用レール4,4を、一方の高架橋スラ
ブ2aの橋脚1aから隣の高架橋スラブ2bの橋脚1b
にわたり移動可能に架ムリし、他方、高架橋スラブ2a
、2bの巾の数分割[1〕とした型枠装置5を構成し、
該装置5の複数個を、前記一方の高架橋スラブ2aの橋
脚1a、ia間に架設の型枠横動用レール4,4上に、
台座i1. iiを介して所定の位置に並列、架設し、
それらの型枠体8,10上にスラブコンクリートを打設
し該コンクリートの硬化後、型枠装置5,5の型枠体8
.10を降下させてコンクリートより剥離し、ついで、
型枠装置5.5を載架した状態で型枠横動用レール4,
4を隣の高架橋スラブ2bの橋脚1b、Ib間に移動し
て型枠体5,5を所定の位置にセットし、前記同様にし
てスラブコンクリートの打設、型枠体8.10の剥離を
行い、続いて、各型枠装置5.5を一体的に連結プると
ともに、その連結された型枠装置5゜5を前記の台座1
1.11に代え数個のψ輪7.7を介して支持させ、連
結された型枠装@5,5を型枠横動用レール4,4の端
部まで走行移動させ、その端に位置する型枠装置5の連
結を解いて分離し、クレーン等により橋脚1b、Ib外
に吊り出すことを特徴とするものである。
(Means for Solving the Problems) The structure of the present invention is explained with reference to the drawings corresponding to the actual division examples. Piers 1a arranged in each row with
1b, formwork lateral movement rails 4, 4 formed long along the width direction of the viaduct slabs 2a, 2b are connected from the pier 1a of one viaduct slab 2a to the pier 1b of the adjacent viaduct slab 2b.
On the other hand, the elevated bridge slab 2a
, 2b width is divided into several divisions [1], forming a formwork device 5,
A plurality of the devices 5 are placed on the formwork lateral movement rails 4, 4 installed between the piers 1a and ia of the one elevated bridge slab 2a,
Pedestal i1. Parallel and erect at a predetermined position via ii,
After pouring slab concrete onto the formwork bodies 8 and 10 and hardening the concrete, the formwork bodies 8 of the formwork apparatuses 5 and 5
.. 10 is lowered to peel off from the concrete, and then,
With the formwork device 5.5 mounted, the formwork lateral movement rail 4,
4 between the piers 1b and 1b of the adjacent elevated bridge slab 2b, and set the formwork bodies 5, 5 in the predetermined positions, pour slab concrete and peel off the formwork body 8.10 in the same manner as above. Then, each formwork device 5.5 is connected together and the connected formwork device 5.5 is placed on the pedestal 1.
Instead of 1.11, support via several ψ wheels 7.7, move the connected formwork @5, 5 to the end of the formwork lateral movement rails 4, 4, and position it at the end. This method is characterized in that the formwork device 5 is uncoupled and separated, and then lifted out of the piers 1b, Ib by a crane or the like.

(実施例) 以下、本発明の実施例について図面を参照して説明する
(Example) Hereinafter, an example of the present invention will be described with reference to the drawings.

図において1a、’lbは2本並列して施工される高架
橋スラブ2a、2bの長さ方向にほぼ等間隔で列設され
た橋脚で、両スラブ2a、2bの各橋脚1a、1bはほ
ぼ同一線上に並列されたものとなっている。そして、両
高架橋スラブ2a、 2bはそれぞれ列設されたそれら
の橋脚1a、Ia間及び1b、Ib間を施工の単位区間
として施工が行われるのである。
In the figure, 1a and 'lb are the piers installed in a row at approximately equal intervals in the length direction of two elevated bridge slabs 2a and 2b that are constructed in parallel, and the piers 1a and 1b of both slabs 2a and 2b are almost the same. They are arranged in parallel on a line. The construction of both viaduct slabs 2a and 2b is carried out using the sections between the piers 1a and Ia and between the piers 1b and Ib, which are arranged in a row, as unit sections of construction.

この高架橋スラブ2a、2bは、その横断面をみると、
一般的には、橋脚1a、Ib上にある中央部分aと、そ
の両側にあって橋脚1a。
When looking at the cross section of these viaduct slabs 2a and 2b,
Generally, there is a central portion a on piers 1a and Ib, and piers 1a on both sides thereof.

p 1bより外方に突出した部分す、bとが連続した形とな
っている(第1図、第4図参照)。本発明の実施例はこ
のような高架橋スラブの施工を例として説明するが、し
かし、本発明は前記の張出部分す、bを持たないような
高架橋スラブの施工にも適用可能である。
The portions s and b that protrude outward from p 1b are continuous (see Figures 1 and 4). The embodiments of the present invention will be explained by taking the construction of such a viaduct slab as an example, but the present invention is also applicable to the construction of a viaduct slab that does not have the above-mentioned overhanging portions (b).

各列設した橋脚1a、1a及びIb、1bの各対向面側
の上部には、それぞれ、レール滑動用のローラ13と、
このローラ13の上面の上下にわたり高さ調節のできる
昇降ジヤツキ14とを設けたブラケット3.3を複数個
あて取付け、その上に、−高架橋スラブ2a又は2bの
巾より十分長く形成した型枠横動用レール4を、一方の
高架橋の橋脚1a、1aのブラケット3,3上に、ロー
ラ13の上面より高くしだ受座15を介して架設する(
第1図参照)。なお、このレール4を架設覆る手段とし
ては、前記のようなブラケット3.3によらず、地上か
ら支保Tを組みその上にレール4を架設するようにして
もよく、地面からレール4までの高さが低い場合等は経
済的に右利となることがある。また、この型枠横動用レ
ール4は、図示のようにI形鋼自体を適用してもよく、
或は■形鋼の上に別途レールを敷設したものでもよい。
A roller 13 for rail sliding is provided on the upper part of each of the opposing surfaces of the piers 1a, 1a and Ib, 1b arranged in a row, respectively.
A plurality of brackets 3.3 each having a height-adjustable lifting jack 14 are attached to the upper and lower surfaces of the roller 13, and on top of the brackets 3.3, the side of a formwork formed sufficiently longer than the width of the viaduct slab 2a or 2b is attached. The moving rail 4 is installed on the brackets 3, 3 of the piers 1a, 1a of one of the viaducts, higher than the upper surface of the rollers 13, via the ridge seats 15 (
(See Figure 1). In addition, as a means to erect and cover this rail 4, instead of using the bracket 3.3 as described above, a support T may be constructed from the ground and the rail 4 may be erected on it, and the rail 4 may be constructed from the ground to the rail 4. If the height is low, it may be economically advantageous. In addition, the formwork lateral movement rail 4 may be made of I-beam steel itself as shown in the figure.
Alternatively, a separate rail may be laid on top of the section steel.

また、昇降ジヤツキ14は、後述する使用時に載置する
ようにしてもよい。
Further, the elevating jack 14 may be placed in place during use, which will be described later.

5.5・・・は、ぞれぞれ対向しで架設された型枠横動
用レール4,4間に載架1−る走行型枠装置で、各同様
に形成されており、断面方形状をなした架台6の両端部
下面に前記の型枠横動用レール4に係合して走行できる
車輪7,7が着脱自在に設Cブられ、また架台6の上面
部には、バタ材にせき根を取付けた型枠体8が架台6に
上下動調節自在に設けた調節ボルト9,9により胃陪自
在に設けられた構造となっており、装置5の巾は高架橋
スラブ2a、2bの巾の数分割巾となっている。
5.5... is a traveling formwork device in which a rack 1 is mounted between formwork lateral movement rails 4, 4 installed opposite to each other, each of which is formed in the same way, and has a rectangular cross section. Wheels 7, 7, which can run while engaging with the formwork lateral movement rails 4, are removably installed on the lower surface of both ends of the pedestal 6, and the upper surface of the pedestal 6 is made of butter material. The formwork body 8 to which the weir roots are attached is freely mounted on the frame 6 by means of adjustment bolts 9, 9, which are provided for vertical movement adjustment, and the width of the device 5 is the same as that of the viaduct slabs 2a, 2b. The width is divided into several parts.

それで、画商架橋スラブ2a、 2bの施工は、各列設
の橋脚1a、1a、Ib、Ib間において、前記の型枠
装置5.5を用い、一方の高架橋スラブ2aを施工した
後、その隣りである他方の高架橋スラブ2bを施工し、
これを列設の各橋脚間に進めて行くのである。
Therefore, the art shop bridge slabs 2a and 2b were constructed using the formwork device 5.5 described above between the piers 1a, 1a, Ib, and Ib in each row, and after constructing one of the viaduct slabs 2a, the adjacent Construct the other viaduct slab 2b, which is
This is carried out between each pier in the row.

まず、第1図のように、施工すべき一方の高架橋スラブ
2aの橋脚ia、 1a、に架設した型枠横動用レール
4,4上に型枠urff5,5・・・をその車輪7.7
を介して載架し、レール4゜4上を走行移動して一方の
高架橋スラブ2aの下の所定の位置に並列させる。つい
で、第2図に示したように、架台6とレール4との間に
ジヤツキ(図示を略す)を介入し、その操作により車輪
7.7を台座11.11に代えて装置5をレール4上に
支持させ、型枠体を調節ポル(・9゜9の操作により所
定の高さ位置にセットする。
First, as shown in Fig. 1, the formwork urff5,5... is mounted on the formwork lateral movement rails 4,4 installed on the piers ia, 1a of one of the viaduct slabs 2a to be constructed, and its wheels 7.7
They are mounted on the rails, run on rails 4.4, and placed in parallel at predetermined positions under one of the viaduct slabs 2a. Next, as shown in FIG. 2, a jack (not shown) is inserted between the pedestal 6 and the rail 4, and by operating the jack, the wheel 7.7 is replaced with the pedestal 11.11, and the device 5 is moved to the rail 4. Support the formwork above and set the formwork body to a predetermined height position by operating the adjustment pole (・9°9).

なお、車輪7を使用せずに、台座11を介してレール4
,4上に型枠装置5,5をクレーンで所定位置に載置す
ることもできる。また、張出部分すの下方にある走行型
枠装置5には張出部分すの下面に沿う張出型枠10を架
設置る。
Note that the rail 4 can be mounted via the pedestal 11 without using the wheels 7.
, 4, the formwork devices 5, 5 can also be placed in a predetermined position by a crane. Further, an overhanging formwork 10 is mounted on the traveling formwork device 5 below the overhanging part so as to extend along the lower surface of the overhanging part.

そして、それら型枠体8.8.10.10の上に高架橋
スラブ2aの鉄筋を組立てコンクリートを打設する。コ
ンクリートの硬化後は、第3図に示すように、調節ボル
ト9.9を操作して型枠体8,10をコンクリートより
剥離、降下させるとともに張出型枠10を取除く。
Then, the reinforcing bars of the viaduct slab 2a are assembled on top of these formwork bodies 8.8.10.10, and concrete is poured. After the concrete has hardened, as shown in FIG. 3, the formwork bodies 8, 10 are peeled off and lowered from the concrete by operating the adjustment bolts 9.9, and the overhanging formwork 10 is removed.

ついで、ブラケット3,3に設けであるジヤツキ14.
14を一旦上昇させて受座15.15を取除き、ジヤツ
キ14.14を降下させて型枠横動用レール4.4をロ
ーラ13.13上に載置づる。そして、各型枠装置5.
5を架設したままで、型枠横動用レール4,4をローラ
13.13上を滑動して、第4図のように隣の脚411
b、1bに取付けたブラケット3,3のローラ13.1
3上へと移送し、他方の高架橋スラブ2bの施工位置へ
と移し換えるのである。
Next, the jacks 14 provided on the brackets 3, 3.
14 is once raised to remove the catch 15.15, and the jack 14.14 is lowered to place the formwork lateral movement rail 4.4 on the roller 13.13. And each formwork device 5.
5 remains installed, slide the formwork lateral movement rails 4, 4 on the rollers 13.13, and move the adjacent leg 411 as shown in FIG.
b, roller 13.1 of bracket 3, 3 attached to 1b
3 and transferred to the construction position of the other viaduct slab 2b.

この移し換えの後は、さきの高架橋スラブ2aのIIの
場合と同様に、昇降ジヤツキ14.14を操作して型枠
横動用レール4,4を受Fi:15゜15を介して支持
し、張出型枠10.10の架設、型枠体8のセットを行
い、高架橋スラブ2bの鉄筋を相でコンクリートを打設
し、その硬化後、型枠体8.10をコンクリートより剥
離、時下させ、張出型枠10を取除く。続いて、各型枠
装置5.5を結盾具12.12により一体的に連結した
後、第6図に示づように、再び架台6とレール4との間
にジヤツキ(図示を略す)を介し、その操作により台座
11.11を除去し、架台6.6の適宜な個所に数個の
車輪7,7を取付けて連結された各型枠装置5.5を車
輪7.7を介しレール4上に支持させ、施工を柊えた各
型枠装置5,5の移動、搬出準備を終え、この連結した
型枠装置5,5を押進してその端部にある型枠装置5を
レール4の端部に位置させる。そこで、その端部にある
型枠装置5をクレーン(図示を略す)で吊持するととも
に、その隣の型枠装@5との結着具12を除去して分離
し、第7図のようにクレーン(図示を略す)゛により橋
脚1゜1間より吊り出すのである。この吊り出し後は、
必要に応じて車輪7の取付場所を変えて、再び連結され
ている型枠装置5,5を押進してその端部の装置5をレ
ール4の端部に位置させ、以下同様の操作を繰返してす
べての型枠装置の吊り出しを終えるのである。
After this transfer, as in the case of II of the viaduct slab 2a above, operate the lifting jacks 14 and 14 to support the formwork lateral movement rails 4, 4 via the support Fi: 15° 15, The overhanging formwork 10.10 is erected, the formwork body 8 is set, and concrete is poured using the reinforcing bars of the viaduct slab 2b, and after it hardens, the formwork body 8.10 is peeled off from the concrete, and then the formwork body 8 is set. and remove the overhang formwork 10. Subsequently, after each formwork device 5.5 is integrally connected by the tying device 12.12, as shown in FIG. 6, a jack (not shown) is again installed between the frame 6 and the rail 4. By this operation, the pedestal 11.11 is removed, several wheels 7, 7 are attached to appropriate locations on the pedestal 6.6, and the connected formwork devices 5.5 are moved through the wheels 7.7. After completing the movement and preparation for carrying out each formwork device 5, 5 that has been supported on the rail 4 and completed construction, the connected formwork device 5, 5 is pushed forward and the formwork device 5 at the end thereof is moved. It is located at the end of the rail 4. Therefore, the formwork device 5 at the end is suspended by a crane (not shown), and the fasteners 12 connecting it to the formwork device @5 next to it are removed and separated, as shown in Fig. 7. Then, a crane (not shown) was used to lift it out from between the piers. After this lifting,
If necessary, change the mounting location of the wheels 7 and push the connected formwork devices 5, 5 again to position the device 5 at the end on the end of the rail 4, and then repeat the same operation. Repeat this until all formwork equipment has been lifted.

吊り出された型枠装置5.5は、次の施工橋脚間のレー
ル4.4上に載置されて高架橋スラブ2a、2bの施工
が行われる。このようにして並列した高架橋スラブ2a
、2bは各列設の橋脚1a、1a、1b、1b毎にII
を繰返し構築を進めて行くのである。
The suspended formwork device 5.5 is placed on the rail 4.4 between the piers to be constructed next, and construction of the viaduct slabs 2a, 2b is performed. Viaduct slabs 2a paralleled in this way
, 2b is II for each row of piers 1a, 1a, 1b, 1b.
The construction is continued repeatedly.

(発明の効果) 以上説明したように、本発明工法によれば、各橋脚間の
スラブコンクリートの施工に使用する型枠は、小型の走
行型枠装置によるため、走行或はクレーンによる移動が
容易でその作業が安全で能率よくでき、また、使用する
クレーンが小規模のもので足りるとともに、型枠装置は
型枠横動用レール上の移動時だけ車輪を使用し、コンク
リートの打設時には台座を介して支持するようにしたの
で、車輪は型枠装置の移動時のvJ重に耐えるだ番ノの
ものでよいため、簡易、安l l− 価なものとすることができ、車輪経費が節減できること
になる。また、特に、各型枠装置は並+lJ ?lる高
架橋スラブの一方を施工した後は、従来のように次の橋
脚間への縦移動を行うことなく、横隣りである他方の高
架橋スラブ側へレール上に載架したまま横移動させ、同
スラブの施工後、レールの端部より各個に吊り出し、次
の橋脚間でのIIを行うようにしたので、型枠装置の橋
脚間にわたって行う縦移動の繁雑な作業を半減すること
ができ、しかも、一方の橋脚間から隣りの橋脚間への型
枠装置の横移動も、型枠装置を個々に移動することなく
簡易にでき、施工が一層能率よく経済的に行える等、多
くの優れた効果を奏するものである。
(Effects of the Invention) As explained above, according to the construction method of the present invention, the formwork used for constructing slab concrete between each pier is a small traveling formwork device, so it can be easily moved by traveling or using a crane. The work can be done safely and efficiently, and only a small crane is needed, and the formwork equipment uses wheels only when moving the formwork on the rails for lateral movement of the formwork, and the pedestal is not used when pouring concrete. Since the wheels are supported through the formwork, the wheels can be of a size that can withstand the vJ weight when the formwork equipment is moved, so it can be made simple and inexpensive, and wheel costs can be reduced. It will be possible. Also, in particular, each formwork device has an average +lJ? After constructing one of the viaduct slabs, instead of moving vertically to the next pier as in the conventional method, the slab is moved horizontally to the other adjacent viaduct slab while remaining on the rail. After the slabs are constructed, they are lifted individually from the end of the rail and II is carried out between the next piers, which makes it possible to halve the complicated work of moving the formwork equipment vertically between the piers. Furthermore, the formwork equipment can be easily moved laterally from one pier to the next without having to move the formwork equipment individually, making construction more efficient and economical. It is effective.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明工法の一実施例を略示したもので、第1図
は一方の橋脚間に型枠横動用レールを架設し型枠装置を
搬入並列した状態を示ず正断面図、第2図は同高架橋ス
ラブの型枠をセットした状態を示す正断面図、第3図は
型枠を剥−12= 離したところを示り正断面図、第4図は型枠装置を載置
した型枠横動用レールの移動状態を示す正断面図、第5
図は型枠装置を隣りの橋脚間に移動し型枠をセットした
ところを示す正断面図、第6図−は型枠を剥離して型枠
装置を台座に代え車輪で支持し、レールの端部へ移動し
たところを示す正断面図、第7図は端部にある型枠装 2a、2b・・・高架学スラブ
The drawings schematically show one embodiment of the construction method of the present invention, and Fig. 1 is a front sectional view without showing the state in which a formwork lateral movement rail is installed between one pier and the formwork equipment is carried in parallel. The figure is a front sectional view showing the viaduct slab with formwork set in place, Figure 3 is a front sectional view showing the formwork removed, and Figure 4 is a front sectional view showing the formwork installed. Front sectional view showing the movement state of the formwork lateral movement rail, No. 5
The figure is a front cross-sectional view showing the formwork set after moving the formwork device between adjacent piers, and Figure 6 shows the formwork being removed and the formwork device being supported by wheels instead of a pedestal, and the rail A front sectional view showing the area moved to the end, Figure 7 shows the formwork 2a, 2b at the end... elevated slab

Claims (1)

【特許請求の範囲】[Claims] 並列する高架橋スラブの各長さ方向に所定の間隔をおい
て各列設した橋脚に、高架橋スラブの巾方向に沿って長
く形成した型枠横動用レールを、一方の高架橋スラブの
橋脚から隣の高架橋スラブの橋脚にわたり移動可能に架
設し、他方、高架橋スラブの巾の数分割巾とした型枠装
置を構成し、該装置の複数個を、前記一方の高架橋スラ
ブの橋脚間に架設の型枠横動用レール上に、台座を介し
て所定の位置に並列、架設し、それらの型枠体上にスラ
ブコンクリートを打設し、該コンクリートの硬化後、型
枠装置の型枠体を降下させてコンクリートより剥離し、
ついで、型枠装置を載架した状態で型枠横動用レールを
隣の高架橋スラブの橋脚間に移動して型枠体を所定の位
置にセットし、前記同様にしてスラブコンクリートの打
設、型枠体の剥離を行い、続いて、各型枠装置を一体的
に連結するとともに、その連結された型枠装置を前記の
台座に代え数個の車輪を介して支持させ、連結された型
枠装置を型枠横動用レールの端部まで走行移動させ、そ
の端に位置する型枠装置の連結を解いて分離し、クレー
ン等により橋脚外に吊り出すことを特徴とする、並列す
る複数の高架橋スラブの移動式型枠工法。
A formwork lateral movement rail formed long along the width direction of the viaduct slabs is installed on each pier arranged at a predetermined interval in the length direction of the parallel viaduct slabs. A formwork device is movably installed across the piers of the viaduct slab, and has a width divided by several parts of the width of the viaduct slab. The slabs are installed in parallel at predetermined positions on the lateral movement rails via pedestals, slab concrete is poured onto these formwork bodies, and after the concrete has hardened, the formwork body of the formwork device is lowered. Peeling off from concrete,
Next, with the formwork device mounted, the formwork lateral movement rail is moved between the piers of the adjacent viaduct slab, the formwork body is set in a predetermined position, and the slab concrete is poured and molded in the same manner as described above. The frame bodies are separated, and then each formwork device is integrally connected, and the connected formwork device is supported via several wheels instead of the pedestal, and the connected formwork is A plurality of parallel elevated bridges, characterized in that the equipment is moved to the end of the formwork lateral movement rail, the formwork equipment located at that end is uncoupled and separated, and then lifted out of the bridge piers by a crane, etc. Mobile formwork construction method for slabs.
JP61215503A 1986-09-12 1986-09-12 Mobile formwork method for multiple viaducts in parallel Expired - Lifetime JPH07116833B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61215503A JPH07116833B2 (en) 1986-09-12 1986-09-12 Mobile formwork method for multiple viaducts in parallel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61215503A JPH07116833B2 (en) 1986-09-12 1986-09-12 Mobile formwork method for multiple viaducts in parallel

Publications (2)

Publication Number Publication Date
JPS6370772A true JPS6370772A (en) 1988-03-30
JPH07116833B2 JPH07116833B2 (en) 1995-12-18

Family

ID=16673472

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61215503A Expired - Lifetime JPH07116833B2 (en) 1986-09-12 1986-09-12 Mobile formwork method for multiple viaducts in parallel

Country Status (1)

Country Link
JP (1) JPH07116833B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691270A (en) * 2012-06-27 2012-09-26 中铁四局集团机电设备安装有限公司 Efficient and quick movable mould frame

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5640208A (en) * 1979-09-10 1981-04-16 Hitachi Ltd Electric winding power loading source supporting device
JPS60192011A (en) * 1984-03-12 1985-09-30 岡部株式会社 Moving type mold frame construction method of slab of high bridge

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5640208A (en) * 1979-09-10 1981-04-16 Hitachi Ltd Electric winding power loading source supporting device
JPS60192011A (en) * 1984-03-12 1985-09-30 岡部株式会社 Moving type mold frame construction method of slab of high bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691270A (en) * 2012-06-27 2012-09-26 中铁四局集团机电设备安装有限公司 Efficient and quick movable mould frame

Also Published As

Publication number Publication date
JPH07116833B2 (en) 1995-12-18

Similar Documents

Publication Publication Date Title
JPS6370772A (en) Movable type mold frame construction method of plural high bridge slabs arranged in parallel
CN209722743U (en) A kind of mobile bracket of composite multi-functional for concrete girder cast-in-place construction
JPS62288262A (en) Moving type mold frame construction method of plural high bridging slabs arranged in parallel
JPS6370773A (en) Movable type mold frame construction method of plural high bridge slabs arranged in parallel
JPS62185905A (en) Moving type mold frame construction method of slab of high bridge
JPS5894504A (en) Mold frame moving type constructing process of high bridge slab
JPS62189255A (en) Running and moving mold frame apparatus for constructing high bridge slab
JPH0426377B2 (en)
JPS62288261A (en) Moving type mold frame construction method of high bridging slab
CN219033458U (en) Ballast bed ditch template capable of achieving one-time pouring molding
JPH0481023B2 (en)
JPS62189256A (en) Running and moving mold frame apparatus for constructing high bridge slab
CN109629443B (en) Cast-in-place channel beam three-point pushing system crossing existing road and construction method
JPS62233312A (en) Running truck for moving mold frame apparatus
JPS62197509A (en) Moving type mold frame construction method high bridge slab
JPS59122667A (en) Method and apparatus for constructing mold frame of ceiling slab concrete inclined to longitudinal direction
JPS62288260A (en) Moving type mold frame construction method of high bridging slab
JPS62197508A (en) Moving type mold frame construction method high bridge slab
JPH049902B2 (en)
JPH0214507B2 (en)
CN109457618A (en) A kind of concrete girder cast-in-situ construction method
JPS62253872A (en) Running movement type mold frame apparatus
JPH0352811Y2 (en)
JPH0347363B2 (en)
JPS6183770A (en) Moving mold frame apparatus of slab concrete of high bridge