JPH0511163B2 - - Google Patents

Info

Publication number
JPH0511163B2
JPH0511163B2 JP61040960A JP4096086A JPH0511163B2 JP H0511163 B2 JPH0511163 B2 JP H0511163B2 JP 61040960 A JP61040960 A JP 61040960A JP 4096086 A JP4096086 A JP 4096086A JP H0511163 B2 JPH0511163 B2 JP H0511163B2
Authority
JP
Japan
Prior art keywords
formwork
rail
piers
traveling
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP61040960A
Other languages
Japanese (ja)
Other versions
JPS62197509A (en
Inventor
Nobuyuki Matsugashita
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OKABE KK
OKABE TEKUNO SHISUTEMU KK
Original Assignee
OKABE KK
OKABE TEKUNO SHISUTEMU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OKABE KK, OKABE TEKUNO SHISUTEMU KK filed Critical OKABE KK
Priority to JP4096086A priority Critical patent/JPS62197509A/en
Publication of JPS62197509A publication Critical patent/JPS62197509A/en
Publication of JPH0511163B2 publication Critical patent/JPH0511163B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】[Detailed description of the invention]

「産業上の利用分野」 本発明は、鉄道、道路等の高架橋スラブを連続
的に打設することのできる高架橋スラブの移動式
型枠工法に関するものである。 「従来の技術」 コンクリート高架橋等の工事は、殆ど同じ形状
の構造物を連続的に構築する工事であるため、そ
の型枠施工においては、工事の省略化と能率化の
上から、移動式型枠による工法が採用されるよう
になつてきた。 この種移動式型枠工法は、例えば特公昭56−
37363号公報に示されているように、支保工を組
んでその上に型枠を組立て、その型枠の移動を門
型クレーン等のような大型なクレーンを使つて行
うようにしている。そのため、特別大きなクレー
ンを設置しなければならないばかりでなく、その
クレーンの設置や移動のために広い専用敷地が必
要となり、経費も増大する。また、山間部や橋脚
が非常に高い場合には、大型クレーンの設置が極
めて困難となるので、そのような工事においては
移動式の型枠を使用することができず、旧来の手
組み、手払いによる非能率で多くの人手を要する
型枠施工にならざるを得ないという実情である。 「発明が解決しようとする問題点」 本発明者は、この種移動式型枠による工法の問
題点を解決するため、さきに、特開昭58−94504
号公報に示すような、型枠を走行移動させるよう
にした工法の開発を行つてきた。 本発明は、前記の発明を更に改善することによ
り、施工の経済性を一層向上させると共に、作業
の容易性と安全性と能率性とを高めることがで
き、更には使用する型枠装置の軽量化とコストの
低減が図れる、新たな型枠工法を提供しようとす
るものである。 「問題点を解決するための手段」 本発明の移動式型枠工法を、実施例に対応する
図面を参照して説明すると、本発明は、高架橋ス
ラブ2の巾方向に所定の間隔をおいて複数の架脚
1,1′を列設し、この列設した橋脚1,1′の組
を高架橋の長さ方向に所定の間隔をおいて列設
し、それら橋脚1,1′に取付けのブラケツト3,
3を介して該スラブ2の巾方向に沿つた型枠横動
用レール4,4を、該スラブ2中央部の対向する
橋脚1,1′間を除き架設するとともに、該スラ
ブ2中央部の対向する橋脚間1,1′間に、高架
橋スラブ2の長さ方向に沿つた型枠縦動用レール
7,7を有する支持桁6を架設し、他方、架台8
の上面部に、高架橋スラブ2の巾の数分割巾に形
成した型枠体10を昇降自在に設けると共に、架
台8の両端部下面に型枠横動用レール4上を走行
できる車輪9,9を着脱自在に設けた走行型枠装
置Aを構成し、該走行型枠装置Aの複数個を、前
記型枠横動用レール4,4上にその車輪9,9を
介して載架搬入して並置し、各走行型枠装置Aを
ジヤツキ14の伸縮操作により型枠横動用レール
4,4上に車輪に代わり台座15,15を介して
支持させると共に、前記支持桁6上には支保工1
3を介して型枠体10aを設置して、前記全型枠
体10,10a,11上にスラブコンクリートを
打設し、該コンクリートの硬化後、走行型枠装置
Aの型枠体10,11を降下させてコンクリート
より剥離させ、ジヤツキ14の伸縮操作により台
座15を除去して走行型枠装置Aを型枠横動用レ
ール4,4上に車輪9,9を介して支持させると
共に、支持桁6より型枠体10aと支保工13を
撤去し、型枠縦動用レール7,7上には、前記型
枠横動用レール4と平行となる載置レール17を
有する台車16を一対走行自在に載置し、各走行
型枠装置Aを前記型枠横動用レール4,4上を移
動させて前記台車16の載置レール17上に移乗
させ、各走行型枠装置Aを台車16,16により
順次次の施工橋脚間に走行移動させ、該橋脚間の
型枠横動用レール4,4上に移乗させて走行、搬
入することを特徴とするものである。 「実施例」 以下、本発明の実施例について図面を参照して
説明する。 図において1,1′は施工する高架橋スラブ2
の巾方向に所定の間隔をおいて列設された橋脚
で、この一対の橋脚1,1′は高架橋スラブ2の
長さ方向に、ほぼ等間隔をおいて列設されてお
り、それら橋脚1,1′,1,1′……の上に高架
橋スラブ2を構築するのである。この高架橋スラ
ブ2は、その横断面からみると、一般的には、橋
脚1,1′間にある中央部分aと、その両側にあ
つて橋脚1,1′より外方に突出した張出部分b,
bとが連続した形となつている(第1図参照)。
本発明の実施例は、このような高架橋スラブ2の
施工を例として説明するが、しかし、本発明は、
前記の張出部分b,bを持たないような高架橋ス
ラブの施工にも適用可能である。 高架橋スラブ2の巾方向に立設された各対の橋
脚1,1′の隣の対の橋脚1,1′との対向面側、
即ち橋脚1,1′のスラブ2の巾方向に沿う側面
の上部には、それぞれブラケツト3,3を取付
け、その上に高架橋スラブ2の巾方向に沿つて長
く形成した型枠横動用レール4,4を架設する。
このレール4,4は、その内端はそれぞれ橋脚
1,1′の対向する端面で終わつており、また、
その外端は高架橋スラブ2の張出部分bの外端近
くまで延長されている。なお、この型枠横動用レ
ール4は、図示のようにI形鋼自体を適用しても
よく、或はI形鋼の上に別途レールを敷設したも
のでもよい。また、それら橋脚1,1′の対向面
側にもそれぞれブラケツト5,5が前記ブラケツ
ト3より低い位置に取付けられ、それらブラケツ
ト5,5上に、橋脚1,1′の間隔内に入る巾の
支持桁6が高架橋スラブ2の長さ方向に沿つて架
設され、その支持桁6上には一対の型枠縦動用レ
ール7,7が設けられる。なお、このレール7は
図示のように支持桁6に使用のI形鋼の上面をそ
のまま適用することができる。 A,A……はそれぞれ対向して架設された型枠
横動用レール4,4間に載架する走行型枠装置
で、各同様に形成されており、断面方形状をなし
た架台8の両端部下面に前記の型枠横動用レール
4に係合して走行できる車輪9,9が着脱自在に
設けられ、また、架台8の上面部には、バタ材に
せき板を取付けた、高架橋スラブ2の巾の数分割
巾に形成した型枠体10が、架台8に上下動調節
自在に設けた調節ボルト12,12により昇降自
在に設けられた構造となつている。そして、この
走行型枠装置Aの巾は、対向する橋脚1,1′の
間を支持桁6の長さ方向、即ち高架橋スラブ2の
長さ方向に沿つて移動できる巾に形成されてい
る。そして、支持桁6のレール7,7上には、型
枠横動用レール4と平行な載置レール17に前記
のレール7,7上を走行できる車輪18,18を
高さ調節装置19を介して取付けた台車16が載
置されるようになつている。 それで、上記構成の走行型枠装置A,A……
は、第1図、及び第5図イに示すように、列設の
橋脚1,1′,1,1′間を施工の単位区間とし
て、それらの橋脚1,1′に架設されて対向する
型枠横動用レール4,4上に車輪9,9を介して
載架し、レール4,4上を所定の位置まで走行移
動して並列させる。ついで、第5図ロのように、
架台8レール4との間にジヤツキ14,14を介
入し、ジヤツキ14の伸長により架台8を杠上し
て車輪9,9を取外し、それに代わつてレール4
上に台座15,15を載置し、第5図のハのよう
に、ジヤツキ14を短縮してその台座15,15
上に架台8を降下して支持させる。そして、第2
図、第5図ニ及び第6図のように型枠体10を調
節ボルト12,12の調節で所定の高さ位置にセ
ツトする。 また、支持桁6上には、所要高さの支保工13
(第2図参照)を介して、高架橋スラブ2の橋脚
1,1′間の中央部分下側にあてる中央型枠体1
0aを架設する。また、並列した各走行型枠装置
A,Aの各外端に位置するものには、高架橋スラ
ブ2の張出部bの下側にあてる張出型枠体11を
付加する。 次に、それら型枠体10,10a,11の上に
高架橋スラブ2の鉄筋を組立てコンクリートを打
設する。コンクリートの硬化後は、支保工13及
び型枠体10aを取除くと共に、各走行型枠装置
Aの調節ボルト12,12を操作して型枠体1
0,11をコンクリートより剥離、降下させ型枠
体11を取除き、ついで再びジヤツキ14,14
を架台8とレール4との間に介入して、前記同様
の操作により、架台8を車輪9,9を介してレー
ル4,4上に支持させる(第5図イ参照)と共
に、支持桁6より型枠体10aと支保工13を撤
去する。 そして、第3図のように、支持桁6のレール
7,7上に、前記の台車16,16を載置して、
そのレール17をレール4,4を結ぶ線上に位置
させると共に、そのレール17の高さを高さ当節
装置19の調節によりレール4の高さに合わせ
る。次に、各走行型枠装置A,Aのうち支持桁6
に近いものを、型枠横動用レール4,4上を走行
させて、第4図のように、その車輪9,9を台車
16のレール17上に移乗、載置させる。 続いて、台車16,16上に乗つた走行型枠装
置Aを押進し、第7図に示すように、支持桁6上
を走行させ、次の施工区間である橋脚1,1′,
1,1′間に移動し、台車16のレール17,1
7を次の区間の橋脚に取付けた型枠横動用レール
4,4に合致させ、その走行型枠装置Aを同レー
ル4,4上に移乗させて、次の橋脚1,1,1′,
1間に走行搬入し載架するのである。 このようにして走行型枠装置Aの移動が終えた
なら、台車16,16を元の位置に戻して次の走
行型枠装置Aを台車16,16に移乗させ、同様
にして次の橋脚1,1間に挿入架設し、上述の作
業を繰り返して走行型枠装置A,A……のすべて
の移動を終えるのである。そして、各型枠体1
0,10,10a,11,11を所定の位置にセ
ツトし、以下同様にして、各列設橋脚1,1間の
施工を継続して行くのである。 なお、走行型枠装置Aを昇降させるジヤツキ1
4は架台8に装着したままであつてもよく、車輪
9も前記実施例のように着脱自在とせず、固定式
にしてもよく、その場合、台座15は車輪9に隣
接して介在させればよい。また、支持桁は、前記
実施例のように、必ずしも橋脚に取付けのブラケ
ツトに架設しないでもよく、例えば、地上に組ん
だ支保工に架設することもできる。 「発明の効果」 以上説明したように、本発明工法は、列設した
各橋脚に、高架橋スラブの巾方向に沿う型枠移動
用レールを架設すると共に、該スラブ中央部の橋
脚間に該スラブの長さ方向にわたる支持桁を架設
し、該スラブの巾の数分割に形成した走行型枠装
置を橋脚間の型枠横動用レール上に並列載架して
スラブコンクリートを打設し、該コンクリートの
硬化後は、各走行型枠装置を型枠横動用レール上
を走行移動させて、支持桁上を走行できる台車上
に移乗させ、台車の走行により走行型枠装置を次
の施工橋脚間に移動させて、該橋脚間の型枠横動
用レール上に載せて所定の位置に走行搬入するよ
うにしたので、施工橋脚間にセツトするスラブの
型枠は、施工の単位区間である橋脚間での施工の
都度、組立て解体をすることなく移動することが
でき、しかも、その移動はすべて走行によるた
め、移動のためのクレーンの設置も必要なく、そ
して、型枠装置は分割巾の小型、軽量であるた
め、走行移動は容易、安全で能率よく行うことが
でき、また、走行型枠装置は、その移動時だけに
車輪を使用し、コンクリートの打設時には台座を
介して支持するようにしたので、車輪も型枠装置
の移動時の荷重に耐えるだけのものでよいため、
簡易、安価なものとすることができ、型枠移動用
車輪の経費も節減することができる等、多くの優
れた効果を有するものである。
"Industrial Field of Application" The present invention relates to a method for constructing movable formwork for elevated bridge slabs, which enables continuous construction of elevated bridge slabs for railways, roads, etc. ``Conventional technology'' Construction of concrete viaducts involves constructing structures of almost the same shape continuously, so in order to simplify construction work and improve efficiency, mobile mold construction is recommended. Construction methods using frames have come to be adopted. This type of mobile formwork construction method is, for example,
As shown in Publication No. 37363, shoring is erected and a formwork is assembled on it, and the formwork is moved using a large crane such as a portal crane. Therefore, not only is it necessary to install a particularly large crane, but also a large dedicated site is required for installing and moving the crane, which increases costs. In addition, in mountainous areas or when the piers are very high, it is extremely difficult to install large cranes, so mobile formwork cannot be used for such construction, and traditional hand-building and hand-building methods are not possible. The reality is that the formwork construction is inefficient and requires a lot of manpower. "Problems to be Solved by the Invention" In order to solve the problems of this type of construction method using movable formwork, the present inventor has previously published Japanese Patent Application Laid-Open No. 58-94504.
We have been developing a construction method in which the formwork is moved as shown in the publication. By further improving the above-mentioned invention, the present invention can further improve the economic efficiency of construction, improve the ease of work, safety, and efficiency, and further improve the weight of the formwork equipment used. The aim is to provide a new formwork construction method that can reduce costs and reduce costs. "Means for Solving the Problems" The movable formwork construction method of the present invention will be explained with reference to drawings corresponding to embodiments. A plurality of piers 1, 1' are arranged in a row, and sets of the piers 1, 1' arranged in a row are arranged in a row at a predetermined interval in the length direction of the viaduct. Bracket 3,
3, formwork lateral movement rails 4, 4 along the width direction of the slab 2 are constructed except between the piers 1, 1' which are opposite to each other at the center of the slab 2, and A support girder 6 having rails 7, 7 for longitudinal movement of the formwork along the length direction of the viaduct slab 2 is installed between the piers 1, 1', and a pedestal 8
A form body 10 formed to have a width divided by several parts of the width of the viaduct slab 2 is provided on the upper surface portion so as to be movable up and down, and wheels 9, 9 that can run on the formwork lateral movement rails 4 are provided on the lower surface of both ends of the pedestal 8. A removably installed traveling formwork device A is configured, and a plurality of the traveling formwork devices A are loaded on the formwork lateral movement rails 4, 4 via their wheels 9, 9 and placed side by side. Then, each traveling formwork device A is supported on the formwork lateral movement rails 4, 4 via pedestals 15, 15 instead of wheels by telescopic operation of the jacks 14, and shoring 1 is installed on the support girder 6.
3, and place slab concrete on all the formwork bodies 10, 10a, 11. After the concrete hardens, formwork bodies 10, 11 of the traveling formwork device A are installed. is lowered and peeled off from the concrete, and the pedestal 15 is removed by the expansion and contraction operation of the jack 14, and the traveling formwork device A is supported on the formwork lateral movement rails 4, 4 via wheels 9, 9, and the support girder 6, the formwork body 10a and the support 13 are removed, and a pair of carts 16 having mounting rails 17 parallel to the rails 4 for horizontal movement of the formwork are mounted on the rails 7, 7 for vertical movement of the formwork, so that they can freely run. Each traveling formwork device A is moved on the formwork lateral movement rails 4, 4 and transferred onto the mounting rail 17 of the truck 16, and each traveling formwork device A is moved by the truck 16, 16. It is characterized in that it is moved sequentially between the piers to be constructed and transferred to the formwork lateral movement rails 4, 4 between the piers to be transported and transported. "Embodiments" Examples of the present invention will be described below with reference to the drawings. In the figure, 1 and 1' are the viaduct slabs 2 to be constructed.
A pair of piers 1 and 1' are arranged in a row at a predetermined interval in the width direction of the viaduct slab 2, and these piers 1 and 1' are arranged in a row at approximately equal intervals in the length direction of the viaduct slab 2. , 1', 1, 1'..., the viaduct slab 2 will be constructed. This elevated bridge slab 2, when viewed from its cross section, generally has a central portion a located between the piers 1 and 1', and overhanging portions on both sides of the central portion a that protrude outward from the piers 1 and 1'. b,
b are continuous (see Figure 1).
The embodiments of the present invention will be explained by taking the construction of such a viaduct slab 2 as an example, but the present invention
It is also applicable to the construction of elevated bridge slabs that do not have the above-mentioned overhanging portions b and b. The side facing the adjacent pair of piers 1, 1' of each pair of piers 1, 1' erected in the width direction of the viaduct slab 2,
That is, brackets 3, 3 are attached to the upper portions of the side surfaces of the piers 1, 1' along the width direction of the slab 2, respectively, and on top of these brackets 4, a formwork lateral movement rail 4, which is formed long along the width direction of the viaduct slab 2, is installed. Erection 4.
The rails 4, 4 terminate at their inner ends at opposite end faces of the piers 1, 1', respectively, and
Its outer end extends close to the outer end of the overhanging portion b of the viaduct slab 2. The formwork lateral movement rails 4 may be made of I-beams themselves as shown in the figure, or may be formed by separately laying rails on the I-beams. Further, brackets 5, 5 are installed on the opposite sides of the piers 1, 1' at positions lower than the bracket 3, respectively, and on these brackets 5, 5, there are provided brackets 5, 5 with a width that falls within the interval between the piers 1, 1'. A support girder 6 is constructed along the length direction of the viaduct slab 2, and a pair of formwork longitudinal movement rails 7, 7 are provided on the support girder 6. Note that the upper surface of the I-beam used for the support girder 6 can be applied to the rail 7 as is, as shown in the figure. A, A... are traveling formwork devices mounted between rails 4, 4 for horizontal movement of formwork, which are installed opposite each other, and are formed in the same way, with both ends of a pedestal 8 having a rectangular cross section. Wheels 9, 9 that can run while engaging with the formwork lateral movement rails 4 are removably provided on the lower surface, and on the upper surface of the pedestal 8, a viaduct slab made of butter material with a weir plate attached is provided. A frame body 10 formed to have a width divided into several widths of 2 is movable up and down by adjustment bolts 12, 12 provided on a pedestal 8 so as to be vertically adjustable. The width of the traveling formwork device A is such that it can move between the opposing piers 1 and 1' in the length direction of the support girder 6, that is, along the length direction of the viaduct slab 2. On the rails 7, 7 of the support girder 6, wheels 18, 18 that can run on the rails 7, 7 are mounted on a mounting rail 17 parallel to the formwork lateral movement rail 4 via a height adjustment device 19. The trolley 16 attached thereto is placed thereon. So, traveling formwork devices A, A with the above configuration...
As shown in Fig. 1 and Fig. 5 A, the unit section of construction is between the piers 1, 1', 1, 1' in a row, and the bridges are constructed on the piers 1, 1' and facing each other. The molds are mounted on the formwork lateral movement rails 4, 4 via wheels 9, 9, and run on the rails 4, 4 to a predetermined position to be arranged in parallel. Then, as shown in Figure 5 B,
Jacks 14, 14 are interposed between the pedestal 8 and the rail 4, and the pedestal 8 is lifted up by the extension of the jack 14, the wheels 9, 9 are removed, and the wheels 9, 9 are removed.
Place the pedestals 15, 15 on top, shorten the jack 14, and attach the pedestals 15, 15 as shown in FIG.
The pedestal 8 is lowered and supported. And the second
The form body 10 is set at a predetermined height position by adjusting the adjusting bolts 12, 12 as shown in FIGS. Also, on the support girder 6, a support 13 of the required height is installed.
(see Figure 2), the central formwork 1 is applied to the lower side of the central part between the piers 1 and 1' of the viaduct slab 2.
Erection 0a. Moreover, an overhanging formwork body 11 is added to the one located at each outer end of each of the parallel traveling formwork apparatuses A, A, which is applied to the lower side of the overhanging part b of the viaduct slab 2. Next, reinforcing bars for the viaduct slab 2 are assembled on top of the form bodies 10, 10a, and 11, and concrete is poured. After the concrete has hardened, remove the shoring 13 and the formwork body 10a, and operate the adjustment bolts 12, 12 of each traveling formwork device A to adjust the formwork body 1.
0 and 11 are peeled off from the concrete and lowered to remove the form body 11, and then jacked again.
is inserted between the pedestal 8 and the rail 4, and by the same operation as described above, the pedestal 8 is supported on the rails 4, 4 via the wheels 9, 9 (see Fig. 5 A), and the support girder 6 is Then, the form body 10a and the shoring 13 are removed. Then, as shown in FIG. 3, the carts 16, 16 are placed on the rails 7, 7 of the support girder 6, and
The rail 17 is positioned on a line connecting the rails 4, 4, and the height of the rail 17 is adjusted to the height of the rail 4 by adjusting a height adjustment device 19. Next, support girder 6 of each traveling formwork device A,
4 is run on the formwork lateral movement rails 4, 4, and its wheels 9, 9 are transferred and placed on the rails 17 of the trolley 16, as shown in FIG. Next, the traveling formwork device A mounted on the carts 16, 16 is pushed forward, and as shown in FIG.
1, 1', and move to the rails 17, 1 of the trolley 16.
7 is aligned with the formwork lateral movement rails 4, 4 attached to the piers of the next section, the traveling formwork device A is transferred onto the same rails 4, 4, and the next piers 1, 1, 1',
It is carried in between 1 and placed on a rack. When the movement of the traveling formwork device A is completed in this way, the carts 16, 16 are returned to their original positions, the next traveling formwork device A is transferred to the carts 16, 16, and the next pier 1 is moved in the same manner. , 1, and repeat the above-mentioned operations to complete the movement of the traveling formwork devices A, A, . . . . And each formwork body 1
0, 10, 10a, 11, 11 are set at predetermined positions, and the construction between the row piers 1, 1 is continued in the same manner. In addition, the jack 1 that raises and lowers the traveling formwork device A
4 may remain attached to the pedestal 8, and the wheels 9 may also be fixed instead of being detachable as in the previous embodiment. In that case, the pedestal 15 may be interposed adjacent to the wheels 9. Bye. Further, the support girder does not necessarily have to be installed on the bracket attached to the bridge pier as in the above embodiment, but can also be installed on a support built on the ground, for example. "Effects of the Invention" As explained above, the construction method of the present invention erects rails for moving the formwork along the width direction of the viaduct slab on each of the piers arranged in a row, and A support girder extending in the length direction is erected, and a traveling formwork device formed into several parts of the width of the slab is mounted in parallel on the formwork lateral movement rail between the piers, and slab concrete is poured. After curing, each traveling formwork device is moved on the formwork lateral movement rail and transferred to a trolley that can travel on the support girder. Since the formwork was moved and placed on the rail for lateral movement of the formwork between the piers and transported to a predetermined position, the formwork of the slab to be set between the construction piers was moved between the piers, which is the unit section of construction. It is possible to move the formwork without having to assemble and dismantle it each time it is constructed.Moreover, all movement is done by traveling, so there is no need to install a crane for movement, and the formwork equipment is small and lightweight with a split width. Therefore, traveling movement can be carried out easily, safely and efficiently, and the traveling formwork equipment uses wheels only when moving, and is supported through a pedestal when pouring concrete. Therefore, the wheels only need to be able to withstand the load when the formwork equipment is moved.
It has many excellent effects, such as being simple and inexpensive, and reducing the cost of wheels for moving the formwork.

【発明の詳細な説明】[Detailed description of the invention]

図面は本発明工法の一実施例を略示したもの
で、第1図は橋脚間に走行型枠装置を搬入並列し
た状態を示す正断面図、第2図は高架橋スラブの
型枠をセツトした状態を示す正断面図、第3図は
型枠を剥離し、支持桁上に台車を載置したところ
を示す正断面図、第4図は台車上に走行型枠装置
を移乗させたところを示す正断面図、第5図イ〜
ニは走行型枠装置の搬入から型枠セツト時までの
作業順序を示す正面図、第6図は走行型枠装置及
び支持桁の架設状態を示す側面図、第7図は走行
型枠装置を台車に移乗させて次の橋脚間に移乗さ
せたところを示す側面図である。 A……走行型枠装置、1,1′……橋脚、2…
…高架橋スラブ、3,5……ブラケツト、4……
型枠横動用レール、6……支持桁、7……型枠縦
動用レール、8……架台、9……車輪、10,1
1……型枠体、12……調節ボルト、13……支
保工、14……ジヤツキ、15……台座、16…
…台車、17……載置レール、18……車輪、1
9……高さ調節装置。
The drawings schematically show one embodiment of the construction method of the present invention. Figure 1 is a front cross-sectional view showing the state in which traveling formwork devices are carried in between the piers and arranged in parallel, and Figure 2 is a diagram showing the formwork of the viaduct slab set. Figure 3 is a front cross-sectional view showing the state, with the formwork peeled off and the trolley placed on the support girder, and Figure 4 is a front cross-sectional view showing the trolley mounted on the trolley. Front cross-sectional view shown in Figure 5 I~
D is a front view showing the work order from carrying in the traveling formwork device to setting the formwork, FIG. 6 is a side view showing the installation state of the traveling formwork device and the support girder, and FIG. 7 is the traveling formwork device. It is a side view which shows the place where it was made to transfer to the trolley|bogie and was made to transfer between the next piers. A... Traveling formwork device, 1, 1'... Pier, 2...
... Viaduct slab, 3, 5... Bracket, 4...
Rail for horizontal movement of the formwork, 6... Support girder, 7... Rail for vertical movement of the formwork, 8... Frame, 9... Wheels, 10, 1
1... Form body, 12... Adjustment bolt, 13... Shoring, 14... Jacket, 15... Pedestal, 16...
...Dolly, 17...Package rail, 18...Wheel, 1
9...Height adjustment device.

Claims (1)

【特許請求の範囲】[Claims] 1 高架橋スラブの巾方向に所定の間隔をおいて
複数の橋脚を列設し、この列設した橋脚の組を高
架橋の長さ方向に所定の間隔をおいて列設し、そ
れら橋脚に取付けのブラケツトを介して該スラブ
の巾方向に沿つた型枠横動用レールを、該スラブ
中央部の対向する橋脚間を除き架設するととも
に、該スラブ中央部の対向する橋脚間に、高架橋
スラブの長さ方向に沿つた型枠縦動用レールを有
する支持桁を架設し、他方、架台の上面部に、高
架橋スラブの巾の数分割巾に形成した型枠体を昇
降自在に設けると共に、架台の両端部下面に型枠
横動用レール上を走行できる車輪を着脱自在に設
けた走行型枠装置を構成し、該走行型枠装置の複
数個を、前記型枠横動用レール上にその車輪を介
して載架搬入して並置し、各走行型枠装置をジヤ
ツキの伸縮操作により型枠横動用レール上に車輪
に代わり台座を介して支持させると共に、前記支
持桁上には支保工を介して型枠体を設置して、前
記全型枠体上にスラブコンクリートを打設し、該
コンクリートの硬化後、走行型枠装置の型枠体を
降下させてコンクリートより剥離させ、ジヤツキ
の伸縮操作により台座を除去して走行型枠装置を
型枠横動用レール上に車輪を介して支持させると
共に、支持桁より型枠体と支保工を撤去し、型枠
縦動用レール上には、前記型枠横動用レールと平
行となる載置レールを有する台車を一対走行自在
に載置し、各走行型枠装置を前記型枠横動用レー
ル上を移動させて前記台車の載置レール上に移乗
させ、各走行型枠装置を台車により順次次の施工
橋脚間に走行移動させ、該橋脚間の型枠横動用レ
ール上に移乗させて走行、搬入することを特徴と
する、高架橋スラブの移動式型枠工法。
1. A plurality of piers are arranged in a row at a predetermined interval in the width direction of the viaduct slab, and sets of the arranged piers are arranged in a row at a predetermined interval in the length direction of the viaduct. A rail for horizontal movement of the formwork along the width direction of the slab is installed via a bracket except between the opposing piers at the center of the slab, and a rail for the length of the viaduct slab is installed between the opposing piers at the center of the slab. A support girder having rails for vertical movement of the formwork along the direction is erected, and a formwork body formed to have a width divided by several times the width of the viaduct slab is provided on the upper surface of the trestle so that it can be raised and lowered, and both ends of the trestle are A traveling formwork device is configured in which wheels capable of running on a rail for lateral movement of formwork are removably provided on the lower surface, and a plurality of the traveling formwork devices are mounted on the rail for lateral movement of formwork via the wheels. The traveling formwork devices are carried in and placed side by side, and each traveling formwork device is supported on the formwork lateral movement rail via a pedestal instead of wheels by the expansion and contraction operation of jacks, and the formwork body is placed on the support girder via a shoring. After the concrete has hardened, the formwork of the traveling formwork device is lowered to separate it from the concrete, and the pedestal is removed by expanding and contracting the jack. Then, the traveling formwork device is supported on the formwork lateral movement rail via wheels, the formwork body and the shoring are removed from the support girder, and the formwork lateral movement rail is placed on the formwork vertical movement rail. A pair of trolleys having mounting rails parallel to each other are mounted so as to be freely movable, and each traveling formwork device is moved on the rail for horizontal movement of the formwork and transferred onto the mounting rail of the trolley, and each traveling formwork is A mobile formwork construction method for elevated bridge slabs, characterized in that a frame device is sequentially moved by a trolley between the piers to be constructed, and transferred to a rail for horizontal movement of the formwork between the piers to travel and carry it in.
JP4096086A 1986-02-26 1986-02-26 Moving type mold frame construction method high bridge slab Granted JPS62197509A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4096086A JPS62197509A (en) 1986-02-26 1986-02-26 Moving type mold frame construction method high bridge slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4096086A JPS62197509A (en) 1986-02-26 1986-02-26 Moving type mold frame construction method high bridge slab

Publications (2)

Publication Number Publication Date
JPS62197509A JPS62197509A (en) 1987-09-01
JPH0511163B2 true JPH0511163B2 (en) 1993-02-12

Family

ID=12595047

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4096086A Granted JPS62197509A (en) 1986-02-26 1986-02-26 Moving type mold frame construction method high bridge slab

Country Status (1)

Country Link
JP (1) JPS62197509A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5894504A (en) * 1981-11-30 1983-06-04 岡部株式会社 Mold frame moving type constructing process of high bridge slab

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5894504A (en) * 1981-11-30 1983-06-04 岡部株式会社 Mold frame moving type constructing process of high bridge slab

Also Published As

Publication number Publication date
JPS62197509A (en) 1987-09-01

Similar Documents

Publication Publication Date Title
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
JP2808179B2 (en) Mobile bogie device such as arched mobile form device
JPH049901B2 (en)
JPH0511163B2 (en)
JPH0143086B2 (en)
JPH0426377B2 (en)
JPH0481023B2 (en)
JPH0336362B2 (en)
JPH03107098A (en) Travelling type molding frame support
JPH0511162B2 (en)
JPH07116830B2 (en) Traveling cart for moving formwork equipment
JPS5894504A (en) Mold frame moving type constructing process of high bridge slab
JPH049903B2 (en)
JPH049902B2 (en)
JPH0745773B2 (en) Mobile formwork method for multiple viaducts in parallel
JPH049904B2 (en)
JPS62253872A (en) Running movement type mold frame apparatus
JPS62288262A (en) Moving type mold frame construction method of plural high bridging slabs arranged in parallel
JPH0347363B2 (en)
JPS62288261A (en) Moving type mold frame construction method of high bridging slab
JPH0214507B2 (en)
JPS6333557B2 (en)
JPH07116833B2 (en) Mobile formwork method for multiple viaducts in parallel
JPS62288260A (en) Moving type mold frame construction method of high bridging slab
JPH0214508B2 (en)