JPS6151093B2 - - Google Patents
Info
- Publication number
- JPS6151093B2 JPS6151093B2 JP57181769A JP18176982A JPS6151093B2 JP S6151093 B2 JPS6151093 B2 JP S6151093B2 JP 57181769 A JP57181769 A JP 57181769A JP 18176982 A JP18176982 A JP 18176982A JP S6151093 B2 JPS6151093 B2 JP S6151093B2
- Authority
- JP
- Japan
- Prior art keywords
- casing
- ground
- pile
- foundation pile
- bottom plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 239000000463 material Substances 0.000 claims description 6
- 238000010276 construction Methods 0.000 claims description 5
- 125000006850 spacer group Chemical group 0.000 claims description 5
- 239000004576 sand Substances 0.000 description 5
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 239000011148 porous material Substances 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 239000000126 substance Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- -1 gravel Substances 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/34—Foundations for sinking or earthquake territories
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Description
【発明の詳細な説明】
この発明は液状化地盤における杭工法に関する
ものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a pile construction method in liquefied ground.
軟弱砂質地盤では地震により間隙水圧が増加
し、垂直応力から間隙水圧を差し引いた値である
有効応力がゼロとなり、砂はその剪断強度を失つ
て液状化する。 In soft sandy ground, the pore water pressure increases due to an earthquake, and the effective stress, which is the value obtained by subtracting the pore water pressure from the vertical stress, becomes zero, and the sand loses its shear strength and liquefies.
従来この液状化を防止する方法としてケーシン
グ内に砂利、砂等を供給しながら杭を打ち込み砂
利,砂等を通じて排水する工法が特公昭47―
45285号公報に開示されているが、砂利,砂等を
通つて杭を打込むことによつて砂利,砂を地盤中
に持ち込むことは困難であり、杭周に確実に透水
層を形成することを期待しえない。 Conventionally, as a method to prevent this liquefaction, a construction method was developed in 1975, in which piles were driven into the casing while supplying gravel, sand, etc., and drainage was carried out through the gravel, sand, etc.
Although disclosed in Publication No. 45285, it is difficult to bring gravel or sand into the ground by driving a pile through gravel, sand, etc., and it is difficult to ensure that a permeable layer is formed around the pile. I can't expect that.
この発明は前記発明より施工が容易、かつ確実
であり、地盤の置換、排水によつてより効果的な
液状化対策をなすとともに、従来の圧密工法のよ
うな特殊機械設備を必要とせず、ケーシングの引
抜き、撤去も容易となしたもので、以下その詳細
を実施例によつて説明する。 This invention is easier and more reliable to construct than the above-mentioned invention, provides more effective measures against liquefaction by replacing the ground and draining water, and does not require special mechanical equipment like the conventional consolidation method. The structure is easy to pull out and remove, and the details will be explained below using examples.
軟弱砂利地盤Aに鋼管杭、コンクリート杭等の
既製の基礎杭1を所要深さまで、例えば支持地盤
まで打込むとともに基礎1の周囲に所要の間隔を
おいて、先端部に、杭挿通孔を有する底板2を設
けたケーシング3を地中に打込む。 Ready-made foundation piles 1 such as steel pipe piles and concrete piles are driven into soft gravel ground A to a required depth, for example, to the supporting ground, and pile insertion holes are provided at the tips at required intervals around the foundation 1. A casing 3 provided with a bottom plate 2 is driven into the ground.
このケーシング3は複数板を継手4で連結する
とともにバンド5で緊結したもので、基礎杭1の
外周面とケーシング3の内面との間の所要間隔を
保持させるスペーサー6を有する。 This casing 3 is made up of a plurality of plates connected by a joint 4 and tied together by a band 5, and has a spacer 6 for maintaining a required distance between the outer peripheral surface of the foundation pile 1 and the inner surface of the casing 3.
なお施工順序としてケーシング3を打込み、中
掘りしてからその中央部に基礎杭1を打込むこと
ができる。そして何れの場合もケーシング3の打
込み深さは軟弱砂質地盤の深さまででよい。 In addition, as a construction order, the casing 3 can be driven in, and the foundation pile 1 can be driven into the center of the excavation after digging. In either case, the driving depth of the casing 3 may be up to the depth of soft sandy ground.
次いで、ケーシング3内の基礎杭1の周囲に砕
石または砂利その他化学製品等の透水性の高い材
料を充填する。 Next, the area around the foundation pile 1 in the casing 3 is filled with highly water-permeable material such as crushed stone, gravel, or other chemical products.
次いで底板2を残してケーシング3のみを一枚
宛引上げる。引抜き抵抗が大きい場合は振動を加
えながらケーシング3を一枚づつ引抜く。 Next, only the casing 3 is pulled up one by one, leaving the bottom plate 2 behind. If the pulling resistance is large, pull out the casing 3 one by one while applying vibration.
この発明は以上の構成からなり、もつとも重要
である基礎杭の周囲の砂質地盤を透水性の高い砕
石,砂利その他化学製品等の透水の高い材料に置
換え、かつ周辺軟弱砂質地盤からの排水をそれら
材料間を通じて行なうことができる。特に基礎杭
とケーシングとの間にスペーサーを介在させ、そ
れらを地盤中に埋設してから透水性材料を投入す
るので透水性材料を一定厚さに確実に充填するこ
とができる。 This invention has the above-mentioned structure, and replaces the sandy ground around the foundation pile, which is extremely important, with highly permeable materials such as crushed stone, gravel, and other chemical products, and drains water from the surrounding soft sandy ground. can be carried out between these materials. In particular, since a spacer is interposed between the foundation pile and the casing, and the permeable material is introduced after the spacers are buried in the ground, the permeable material can be reliably filled to a constant thickness.
さらにケーシングは分割したものをバンドによ
り緊結してあつてケーシングの引抜きに際しては
一枚宛引上げるので、その作業が容易である。 Further, since the casing is divided into pieces and tied together with a band, and when the casing is to be pulled out, it is pulled up one by one, making the work easy.
第1図、第2図a,b,第3図および第4図は
施工過程の概要を示した縦断面図および横断面
図、第5図、第6図は他の実施例の横断面図であ
る。
A……地盤、1……基礎杭、2……底板、3…
…ケーシング、4……継手、5……バンド、6…
…スペーサー、7……骨材。
Fig. 1, Fig. 2 a, b, Fig. 3, and Fig. 4 are vertical and cross-sectional views showing an overview of the construction process, and Fig. 5 and Fig. 6 are cross-sectional views of other embodiments. It is. A...Ground, 1...Foundation pile, 2...Bottom plate, 3...
...Casing, 4...Joint, 5...Band, 6...
...Spacer, 7...Aggregate.
Claims (1)
たケーシングをバンドにより緊結し、該ケーシン
グをスペーサーにより間隔を保つて、基礎杭の周
囲に配置し、これを地盤中に埋込み、 次いでケーシング内の基礎杭の周囲に、透水性
の高い材料を充填し、前記ケーシングを底板を残
し置いて、一枚宛引上げることを特徴とする液状
化地盤における杭工法。[Scope of Claims] 1. A bottom plate is provided at the tip, a continuous casing of multiple plates is tied together with a band, the casings are placed around the foundation pile with intervals maintained by spacers, and the casing is placed in the ground. A pile construction method for liquefied ground, characterized in that the casing is filled with a highly permeable material around the foundation pile, and the casing is pulled up one by one, leaving the bottom plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18176982A JPS5972321A (en) | 1982-10-16 | 1982-10-16 | Piling work for liquefied ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18176982A JPS5972321A (en) | 1982-10-16 | 1982-10-16 | Piling work for liquefied ground |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5972321A JPS5972321A (en) | 1984-04-24 |
JPS6151093B2 true JPS6151093B2 (en) | 1986-11-07 |
Family
ID=16106559
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18176982A Granted JPS5972321A (en) | 1982-10-16 | 1982-10-16 | Piling work for liquefied ground |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5972321A (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2634071B2 (en) * | 1988-09-29 | 1997-07-23 | 株式会社クボタ | Pile installation method |
JP6715452B2 (en) * | 2015-09-11 | 2020-07-01 | 五洋建設株式会社 | Ground flow countermeasure structure of pile type structure and its construction method |
JP6707778B2 (en) * | 2016-02-26 | 2020-06-10 | 大西 正人 | Excavation member and ground improvement method using the same |
-
1982
- 1982-10-16 JP JP18176982A patent/JPS5972321A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS5972321A (en) | 1984-04-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105464686B (en) | Multi-layer underground space curtain posture excavating construction method and supporting construction under existing facility | |
CN109538246A (en) | Ledge method tunneling subway station arch springing ruggedized construction and construction method | |
CN108442370A (en) | The broken pile connector processing method of prestressed concrete pipe pile | |
CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
JPS60156818A (en) | Compacted deep layer foundation construction and its construction method and apparatus | |
CN108149682A (en) | A kind of slip casting casing device and the pile foundation drilling construction method using the casing device | |
JPH02232416A (en) | Foundation pile structure | |
JPS6151093B2 (en) | ||
JP2000136541A (en) | Liquefaction preventing construction method | |
JPH05302318A (en) | Method and apparatus for stabilizing friction soiland adjacent cohesion soil layers | |
US4981399A (en) | Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall | |
JP2730705B2 (en) | Improvement method for soft ground | |
JPH01278612A (en) | Method of taking countermeasure against liquefaction of linear structure buried in ground | |
CN109667278A (en) | Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing | |
JPS621930A (en) | Foundation structure of underground structure | |
JP3099040B2 (en) | Embankment culvert | |
JP3176530B2 (en) | Liquefaction countermeasures | |
JPS60144412A (en) | Liquefaction preventive foundation structure for ground | |
JP2927612B2 (en) | Foundation method | |
JPH0415791Y2 (en) | ||
JPS58127823A (en) | Liquefaction preventive structure of foundation ground | |
JPS6240488B2 (en) | ||
GB1577199A (en) | Method of constructing underground gallery | |
JPH02104812A (en) | Ground reinforcing drain pipe | |
JPH0649988B2 (en) | Basics of landfill structure |