GB1577199A - Method of constructing underground gallery - Google Patents
Method of constructing underground gallery Download PDFInfo
- Publication number
- GB1577199A GB1577199A GB2018778A GB2018778A GB1577199A GB 1577199 A GB1577199 A GB 1577199A GB 2018778 A GB2018778 A GB 2018778A GB 2018778 A GB2018778 A GB 2018778A GB 1577199 A GB1577199 A GB 1577199A
- Authority
- GB
- United Kingdom
- Prior art keywords
- gallery
- backfill
- pit
- initially applied
- initially
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000000034 method Methods 0.000 title claims description 50
- 239000000463 material Substances 0.000 claims description 62
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 19
- 239000002689 soil Substances 0.000 claims description 18
- 230000000694 effects Effects 0.000 claims description 17
- 239000000203 mixture Substances 0.000 claims description 14
- 239000011398 Portland cement Substances 0.000 claims description 12
- 239000004567 concrete Substances 0.000 claims description 9
- 230000000087 stabilizing effect Effects 0.000 claims description 7
- 239000004615 ingredient Substances 0.000 claims description 6
- 239000004568 cement Substances 0.000 claims description 5
- 239000004576 sand Substances 0.000 claims description 5
- 239000011435 rock Substances 0.000 claims description 4
- 239000002131 composite material Substances 0.000 claims description 3
- 235000008733 Citrus aurantifolia Nutrition 0.000 claims description 2
- 235000011941 Tilia x europaea Nutrition 0.000 claims description 2
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 238000001035 drying Methods 0.000 claims description 2
- -1 for example Substances 0.000 claims description 2
- 239000004571 lime Substances 0.000 claims description 2
- 229920005989 resin Polymers 0.000 claims description 2
- 239000011347 resin Substances 0.000 claims description 2
- 230000006641 stabilisation Effects 0.000 claims description 2
- 238000011105 stabilization Methods 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 15
- 238000005056 compaction Methods 0.000 description 9
- 230000008093 supporting effect Effects 0.000 description 9
- 238000007792 addition Methods 0.000 description 5
- 238000009412 basement excavation Methods 0.000 description 5
- 239000007788 liquid Substances 0.000 description 3
- 239000002002 slurry Substances 0.000 description 3
- 239000011800 void material Substances 0.000 description 3
- 239000000654 additive Substances 0.000 description 2
- 238000005266 casting Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 238000011065 in-situ storage Methods 0.000 description 2
- 230000000717 retained effect Effects 0.000 description 2
- 208000031968 Cadaver Diseases 0.000 description 1
- 229910001018 Cast iron Inorganic materials 0.000 description 1
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 150000001768 cations Chemical class 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000001747 exhibiting effect Effects 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 230000000284 resting effect Effects 0.000 description 1
- 239000003381 stabilizer Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 208000016261 weight loss Diseases 0.000 description 1
- 239000013585 weight reducing agent Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/12—Temporary supports for use during building; Accessories
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Architecture (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
(54) METHOD OF CONSTRUCTING UNDERGROUND
GALLERY
(71) We, PROMON ENGENHARIA
SA, a Corporation organized~ and existing under the laws of Brazil, of Avenida 9 de
Julho 4939, 01407 Sao Paulo SP, Brazil, do hereby declare the invention, for which we pray that a patent may be granted to us, and the method by which it is to be performed, to be particularly described in and by the following statement: The invention relates to a method of constructing underground galleries and finds particular application in the construction of tunnels which may be considered as a series of galleries joined end-to-end.
Throughout the specification the term "gallery" is used to describe the invention and such term is intended to include isolated galleries and chambers as well as tunnels.
The construction of tunnels has traditionally raised problems due to the large forces exerted by the earth or ground medium surrounding the tunnel. The construction of large diameter tunnels, such as are suitable for accommodating subways or roads, has proved particularly problematical due to the relatively large structural dimensions involved. On the other hand, the laying of relatively small diameter pipes is not so difficult since it is less easy for the overlying earth to crush the pipe. The present invention is primarily concerned with the construction of large diameter galleries such as, for example, subway tunnels.
Traditionally underground galleries and similar structures have been formed by one of two methods.
The first method involves boring below the earth's surface and shoring up as the gallery or tunnel progresses.
The second method is the so-called "cut and cover" method whereby a pit or trench
is excavated and the gallery or tunnel is
assembled or built on the floor of the pit or
trench. Thereafter the trench is filled to cover the gallery or tunnel. In such a case the gallery
or tunnel itself supports the entire load of
the infilled earth material.
The present invention represents an improvement in the cut and cover method and makes it possible substantially to reduce the thickness of the gallery shell, thereby effecting a saving in materials. This is made possible by the fact that the applied backfill together with the gallery acts to support the total load of backfill, buildings, traffic, etc., thereby removing much of the stress which would otherwise be applied directly to the gallery shell. Put another way, structures for galleries constructed by the "cut and cover method" must withstand by themselves all stresses originated by the total backfill weight.
Consequently, those structures use large quantities of structural materials which substantially increases the cost of construction. In addition the greater consumption of materials complicates the use of precast units because of excessive weight or the need of a great number of joints. The present invention makes possible a reduction in the amount of structural materials utilised in galleries since the backfill becomes a structural element and the stresses originated by the total backfill weight are withstood jointly by the structure of the gallery and the backfill.
The present invention involves a development of the known cut and cover method of constructing an underground gallery and provides an improvement over prior methods in that in the finished gallery the ground load above the gallery is not supported solely by the gallery shell.
The method of the present invention includes the steps of excavating a trench and locating a gallery within the trench. The gallery may either be built in situ on the trench floor, or preferably, prefabricated in annular sections which are lowered into the trench and subsequently joined together to form the completed structure.
The trench is then refilled, but before the refill material can exert any substantial force on the gallery the gallery is braced by internal braces. The braces are most conveniently applied either before prefabricated sections are lowered into position or when the sections have been joined and before introduction of the backfill. Although these are the most convenient times to insert the braces, it would of course be possible to have the braces positioned during the initial stages of backfilling providing care is taken to ensure the bracing is completed before the backfill begins to apply any substantial force. In this manner the braces reinforce the gallery structure to withstand the load of the backfill.
The crux of the invention resides in the controlled application of the initial backfill in such manner that upon removal of the bracing from within the gallery the backfill initially applied which completely covers the gallery will form in conjunction with the gallery structure a load supporting arch over said gallery.
At that point in time final backfill may be applied to complete filling of the trench and the weight of such final backfill will be borne jointly by the initially applied backfill and the gallery structure and not, as in the case of the prior art, solely by the gallery. Removal of the bracing may be effected at any time after the initially applied backfill is capable of adopting its load supporting function. Upon removal of the bracing there will be some, necessarily minor, deformation of the gallery shell. This minor deformation will cause some shifting and redistribution of the applied backfill in the immediate vicinity. It is the redistribution of the applied backfill that creates the arching structure internally within the body of the backfill material.
According to the present invention, there is provided a method of constructing an underground gallery comprising excavating to form a pit having a depth greater than the overall height of the gallery, locating the gallery within the pit, internally bracing the structure of said gallery to withstand loads exerted by ground material upon refilling of the pit, covering the gallery and filling the pit with ground material, said covering being effected initially by applying and compacting backfill material in incremental steps around and over the gallery, removing the bracing from within the gallery and thereby causing said initially applied backfill material to adopt an internal arching structure which together with said gallery will support applied loads, and completing the filling of the pit.
The actual point at which the initially applied backfill will assume a state of compaction and adopt an internal structure to support the subsequently applied load of final backfill and its own weight will depend on the nature of the ground material in which the gallery is constructed. Some soils have a consistency such that the arching effect will occur relatively close to the crown of the gallery and are generally termed "good soils" and neither special treatment thereof nor additions thereto is necessary. On the other hand, some soils, e.g. sandy or silty clays, without special treatment would either not adopt a load supporting condition or would only do so at a substantial height, for example more than 10 meters above the arch crown.The present invention teaches the treatment of such materials for example, by the addition of a stabilizing agent such as portland cement, to lower the height at which the supporting arch is formed. The amount of cement added will obviously govern the "stiffness" induced into the ground material to make it less deformable. Such treated material is generally referred to as "soil cement" and although it does not set to a rigid crust in the manner of a pavement it does stabilize the initially applied backfill to adopt a condition where compaction of the backfill will result in a load bearing arch in the preferred range of from two to four meters above the gallery.
As explained, the point at which the load supporting condition is reached will depend upon the stiffness induced into the initially applied backfill and this, in turn, will affect selection of the thickness of the gallery structure. This can be illustrated by considering the arching effect adopted by the initially applied backfill over and above the gallery.
With the arching effect so adopted upon removal of the bracing backfill above the arch will be supported jointly by the arch and gallery structure. Consequently the stiffer the initial backfill the closer to the gallery is the arching supporting effect achieved and the thinner may be the walls of the gallery.
This eviaences a major advantage of the invention which makes it possible to reduce the amount of material utilized in building the gallery shell which not only represents a saving in cost of material employed but also facilitates construction by making it possible more easily to handle the gallery sections prior to embedding them within the ground.
The stiffness or deformability of the material used to refill the trench, which most conveniently will be the excavated ground material, will be considered in conjunction with its ability to settle which governs the elapse of time before a stable condition is reached and, in addition, any creep (i.e.
deformation slowly over a period of years) characteristics of the ground material. By the addition of stabilizing material to the initially applied backfill, the time taken to settle will be shortened and creep eliminated.
Finally, water action also affects stresses on a constructed gallery since buoyancy will tend to reduce pressures exerted by the backfill.
Furthermore, pressures due to water will act directly on the gallery shell confined by the backfill material and will . remain constant.
To a certain extent, the shape of the gallery can reduce the effect of such pressure and in all the examples described and illustrated in the description of preferred embodiments the gallery is of substantially circular configuration. This, however, is not essential and, for example, a horizontally orientated hourglass configuration might be appropriate if the gallery is to be a tunnel dimensioned to accommodate twin tracks of a subway.
Before beginning excavation of the trench it is generally necessary to lower the water table by means of dewatering. This may be accomplished in any of a number of conventional ways. Upon completion of the backfilling operation the dewatering is stopped.
Thereupon the water will seep back and exert pressure on the gallery.
Although the depth of excavation of the trench will obviously depend upon the indi
vidual circumstances, in case of cut and cover methods including the method of the invention depths will usually be in the range of
from 2 to 4 times the height of the gallery.
In order that the present invention may be
more clearly understood and readily carried
into effect, a nurnber of embodiments will
now be described with reference to the
accompanying drawings, in which: - Figures 1(a) through l(d) schematically
represent the sequential steps of con
structing an underground gallery by a
method in accordance with one embodi
ment of the invention, Figures 2(a) and 2(b) show an alterna
tive method of construction in accor
dance with a second embodiment of the
invention, - Figures 3(a) through 3(c) show a
further embodiment of the invention, - Figures 4(a) through 4(c) show a still
further embodiment of the invention, - Figure 5 shows an alternative detail of
construction which may be incorporated
in any of the embodiments of Figures
1 to 4, - Figure 6 shows a further alternative
detail which may be incorporated in any
of the embodiments of Figures 1 to 4, - Figure 7 shows an alternative of a
different detail of construction which
may be incorporated in any of the
embodiments of Figures 1 to 4, and - Figure 8 is a schematic diagram show
ing dimensional parameters referred to
in specific examples given in the follow
ing description.
Referring now to the drawings in which
like reference numerals are used to indicate
corresponding parts in the several illustrated
embodiments, Figures 1(a) through l(d) show a first embodiment of the invention. As
is most clearly shown in Figure 1(a) a trench has been excavated by any conventional method and is shown with downwardly and inwardly sloping side walls (30) to eliminate the need for retaining braces. The conventional method adopted for excavating the trench will be largely determined by the circumstances and will depend upon a number of factors including, inter alia, the type of soil, excavation depth, loads imposed by adjacent buildings, protection of existing foundation and ground water level.
In the case of a high water table in the area where the tunnel or gallery is to be constructed, it will first be necessary to lower the ground water level. The lowering of the water level or dewatering may be achieved by any acceptable method and will not be described in detail.
Following excavation of the trench, compaction of the trench bottom may be effected by tamping or other compacting methods to provide a firm foundation for the gallery. To this end, the gallery may simply rest on the bottom of the trench for which purpose the trench bottom may be appropriately profiled as shown at 49 in Fgure ~5.Sore~ usually, however, and as shown in Figures 1 through 4, a cradle (32) is placed on the trench bottom and is profiled to support the gallery (31).
Figure 6 shows an embodiment where the gallery also rests on the bottom of the trench.
In this case, however, the trench bottom is not profiled, but instead the gallery rests directly on the trench bottom which has been appropriately hardened by tamping and is retained in position by wedges (51) which may either be applied in the manner of chocks or may be an integral part of the casting of the gallery. More usually, however, a cradle (32) is placed on the trench bottom and profiled to support the gallery (31). Again, the actual construction of such a cradle will vary depending on the circumstances and may, for example, be in the form of a one piece poured casting or in the form of a prefabricated structure which is assembled on site on the trench bottom. If a poured in place or precast concrete cradle is used it should, for purposes of complete support and rigidity, be dimensioned to cover the entire width of the trench bottom.Such a construction would in itself assist in retention of the trench walls (30) and if, instead of sloped side walls of the trench walls are retained by braces (not shown), then the lowermost braces may be omitted or removed since then the concrete cradle extending from wall to wall across the trench provides a bracing effect.
With the cradle (32) firmly emplaced on the bottom of the trench, the gallery (31) is then positioned on the cradle. This method of construction is ideally suited to the utilization of precast sections which may be lowered into the trench, seated on the cradle and joined end to end to form a composite structure. The actual dimensions of the sections will vary depending upon the intended purpose of the construction and, for ease of handling, the length of the sections will be governed by the total weight and size thereof.
Generally, lengths of two to three meters are appropriate in the case of a tunnel for a subway system. The aligned sections are joined by circumferential joints in a known manner which need not be described in detail.
It is contemplated within the scope of the invention that the gallery sections may be positioned within the trench before the material of a cast cradle has set. In this manner, a settable slurry of concrete and clay having a setting or hardening time of, for example, from ten to thirty hours, may be poured onto the already compacted bottom of an excavated trench. The prefabricated gallery sections may then be "floated" into the desired position before the slurry sets completely to support the gallery. Alternatively, the settle slurry may be poured into the trench after the gallery has been positioned therein.
It is crucial to the method of the invention that the assembled gallery sections be internally braced to withstand the exertion of external substantial forces which would otherwise damage the gallery. To this end although braces (33) might be applied after the sections are joined to form a tunnel shell, it is obviously more convenient to position such braces (33) in the individual sections before they are lowered into the trench. This however, may create a weight problem since the necessarily substantial weight of the braces may hinder transportation and emplacing of the gallery sections. To solve such problem it may be practical to apply some braces only before the sections are lowered into place and subsequently to complete the bracing when the sections are in situ.In any event, to avoid any damage to the sections, there should always be some braces within the sections when the latter are transported and moved into position.
As shown schematically in Figures 1 through 4 the braces (33) may be applied in a lattice
or grid formation. Alternatively, the braces may be arranged diametrically or radially (not
shown) or may, as shown in Figure 7, be provided by quadrant sectors (59, 60, 61, 62)
interconnected by hinges (65) and extending
peripherally around the inner surface of the
gallery (31). Such sectors, which may have
holes (66) for weight-reduction purposes, are
secured in position by plates (63) and bolts
(64) and shims (67) ensure a close fit with
the gallery (31).
With the gallery in place on the cradle in
the trench and with the gallery complete with internal bracing, the next step is to begin to fill the trench with backfill.
The various stages of the backfilling comprising an initial controlled backfill (37) and a subsequent final backfill (39) to the level of the top of the excavation are shown in
Figures 1 (a) through 1(d).
Figure 1 (a) shows the internally braced gallery (31) resting on the cradle (33) within the trench prior to the introduction of any backfill. In Figure l(b) the controlled initially applied backfill (37) has been introduced and carefully tamped or otherwise compacted.
Although Figure l(b) shows all of the initial backfill in position, it is important that such backfill is not applied in a single batch, but, rather, is built up layer by layer with each applied layer being carefully tamped or otherwise compacted before introduction of the next subsequent layer. The actual thickness or depth of each applied layer will depend on the conditions and 15cm is a common thickness.
The final backfill (39) is then applied above the initial backfill (37) and is tamped to level the surface at ground level. Reference numeral (38) shows the demarkation between the initial (37) and~~fi:ial (39) backfills.
Figures 1 (c) and 1 (d) schematically show that the final backfill has been similarly applied layer-by-layer. In the case of the final backfill, however, this may not be essential. Figure 1 (c) shows final backfill applied and tamped above the initial backfill before removal of the internal bracing from within the gallery. Figure 1 (d) shows this bracing removed.
Figures 2(a) and 2(b) show a second embodiment of the invention. In this second embodiment there is no line of demarkation between initial and final backfills because the material used is the same. Although the material is the same, it is nevertheless applied in the same manner as in the first embodiment described with reference to Figures 1(a) to l(d). That is to say, with the gallery or tunnel shell appropriately internally braced, the backfill is applied initially in a controlled manner and is tamped in place layer-by-layer until internal arching may provide sufficient support for the backfill. Thereafter, the backfilling operation is completed and the internal bracing (33) is removed as shown in Figure 2(b).
Figures 3 and 4 respectively show minor variations of the methods described and illustrated with reference to Figures 1 and 2. In the case of each of these variations, the internal bracing (33) is removed during the backfilling operation. Thus, Figure 3(a) shows a condition corresponding to Figure 1 (b) where the initial backfilling (37) has been applied in a controlled manner up to the level (38). Thereupon, the internal bracing
(33) is removed as shown in Figure 3(b)
and the final backfill (39) applied is shown in Figure 3(c). Similarly in Figure 4(a) backfilling (40) is applied in a controlled manner up to a level (41) whereupon the bracing (33) is removed (Figure 4(b)) prior to completion of the backfilling operation with the same material (Figure 4c).In each case the initially applied backfill must be capable of achieving its load bearing function due to removal of the bracing.
In these embodiments, the gallery is a concrete shell. However other materials may be utilised within the scope of the accompanying claims and include, for example, steel and cast iron.
A complete explanation of the support characteristics of the backfill, together with specific examples will now be described and given.
The crux of the invention resides in the combined support provided by the gallery shell and the initially applied backfill. This support is provided by the initial backfill adopting an arching effect which provides with the gallery shell support for the load of the backfill. ~
As described, the method of the invention involves excavating the trench, emplacing the gallery within the trench ready to receive the backfill, ensuring that the gallery so emplaced is internally braced before applied backfill will exert any substantial force on the gallery, applying backfill initially in controlled amounts, completing the backfill up to the ground surface level and removing the internal braces from the gallery.
Before removing the braces, pressures on the gallery lining or shell are those caused by the weight of the backfill and resisted fully by the interior bracing. Upon removal of the braces the initially applied backfill assumes a structural function and together with the gallery shell contributes to resist the stresses originated by the total weight imposed. The bracing can be removed when the initially applied backfill has been applied to a depth at which upon removal of said bracing said material will adopt an internally arched structure. Providing this condition is observed, the bracing may be removed before, during or after the final backfill is applied.
Compaction of the initially applied backfill (37) regardless of materials utilized must be carefully performed, leaving no voids or defective areas.
Compaction of the backfill material immediately adjacent the gallery shell should begin with smaller equipment until a protective compacted layer is built above the shell.
Thereafter larger vibrating compactors may be utilized.
In the case of braced trenches conventional compaction equipment such as mechanical rollers may be inappropriate and compaction will be performed with hand vibrating compactors, mechanical tampers, etc. As backfilling progresses removal of trench bracing is performed and after removal of the remaining bracing, larger size compacting equipment
can enter the trench to complete the job. At this stage, of course, extreme care must be exercised to avoid damaging existing utilities.
From the foregoing detailed description it
will be appreciated that the method of con
struction of the invention produces an under
ground gallery in which the total load of the
ground above the gallery is not borne by
the material of the gallery but jointly by the
gallery and the initially applied backfill which
forms a supporting arch within the ground
above the gallery.
The extent to which the arching effect is
achieved by and within the initially applied
backfill is controlled and will be determined by many factors, among the most important
of which is the actual nature of the ground material. Other factors governing the load supporting characteristics of the initially applied backfill include the outside dimensions of the gallery, the thickness of the gallery
shell, and the total depth of the trench which
governs the total weight of material above the
gallery.
Consequently, in order to achieve optimum
construction conditions with consequent saving
of costly materials including labor it is in
most situations necessary to treat that portion
of the excavated ground material which will
be tamped and compacted around and over
the gallery structure positioned within the
trench.
This treatment will be exemplified by the
following examples, which are included for
illustrative purposes only, which have been established by research and calculation with
five ground conditions. The results of the researched examples are tabulated in Table I and establish that it was necessary to treat each ground material differently in order to achieve the desired arching load bearing characteristics within a preferred range.
Before detailing the composition and consistency of each of the five sample ground conditions, reference is made to Figure 8 of the drawings which illustrates constants utilized in the calculations.
The illustrative examples are in each case based on a trench of uniform depth (H) and width (W) at the level of the horizontal major axis of the gallery and a gallery shell having both uniform diameter (D) and shell thickness (d). In the examples considered, these constants are as follows:
H = 21 meters
W = 10 meters
D = 6 metres
d = 0.10 metres
Consequently, in the case of each example the total depth of earth above the positioned gallery is 15 meters.
In each example, in order to locate the arching effect of the initially applied backfill at a mean location (h) above the top of the gallery (31) the extracted earth is mixed with portland cement and water at atmospheric pressure and applied layer-by-layer with compacting as described.
Setting time of the compacted initially applied backfill (37) without any accelerating additives will be at least 6 days and thereafter the braces may be removed and the remaining or final backfill applied. This setting time may be accelerated by using additives in known manner.
The five soil samples considered are selected from the Unified Soil Classification System (USCS) adopted by the Corps of Engineers and Bureau of Reclamation and are as follows:
SAMPLE I.
Gravels having a grain structure where more than 50% of the coarse fraction of the mate?iaVwfWnt pass through a stan ara NO.
4 sieve and compacted to a relative density of not less than 70%.
The relative density is defined as the ratio emax e eml,,x Where emax = maximum void ratio eml,l, = minimum void ratio
e = void ratio
SAMPLE II.
Sand having a grain structure where more than 50% of the coarse fraction of the material will pass through a standard No. 4 sieve and compacted to a relative density (as calculated in Sample I) of not less than 70%.
In both SAMPLE I and SAMPLE II poorly graded materials, i.e. those in which the sizes of the individual grains are too similar to achieve good compaction must be treated-for example, by the addition of other granular structure-to provide a mixture with grain sizes appropriately varying within accepted limits for compaction.
SAMPLE III.
Sandy or silty clays having a liquid limit of less than 50 and compacted to not less than 98% of maximum density at within -2% of the optimum moisture content.
SAMPLE IV.
Fine sands and silts which have a liquid limit of less than 50 and which, unlike the clays of Sample III may tend to creep, i.e.
deform slowly with time over a prolonged period under constant load.
SAMPLE V.
Fine sands and silts having a liquid limit
of greater than 50 and exhibiting the same creep characteristics as Sample IV.
These samples are all classified according to the Unified Soil Classification System in which Samples I and II are so-called coarsegrained materials in which more than 50%
of the grains will not pass through a standard
No. 200 sieve. According to the same classifi
cation, samples III to V are so-called fine
grained soils in which more than 50% of the
grains will pass through such a sieve.
The need to treat these earth samples to
locate the necessary arching effect at the desired location (h) is substantiated by considering that, for example, in the case of Sample III
if no such treatment were to be effected, the
arching effect would not be achieved until a
point some 10 to 14 meters above the crown
of the gallery (31) which is clearly undesir
able where the total depth of earth above the
gallery is only 15 meters. Indeed, in the cases
of Samples IV and V a depth of 15 meters would be insufficient to achieve the supporting
arching effect unless the initial backfill is treated.
TAkLE I- reproduced herebelow specifies
the parameters of the mixtures utilized in the
illustrative examples to cause the load bearing
arching effect to occur at the mean height (h)
(column 3). The amount of cement added is
indicated in column (4) and the water con
tent in the complete treated mixture is indi
cated in column (5).
TABLE I
(1) (2) (3) (4) (5) Height of Arching Height of Arching Effect with Backfill Effect with Portland Cement Water Content Sample of Untreated Soil Treated Backfill in Mixture Meters Meters Sc by Weight % by Weight I 5 - 8 3 * 1 3 9 7 10 .
II 7 - 10 3 +1 3 - 9 9 - 12 III 10 - 14 3 +1 5 - 11 10 - 14 IV - 3 + 1 8 - 12 10 - 13 V 3 + 1 9 - 14 11 - 14 The above reproduced table is a compilation of calculations based on actual soil samples and utilizing portland cement with an appropriate moisture content in the set mixture.
This required moisture content will be achieved by addition of water unless the soil sample is too wet initially in which case it will be achieved by drying.
In all the samples considered in the above table, the initially applied backfill is mixed with a stabilizing material identified as cement. A stabilized load bearing structure can be achieved by utilising "Lean Concrete" as the initial backfill. Such lean concrete will have as its ingredients portland cement, sand, crushed rock (gravel) and water. The relative proportions of these ingredients in the mixed lean concrete will be determined by the compressive strength desired.For example, in a situation where the initially applied backfill, when set, is to have a compressive strength of approximately 50 kg/sq cm, the ingredients would be mixed as follows:
Portland Cement 80 kg/cu meter
Sand 880 kg/cu meter
Crushed Rock 1220 kg/cu meter
Water 180 litres
Of course, other stabilizing materials, for example, lime or resins may be utilized to bring about the desired solidifying stabilization, or setting of the initially applied backfill to produce a load bearing structure.
WHAT WE CLAIM IS:
1. A method of constructing an underground gallery comprising excavating to form a pit having a depth greater than the overall height of the gallery, locating the gallery within the pit,. internally bracing the structure of said gallery to withstand loads exerted by ground material upon refilling of the pit, covering the gallery and filling the pit with ground material, said covering being effected initially by applying and compacting backfill material in incremental steps around and over the gallery, removing the bracing from within.
the gallery and thereby causing said initially applied backfill material to adopt an internal arching structure which together with said gallery will support applied loads, and completing the filling of the pit.
2. A method according to Claim 1, wherein the initially applied backfill is applied layerby-layer with each so applied layer being tamped compacted before application as the next subsequent layer.
3. A method according to Claim 1 or
Claim 2, wherein the initially applied backfill and subsequently applied final backfill are the same material and are of the same consistency.
4. A method according to Claim 1 or
Claim 2, wherein the initially applied backfill and subsequently applied final backfill have a different composition.
5. A method according to Claim 4, wherein the initially applied backfill comprises a mixture of the material of the backfill and stabilizing material.
6. A method according to Claim 5, wherein the ground material is a coarse-grained soil,
**WARNING** end of DESC field may overlap start of CLMS **.
Claims (19)
1. A method of constructing an underground gallery comprising excavating to form a pit having a depth greater than the overall height of the gallery, locating the gallery within the pit,. internally bracing the structure of said gallery to withstand loads exerted by ground material upon refilling of the pit, covering the gallery and filling the pit with ground material, said covering being effected initially by applying and compacting backfill material in incremental steps around and over the gallery, removing the bracing from within.
the gallery and thereby causing said initially applied backfill material to adopt an internal arching structure which together with said gallery will support applied loads, and completing the filling of the pit.
2. A method according to Claim 1, wherein the initially applied backfill is applied layerby-layer with each so applied layer being tamped compacted before application as the next subsequent layer.
3. A method according to Claim 1 or
Claim 2, wherein the initially applied backfill and subsequently applied final backfill are the same material and are of the same consistency.
4. A method according to Claim 1 or
Claim 2, wherein the initially applied backfill and subsequently applied final backfill have a different composition.
5. A method according to Claim 4, wherein the initially applied backfill comprises a mixture of the material of the backfill and stabilizing material.
6. A method according to Claim 5, wherein the ground material is a coarse-grained soil,
having a grain size of which more than 50% will not pass through a standard No. 200 sieve and wherein the initially applied backfill comprises such ground material mixed with from 3% to 9% by weight of portland cement to provide a mixture with a controlled water content of from 7% to 12% by weight.
7. A method according to Claim 5, wherein the ground material is a fine-grained soil having a grain size of which more than 50% will pass through a standard No. 200 sieve and wherein the initially applied backfill comprises such ground material mixed with from 5% to 14% by weight of portland cement to provide a mixture with a controlled water content of from 10% to 14% by weight.
8. A method according to any of Claims
1 to 7, wherein the internal braces are arranged inside the gallery structure in a grid formation.
9. A method according to any of Claims
1 to 7, wherein the gallery is of substantially
circular configuration and wherein each brace
comprises four quadrant sectors assembled
within said gallery to mate with the itnernal surface of the gallery shell substantially
around the entire periphery thereof.
10. A method according to any of Claims
1 to 9, wherein the gallery is positioned on a cradle within the pit.
11. A method according to any of Claims
1 to 10, wherein the pit is a trench and wherein the gallery is constructed as a tunnel extending lengthwise along and within the trench.
12. A method according to any of Claims
1 to 11, wherein the- gallery is a composite structure comprising a plurality of prefabricated sections which are lowered into the pit and assembled therein to form said composite structure.
13. A method according to Claim 12, wherein the prefabricated sections are joined end to end.
14. A method according to any of Claims 1 to 11, wherein the gallery is constructed in the pit.
15. A method according to any of Claims 1 to 13, wherein the braces are applied inside the gallery before the gallery is lowered into the pit.
16. A method according to any of Claims 1 to 14, wherein the braces are applied inside the gallery after said gallery has been positioned within the pit and before initially applied backfill can exert any substantial load on said gallery.
17. A method according to any of Claims 1 to 16, wherein the braces are removed when the pit has been completely filled.
18. A method according to any of Claims 1 to 17, wherein the local water table is lowered before the gallery is located in the excavated pit.
19. A method of constructing an underground gallery substantially as hereinbefore described.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
BR7705555A BR7705555A (en) | 1977-08-19 | 1977-08-19 | PROCESS FOR BUILDING A PREMOLDED GALLERY |
US05/836,105 US4150910A (en) | 1977-08-19 | 1977-09-23 | Construction of underground galleries |
Publications (1)
Publication Number | Publication Date |
---|---|
GB1577199A true GB1577199A (en) | 1980-10-22 |
Family
ID=25663958
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB2018778A Expired GB1577199A (en) | 1977-08-19 | 1978-05-17 | Method of constructing underground gallery |
Country Status (4)
Country | Link |
---|---|
DE (1) | DE2834875A1 (en) |
FR (1) | FR2412654A1 (en) |
GB (1) | GB1577199A (en) |
NL (1) | NL7808071A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105586986A (en) * | 2015-12-19 | 2016-05-18 | 赵学坤 | Urban underground intelligent comprehensive pipe rack quakeproof device |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2644098B1 (en) * | 1989-03-07 | 1993-02-05 | Beton Routes Securite | METHOD FOR PRODUCING A SLOTTED CHANNEL FOR WATER DISCHARGE, AND CHANNEL OBTAINED ACCORDING TO THIS METHOD |
-
1978
- 1978-05-17 GB GB2018778A patent/GB1577199A/en not_active Expired
- 1978-07-31 NL NL7808071A patent/NL7808071A/en not_active Application Discontinuation
- 1978-08-07 DE DE19782834875 patent/DE2834875A1/en not_active Withdrawn
- 1978-08-18 FR FR7824137A patent/FR2412654A1/en not_active Withdrawn
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105586986A (en) * | 2015-12-19 | 2016-05-18 | 赵学坤 | Urban underground intelligent comprehensive pipe rack quakeproof device |
Also Published As
Publication number | Publication date |
---|---|
NL7808071A (en) | 1979-02-21 |
FR2412654A1 (en) | 1979-07-20 |
DE2834875A1 (en) | 1979-03-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2016358214B2 (en) | Method for forming a stable foundation ground | |
EA027027B1 (en) | Method for forming a retaining wall | |
CN110777836A (en) | Reinforced concrete plate-anchor rod composite foundation and using method thereof | |
RU2392387C2 (en) | Device and method for reinforcement of mast base | |
US4150910A (en) | Construction of underground galleries | |
WO2020136664A1 (en) | Method of reducing swelling of expansive soils reinforced with granular pile | |
KR101372182B1 (en) | Pre-support tunneling reinforced by in-situ soil mixed with cement | |
KR20020022446A (en) | Repairing method of earth-fill dam | |
Nonveiller | Open caissons for deep foundations | |
CN114164726B (en) | Local deep excavation backfill structural roadbed and rapid construction method | |
KR20120079987A (en) | Method of pre-support tunneling reinforced by in-situ soil mixed with cement | |
RU2344231C1 (en) | Method of foundation bed construction by horizontal reinforcing with precast concrete components | |
GB1577199A (en) | Method of constructing underground gallery | |
JPH03172412A (en) | Forming method for under surface area and liquid state-generating apparatus | |
CN109667278A (en) | Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing | |
JP3099040B2 (en) | Embankment culvert | |
Lutenegger | Uplift tests on shallow cast-in-place enlarged base pedestal foundations in clay | |
JP2004124452A (en) | Foundation pile structure in bearing ground and working method of foundation pile | |
Gitskin et al. | Settlement of building floor slab-on-grade constructed on unsuitable urban fill in Chicago | |
JP3099039B2 (en) | Embankment culvert | |
US3442089A (en) | Method for casting concrete foundation | |
Scheller et al. | Combined soil stabilization with vertical columns (CSV): a new method to improve soft soils | |
Singh et al. | Upgrading existing footings with micro-piles | |
Broomhead et al. | Shallow Soil Mixing—A Case History | |
Hussin et al. | Analysis of quick load tests on stone columns: case histories |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
CSNS | Application of which complete specification have been accepted and published, but patent is not sealed |