JPH0415791Y2 - - Google Patents

Info

Publication number
JPH0415791Y2
JPH0415791Y2 JP1985103562U JP10356285U JPH0415791Y2 JP H0415791 Y2 JPH0415791 Y2 JP H0415791Y2 JP 1985103562 U JP1985103562 U JP 1985103562U JP 10356285 U JP10356285 U JP 10356285U JP H0415791 Y2 JPH0415791 Y2 JP H0415791Y2
Authority
JP
Japan
Prior art keywords
concrete
pile
steel pipe
composite part
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1985103562U
Other languages
Japanese (ja)
Other versions
JPS6212639U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP1985103562U priority Critical patent/JPH0415791Y2/ja
Publication of JPS6212639U publication Critical patent/JPS6212639U/ja
Application granted granted Critical
Publication of JPH0415791Y2 publication Critical patent/JPH0415791Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、建造物等を支持する為に地中に埋設
する、下部に拡大部を有するコンクリート杭に関
するものであり、特に寒冷地特有の地層である厚
い泥炭層の下に傾斜した堅固な地盤を有する地中
に強い打撃力を加えて杭を打ち込んでも、先端部
が破損されなく、寒冷地でも支持力が大きい値と
なる基礎杭に関するものである。
[Detailed description of the invention] [Field of industrial application] The present invention relates to a concrete pile with an enlarged portion at the bottom, which is buried underground to support structures, etc., and is particularly suitable for use in cold regions. Concerning foundation piles that do not damage the tips of the piles even when driven into the ground with a strong impact force and have a large bearing capacity even in cold regions. It is something.

〔従来の技術〕[Conventional technology]

従来、既成杭を建造物等を支持するために地中
に埋設する際に、施工現場で杭の下部に拡大球根
コンクリート部を形成させて支持力を大きくした
り、また、杭の下部に外径の大きなコンクリート
杭を接続して一体化して支持力を大きくしようと
していた(実開昭54−154501号公報)。
Conventionally, when burying prefabricated piles underground to support structures, etc., an expanded bulbous concrete section was formed at the bottom of the pile at the construction site to increase the supporting capacity, or an external layer was placed at the bottom of the pile. An attempt was made to increase the bearing capacity by connecting and integrating concrete piles with large diameters (Japanese Utility Model Publication No. 154501/1983).

〔考案が解決しようとする課題〕[The problem that the idea aims to solve]

施工現場で杭下部に拡大球根部を形成する為に
は、杭下部を掘削し、その掘削部分にコンクリー
トを打設する必要があるが、寒冷地では、コンク
リートの凍結がおこり、充分な支持力が得られな
かつたり、極端な場合では施工し難くなるという
欠点がある。また、コンクリートの凍結が起こら
ない場合であつても、その支持力は杭に打設を加
えて杭を強固な支持地盤まで沈設する工法によつ
て得られる支持力よりも劣つている。
In order to form an enlarged bulb at the bottom of the pile at the construction site, it is necessary to excavate the bottom of the pile and pour concrete into the excavated area, but in cold regions, the concrete freezes and does not have enough bearing capacity. It has the disadvantage that it may not be possible to obtain the necessary conditions, or in extreme cases, it may be difficult to construct. Further, even if the concrete does not freeze, its bearing capacity is inferior to that obtained by a construction method in which the piles are driven into solid supporting ground.

また、実開昭54−154501号公報等に示されてい
るような、杭の下部に外径の大きなコンクリート
杭を接続して一体化した杭は、寒冷地特有の地層
である厚い泥炭層の下に傾斜した堅固な地盤を有
する地中に強い打撃力を杭上部に加えて杭を打ち
込むと、杭の下部の先端部が破損されて、やはり
充分な支持力を得られないという欠点があるとい
うことを我々は見出した。
In addition, as shown in Japanese Utility Model Application Publication No. 54-154501, etc., piles that are integrated by connecting a concrete pile with a large outer diameter to the lower part of the pile are suitable for use in thick peat layers, which are unique to cold regions. If a pile is driven into the ground, where the ground is firm and slopes downward, by applying a strong impact force to the top of the pile, the bottom tip of the pile will be damaged, resulting in insufficient support. We found that.

本考案は、これら従来技術の欠点を解決するも
のであり、予めコンクリート杭の下部に拡大部を
形成しても、地盤状態に悪い寒冷地で杭を打撃工
法により沈設しても、その施工時に杭下部の拡大
先端部の損傷が少なく、且つ上部より拡大部に掛
かる圧力を確実に拡大先端部に伝えて大きな支持
力を確実に発現できる構造のコンクリート杭を提
供することを目的とする。
The present invention solves the drawbacks of these conventional technologies, and even if an enlarged part is formed at the bottom of the concrete pile in advance or the pile is sunk by the impact method in a cold region where the ground condition is poor, it can be used at the time of construction. To provide a concrete pile having a structure in which the enlarged tip of the lower part of the pile is less damaged, and the pressure applied to the enlarged tip from the upper part is surely transmitted to the enlarged tip to surely express a large supporting force.

〔課題を解決するための手段〕[Means to solve the problem]

本考案のコンクリート杭は、コンクリート杭5
の下方に、該コンクリート杭5の外径よりも大き
な径のコンクリート鋼管複合部が設けられてお
り、該コンクリート鋼管複合部は、鋼管2内に中
空部を有するコンクリート1が存在するものであ
つて、該コンクリート1と鋼管2とは膨張剤の膨
張力により一体化されており、且つ少なくとも該
コンクリート鋼管複合部のコンクリート1の上部
と下部は該鋼管2に一体化した棡板3,4により
保護された構造のコンクリート鋼管複合部である
コンクリート鋼管複合部付コンクリート杭であ
る。
The concrete pile of this invention is concrete pile 5
A concrete-steel pipe composite part having a diameter larger than the outer diameter of the concrete pile 5 is provided below, and the concrete-steel pipe composite part has concrete 1 having a hollow part inside the steel pipe 2. , the concrete 1 and the steel pipe 2 are integrated by the expansion force of the expanding agent, and at least the upper and lower parts of the concrete 1 of the concrete-steel pipe composite part are protected by cross plates 3 and 4 integrated with the steel pipe 2. This is a concrete pile with a concrete steel pipe composite part, which has a concrete steel pipe composite part.

本発明に用いられる上部に接続されるコンクリ
ート杭5は、鉄筋コンクリート杭やプレストレス
トコンクリート杭等である。支持耐力等を更に大
きくするためには、圧縮強度が800Kg/cm2以上の
コンクリート杭であることが好ましい。なお、こ
のコンクリート杭5は一般的には中央が中空状に
なつている。
The concrete pile 5 connected to the upper part used in the present invention is a reinforced concrete pile, a prestressed concrete pile, or the like. In order to further increase the supporting strength, it is preferable to use concrete piles with a compressive strength of 800 kg/cm 2 or more. Note that this concrete pile 5 is generally hollow in the center.

このコンクリート杭5は、その外径よりも大き
い外径のコンクリート鋼管複合部に、例えば、第
1図に示すようにコンクリート杭5の端板7とコ
ンクリート鋼管複合部の鋼板3とを溶接により溶
接部8を形成して、一体的に接続されている。
This concrete pile 5 is made by welding the end plate 7 of the concrete pile 5 and the steel plate 3 of the concrete steel pipe composite part to a concrete steel pipe composite part having an outer diameter larger than that of the concrete pile, for example, as shown in FIG. 8 and are integrally connected.

また、コンクリート鋼管複合部は、鋼管2内に
中空部を有するコンクリート部が存在するもので
あつて、そのコンクリート部1と鋼管2とは酸化
マグネシウム、カルシウムサルフアアルミネー
ト、石膏石灰系等の膨張剤の膨張力により一体化
されたものである。なお、コンクリート鋼管複合
部の鋼管2の厚みは、上部からの圧力などにより
変形に耐える厚みがあればよく、3〜20mmの鋼管
がその径に応じて使用される。また、鋼管の長さ
は、コンクリートを充分に鋼管2と一体化させる
ためにある程度の長さが必要であるが、長すぎて
も鋼管の使用量が多くなり不経済であるという点
を考慮の上、適誼設定すればよい。好ましくは、
40〜70cm程度である。
In addition, the concrete-steel pipe composite part has a concrete part having a hollow part in the steel pipe 2, and the concrete part 1 and the steel pipe 2 are made of expanded material such as magnesium oxide, calcium sulfur aluminate, gypsum lime, etc. They are integrated by the expansion force of the agent. Note that the thickness of the steel pipe 2 of the concrete-steel pipe composite section is sufficient as long as it can withstand deformation due to pressure from above, etc., and a steel pipe of 3 to 20 mm is used depending on its diameter. In addition, the length of the steel pipe needs to be a certain length in order to fully integrate the concrete with the steel pipe 2, but if it is too long, the amount of steel pipe used will increase, which is uneconomical. All you have to do is set it appropriately. Preferably,
It is about 40-70cm.

コンクリート鋼管複合部の少なくともコンナク
リート1の上部と下部は前記の鋼管2に、例えば
溶接により一体化された棡板3,4で保護されて
いる。これらの鋼板3,4はコンクリート鋼管複
合部に上下から掛かる外力からコンクリート1部
を保護する為のものであり、5〜20mmの厚みの鋼
板が用いられ、鋼板3,4の外径は外力からの保
護という目的から鋼管2の内径より大であること
が好ましい。コンクリート鋼管複合部の外径は、
支持力を増大させるため、コンクリート杭の外径
より大きくなるよう適誼設定すればよい。好まし
くは、コンクリート杭より該複合部を5〜10cm程
大きくする。
At least the upper and lower parts of the conacrete 1 of the concrete-steel-pipe composite section are protected by cross plates 3 and 4 that are integrated with the steel pipe 2 by, for example, welding. These steel plates 3 and 4 are used to protect one part of the concrete from external forces that are applied to the concrete steel pipe composite part from above and below. Steel plates with a thickness of 5 to 20 mm are used, and the outer diameters of the steel plates 3 and 4 are designed to protect the concrete from external forces that are applied from above and below. It is preferable that the inner diameter of the steel pipe 2 be larger than the inner diameter of the steel pipe 2 for the purpose of protecting the steel pipe 2. The outer diameter of the concrete steel pipe composite part is
In order to increase the bearing capacity, the diameter should be set appropriately so that it is larger than the outer diameter of the concrete pile. Preferably, the composite portion is approximately 5 to 10 cm larger than the concrete pile.

また、コンクリート鋼管複合部のコンクリート
部1の圧縮強度も上部のコンクリート杭5の圧縮
強度と同等かそれ以上であることが好ましく、従
つて、圧縮強度が800Kg/cm2以上であることが好
ましい。かかる高い圧縮強度のコンクリート1
は、例えば、コンクリート鋼管複合部をオートク
レーブ養生する等の方法によつて達成される。
Further, it is preferable that the compressive strength of the concrete section 1 of the concrete-steel pipe composite section is equal to or higher than the compressive strength of the upper concrete pile 5, and therefore, it is preferable that the compressive strength is 800 Kg/cm 2 or more. Such high compressive strength concrete 1
This can be achieved, for example, by autoclaving a concrete-steel pipe composite.

かかるコンクリート鋼管複合部の製造に際して
は、長さの長い鋼管の内部に膨張剤を入れたコン
クリートを遠心力成型法などで形成し、養生時の
膨張作用により鋼管と一体化させたものを製造
し、これを適宜長さに切断し、それに上下の鋼板
を一体化して製造してもよい。
When manufacturing such a concrete-steel pipe composite part, concrete containing an expanding agent is formed inside a long steel pipe using a centrifugal force forming method, and the concrete is integrated with the steel pipe by the expansion action during curing. , this may be cut to an appropriate length and the upper and lower steel plates may be integrated into it.

〔作用〕[Effect]

本考案の杭下部に接続されたコンクリート鋼管
複合部は、鋼管2内に中空部を有するコンクリー
ト1が存在し、該コンクリート1と鋼管2とは膨
張剤の膨張力により一体化されている。そのた
め、この複合部に鋼管2の耐力以上の曲力等が掛
つた際、端に鋼管内にコンクリートが存在してい
る場合に比べ、曲力に対し一層強く抵抗するとい
う作用を発現する。
In the concrete-steel-pipe composite part connected to the lower part of the pile of the present invention, there is a concrete 1 having a hollow part inside the steel pipe 2, and the concrete 1 and the steel pipe 2 are integrated by the expansion force of the expansion agent. Therefore, when a bending force greater than the yield strength of the steel pipe 2 is applied to this composite part, the composite part exhibits an effect of resisting the bending force more strongly than when concrete is present in the steel pipe at the end.

更に、本考案のコンクリート鋼管複合部は、少
なくとも該複合部のコンクリート1の上部と下部
には鋼管2に一体化された鋼板3,4が存在する
構造となつているので、コンクリート1の曲力に
対して抵抗できると共に、支持力を高くするため
に打込工法で杭を沈設する際に、上部の杭の上端
に加えられる打撃力をコンクリート1を破損する
ことなく圧縮力の強いコンクリート1に伝達で
き、かつ、地盤中でコンクリート1が破損されな
いよう保護される。
Furthermore, the concrete-steel pipe composite section of the present invention has a structure in which steel plates 3 and 4 integrated with the steel pipe 2 are present at least at the upper and lower parts of the concrete 1 of the composite section, so that the bending force of the concrete 1 is reduced. In addition, when sinking piles using the driving method to increase bearing capacity, the impact force applied to the top end of the upper pile can be applied to the concrete 1, which has a strong compressive force, without damaging the concrete 1. can be transmitted, and the concrete 1 is protected from being damaged in the ground.

特に、N値の極めて小さく泥炭層が厚く堆積
し、その下に堅固な層が傾斜していることが非常
に多い寒冷地特有の地層に打込工法により杭を沈
設する場合、傾斜した堅固な支持層とその上の地
層との境界面に杭の先端が到達すると、打撃の瞬
間に杭先端の拡大部に大きな剪断力や曲力が加え
られる。ところが、前述の構成とした本考案の杭
下部に接続したコンクリート鋼管複合部は、破損
されることなく、かつ、打撃の際、杭の上部より
かかる圧力を、前記複合部に確実に伝えて大きな
支持力を確実に発現できる。従つて、本考案の杭
によれば寒冷地では施工が困難になることが多い
施工現場で、コンクリートを打設して球根部を形
成する工法によることなく、寒冷地で大きな支持
力を得ることができる。
In particular, when installing piles using the driving method in geological formations typical of cold regions, where a thick layer of peat is deposited with an extremely low N value, and a hard layer beneath it is often sloped, When the tip of the pile reaches the interface between the supporting layer and the stratum above it, a large shearing force and bending force are applied to the enlarged portion of the pile tip at the moment of impact. However, the concrete-steel pipe composite part connected to the lower part of the pile of the present invention having the above-mentioned structure does not break and can reliably transmit the pressure applied from the upper part of the pile to the composite part during an impact. Supporting capacity can be reliably expressed. Therefore, according to the pile of the present invention, it is possible to obtain a large bearing capacity in cold regions without using the method of pouring concrete to form a bulbous part at a construction site, where construction is often difficult in cold regions. I can do it.

また、打込工法で沈設した場合、コンクリート
鋼管複合部の下部は支持地盤中に沈設されるが、
この複合部の一部上部はその上のN値の小さな層
等の支持層とは異なる地層中に出ている場合が多
く、地震が発生すると性質の異なる地層の境目で
は滑動が発生して、埋設されている杭に大きな剪
断力が加わる。この際も、前述の構成としたコン
クリート鋼管複合部とすることで大きな抵抗力を
発揮することができる。
In addition, when the concrete-steel pipe composite section is sunk using the pouring method, the lower part of the concrete-steel pipe composite section is sunk into the supporting ground;
A part of the upper part of this complex is often exposed in a stratum different from the supporting layer, such as a layer with a small N value, and when an earthquake occurs, sliding occurs at the boundary between strata with different properties. A large shearing force is applied to the buried pile. In this case as well, the use of the concrete-steel pipe composite section with the above-mentioned structure can provide great resistance.

〔実施例〕〔Example〕

実施例 1 外径40cm、肉厚4.5mm、長さ5mの鋼管を端板を
有する型枠内に入れ、酸化マグネシウムを混合し
たコンクリートのスラリーを遠心力の作用下に中
空部の径が27cmとなるように注入し、オートクレ
ーブ養生した後に、50cmの長さに切断し、この上
下に肉厚12mmの外径が40cmの鋼管を接続してコン
クリート鋼管複合部に製造した。
Example 1 A steel pipe with an outer diameter of 40 cm, a wall thickness of 4.5 mm, and a length of 5 m was placed in a formwork with end plates, and a slurry of concrete mixed with magnesium oxide was applied to the pipe under the action of centrifugal force until the diameter of the hollow part was 27 cm. After pouring and curing in an autoclave, it was cut into 50 cm lengths, and steel pipes with a wall thickness of 12 mm and an outer diameter of 40 cm were connected above and below to manufacture a concrete steel pipe composite part.

この上部にコンクリート杭の一種である外径30
cm内径18cmの旭化成工業(株)製のAHSパイルを中
心が一致するように載せて、AHSパルイの端板
7とコンクリート鋼管複合部の鋼板3とを溶接に
より一体化してコンクリート鋼管複合部付のコン
クリート杭とした。
At the top of this is a type of concrete pile with an outer diameter of 30
An AHS pile manufactured by Asahi Kasei Industries, Ltd. with an inner diameter of 18 cm is placed so that their centers coincide, and the end plate 7 of the AHS palui and the steel plate 3 of the concrete steel pipe composite part are integrated by welding to form a concrete steel pipe composite part. Concrete piles were used.

この杭をN値の極めて小さく泥炭層が厚く堆積
し、その下に堅固な層が傾斜している寒冷地の地
層に杭の上方を打撃して沈設した。更に、この杭
の上方に前記のAHSパイルを溶接して継ぎ足し、
杭の最上部を打撃しながら沈設して杭先端のコン
クリート鋼管複合部の先端部を所定の支持地盤中
に到達させた。
This pile was sunk by hitting the top of the pile into a geological stratum in a cold region with a thick peat layer with an extremely low N value and a sloping hard layer underneath. Furthermore, the above-mentioned AHS pile is welded and added above this pile,
The top of the pile was hammered and lowered to allow the tip of the concrete-steel pipe composite section at the tip of the pile to reach the specified supporting ground.

このように沈設した本考案の基礎杭は、打撃を
加えながらの打込沈設時に、杭下部の破損による
異常が感じられず、かつ、62トン以上の支持力が
確保された。
The foundation pile of the present invention, which was sunk in this way, showed no abnormality due to damage to the lower part of the pile when it was driven and sunk while applying a blow, and a supporting capacity of more than 62 tons was secured.

次に、支持力を測定した後、杭先端部の状態を
確認するために杭を掘り出した。その結果、杭先
端のコンクリート鋼管複合部にも全く損傷は認め
られなかつた。
Next, after measuring the bearing capacity, the pile was dug out to check the condition of the tip of the pile. As a result, no damage was observed to the concrete-steel pipe composite section at the tip of the pile.

実施例 2 実施例1と同じ工法を使用して実施例1の杭
を、地層の途中に転石層を含む地層に設けた転石
層を貫通して支持地盤に達するまで予め掘削した
孔の中に沈設しようとしたが、掘削孔の部分的な
崩壊や曲がり等があつたためか、杭が自重によつ
ては沈設できなかつたので、杭の上方を打撃して
沈設した。更に、この杭の上方に前記のAHSパ
イルを溶接して継ぎ足し、杭の最上部を打撃しな
がら沈設して予定の深さの支持地盤まで杭先端の
コンクリート鋼管複合部の先端部を到達させた。
Example 2 Using the same construction method as Example 1, the pile of Example 1 was inserted into a hole that had been drilled in advance until it reached the supporting ground, penetrating the boulder layer provided in the stratum including a boulder layer in the middle of the stratum. An attempt was made to sink the pile, but perhaps because the excavation hole had partially collapsed or bent, the pile could not be sunk under its own weight, so the pile was sunk by hitting the top of the pile. Furthermore, the above-mentioned AHS pile was welded and added to the top of this pile, and the top of the pile was sunk while being hammered, allowing the tip of the concrete-steel pipe composite section at the tip of the pile to reach the supporting ground at the planned depth. .

このように沈設した本考案の基礎杭は、打撃を
加えながらの打込沈設時に、杭下部の破損による
異常が感じられず、かつ、62トン以上の支持力が
確保された。
The foundation pile of the present invention, which was sunk in this way, showed no abnormalities due to damage to the lower part of the pile when it was driven and sunk while applying a blow, and a supporting capacity of more than 62 tons was secured.

次に、支持力を測定した後、杭先端部の状態を
確認するために杭を掘り出した。その結果、杭先
端のコンクリート複合部にも全く損傷は認められ
なかつた。
Next, after measuring the bearing capacity, the pile was dug out to check the condition of the tip of the pile. As a result, no damage was found to the concrete composite part at the tip of the pile.

比較例1および2 一方、比較のために、本考案のコンクリート鋼
管複合部の代わりに、コンクリート鋼管複合部と
ほぼ同じ寸法の中空コンクリートとして、コンク
リート杭である旭化成工業株式会社製のAHSパ
イルを切断してその上下に鋼管を乗せてモルタル
でコンクリートと接着させて先端拡大部を製造し
た。この上に実施例1で使用したものと同じ大き
さのASHパイルを前記の拡大部と中心が一致す
るように載せて一体化して拡径コンクリート部付
のコンクリート杭とした。
Comparative Examples 1 and 2 On the other hand, for comparison, instead of the concrete steel pipe composite part of the present invention, an AHS pile manufactured by Asahi Kasei Corporation, which is a concrete pile, was cut as a hollow concrete with almost the same size as the concrete steel pipe composite part. Then, we placed steel pipes on top and bottom of the pipes and adhered them to concrete using mortar to manufacture the enlarged tip. An ASH pile of the same size as that used in Example 1 was placed on top of this so that its center coincided with the enlarged section, and the pile was integrated to form a concrete pile with an enlarged diameter concrete section.

この杭を実施例1と同じ地盤と実施例2と同じ
地盤で、各々実施例と同様な工法により沈設しよ
うとしたが、実施例1の寒冷地の地盤では所定の
地盤とその上の地盤面の境目に該当する位置に先
端が到達した際に杭の損傷が感じられ、また実施
例2の地盤では所定の支持地盤まで達する前に、
途中で先端拡大部が破損したようである。何れの
場合も、杭の損傷にかまわず、所定の支持地盤ま
で強引に沈設したが、何れの場合もその支持力は
10トンに達しなかつた。
An attempt was made to sink this pile in the same ground as in Example 1 and in the same ground as in Example 2 using the same method as in each example, but in the ground in the cold region of Example 1, it was difficult to sink the pile into the specified ground and the ground surface above it. Damage to the pile was felt when the tip reached the position corresponding to the boundary, and in the ground of Example 2, before reaching the specified supporting ground,
It appears that the enlarged tip part was damaged during the process. In both cases, the piles were forcibly sunk to the designated supporting ground, regardless of the damage to the piles, but in each case, the bearing capacity was low.
It did not reach 10 tons.

このように支持力を測定した後、杭先端部の状
態を確認するために杭を掘り出した。その結果、
この二つの比較例の杭はいずれも先端のコンクリ
ート複合部が破損していた。
After measuring the bearing capacity in this way, the pile was dug out to check the condition of the tip of the pile. the result,
In both of these comparative piles, the concrete composite part at the tip was damaged.

比較例3および比較例4 先端拡大部として比較例2や比較例3で使用し
た同じ拡径コンクリート部を使用し、この上に中
空のコンクリート鋼管複合杭の一種である外径30
cmで肉厚6mmの鋼管の内側に54mm厚みでコンクリ
ートが一体化された中空のコンクリート鋼管複合
杭の旭化成工業(株)製のACCSパイルを前記の拡大
部と中心が一致するように載せて一体化して拡径
コンクリート部付のコンクリート杭とした。
Comparative Example 3 and Comparative Example 4 The same enlarged diameter concrete part used in Comparative Example 2 and Comparative Example 3 was used as the enlarged tip part, and on top of this, an outer diameter of 30 mm, which is a type of hollow concrete steel pipe composite pile, was used.
An ACCS pile made by Asahi Kasei Industries, Ltd., which is a hollow concrete-steel pipe composite pile with concrete integrated with a thickness of 54 mm, is placed on the inside of a steel pipe with a wall thickness of 6 mm. It was made into a concrete pile with an enlarged diameter concrete section.

この杭を実施例1と同じ地盤と実施例2と同じ
地盤の双方の地盤で、各々実施例と同様な工法を
使用して沈設しようとしたが、実施例1の寒冷地
の地盤では所定の地盤とその上の地盤面の境目に
該当する位置に杭先端が到達した際に杭の損傷が
感じられ、また、実施例2に記載した地盤では所
定の支持地盤まで達する前に、途中で先端拡大部
が破損したようである。何れの場合も、杭の損傷
にかまわず、所定の支持地盤まで強引に沈設した
が、その支持力は10トンに達しなかつた。
An attempt was made to sink this pile in the same ground as in Example 1 and in the same ground as in Example 2, using the same method as in each example, but in the ground in the cold region of Example 1, the specified Damage to the pile was felt when the tip of the pile reached the boundary between the ground and the ground surface above it, and in the ground described in Example 2, the tip of the pile was damaged on the way before reaching the specified supporting ground. It looks like the enlarged part is damaged. In both cases, the piles were forcibly sunk to the designated supporting ground, regardless of the damage to the piles, but their bearing capacity did not reach 10 tons.

このように支持力を測定した後、杭先端部の状
態を確認するために杭を堀り出した。その結果、
この二つの比較例の杭はいずれも先端のコンクリ
ート複合部が破損していた。
After measuring the bearing capacity in this way, the pile was dug out to check the condition of the tip of the pile. the result,
In both of these comparative piles, the concrete composite part at the tip was damaged.

〔考案の効果〕[Effect of idea]

本考案の杭は、前述の通りの構成とすることに
より、支持力を高くするために杭の上端に高い打
撃を加える打込工法を使用しても、杭下部のコン
クリート鋼管複合部の損傷が少なく、且つ、上部
より該複合部に掛かる圧力を確実に該複合部に伝
えて大きな支持力を確実に発現できるという効果
を発現する。特に、打込工法(打撃工法)を適用
使用しても高い支持力が得られなかつた寒冷地等
の杭先端が損傷を受け易い状態の悪い地盤におい
ても、打撃工法により沈設可能となり高い支持力
が得られるという従来の杭では得られない優れた
効果を発揮する。
By having the structure of the pile of the present invention as described above, even if a driving method that applies a high blow to the top end of the pile is used to increase the bearing capacity, the concrete and steel pipe composite section at the bottom of the pile will not be damaged. The effect is that the pressure applied to the composite part is small and that the pressure applied to the composite part is reliably transmitted from the upper part to the composite part, and a large supporting force can be reliably expressed. In particular, even in poor ground conditions where pile tips are easily damaged, such as in cold regions, where high bearing capacity could not be obtained even with the application of the driving method (impact method), it is possible to sink the pile using the hammering method, resulting in a high bearing capacity. It has excellent effects that cannot be obtained with conventional piles.

更に、地震などにより大きな剪断力が杭にかけ
られた場合にも、大きな抵抗力を発揮する。
Furthermore, it exhibits great resistance even when large shearing forces are applied to the piles due to earthquakes, etc.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図、第2図は、本考案のコンクリート杭の
例を示す半切断正面図である。 1……コンクリート部、2……鋼管、3,4…
…鋼板、5……コンクリート杭、6,8……溶接
部、7……端板。
1 and 2 are half-cut front views showing an example of the concrete pile of the present invention. 1... Concrete part, 2... Steel pipe, 3, 4...
... Steel plate, 5 ... Concrete pile, 6, 8 ... Welded part, 7 ... End plate.

Claims (1)

【実用新案登録請求の範囲】 コンクリート杭5の下方に、該コンクリート杭
5の外径よりも大きな径のコンクリート鋼管複合
部が設けられており、 該コンクリート鋼管複合部は、鋼管2内に中空
部を有するコンクリート1が存在するものであつ
て、該コンクリート1と鋼管2とは膨張剤の膨張
力により一体化されており、且つ少なくとも該コ
ンクリート鋼管複合部のコンクリート1の上部と
下部は該鋼管2に一体化した鋼板3,4により保
護された構造のコンクリート鋼管複合部であるコ
ンクリート鋼管複合部付コンクリート杭。
[Scope of Claim for Utility Model Registration] A concrete steel pipe composite part having a diameter larger than the outer diameter of the concrete pile 5 is provided below the concrete pile 5, and the concrete steel pipe composite part has a hollow part inside the steel pipe 2. There is concrete 1 having A concrete pile with a concrete steel pipe composite part, which is a concrete steel pipe composite part with a structure protected by steel plates 3 and 4 integrated with the concrete steel pipe composite part.
JP1985103562U 1985-07-09 1985-07-09 Expired JPH0415791Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1985103562U JPH0415791Y2 (en) 1985-07-09 1985-07-09

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1985103562U JPH0415791Y2 (en) 1985-07-09 1985-07-09

Publications (2)

Publication Number Publication Date
JPS6212639U JPS6212639U (en) 1987-01-26
JPH0415791Y2 true JPH0415791Y2 (en) 1992-04-09

Family

ID=30976232

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1985103562U Expired JPH0415791Y2 (en) 1985-07-09 1985-07-09

Country Status (1)

Country Link
JP (1) JPH0415791Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0398092U (en) * 1990-01-24 1991-10-09

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54154501U (en) * 1978-04-18 1979-10-27

Also Published As

Publication number Publication date
JPS6212639U (en) 1987-01-26

Similar Documents

Publication Publication Date Title
Bruce et al. Soil nailing: application and practice-part 1
EP2141286B1 (en) Spiral steel pipe pile
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN112554198B (en) Construction method of deep foundation pit protection structure adjacent to high-rise building
JPWO2004035942A1 (en) Pile digging method, foundation pile structure
Vickars et al. Performance of helical piles with grouted shafts
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
JPH08184037A (en) Double pipe steel pipe pile
JP5777435B2 (en) Reinforcement method for foundations for small buildings
JPH0415791Y2 (en)
JP3967473B2 (en) Construction method of underground structure
CN217518646U (en) Barrier removing tunnel structure for passing through existing station
CN207846409U (en) A kind of consolidation layer of sand concrete reinforced pipe section broken stone pile
CN1027387C (en) Method for supporting deep-foundation side wall by use of channel-section steel and anchor bar concrete pile
CN115613559A (en) Telescopic steel spiral pile and construction method
CN108277798A (en) Prestressing force shaped steel support pile and its construction method
JP4074198B2 (en) How to remove existing piles
CN208039240U (en) A kind of built pile
JP2001271347A (en) Drop method for ready-made pile
KR200331377Y1 (en) Soil Cement Wall with Removable H-Pile
JPH0324924B2 (en)
JP3708795B2 (en) Casing placement method
CN214993810U (en) Anti-pulling steel pipe soil nail
CN113404055B (en) Inter-pile soil-retaining and water-stopping curtain structure and construction method thereof
CN108019211A (en) Waterproof of man and its construction method in a kind of pilot tunnel of rich water sand-pebble layer