JPS6145010A - Formation of reclamation site - Google Patents
Formation of reclamation siteInfo
- Publication number
- JPS6145010A JPS6145010A JP16479684A JP16479684A JPS6145010A JP S6145010 A JPS6145010 A JP S6145010A JP 16479684 A JP16479684 A JP 16479684A JP 16479684 A JP16479684 A JP 16479684A JP S6145010 A JPS6145010 A JP S6145010A
- Authority
- JP
- Japan
- Prior art keywords
- sand
- soft mud
- layer
- soft
- mud
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/18—Reclamation of land from water or marshes
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
Abstract
Description
【発明の詳細な説明】
本発明は、埋立地の造成方法に係り、特にl毎や湖の一
定区域を護岸で区切り、この区切った区域を軟泥を用い
て埋立て、この後砂で圧密して地盤を形成する埋立地の
造成方法において、軟泥の取り扱い及びその施工方法と
砂の施工方法を改善したものに関する。[Detailed Description of the Invention] The present invention relates to a method for creating a reclaimed land, in particular, dividing a certain area of a lake by a seawall, filling the divided area with soft mud, and then compacting it with sand. This invention relates to a method for creating a reclaimed land in which the ground is formed by improving the handling of soft mud and its construction method, as well as the construction method for sand.
海や湖の一定区域を埋め立てて埋立地を造成することが
行なわれている。このような埋立には産業廃棄物を埋立
区域に投入して埋め立てていく方法も行なわれているが
、海底、河床あるいは湖底から取り出した土を埋立区域
に投入して埋め立てていく浚渫埋立ての方法も広く行な
われている。Reclaimed land is created by reclaiming certain areas of oceans and lakes. This type of reclamation can be done by dumping industrial waste into a landfill area, but there is also a dredging method in which soil taken from the ocean floor, river bed, or lake bed is dumped into a landfill area. The method is also widely used.
この場合、海底、河床あるいは湖底の砂が硬いものであ
れば、カッター付きポンプ船を用いてこれをそのカッタ
ーでほくし、このほくしたものを吸い上げて埋立区域に
投入してもその比重が大きいことにより速やかに自然沈
降して堆積するので地盤の形成は速く行なわれる。これ
が細砂に代わっても同様にその沈降は速いので地盤の形
成は速くできる。しかしながら、これらの例えば適当に
粘性土が混入した良質の土砂だけで埋立を行なうことが
望ましいが、通常、粘性土の捨場を確保して良質土のみ
で埋立を行なうことは現実には困難であり、やはり多量
の軟泥をも埋立土砂として用いることが行なわれている
。In this case, if the sand on the seabed, riverbed, or lakebed is hard, a pump boat with a cutter is used to loosen it, and even if the loosened material is sucked up and placed in a landfill area, its specific gravity is still low. Because it is large, it naturally settles and accumulates quickly, so the formation of the ground occurs quickly. Even if this is replaced by fine sand, it settles quickly and the ground can be formed quickly. However, although it is desirable to perform landfilling using only high-quality soil mixed with an appropriate amount of clayey soil, it is usually difficult in reality to secure a dumping site for clayey soil and perform landfilling using only high-quality soil. However, a large amount of soft mud is also used as landfill soil.
しかしながら、この軟泥を通常のポンプ式浚渫船で取り
出してこれを埋立区域に琢入する方法では、ポンプ船で
土を吸い込むときに軟泥を流動化してしまい、スラリー
化してしまう。すなわち、軟泥ばシルト、粘土及びその
他のコロイド沈降物等から構成され、これらは元々水中
に懸濁又は浮遊していたものが長い時間をかけて沈降し
、堆積したものであるので、この堆積した層は長い間に
圧密されて泥の粒子と粒子が相互に緩く結合されて塊と
して取り出せる構造になっている。しかし、この土塊に
大きな力が加わると粒子の緩い結合が解かれて粒子はバ
ラバラになり、泥は流動化し易い。However, with the method of extracting this soft mud using a conventional pump-type dredger and depositing it in a reclaimed area, the soft mud fluidizes when the pump dredge sucks the soil into a slurry. In other words, soft mud is composed of silt, clay, and other colloidal sediments, which were originally suspended or floating in water and then settled and deposited over a long period of time. The layers have been compacted over time, resulting in mud particles that are loosely bound to each other and can be extracted as chunks. However, when a large force is applied to this clod, the loose bonds between the particles break down and the particles break apart, making the mud more likely to become fluid.
このように流動化した泥がポンプ船で埋立区域に投入さ
れると、泥はその体積が例えば数倍に膨張しているので
埋立区域内に占める割合が多くなり、そのため後続の軟
泥の投入容量が制限される結果、この先行の投入軟泥の
沈降を待たなければ他の軟泥を投入できないということ
になる。しかもこのようにスラリー化した泥水が埋め立
て区域に投入されると、泥の粒子は水中に浮遊して容易
には沈降せず、地盤の形成速度を著しく遅らせる結果と
なる。そしてこの沈降した泥が元の地盤を形成していた
泥のように圧密された構造を有するようになるには相当
の年月を要することになる。When this fluidized mud is introduced into a landfill area by a pump ship, the volume of the mud has expanded, for example, by several times, so that it occupies a large proportion of the landfill area, which reduces the volume of subsequent soft mud input. As a result, other soft mud cannot be added until the previously introduced soft mud has settled. Moreover, when such slurry water is poured into a landfill area, the mud particles are suspended in the water and do not easily settle, resulting in a significant slowdown in the rate of soil formation. It would take many years for this settled mud to have the same compacted structure as the mud that formed the original ground.
そのためこの軟泥による強固な地盤を形成するために、
積み重ねた軟泥の上に比重の大きい砂の層を設け、この
砂の層で軟泥層を押しつけることも行なわれているが、
この場合砂の吹き出しは埋立区域の一個所で行なわれる
ことが多いので吹き出された比重の大きい砂により比重
の小さい軟泥゛ が上層に押し上げられることがあり、
このため軟泥を再度沈降させねばならないのみならず、
砂層と軟泥層の逆転するような場所も生じて軟泥層を密
にするには上述のように長期間要することになったり、
軟泥層や砂層の厚さに不均一な場所が生じ、この修正に
も多大な時間を費やすことになったりしている。Therefore, in order to form a solid ground with this soft mud,
It is also possible to place a layer of sand with a high specific gravity on top of the piled up soft mud and press the soft mud layer with this layer of sand.
In this case, the sand is often blown out at one location in the reclaimed area, so the blown out sand with a high specific gravity may push the soft mud with a low specific gravity to the upper layer.
For this reason, not only does the soft mud have to settle again, but
There are places where the sand layer and soft mud layer are reversed, and it takes a long time to make the soft mud layer dense as mentioned above.
There are places where the thickness of the soft mud and sand layers is uneven, and it takes a lot of time to correct them.
このように、軟泥を投入し、この投入した軟泥を水底に
沈降させ、さらにこの軟泥を砂により圧密して地盤を形
成していく方法では、例えば軟泥投入期間に1年要した
とすると、その泥が沈降するのに数ケ月要し、さらに砂
による地盤改良に数ケ月要するというように工期が長く
なる。このように埋立地盤の造成に時間がかかると、施
工業者にとっては作業能率が悪く、大きな負担であるの
みならず、埋立地の有効利用が遅れる結果となり、経済
効果の点で大きな損失となる。In this way, the method of adding soft mud, letting it settle to the bottom of the water, and then compacting this soft mud with sand to form the ground takes, for example, one year to add soft mud. It takes several months for the mud to settle, and then several months to improve the ground with sand, making the construction process longer. If it takes time to prepare the reclaimed ground in this way, it not only results in poor work efficiency and a heavy burden on the construction contractor, but also results in delays in the effective use of the reclaimed land, resulting in a large loss in terms of economic effects.
この場合、工期を短縮しようとして軟泥と砂をポンプ船
で同時に吸い上げ、これらを−緒に埋立区域に投入しよ
うとしても、比重の大きい砂だけが先に沈降し、埋立地
の表層部が軟泥により形成されることになって地盤とし
ては軟弱なものになり易く、重量のある建造物の敷地と
しては適当でないものになり好ましくない。In this case, even if you try to shorten the construction period by sucking up soft mud and sand at the same time using a pump ship and putting them into the landfill area together, only the sand with a higher specific gravity will settle first, and the surface layer of the reclaimed land will be covered with soft mud. As a result, the ground tends to be soft, making it unsuitable as a site for a heavy building, which is undesirable.
また、従来の浚渫埋立方法の場合、汚濁水が埋立地域外
に余水の排水とともに流出し、外界の例えば海を汚すこ
とがある。Furthermore, in the case of the conventional dredging and reclamation method, polluted water may flow out of the reclamation area along with drainage of surplus water, polluting the outside world, for example, the ocean.
このようなことから、軟泥の沈降期間を設けず直ぐに砂
による地盤の改良工事を行なえるとともに外界を汚染し
ないように軟泥をスラリー化することなく埋め立て区域
に移動し、また、砂の吹き出しにより軟泥層が砂層と逆
転するようなこともなく、しかも砂の吹き出しにより軟
泥や砂が偏って埋立層を形成するようなことのない地盤
の強固な埋立地を造成できる埋立地の造成方法の開発が
望まれていた。Because of this, it is possible to immediately carry out ground improvement work with sand without allowing the soft mud to settle, and to move the soft mud to the landfill area without turning it into a slurry so as not to pollute the outside world. Development of a method for creating a reclaimed land that can create a solid reclaimed land that does not cause the layer to reverse with the sand layer, and also prevent soft mud and sand from being skewed and forming a reclaimed layer due to sand blowing out. It was wanted.
本発明は、以上のように、従来行なわれている軟泥を用
いて埋立、これを砂で圧密して埋立地を造成する埋立地
造成方法の問題点を改善するために、軟泥の取り出し、
移動及び投入をその軟泥の構造が崩れないように行ない
、さらにこの軟泥の堆積層に砂の層を多点吹き出しによ
り積層して軟泥層を圧密し、これにより埋め立て地の造
成作業能率を向上するとともに、地盤の強固な埋め立て
地を得られるようにしたものである。As described above, the present invention aims to improve the problems of the conventional method of reclaiming land using soft mud and compacting it with sand to create a reclaimed land.
The soft mud is moved and put in such a way that the structure of the soft mud does not collapse, and then a layer of sand is layered on top of the soft mud pile by multi-point blowing to compact the soft mud layer, thereby improving the efficiency of the construction work of the reclaimed land. At the same time, it was possible to obtain reclaimed land with solid ground.
次に本発明の一実施例を第1図ないし第4図に基づいて
説明する。Next, one embodiment of the present invention will be described based on FIGS. 1 to 4.
第1図は海底、河床ですでに地盤を形成している地山の
軟泥を取り出して土運船に積み込む状態を示す図であっ
て、グラブ船1のクレーン1aの先端に設けたグラブ1
bにより水底の軟泥aがその構造を乱さないようにして
採堆され、この軟泥がクレーン1aの旋回により土運船
2に積み込まれる。この際、軟泥はその構造が乱れない
ように静かに船中に積載される。このように軟泥が順次
土運船2に積み込まれ、この船が満杯になったときに、
この船を第2図に示すように埋立地域に移動する。FIG. 1 is a diagram showing the state in which soft mud from the ground that has already formed the ground on the seabed or river bed is taken out and loaded onto an earth transport vessel, and the grab 1 is installed at the tip of the crane 1a of the grab vessel
By b, the soft mud a from the water bottom is collected without disturbing its structure, and this soft mud is loaded onto the earth transport vessel 2 by the rotation of the crane 1a. At this time, the soft mud is loaded onto the ship quietly so as not to disturb its structure. In this way, the soft mud is sequentially loaded into the earth transport vessel 2, and when this vessel is full,
This ship will be moved to the reclaimed area as shown in Figure 2.
この移動した土運船はその船底が開口されて上記の積載
した軟泥が水底に投下される。この際、軟泥の塊りが個
々にできるだけ静かに自然落下するように投下する。こ
のようなことを埋立区域の全個所に順次行ない、軟泥の
投下されない個所がないように軟泥を隈なく敷き詰める
。このようなことを繰り返して土運船2が投入可能な限
り順次軟泥層を盛り上げる。The bottom of the moved earth carrier is opened and the loaded soft mud is dumped onto the water bottom. At this time, drop the lumps of soft mud individually so that they fall naturally as quietly as possible. This process is carried out one after another in all parts of the landfill area, and the soft mud is spread everywhere so that there is no place where the soft mud will not be dumped. By repeating this process, the soft mud layer is gradually heaped up as much as possible by the soil transport vessel 2.
ついで、第3図に示すようにポンプ船3により砂すを吸
い上げてこの砂を埋立区域に漏らし吹きする。すなわち
、第3図に示すように、両端にパイプ管4.4・・・を
相互に隙間を設けて接続して排砂管5を形成し、その一
端のパイプに送砂管6を接続してこの送砂管6にポンプ
船3により吸い上げた砂を供給する。このようにすると
砂は送砂管6中を流れてその端部から押し出される。こ
の押し出された砂の一部は送砂管6とこれに隣接する排
砂管5の端部のパイプ4との間の隙間から漏れ出て埋立
区域の上記軟泥層の上にまき散らされる。このようにし
て砂の漏らし吹きが行なわれる。一方、押し出された砂
の残部は次の隣接するパイプ4の方に送出され、上記の
場合と同様にその一部が漏らし吹きされるとともに、他
の残部がさらに次の隣接するパイプ4の方に送出される
。Then, as shown in FIG. 3, the sand is sucked up by the pump ship 3 and the sand is blown into the reclaimed area. That is, as shown in FIG. 3, a sand discharge pipe 5 is formed by connecting pipes 4, 4, etc. at both ends with a gap between them, and a sand transport pipe 6 is connected to one end of the pipe. The sand sucked up by the pump ship 3 is supplied to the sand pipe 6 of the lever. In this way, the sand flows through the sand pipe 6 and is pushed out from its end. A part of this extruded sand leaks out from the gap between the sand pipe 6 and the adjacent pipe 4 at the end of the sand discharge pipe 5, and is scattered on the soft mud layer in the reclaimed area. In this way, the sand is blown off. On the other hand, the remaining part of the pushed out sand is sent to the next adjacent pipe 4, and as in the case above, a part of it leaks and is blown away, and the remaining part is further sent to the next adjacent pipe 4. sent to.
以下同様に他のパイプとパイプの間の隙間からも同様の
漏らし吹きが行なわれる。Thereafter, similar leakage blowing is performed from the gaps between other pipes as well.
このようにして砂の漏らし吹きが行なわれるが、この漏
らし吹きを埋立区域の全個所に行なうために、第4図に
示すように配管を行なう。すなわち、第4図に示す送砂
管6に排砂管5.5・・を分岐して平行に接続し、さら
にこの排砂管5.5・・・の両側にこの排砂管5と同様
の排砂管5a、5a・・・・、5b、5b、・・・を分
岐して設ける。Sand is sprayed in this way, and in order to spray sand to all parts of the reclaimed area, piping is installed as shown in FIG. 4. That is, sand discharge pipes 5.5... are branched and connected in parallel to the sand conveyance pipe 6 shown in FIG. The sand discharge pipes 5a, 5a, . . . , 5b, 5b, . . . are branched and provided.
なお、7は護岸である。In addition, 7 is a seawall.
このような排砂管5.5・・・、5a、5a・・・及び
5b、5b・・より砂を漏らし吹きするときは、第3図
に示すパイプ4との間全部について上記と同様に砂をま
き散らしても良いが、このようにすると隣接する隙間か
らまき散らされる砂が重なりあって砂が一度に大量に軟
泥層の上に落下することがあり、このようになると比較
的軽い軟泥が砂の衝撃により上層に上がるので、一つ置
きの隙間毎に漏らし吹きを行い、これが−巡したときつ
ぎに今度は前回とは逆に漏らし吹きを行ない、順次これ
を繰り返して砂の層を順次積層していくようにすること
がより好ましい。なお、この際漏らし吹きをしない隙間
については隣接パイプのフランジを密接してボルト締め
を行なえば良い。When sand is leaked and blown from such sand discharge pipes 5.5..., 5a, 5a... and 5b, 5b, etc., the same procedure as above is applied to the entire area between the pipes 4 and 4 shown in Fig. 3. You can also scatter sand, but if you do this, the sand scattered from adjacent gaps may overlap and a large amount of sand may fall onto the soft mud layer at once, and if this happens, the relatively light soft mud will The impact of the sand causes it to rise to the upper layer, so spray every other gap, and when this cycle has been completed, spray again in the opposite direction to the previous one. It is more preferable to layer them one after another. At this time, in the gaps where no leakage occurs, the flanges of adjacent pipes may be brought into close contact with each other and bolted.
上記のようにして砂を軟泥層にまき散らすと、砂の粒子
はばらばらに軟泥層に落下するので、軟泥を舞い上げる
こともなく、しかも砂は軟泥より比重が大きいので、軟
泥の土塊の間及び軟泥の中に入り込み、その分だけ水を
追い出し、この追い出された水は砂の隙間を毛細管現象
により上昇して除かれる。このようにして軟泥の構造を
密にするとともに、砂が粘着質の軟泥成分により結合さ
れて軟泥層はより強固になる。When sand is sprinkled on the soft mud layer as described above, the sand particles will fall into the soft mud layer in pieces, so the soft mud will not be thrown up, and since sand has a higher specific gravity than the soft mud, it will spread between the soft mud clods. It penetrates into the soft mud and expels that much water, and this expelled water rises through the gaps in the sand by capillary action and is removed. In this way, the structure of the soft mud becomes denser, and the sand is bound together by the sticky soft mud component, making the soft mud layer stronger.
次に第5図及び第6図に示す他の実施例を説明する。Next, another embodiment shown in FIGS. 5 and 6 will be described.
第5図は配管5゛の設置状態を示すものであって、埋立
区域が基盤目状の配管5゛により小区域に区分され、そ
れぞれの区分毎に砂の吹き出しが行なわれる。それぞれ
の区分の配管は相対する辺の間隔が例えば50〜150
m以内に設けられている。FIG. 5 shows the installation state of the piping 5', in which the reclaimed area is divided into small areas by the base-like piping 5', and sand is blown out for each division. The distance between opposing sides of each section of piping is, for example, 50 to 150.
It is located within m.
このような配管状態で、第3図に示すように砂を多点で
吹き出すと、第6図に示すように大きな砂の粒子は沈1
;イ速度が早いため吹き出し地点に近い方にたまり易く
、このため、(lJt tlができて沈降速度の遅い砂
は遠くの方にたまるようになる。そして砂の吹き出しが
継続されるにつれて砂の堆積層の先端は遠くの方に延び
、配管の相対する辺の吹き出し点から吹き出された砂の
堆積層先端は互いに接近して倒立した偏平四角錐状の四
部を形成する堆積層ができあがる。そしてこの堆積層の
四部を周囲の砂でならして造成地ができあがる。なお、
5’aば受枠である。With this piping condition, if sand is blown out from multiple points as shown in Figure 3, the large sand particles will settle out as shown in Figure 6.
; Because sand velocity is fast, sand tends to accumulate near the blowout point, and for this reason, (lJt tl) is formed, and sand with a slow settling speed accumulates in the far direction.And as the sand blowout continues, the sand The tips of the sand deposits extend far away, and the tips of the sand deposits blown out from the blow-off points on opposite sides of the pipe approach each other, creating a deposit layer that forms four parts in the shape of an inverted oblate pyramid. The four parts of this sedimentary layer are leveled with the surrounding sand to create a created area.
5'a is a receiving frame.
このようにして埋立地盤を形成すると、配管の節約がで
きるとともに、底の軟泥の圧密も行なわれる。この圧密
の程度は、例えば軟泥層の」二の砂吹き出し地点におけ
る砂の堆積層が2.5mになってその堆積層先端が25
m遠くに延びているような場合には、砂の吹き出し地点
、中間及び先端での軟泥は水分が固形分に対してそれぞ
れ50〜60%、60〜80%、70〜90%になり、
この軟泥がその敷き詰められるま前に取り出された元の
他山では水分が固形分に対して100%であるのに比べ
て軟泥の構造をより密にしている。Forming the reclaimed ground in this way not only saves on piping, but also consolidates the soft mud at the bottom. The degree of consolidation is such that, for example, the sand deposit layer at the second sand blowout point of the soft mud layer is 2.5 m long, and the tip of the sand deposit layer is 2.5 m long.
In the case where the sand extends far away, the water content of the soft mud at the point, middle and tip of the sand is 50-60%, 60-80% and 70-90% of the solid content, respectively.
The soft mud has a denser structure compared to the original pile where the soft mud was taken out before it was spread, where the water content is 100% of the solid content.
なお、第5図では基盤目状に配管したが、第7図、第8
図、第9図に示すように、埋立区域の小区分を、平行の
配管5°°、コの字状配管5°パ、直交する配管5゛”
1により区分しても良い。In addition, in Fig. 5, the piping is arranged in the shape of the base plate, but in Figs.
As shown in Figure 9, the subdivisions of the landfill area are divided into parallel pipes of 5°, U-shaped pipes of 5°, and orthogonal pipes of 5°.
It may be classified according to 1.
本発明によれば、軟泥をその構造が乱れないようにして
埋立区域に投入して軟泥層を形成し、さらにこの軟泥層
の上に多点吹き出しにより砂の層を形成したので、汚濁
水の外界への流出がなく、軟泥層の形成速度を大きくで
きるとともに、その地盤の強度も大きくできる。これに
より、埋め立て作業の能率を向上し、工期の短縮をはか
ることができる。特に従来の浚渫による埋立地造成方法
に比べ、軟泥を沈降させる期間が不必要になるのみなら
ず、地盤を形成する軟泥層も元の他山の圧密された構造
がそのまま保持されているので従来のような砂による圧
密のための工期が短縮され、軟泥層を形成した後は従来
例えば6力月要した砂による圧密のための工期、すなわ
ち地盤改良工期を例えば1ケ月に短縮できる。この結果
、従来の方法における泥の沈降に要する工期の短縮とこ
の砂による地盤改良工期の短縮分を合わせると従来の方
法による浚渫埋立地造成方法による工期が例えば2年で
あるとすると、その約半分の1aケ月で埋め立て地を造
成できることになる。According to the present invention, soft mud is poured into a landfill area without disturbing its structure to form a soft mud layer, and a layer of sand is further formed on top of this soft mud layer by multi-point blowing. Since there is no outflow to the outside world, the formation speed of the soft mud layer can be increased, and the strength of the ground can also be increased. This will improve the efficiency of the landfill work and shorten the construction period. In particular, compared to the conventional method of creating a landfill by dredging, not only is there no need for a period for settling soft mud, but the soft mud layer that forms the ground retains its original compacted structure. The construction period for consolidation with sand can be shortened, and after forming a soft mud layer, the construction period for consolidation with sand, which conventionally required six months, ie, the period for soil improvement work, can be shortened to one month, for example. As a result, the reduction in the construction period required for mud settling in the conventional method and the reduction in the construction period for ground improvement using this sand means that if the construction period for the conventional method of creating a dredged and reclaimed land is, for example, two years, approximately This means that a landfill can be created in half the time of 1a month.
第1図は本発明の方法の一実施例に使用する装置の一部
の説明図、第2図はその装置の他の一部の説明図、第3
図はさらに他の一部の説明図、第4図G才第3図に示ず
送砂管、排砂管の配置の具体例を示す平面説明図、第5
図は他の実施例における第4図に相当する図、第6図は
この実施例における地盤形成過程の第2図に相当する説
明図、第7図〜第9図はそれぞれさらに他の実施例にお
ける第4図に相当する図である。
図中、1はグラブ船、2は土運船、3はポンプ船、5.
5a、5b、5゛、5°゛、5パ、5+111は排砂管
、aは軟泥、bは砂である。
第1図
第2図FIG. 1 is an explanatory diagram of a part of the apparatus used in one embodiment of the method of the present invention, FIG. 2 is an explanatory diagram of another part of the apparatus, and FIG.
The figures also include some other explanatory diagrams, Figure 4.
The figure corresponds to FIG. 4 in another embodiment, FIG. 6 is an explanatory diagram corresponding to FIG. 2 of the ground formation process in this embodiment, and FIGS. 7 to 9 each correspond to still another embodiment. FIG. 4 is a diagram corresponding to FIG. 4 in FIG. In the diagram, 1 is a grab ship, 2 is an earth carrier, 3 is a pump ship, and 5.
5a, 5b, 5゛, 5゛, 5pa, 5+111 are sand discharge pipes, a is soft mud, and b is sand. Figure 1 Figure 2
Claims (2)
として乱さないように採取し、この土塊を乱さないよう
にして土運船に積み込み、この積み込んだ土塊を埋立て
区域に静かに投入して均一厚さの軟泥層を形成し、この
層の上方に多点で砂を吹き出す多点砂吹き出し装置を設
け、この多点砂吹き出し装置により吹き出した砂を上記
軟泥層に堆積させて圧密し地盤を形成することを特徴と
する埋立地の造成方法。(1) Collect the compacted soft mud that forms the ground at the bottom of the water without disturbing it as a clod, load it onto an earth transport ship without disturbing it, and gently place the loaded clod in the reclamation area. A multi-point sand blowing device is provided above this layer to blow out sand at multiple points, and the sand blown out by this multi-point sand blowing device is deposited on the soft mud layer. A method of creating a reclaimed land characterized by forming a compacted ground.
砂管により構成し、この排砂管を埋立区域を小区域に区
分して配管し、かつこの配管の砂吹き出し点を互いに離
間した位置にして砂を吹き出したときその砂の堆積層先
端が重層又は近接するように設けたことを特徴とする特
許請求の範囲第1項記載の埋立地の造成方法。(2) The multi-point blowing device is composed of sand discharge pipes that blow sand from multiple locations, and the sand discharge pipes are piped to divide the reclaimed area into small areas, and the sand blowing points of the pipes are placed at locations spaced apart from each other. 2. The method of creating a reclaimed land according to claim 1, wherein the sand is provided so that when the sand is blown out, the tips of the sand piles overlap or are close to each other.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16479684A JPS6145010A (en) | 1984-08-08 | 1984-08-08 | Formation of reclamation site |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16479684A JPS6145010A (en) | 1984-08-08 | 1984-08-08 | Formation of reclamation site |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6145010A true JPS6145010A (en) | 1986-03-04 |
JPH0132329B2 JPH0132329B2 (en) | 1989-06-30 |
Family
ID=15800097
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16479684A Granted JPS6145010A (en) | 1984-08-08 | 1984-08-08 | Formation of reclamation site |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6145010A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6480603A (en) * | 1987-09-18 | 1989-03-27 | Nikko Kk | Kneading method of mixer in asphalt plant |
JPH02153102A (en) * | 1988-12-02 | 1990-06-12 | Maeda Road Constr Co Ltd | Arrival and shipment control in plant for shipment of stored object |
US5849883A (en) * | 1988-05-13 | 1998-12-15 | Amgen Inc. | Method for purifying granulocyte colony stimulating factor |
NL1012292C2 (en) * | 1999-06-10 | 2000-12-12 | Ballast Nedam Baggeren Bv | Method of building up height of land in polder, uses off-shore sand-sucker vessel to pipe sand and silt from seabed into pans on shore |
CN117344692A (en) * | 2023-10-11 | 2024-01-05 | 中国海洋大学 | Silt bag layout method taking underground fresh water storage into consideration by artificial island |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4222612Y1 (en) * | 1964-01-29 | 1967-12-22 | ||
JPS5629055A (en) * | 1979-08-09 | 1981-03-23 | Lucas Industries Ltd | Reciprocating plunger type fuel injection pump |
-
1984
- 1984-08-08 JP JP16479684A patent/JPS6145010A/en active Granted
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4222612Y1 (en) * | 1964-01-29 | 1967-12-22 | ||
JPS5629055A (en) * | 1979-08-09 | 1981-03-23 | Lucas Industries Ltd | Reciprocating plunger type fuel injection pump |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6480603A (en) * | 1987-09-18 | 1989-03-27 | Nikko Kk | Kneading method of mixer in asphalt plant |
JPH052041B2 (en) * | 1987-09-18 | 1993-01-11 | Nikko Kk | |
US5849883A (en) * | 1988-05-13 | 1998-12-15 | Amgen Inc. | Method for purifying granulocyte colony stimulating factor |
JPH02153102A (en) * | 1988-12-02 | 1990-06-12 | Maeda Road Constr Co Ltd | Arrival and shipment control in plant for shipment of stored object |
JPH0569921B2 (en) * | 1988-12-02 | 1993-10-04 | Maeda Doro Kk | |
NL1012292C2 (en) * | 1999-06-10 | 2000-12-12 | Ballast Nedam Baggeren Bv | Method of building up height of land in polder, uses off-shore sand-sucker vessel to pipe sand and silt from seabed into pans on shore |
CN117344692A (en) * | 2023-10-11 | 2024-01-05 | 中国海洋大学 | Silt bag layout method taking underground fresh water storage into consideration by artificial island |
CN117344692B (en) * | 2023-10-11 | 2024-05-17 | 中国海洋大学 | Silt bag layout method taking underground fresh water storage into consideration by artificial island |
Also Published As
Publication number | Publication date |
---|---|
JPH0132329B2 (en) | 1989-06-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US5150986A (en) | Process and apparatus for depositing silt on the bottom and slopes of the wet open working or dredging | |
CN109914174B (en) | Construction method for backfilling, stone throwing and silt squeezing of pond | |
JPS6145010A (en) | Formation of reclamation site | |
RU2513816C1 (en) | Method to form anthropogenic field | |
Burt | Guidelines for the beneficial use of dredged material | |
CN100582382C (en) | Process for constructing quickly consolidated temperory horizontal platform by picking clay of lake bottom | |
US4072016A (en) | Method of reconstructing and reclamation of river channels | |
CN204661517U (en) | The dredging of seasonal stream heavy metal polluted bed mud and dystopy governing system | |
Lam | Land reclamation & soil improvement using dredged slurry as fill | |
Partridge | The significance of origin for the identification of engineering problems in transported Quaternary soils | |
EP0960660B1 (en) | Process for filling a disposal site for silt supplied with a high water content and device for applying drainage wicks | |
RU2275461C2 (en) | Method for dam and other fill structure construction | |
US3722138A (en) | Procedure for a directed hydraulic fill | |
JPH03244716A (en) | Dredge system | |
CN214091219U (en) | Large-scale grit aggregate processing system production waste residue safety protection structure | |
JP6534131B2 (en) | Creation method of artificial island | |
CN113684815B (en) | Solid-liquid separation method for high-water-content soft material | |
Robertson et al. | The influence of depositional methods on the engineering properties of tailings deposits | |
SU1263850A1 (en) | Method of dumping stripped rock | |
Kog | Rehabilitation of abandoned non-hazardous tailings ponds | |
Marlin | Potential use of innovative dredge technology and beneficial use of sediment for river restoration | |
JP3806832B2 (en) | Subsurface landfill method and subsurface landfill | |
Shields et al. | Controlling sand placement during the building of artificial islands | |
JPS6056852B2 (en) | Sludge dredging method | |
Bartos | Containment area management to promote natural dewatering of fine-grained dredged material |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |