JPH0132329B2 - - Google Patents

Info

Publication number
JPH0132329B2
JPH0132329B2 JP59164796A JP16479684A JPH0132329B2 JP H0132329 B2 JPH0132329 B2 JP H0132329B2 JP 59164796 A JP59164796 A JP 59164796A JP 16479684 A JP16479684 A JP 16479684A JP H0132329 B2 JPH0132329 B2 JP H0132329B2
Authority
JP
Japan
Prior art keywords
sand
soft mud
layer
mud
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP59164796A
Other languages
Japanese (ja)
Other versions
JPS6145010A (en
Inventor
Setsuji Umezaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP16479684A priority Critical patent/JPS6145010A/en
Publication of JPS6145010A publication Critical patent/JPS6145010A/en
Publication of JPH0132329B2 publication Critical patent/JPH0132329B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/18Reclamation of land from water or marshes

Description

【発明の詳細な説明】 本発明は、埋立地の造成方法に係り、特に海や
湖の一定区域を護岸で区切り、この区切つた区域
を軟泥を用いて埋立て、この後砂で圧密して地盤
を形成する埋立地の造成方法において、軟泥の取
り扱い及びその施工方法と砂の施工方法を改善し
たものに関する。
[Detailed Description of the Invention] The present invention relates to a method of creating a reclaimed land, in particular, dividing a certain area of the sea or a lake with a seawall, filling the divided area with soft mud, and then compacting it with sand. This invention relates to improved methods for handling and constructing soft mud, as well as methods for constructing sand, in a method for creating a reclaimed land that forms the ground.

海や湖の一定区域を埋め立てて埋立地を造成す
ることが行なわれている。このような埋立には産
業廃棄物を埋立区域に投入して埋め立てていく方
法も行なわれているが、海底、河床あるいは湖底
から取り出した土を埋立区域に投入して埋め立て
ていく浚渫埋立ての方法も広く行なわれている。
この場合、海底、河床あるいは湖底の砂が硬いも
のであれば、カツター付きポンプ船を用いてこれ
をそのカツターでほぐし、このほぐしたものを吸
い上げて埋立区域に投入してもその比重が大きい
ことにより速やかに自然沈降して堆積するので地
盤の形成は速く行なわれる。これが細砂に代わつ
ても同様にその沈降は速いので地盤の形成は速く
できる。しかしながら、これらの例えば適当に粘
性土が混入した良質の土砂だけで埋立を行なうこ
とが望ましいが、通常、粘性土の捨場を確保して
良質土のみで埋立を行なうことは現実には困難で
あり、やはり多量の軟泥をも埋立土砂として用い
ることが行なわれている。
Reclaimed land is created by reclaiming certain areas of oceans and lakes. This type of reclamation can be done by dumping industrial waste into a landfill area, but there is also a dredging method in which soil taken from the ocean floor, river bed, or lake bed is dumped into a landfill area. The method is also widely used.
In this case, if the sand on the seabed, riverbed, or lakebed is hard, a pump boat with a cutter is used to loosen it, and even if the loosened material is sucked up and thrown into the landfill area, its specific gravity is high. Because the soil naturally settles and accumulates more quickly, the formation of the ground occurs more quickly. Even when this is replaced by fine sand, it settles quickly and the ground can be formed quickly. However, although it is desirable to perform landfilling using only high-quality soil mixed with an appropriate amount of clayey soil, it is usually difficult in reality to secure a dumping site for clayey soil and perform landfilling using only high-quality soil. However, a large amount of soft mud is also used as landfill soil.

しかしながら、この軟泥を通常のポンプ式浚渫
船で取り出してこれを埋立区域に投入する方法で
は、ポンプ船で土を吸い込むときに軟泥を流動化
してしまい、スラリー化してしまう。すなわち、
軟泥はシルト、粘土及びその他のコロイド沈降物
等から構成され、これらは元々水中に懸濁又は浮
遊していたものが長い時間をかけて沈降し、堆積
したものであるので、この堆積した層は長い間に
圧密されて泥の粒子と粒子が相互に緩く結合され
て塊として取り出せる構造になつている。しか
し、この土塊に大きな力が加わると粒子の緩い結
合が解かれて粒子はバラバラになり、泥は流動化
し易い。
However, if this soft mud is extracted using a conventional pump-type dredger and placed in a landfill area, the soft mud fluidizes and becomes a slurry when the pump dredge sucks the soil. That is,
Soft mud is composed of silt, clay, and other colloidal sediments, which were originally suspended or floating in water and then settled and deposited over a long period of time. Consolidated over a long period of time, the mud particles are loosely bonded to each other, creating a structure that can be extracted as a lump. However, when a large force is applied to this clod, the loose bonds between the particles break down and the particles break apart, making the mud more likely to become fluid.

このように流動化した泥がポンプ船で埋立区域
に投入されると、泥はその体積が例えば数倍に膨
張しているので埋立区域内に占める割合が多くな
り、そのため後続の軟泥の投入容量が制限される
結果、この先行の投入軟泥の沈降を待たなければ
他の軟泥を投入できないということになる。しか
もこのようにスラリー化した泥水が埋め立て区域
に投入されると、泥の粒子は水中に浮遊して容易
には沈降せず、地盤の形成速度を著しく遅らせる
結果となる。そしてこの沈降した泥が元の地盤を
形成していた泥のように圧密された構造を有する
ようになるには相当の年月を要することになる。
When this fluidized mud is introduced into a landfill area by a pump ship, the volume of the mud has expanded, for example, by several times, so that it occupies a large proportion of the landfill area, which reduces the volume of subsequent soft mud input. As a result, other soft mud cannot be added until the previously introduced soft mud has settled. Moreover, when such slurry water is poured into a landfill area, the mud particles are suspended in the water and do not easily settle, resulting in a significant slowdown in the rate of soil formation. It would take many years for this settled mud to have the same compacted structure as the mud that formed the original ground.

そのためこの軟泥による強固な地盤を形成する
ために、積み重ねた軟泥の上に比重の大きい砂の
層を設け、この砂の層で軟泥層を押しつけること
も行なわれているが、この場合砂の吹き出しは埋
立区域の一個所で行なわれることが多いので吹き
出された比重の大きい砂により比重の小さい軟泥
が上層に押し上げられることがあり、このため軟
泥を再度沈降させねばならないのみならず、砂層
と軟泥層の逆転するような場所も生じて軟泥層を
密にするには上述のように長期間要することにな
つたり、軟泥層や砂層の厚さに不均一な場所が生
じ、この修正にも多大な時間を費やすことになつ
たりしている。
Therefore, in order to form a solid ground with this soft mud, a layer of sand with a high specific gravity is placed on top of the piled up soft mud, and this sand layer is used to press the soft mud layer, but in this case, the sand is blown out. Since this is often carried out in one place in the reclamation area, the blown out sand with a higher specific gravity may push the soft mud with a lower specific gravity to the upper layer, which not only requires the soft mud to settle again, but also creates a gap between the sand layer and the soft mud. There are places where the layers are reversed and it takes a long time to make the soft mud layer denser as mentioned above, and there are places where the soft mud and sand layers are uneven in thickness, and it takes a lot of effort to correct this. I end up spending a lot of time doing it.

このように、軟泥を投入し、この投入した軟泥
を水底に沈降させ、さらにこの軟泥を砂により圧
密して地盤を形成していく方法では、例えば軟泥
投入期間に1年要したとすると、その泥が沈降す
るのに数ケ月要し、さらに砂による地盤改良に数
ケ月要するというように工期が長くなる。このよ
うに埋立地盤の造成に時間がかかると、施工業者
にとつては作業能率が悪く、大きな負担であるの
みならず、埋立地の有効利用が遅れる結果とな
り、経済効果の点で大きな損失となる。
In this way, the method of adding soft mud, letting it settle to the bottom of the water, and then compacting this soft mud with sand to form the ground takes, for example, one year to add soft mud. It takes several months for the mud to settle, and then several months to improve the ground with sand, making the construction process longer. If it takes time to prepare the reclaimed ground in this way, it not only results in poor work efficiency and a heavy burden on the construction contractor, but also delays the effective use of the reclaimed land, resulting in a large loss in terms of economic effects. Become.

この場合、工期を短縮しようとして軟泥と砂を
ポンプ船で同時に吸い上げ、これらを一緒に埋立
区域に投入しようとしても、比重の大きい砂だけ
が先に沈降し、埋立地の表層部が軟泥により形成
されることになつて地盤としては軟弱なものにな
り易く、重量のある建造物の敷地としては適当で
ないものになり好ましくない。
In this case, even if you try to shorten the construction period by sucking up soft mud and sand at the same time using a pump ship and putting them into the landfill area together, only the sand with a higher specific gravity will settle first, and the surface layer of the reclaimed land will be formed by soft mud. As a result, the ground tends to be soft, making it unsuitable as a site for a heavy building, which is undesirable.

また、従来の浚渫埋立方法の場合、汚濁水が埋
立地域外に余水の排水とともに流出し、外界の例
えば海を汚すことがある。
Furthermore, in the case of the conventional dredging and reclamation method, polluted water may flow out of the reclamation area along with drainage of surplus water, polluting the outside world, for example, the ocean.

このようなことから、軟泥の沈降期間を設けず
直ぐに砂による地盤の改良工事を行なえるととも
に外界を汚染しないように軟泥をスラリー化する
ことなく埋め立て区域に移動し、また、砂の吹き
出しにより軟泥層が砂層と逆転するようなことも
なく、しかも砂の吹き出しにより軟泥や砂が偏つ
て埋立層を形成するようなことのない地盤の強固
な埋立地を造成できる埋立地の造成方法の開発が
望まれていた。
Because of this, it is possible to immediately carry out ground improvement work with sand without allowing the soft mud to settle, and to move the soft mud to the landfill area without turning it into a slurry so as not to pollute the outside world. It is necessary to develop a method for creating a reclaimed land that can create a solid reclaimed land with a solid ground that does not cause the layer to reverse with the sand layer and also prevent soft mud and sand from being skewed and forming a reclaimed layer due to sand blowing out. It was wanted.

本発明は、以上のように、従来行なわれている
軟泥を用いて埋立、これを砂で圧密して埋立地を
造成する埋立地造成方法の問題点を改善するため
に、軟泥の取り出し、移動及び投入をその軟泥の
構造が崩れないように行ない、さらにこの軟泥の
堆積層に砂の層を多点吹き出しにより積層して軟
泥層を圧密し、これにより埋め立て地の造成作業
能率を向上するとともに、地盤の強固な埋め立て
地を得られるようにしたものである。
As described above, the present invention aims to improve the problems of the conventional method of reclaiming land using soft mud and compacting it with sand to create a reclaimed land. In addition, a layer of sand is layered on the soft mud layer by multi-point blowing to compact the soft mud layer, thereby improving the efficiency of the construction work of the reclaimed land. This made it possible to obtain reclaimed land with solid ground.

次に本発明の一実施例を第1図ないし第4図に
基づいて説明する。
Next, one embodiment of the present invention will be described based on FIGS. 1 to 4.

第1図は海底、河床ですでに地盤を形成してい
る地山の軟泥を取り出して土運船に積み込み状態
を示す図であつて、グラブ船1のクレーン1aの
先端に設けたグラブ1bにより水底の軟泥aがそ
の構造を乱さないようにして採取され、この軟泥
がクレーン1aの旋回により土運船2に積み込ま
れる。この際、軟泥はその構造が乱れないように
静かに船中に積載される。このように軟泥が順次
土運船2に積み込まれ、この船が満杯になつたと
きに、この船を第2図に示すように埋立地域に移
動する。
Figure 1 shows the state in which soft mud from the ground that has already formed the ground on the seabed or river bed is taken out and loaded onto a cargo ship, in which a grab 1b installed at the tip of a crane 1a of a grab ship 1 is used. Soft mud a from the bottom of the water is collected without disturbing its structure, and this soft mud is loaded onto the earth transport vessel 2 by the rotation of the crane 1a. At this time, the soft mud is loaded onto the ship quietly so as not to disturb its structure. In this way, the soft mud is sequentially loaded into the soil transport vessel 2, and when the vessel is full, the vessel is moved to the reclamation area as shown in FIG.

この移動した土運船はその船底が開口されて上
記の積載した軟泥が水底に投下される。この際、
軟泥の塊りが個々にできるだけ静かに自然落下す
るように投下する。このようなことを埋立区域の
全個所に順次行ない、軟泥の投下されない個所が
ないように軟泥を隈なく敷き詰める。このような
ことを繰り返して土運船2が投入可能な限り順次
軟泥層を盛り上げる。
The bottom of the moved earth carrier is opened and the loaded soft mud is dumped onto the water bottom. On this occasion,
Drop each lump of soft mud so that it falls naturally as quietly as possible. This process is carried out one after another in all parts of the landfill area, and the soft mud is spread everywhere so that there is no place where the soft mud will not be dumped. By repeating this process, the soft mud layer is gradually heaped up as much as possible by the soil transport vessel 2.

ついで、第3図に示すようにポンプ船3により
砂bを吸い上げてこの砂を埋立区域に漏らし吹き
する。すなわち、第3図に示すように、両端にパ
イプ管4,4…を相互に隙間を設けて接続して排
砂管5を形成し、その一端のパイプに送砂管6を
接続してこの送砂管6にポンプ船3により吸い上
げた砂を供給する。このようにすると砂は送砂管
6中を流れてその端部から押し出される。この押
し出された砂の一部は送砂管6とこれに隣接する
排砂管5の端部のパイプ4との間の隙間から漏れ
出て埋立区域の上記軟泥層の上にまき散らされ
る。このようにして砂の漏らし吹きが行なわれ
る。一方、押し出された砂の残部は次の隣接する
パイプ4の方に送出され、上記の場合と同様にそ
の一部が漏らし吹きされるとともに、他の残部が
さらに次の隣接するパイプ4の方に送出される。
以下同様に他のパイプとパイプの間の隙間からも
同様の漏らし吹きが行なわれる。
Then, as shown in FIG. 3, the sand b is sucked up by the pump ship 3 and is blown into the reclaimed area. That is, as shown in Fig. 3, a sand discharge pipe 5 is formed by connecting the pipes 4, 4, . The sand sucked up by the pump ship 3 is supplied to the sand pipe 6. In this way, the sand flows through the sand pipe 6 and is pushed out from its end. A part of this extruded sand leaks out from the gap between the sand pipe 6 and the adjacent pipe 4 at the end of the sand discharge pipe 5, and is scattered on the soft mud layer in the reclaimed area. In this way, the sand is blown off. On the other hand, the remaining part of the pushed out sand is sent to the next adjacent pipe 4, and as in the case above, a part of it leaks and is blown away, and the remaining part is further sent to the next adjacent pipe 4. sent to.
Thereafter, similar leakage blowing is performed from the gaps between other pipes as well.

このようにして砂の漏らし吹きが行なわれる
が、この漏らし吹きを埋立区域の全個所に行なう
ために、第4図に示すように配管を行なう。すな
わち、第4図に示す送砂管6に排砂管5,5…を
分岐して平行に接続し、さらにこの排砂管5,5
…の両側にこの排砂管5と同様の排砂管5a,5
a…,5b,5b,…を分岐して設ける。なお、
7は護岸である。
Sand is sprayed in this way, and in order to spray sand to all parts of the reclaimed area, piping is installed as shown in FIG. 4. That is, the sand discharge pipes 5, 5... are branched and connected in parallel to the sand conveyance pipe 6 shown in FIG.
Sand discharge pipes 5a, 5 similar to this sand discharge pipe 5 are disposed on both sides of...
a..., 5b, 5b,... are provided in a branched manner. In addition,
7 is a seawall.

このような排砂管5,5…,5a,5a…及び
5b,5b…より砂を漏らし吹きするときは、第
3図に示すパイプ4との間全部について上記と同
様に砂をまき散らしても良いが、このようにする
と隣接する隙間からまき散らされる砂が重なりあ
つて砂が一度に大量に軟泥層の上に落下すること
があり、このようになると比較的軽い軟泥が砂の
衝撃により上層に上がるので、一つ置きの隙間毎
に漏らし吹きを行い、これが一巡したときつぎに
今度は前回とは逆に漏らし吹きを行ない、順次こ
れを繰り返して砂の層を順次積層していくように
することがより好ましい。なお、この際漏らし吹
きをしない隙間については隣接パイプのフランジ
を密接してボルト締めを行なえば良い。
When sand is leaked and blown from such sand discharge pipes 5, 5..., 5a, 5a... and 5b, 5b..., sand may be scattered in the same manner as above throughout the area between the pipes 4 shown in Fig. 3. However, if you do this, the sand scattered from adjacent gaps may overlap and a large amount of sand may fall on top of the soft mud layer at once, and in this case, the relatively light soft mud may fall onto the upper layer due to the impact of the sand. As the sand gets wet, spray every other gap, and when the sand has completed one cycle, spray again in the opposite direction to the previous one. It is more preferable to do so. At this time, in the gaps where no leakage occurs, the flanges of adjacent pipes may be brought into close contact with each other and bolted.

上記のようにして砂を軟泥層にまき散らすと、
砂の粒子はばらばらに軟泥層に落下するので、軟
泥を舞い上げることもなく、しかも砂は軟泥より
比重が大きいので、軟泥の土塊の間及び軟泥の中
に入り込み、その分だけ水を追い出し、この追い
出された水は砂の隙間を毛細管現象により上昇し
て除かれる。このようにして軟泥の構造を密にす
るとともに、砂が粘着質の軟泥成分により結合さ
れて軟泥層はより強固になる。
When sand is sprinkled on the soft mud layer as described above,
Since the sand particles fall into the soft mud layer in pieces, they do not kick up the soft mud, and since sand has a higher specific gravity than the soft mud, they penetrate between the lumps of soft mud and into the soft mud, displacing that much water. This expelled water rises through the gaps in the sand by capillary action and is removed. In this way, the structure of the soft mud becomes denser, and the sand is bound together by the sticky soft mud component, making the soft mud layer stronger.

次に第5図及び第6図に示す他の実施例を説明
する。
Next, another embodiment shown in FIGS. 5 and 6 will be described.

第5図は配管5′の設置状態を示すものであつ
て、埋立区域が碁盤目状の配管5′により小区域
に区分され、それぞれの区分毎に砂の吹き出しが
行なわれる。それぞれの区分の配管は相対する辺
の間隔が例えば50〜150m以内に設けられている。
このような配管状態で、第3図に示すように砂を
多点で吹き出すと、第6図に示すように大きな砂
の粒子は沈降速度が早いため吹き出し地点に近い
方にたまり易く、このため、傾斜ができて沈降速
度の遅い砂は遠くの方にたまるようになる。そし
て砂の吹き出しが継続されるにつれて砂の堆積層
の先端は遠くの方に延び、配管の相対する辺の吹
き出し点から吹き出された砂の堆積層先端は互い
に接近して倒立した偏平四角錐状の凹部を形成す
る堆積層ができあがる。そしてこの堆積層の凹部
を周囲の砂でならして造成地ができあがる。な
お、5′aは受枠である。
FIG. 5 shows the installation state of the pipes 5', in which the reclaimed area is divided into small areas by the grid-shaped pipes 5', and sand is blown out for each section. The piping of each section is provided with an interval of 50 to 150 m between opposing sides, for example.
With this kind of piping, if sand is blown out at multiple points as shown in Figure 3, large sand particles tend to accumulate closer to the point where they are blown out due to their faster settling speed, as shown in Figure 6. , the sand that settles slowly due to the slope will accumulate in the far direction. As the sand continues to be blown out, the tips of the sand piles extend farther away, and the tips of the sand piles blown out from the blowout points on opposite sides of the pipe approach each other in the shape of an inverted oblate square pyramid. A deposited layer is formed that forms the recesses. The depressions in this sedimentary layer are then smoothed out with the surrounding sand to create a developed area. Note that 5'a is a receiving frame.

このようにして埋立地盤を形成すると、配管の
節約ができるとともに、底の軟泥の圧密も行なわ
れる。この圧密の程度は、例えば軟泥層の上の砂
吹き出し地点における砂の堆積層が2.5mになつ
てその堆積層先端が25m遠くに延びているような
場合には、砂の吹き出し地点、中間及び先端での
軟泥は水分が固形分に対してそれぞれ50〜60%、
60〜80%、70〜90%になり、この軟泥がその敷き
詰められるま前に取り出された元の地山では水分
が固形分に対して100%であるのに比べて軟泥の
構造をより密にしている。
Forming the reclaimed ground in this way not only saves on piping, but also consolidates the soft mud at the bottom. For example, in the case where the sand deposit layer at the sand blowout point above the soft mud layer is 2.5 m long and the tip of the deposit layer extends 25 meters away, the degree of this consolidation is determined by The soft mud at the tip has a water content of 50 to 60% of the solid content, respectively.
60 to 80% and 70 to 90%, making the structure of the soft mud more dense compared to the original rock where the soft mud was taken out before it was laid down, where the water content was 100% relative to the solid content. I have to.

なお、第5図では碁盤目状に配管したが、第7
図、第8図、第9図に示すように、埋立区域の小
区分を、平行の配管5″、コの字状配管5、直
交する配管5′′′′により区分しても良い。
Note that although the piping is arranged in a grid pattern in Figure 5,
As shown in Figures 8 and 9, subdivisions of the reclaimed area may be divided by parallel pipes 5'', U-shaped pipes 5, and orthogonal pipes 5''''.

本発明によれば、軟泥をその構造が乱れないよ
うにして埋立区域に投入して軟泥層を形成し、さ
らにこの軟泥層の上に多点吹き出しにより砂の層
を形成したので、汚濁水の外界への流出がなく、
軟泥層の形成速度を大きくできるとともに、その
地盤の強度も大きくできる。これにより、埋め立
て作業の能率を向上し、工期の短縮をはかること
ができる。特に従来の浚渫による埋立地造成方法
に比べ、軟泥を沈降させる期間が不必要になるの
みならず、地盤を形成する軟泥層も元の地山の圧
密された構造がそのまま保持されているので従来
のような砂による圧密のための工期が短縮され、
軟泥層を形成した後は従来例えば6カ月要した砂
による圧密のための工期、すなわち地盤改良工期
を例えば1ケ月に短縮できる。この結果、従来の
方法における泥の沈降に要する工期の短縮とこの
砂による地盤改良工期の短縮分を合わせると従来
の方法による浚渫埋立地造成方法による工期が例
えば2年であるとすると、その約半分の13ケ月で
埋め立て地を造成できることになる。
According to the present invention, soft mud is poured into a landfill area without disturbing its structure to form a soft mud layer, and a layer of sand is further formed on top of this soft mud layer by multi-point blowing. There is no leakage to the outside world,
Not only can the formation speed of the soft mud layer be increased, but also the strength of the ground can be increased. This will improve the efficiency of the landfill work and shorten the construction period. In particular, compared to the conventional method of creating a reclaimed land by dredging, not only is there no need for a period for settling soft mud, but the soft mud layer that forms the ground retains the consolidated structure of the original ground, which was not the case. The construction period for consolidation with sand, such as
After the soft mud layer is formed, the period for consolidation with sand, that is, the period for ground improvement work, which conventionally required six months, can be shortened to, for example, one month. As a result, the reduction in the construction period required for mud settling in the conventional method and the reduction in the construction period for ground improvement using this sand means that if the construction period for the conventional method of creating a dredged and reclaimed land is, for example, two years, approximately This means that the landfill can be created in half the time, 13 months.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の方法の一実施例に使用する装
置の一部の説明図、第2図はその装置の他の一部
の説明図、第3図はさらに他の一部の説明図、第
4図は第3図に示す送砂管、排砂管の配置の具体
例を示す平面説明図、第5図は他の実施例におけ
る第4図に相当する図、第6図はこの実施例にお
ける地盤形成過程の第2図に相当する説明図、第
7図〜第9図はそれぞれさらに他の実施例におけ
る第4図に相当する図である。 図中、1はグラブ船、2は土運船、3はポンプ
船、5,5a,5b,5′,5″,5,5′′′′は
排砂管、aは軟泥、bは砂である。
FIG. 1 is an explanatory diagram of a part of the apparatus used in one embodiment of the method of the present invention, FIG. 2 is an explanatory diagram of another part of the apparatus, and FIG. 3 is an explanatory diagram of still another part. , FIG. 4 is an explanatory plan view showing a specific example of the arrangement of the sand feeding pipe and sand discharge pipe shown in FIG. 3, FIG. 5 is a diagram corresponding to FIG. 4 in another embodiment, and FIG. An explanatory diagram corresponding to FIG. 2 of the ground formation process in the embodiment, and FIGS. 7 to 9 are diagrams corresponding to FIG. 4 in other embodiments, respectively. In the figure, 1 is a grab ship, 2 is an earth carrier, 3 is a pump ship, 5, 5a, 5b, 5', 5'', 5, 5''''' is a sand pipe, a is soft mud, and b is sand. It is.

Claims (1)

【特許請求の範囲】 1 圧密されて水底の地盤を形成している軟泥を
土塊として乱さないように採取し、この土塊を乱
さないようにして土運船に積み込み、この積み込
んだ土塊を埋立て区域に静かに投入して均一厚さ
の軟泥層を形成し、この軟泥層の上方に多点で砂
を吹き出す多点砂吹き出し装置を設け、この多点
砂吹き出し装置により吹き出した砂を上記軟泥層
に堆積させて圧密し地盤を形成することを特徴と
する埋立地の造成方法。 2 多点砂吹き出し装置を離間した複数個所から
砂を吹き出す排砂管により構成し、この排砂管を
配管して埋立区域を小区域に区分し、かつこの配
管の間隔を相対する排砂管から砂を吹き出したと
きその砂の堆積層先端が重層又は接するように設
けたことを特徴とする特許請求の範囲第1項記載
の埋立地の造成方法。
[Claims] 1. Collecting the compacted soft mud that forms the ground at the bottom of the water as soil clods without disturbing them, loading the soil clods onto an earth transport ship without disturbing them, and reclamation of the loaded soil clods. A layer of soft mud with a uniform thickness is formed by gently pouring sand into the area, and a multi-point sand blowing device is installed above the soft mud layer to blow sand at multiple points. A method of creating a reclaimed land characterized by forming the ground by depositing layers and compacting them. 2. The multi-point sand blowing device is composed of sand discharge pipes that blow sand from multiple locations spaced apart, and the sand discharge pipes are piped to divide the reclaimed area into small areas, and the intervals between the pipes are set by the opposing sand discharge pipes. 2. The method of creating a reclaimed land according to claim 1, wherein the sand is provided so that when the sand is blown out, the tips of the sand piles overlap or are in contact with each other.
JP16479684A 1984-08-08 1984-08-08 Formation of reclamation site Granted JPS6145010A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16479684A JPS6145010A (en) 1984-08-08 1984-08-08 Formation of reclamation site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16479684A JPS6145010A (en) 1984-08-08 1984-08-08 Formation of reclamation site

Publications (2)

Publication Number Publication Date
JPS6145010A JPS6145010A (en) 1986-03-04
JPH0132329B2 true JPH0132329B2 (en) 1989-06-30

Family

ID=15800097

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16479684A Granted JPS6145010A (en) 1984-08-08 1984-08-08 Formation of reclamation site

Country Status (1)

Country Link
JP (1) JPS6145010A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6480603A (en) * 1987-09-18 1989-03-27 Nikko Kk Kneading method of mixer in asphalt plant
JP2796388B2 (en) * 1988-05-13 1998-09-10 アムジエン・インコーポレーテツド Method for purifying G-CSF
JPH02153102A (en) * 1988-12-02 1990-06-12 Maeda Road Constr Co Ltd Arrival and shipment control in plant for shipment of stored object
NL1012292C2 (en) * 1999-06-10 2000-12-12 Ballast Nedam Baggeren Bv Method of building up height of land in polder, uses off-shore sand-sucker vessel to pipe sand and silt from seabed into pans on shore

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4222612Y1 (en) * 1964-01-29 1967-12-22
JPS5629055A (en) * 1979-08-09 1981-03-23 Lucas Industries Ltd Reciprocating plunger type fuel injection pump

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4222612Y1 (en) * 1964-01-29 1967-12-22
JPS5629055A (en) * 1979-08-09 1981-03-23 Lucas Industries Ltd Reciprocating plunger type fuel injection pump

Also Published As

Publication number Publication date
JPS6145010A (en) 1986-03-04

Similar Documents

Publication Publication Date Title
US4352590A (en) Stabilization of erodible marine or fluviatile sediments
CN109914174B (en) Construction method for backfilling, stone throwing and silt squeezing of pond
Gowan et al. Co-disposal techniques that may mitigate risks associated with storage and management of potentially acid generating wastes
JPH0132329B2 (en)
RU2513816C1 (en) Method to form anthropogenic field
Burt Guidelines for the beneficial use of dredged material
JPWO2014141679A1 (en) Seawalls and methods for reinforcing or constructing seawalls
CN100582382C (en) Process for constructing quickly consolidated temperory horizontal platform by picking clay of lake bottom
US4072016A (en) Method of reconstructing and reclamation of river channels
Partridge The significance of origin for the identification of engineering problems in transported Quaternary soils
Lam Land reclamation & soil improvement using dredged slurry as fill
EP0960660B1 (en) Process for filling a disposal site for silt supplied with a high water content and device for applying drainage wicks
CN214091219U (en) Large-scale grit aggregate processing system production waste residue safety protection structure
Kog Rehabilitation of abandoned non-hazardous tailings ponds
Roy Site Development
Robertson et al. The influence of depositional methods on the engineering properties of tailings deposits
Marlin Potential use of innovative dredge technology and beneficial use of sediment for river restoration
SU1263850A1 (en) Method of dumping stripped rock
Shields et al. Controlling sand placement during the building of artificial islands
JP2024016777A (en) Large amount of earth and sand reduction method, semi-buried dam, earth and sand spreading method, earth and sand spreading auxiliary method, turbidity reduction method, and soft river bed improvement method
CN112459552A (en) Production waste residue protection structure of large sand aggregate processing system and construction method
JPS6290409A (en) Reclamation work
SU1716131A1 (en) Method for piling potassium ore tailings
Bartos Containment area management to promote natural dewatering of fine-grained dredged material
JPH0988066A (en) Underwater filling method of light weight premixed soil

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees