JPS6131594A - Bypass tunnel construction method - Google Patents

Bypass tunnel construction method

Info

Publication number
JPS6131594A
JPS6131594A JP15266584A JP15266584A JPS6131594A JP S6131594 A JPS6131594 A JP S6131594A JP 15266584 A JP15266584 A JP 15266584A JP 15266584 A JP15266584 A JP 15266584A JP S6131594 A JPS6131594 A JP S6131594A
Authority
JP
Japan
Prior art keywords
tunnel
main
sectional area
cross
bypass
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15266584A
Other languages
Japanese (ja)
Other versions
JPH0468440B2 (en
Inventor
貝沼 憲男
隆三郎 大塚
実 片山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc, IHI Corp filed Critical Tokyo Electric Power Co Inc
Priority to JP15266584A priority Critical patent/JPS6131594A/en
Publication of JPS6131594A publication Critical patent/JPS6131594A/en
Publication of JPH0468440B2 publication Critical patent/JPH0468440B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、バイパストンネル工法に係り、特に、既存の
本トンネルの所定箇所の必要断面積を広くとりたい場合
に、立坑を掘削することなく必要断面積を確保すること
ができ、工事費の削減化、工期の短縮化を達成すること
ができるばいばすトンネル工法に関する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a bypass tunnel construction method, and in particular, when it is desired to widen the required cross-sectional area of a predetermined part of an existing main tunnel, it is possible to construct a bypass tunnel without excavating a vertical shaft. This invention relates to a bypass tunnel construction method that can secure the necessary cross-sectional area, reduce construction costs, and shorten the construction period.

[従来の技術J 一般に、電力或いは通信ケーブルを布設したり或いは上
下水等を流通させる地下トンネルにおいては、必要に応
じてその所定の箇所の必要断面積を周囲よりも広く採る
必要が生ずる。。例えば電力、通信ケーブルを布設する
地下トンネルにあっては、必然的にケーブルのジヨイン
ト部が生ずることからこれを収容するためにこの部分の
トンネル断面積を周囲よりも大きく形成しなければなら
ない。
[Prior Art J] In general, in underground tunnels in which power or communication cables are laid or water and sewage are distributed, it is necessary to make the required cross-sectional area of a predetermined part larger than that of the surrounding area, as necessary. . For example, in underground tunnels in which power and communication cables are laid, cable joints inevitably occur, and in order to accommodate these joints, the cross-sectional area of the tunnel must be made larger than the surrounding area.

この場合、トンネル内部から拡幅工事を行なうことも考
えられるがトンネル内壁を支持するセグメントには比較
的高い土圧などが付加されているのでセグメントをトン
ネル内から取り外すことは困難である。
In this case, it is possible to carry out widening work from inside the tunnel, but since relatively high earth pressure is applied to the segments that support the tunnel inner wall, it is difficult to remove the segments from inside the tunnel.

そこで、従来にあっては、地上からトンネルの所定の箇
所に向けて立坑を掘削し、拡幅工事などを行なっていた
Therefore, in the past, a vertical shaft was excavated from the ground to a predetermined point in the tunnel, and work such as widening the tunnel was carried out.

[発明が解決しようとする問題点] しかしながら、従来工法に−あっては、必ず立坑を必要
とすることから、これを掘削するための費用が嵩むばか
りか工期も長期化する傾向にあった。
[Problems to be Solved by the Invention] However, conventional construction methods always require a vertical shaft, which not only increases the cost of excavating the shaft but also tends to lengthen the construction period.

特に、トンネルがより深い地中に掘削される傾向にある
今日にあっては、上記問題点が助長される傾向にある。
In particular, as tunnels tend to be dug deeper underground, the above problems tend to be exacerbated.

また、拡幅工事に先立ってその部分の広範囲の地盤に多
量の薬剤を注入し、破砕防止のための地盤改良を施さね
ばならず、この点からしても上記問題点を助長していた
Additionally, prior to widening work, a large amount of chemicals had to be injected into a wide area of the ground to improve the ground to prevent crushing, which also exacerbated the above problems.

更に、立坑の設置位置は地上条件に左右されることから
、家屋密集地においては立坑用地の確保が非常に困難に
なっていた。
Furthermore, since the installation location of the shaft depends on ground conditions, it has become extremely difficult to secure land for the shaft in areas with a large number of houses.

[発明の目的] 本発明は以上のような問題点に着目し、これを有効に解
決すべく創案されたものである。
[Object of the Invention] The present invention has focused on the above-mentioned problems and has been devised to effectively solve the problems.

本発明の目的は、既存本トンネルの所定箇所の必要断面
積を広くとりたい場合に、立坑を掘削することなくバイ
パストンネルを形成して、これらの断面積の総和が必要
断面積以上となるようにし、もって工事費の削減化、工
期の短縮化を達成することができるバイパストンネル工
法を提供するにある。
The purpose of the present invention is to form a bypass tunnel without excavating a shaft when it is desired to increase the required cross-sectional area of a predetermined part of an existing main tunnel so that the sum of these cross-sectional areas becomes greater than or equal to the required cross-sectional area. The object of the present invention is to provide a bypass tunnel construction method that can reduce construction costs and shorten the construction period.

[発明の概要] 本発明は、本トンネルの必要断面積を確保するには本ト
ンネルの所定箇所の上流側と下流側とを所定の断面積の
バイパストンネルで連通ずればよいという知見を得るこ
とによりなされたもので、上記目的に沿う本発明の構成
は、本トンネル内の断面積の増加が必要とされる所定の
箇所を迂回して、上記所定の箇所の上流側と下流側との
間を、その径が上記本トンネルの内径よりも小径のシー
ルド掘進機により掘削して所定の断面積のバイパストン
ネルを形成し、このバイパストンネルの断面積と本トン
ネルの断面積との総和が必要断面積以上となるようにし
たことを要旨とする。
[Summary of the invention] The present invention is based on the knowledge that in order to secure the necessary cross-sectional area of the main tunnel, it is sufficient to connect the upstream and downstream sides of a predetermined part of the main tunnel with a bypass tunnel having a predetermined cross-sectional area. The configuration of the present invention that meets the above objective is to bypass a predetermined location in the main tunnel where it is necessary to increase the cross-sectional area, and to create a bridge between the upstream side and the downstream side of the predetermined location. is excavated by a shield excavator whose diameter is smaller than the inner diameter of the main tunnel to form a bypass tunnel with a predetermined cross-sectional area, and the sum of the cross-sectional area of this bypass tunnel and the cross-sectional area of the main tunnel is the required cross-sectional area. The gist is that the area is greater than or equal to the area.

[実施例] 以下に、本発明方法の好適一実施例を添付図面に基づい
て詳述する。
[Example] A preferred example of the method of the present invention will be described in detail below with reference to the accompanying drawings.

第1図乃至第8図は本発明方法を説明するための工程図
、第9図及び第10図は本発明方法を実施するためのシ
ールド掘進機を示す図、第11図及び第12図は本発明
方法を実施するための元押し装置を示す図、第13図及
び第14図は本発明方法を実施するための中押し装置を
示す図である。
Figures 1 to 8 are process diagrams for explaining the method of the present invention, Figures 9 and 10 are diagrams showing a shield tunneling machine for carrying out the method of the present invention, and Figures 11 and 12 are FIGS. 13 and 14 are diagrams showing a main pushing device for implementing the method of the present invention, and FIGS. 13 and 14 are diagrams showing a middle pushing device for implementing the method of the present invention.

まず、本発明の使用装置について説明する。本発明にあ
っては、既に掘削の完了した本トンネル内を発進基地と
してその側壁を貫通するが如くシールド掘進機により掘
削するので、これをトンネル内に収容可能にすべく第9
図に示すシールド掘進機1の径(約1メートル)は本ト
ンネルの内径(数メートル)よりも小径に形成されてい
る。このシールド掘進機1としては従来公知のものが使
用され、円筒状のシールドフレーム2の先端に回転自在
にシールド面板3を取付けると共に、この回転軸4には
モータのごとき駆動源5が連結されている。カッタ面板
3の後方に形成されるカッタ室6に掘削土を排出するズ
リ排出管7,7が接続されている。
First, the apparatus used in the present invention will be explained. In the present invention, since the inside of the main tunnel, which has already been excavated, is used as a starting base, the shield excavator excavates so as to penetrate the side wall of the main tunnel, so in order to be able to accommodate this inside the tunnel, the ninth
The diameter of the shield tunneling machine 1 shown in the figure (approximately 1 meter) is smaller than the inner diameter (several meters) of the main tunnel. A conventionally known shield tunneling machine 1 is used as the shield tunneling machine 1. A shield face plate 3 is rotatably attached to the tip of a cylindrical shield frame 2, and a drive source 5 such as a motor is connected to the rotating shaft 4. There is. A cutter chamber 6 formed at the rear of the cutter face plate 3 is connected to waste discharge pipes 7, 7 for discharging excavated soil.

シールドフレーム2は前側シールドフレーム2aと後側
シールドフレーム2bとに前後に2分割され、これらは
図示しない自在継手よりなる中折れ機構を有し、適宜角
度だけ屈曲自在に構成されており、曲線状トンネルの掘
削を可能にしている。図示例にあっては前側シールドフ
レーム2aが角度αだけ屈曲している状態を示す。前側
シールドフレーム2aの屈曲角調整は、このフレーム2
aと後側カッタフレーム2bとの間に連結され、その周
方向に沿って4基配設された油圧ジヤツキ8・・・のス
トローク差によって行なう。
The shield frame 2 is divided into a front shield frame 2a and a rear shield frame 2b, which have a center bending mechanism consisting of a universal joint (not shown), and are configured to be bent at an appropriate angle, and have a curved shape. It makes it possible to excavate tunnels. In the illustrated example, the front shield frame 2a is shown bent by an angle α. The bending angle of the front shield frame 2a can be adjusted using this frame 2.
This is done by adjusting the strokes of four hydraulic jacks 8 connected between the rear cutter frame 2b and the rear cutter frame 2b and arranged along the circumferential direction thereof.

尚、このシールド掘進機1の掘進は前記元押し装置及び
中押し装置により行なう。
Incidentally, the shield tunneling machine 1 excavates by using the main push device and the intermediate push device.

第11図及び第12Kに示す元押し装置9は本トンネル
内に固定れて後述する推進管や前記シールド掘進機1等
押し進めるものであり、第11図及び第12図に示す如
く本トンネル内に固定されることになる元押し基台10
ど、所定長だけ布設されたレール11上を移動する断面
り字状の元押し台車12とにより主に構成されており、
この元押し台車12は元押し基台1oに固定された計4
基の元押し油圧ジヤツキ13・・・の各ロッド14・・
・の先端に取付けられてロッド14・・・の出没により
元押し台車12を前後方向に移動するようになっている
。尚、この台車12上に仮想線に示す推進管15を搭載
することになる。
The main pushing device 9 shown in FIGS. 11 and 12K is fixed inside the main tunnel and pushes forward the propulsion pipe and the shield excavator 1, which will be described later. The original push base 10 to be fixed
It is mainly composed of a main push cart 12 with an orthogonal cross-section that moves on a rail 11 laid a predetermined length,
There are a total of 4 main push carts 12 fixed to the main push base 1o.
Each rod 14 of the base hydraulic jack 13...
The main push cart 12 is moved in the front and back direction by the rods 14, which are attached to the tips of the rods 14 and retract. Incidentally, a propulsion tube 15 shown by a phantom line will be mounted on this truck 12.

第13図及び第14図に示す中押し装置16はシールド
掘進機1の直後に設置され、シールド掘進機1に直接接
してこれを推進させるものであり、円筒状の中押し基台
17と、これに固定された計4基の中押し油圧シリンダ
18・・・の各ロッド19・・・の先端に取付けられた
円板状の押し台2oとにより主に構成され、この押し台
2oを前後移動させることによりシールド掘進機1の後
端を押すようになっている。
The intermediate push device 16 shown in FIGS. 13 and 14 is installed immediately after the shield excavator 1, and is in direct contact with the shield excavator 1 to propel it, and includes a cylindrical intermediate push base 17 and a It is mainly composed of a disk-shaped push stand 2o attached to the tip of each rod 19 of a total of four fixed intermediate push hydraulic cylinders 18..., and this push stand 2o can be moved back and forth. This pushes the rear end of the shield tunneling machine 1.

前記装置を用いて第1図乃至第8図を参照しつつ本発明
方法を具体的に説明する。
The method of the present invention will be specifically explained using the above-mentioned apparatus with reference to FIGS. 1 to 8.

第1図は既にシールド掘削された本トンネルを示し、第
2図は第1図中■−■線矢視断面図を示す。この本トン
ネル21内に例えば通信、電力ケーブル等が布設される
ことになり、これらのジヨイント部が位置するトンネル
内の所定の箇所P(図示例にあってはトンネルの長手方
向中央部)においてその必要断面積が周囲に比較して大
きくなる。この部分すなわち所定の箇所Pは本トンネル
の設計段階において予め決定されているので、この部分
を中心として上流側と下流側とをバイパストンネル22
.23で接続することになる。尚、図示例にあっては左
側を上流側とし右側を下流側とする。また、図示例にあ
っては、2本のバイパストンネル22.23を形成する
ことになっているが、これらの本数は限定されず、これ
ら各バイパストンネルの断面積と本トンネルの断面積と
の総和が必要断面積以上となるように本数を設定する。
Figure 1 shows the main tunnel that has already been shield-excavated, and Figure 2 shows a sectional view taken along the line ■--■ in Figure 1. For example, communication cables, power cables, etc. will be laid inside this main tunnel 21, and these cables will be laid at a predetermined point P in the tunnel where their joints are located (in the illustrated example, the central part in the longitudinal direction of the tunnel). The required cross-sectional area becomes larger compared to the surrounding area. Since this part, that is, the predetermined point P, is determined in advance at the design stage of the main tunnel, the bypass tunnel 22 is connected to the upstream and downstream sides around this part.
.. It will be connected at 23. In the illustrated example, the left side is the upstream side and the right side is the downstream side. Further, in the illustrated example, two bypass tunnels 22 and 23 are formed, but the number is not limited, and the cross-sectional area of each bypass tunnel and the cross-sectional area of the main tunnel are Set the number so that the total sum is greater than or equal to the required cross-sectional area.

従ってバイパストンネル1本の断面積が大きくなれば、
その分バイパストンネルの本数が減少することになる。
Therefore, if the cross-sectional area of one bypass tunnel increases,
The number of bypass tunnels will be reduced accordingly.

バイパストンネル22,2ゴの結合部となるシールド掘
進機の発進基地24及び到達基地25を画する区画壁は
この取り外しを容易にするため予めスチールセグメント
26.27により構成しておき、他の部分は安価なコン
クリートセグメント28により構成しておく。尚、発進
基地24と到達基地25は本トンネルの上下流制逆にし
てもよい。
In order to facilitate this removal, the partition wall that separates the starting base 24 and arrival base 25 of the shield excavator, which are the joining parts of the bypass tunnels 22 and 2, is made of steel segments 26 and 27 in advance, and the other parts are is made up of inexpensive concrete segments 28. Note that the starting base 24 and the destination base 25 may be reversed upstream and downstream of the main tunnel.

まず、バイパストンネル22の結合部となるべき部分す
なわちスチールセグメント26..27の外周全体に予
め薬剤注入をして第2図に示す如く地盤改良部29.3
0を形成し、掘進時のくずれを防止する。特に、到達基
地側の地盤改良部3゜を肉厚にして掘削誤差に対応でき
るようにする。
First, the portion that is to become the joining part of the bypass tunnel 22, that is, the steel segment 26. .. A chemical is injected into the entire outer circumference of the ground improvement section 29.3 in advance as shown in Fig. 2.
0 to prevent collapse during excavation. In particular, the ground improvement portion 3° on the reaching base side is made thicker to accommodate excavation errors.

次に発進基地24側のスチールセグメント26の内バイ
パストンネルの開口部となる部分を切断除去して地盤改
良部29をトンネル内に露出させると共に、第3図に示
す如く、この露出部分に、その開口端31aを本トンネ
ル21側に臨ませて、掘削初期のシールド掘進機の案内
を行なうスチール製のサヤ管31を本トンネルの長手方
向に対して所定の角度でもってスチールセグメント26
の開口円周端部に溶接接続する。尚、開口端31aには
盲板32が取付けられ、これを閉塞している。
Next, the part of the steel segment 26 on the side of the starting base 24 that will become the opening of the bypass tunnel is cut and removed to expose the ground improvement part 29 inside the tunnel, and as shown in FIG. With the open end 31a facing the main tunnel 21 side, the steel sheath pipe 31 that guides the shield tunneling machine during the initial stage of excavation is held at a predetermined angle with respect to the longitudinal direction of the main tunnel, and the steel segment 26 is
Weld connection to the circumferential edge of the opening. Note that a blind plate 32 is attached to the open end 31a to close it off.

サヤ管31の内径はバイパストンネル用シールド掘進機
1を収容する必要からその外径よりも若干大きく形成さ
れている。この場合、サヤ管31の開口端31aの近傍
にシールド掘進機が設置できるように本トンネルに対す
るサヤ管31の角度を決定する。次に、第4図に示すよ
うにサヤ管31の開口端31aに取付けた盲板32に臨
ませてシールド掘進ta1及び元押、し装置9の順序で
セットする。この場合シールド掘進機1を元押し台車1
2上に載置して、この台車上幅方向に取付けた1対の支
持片33により掘進機1の転がりを防止する(第11図
参照)。そして、元押し装置9の基端部に接してシール
ド掘進機推進時の反力を受けるための反力壁34をコン
クリート等により強固に構築する。
The inner diameter of the sheath pipe 31 is slightly larger than its outer diameter because it is necessary to accommodate the bypass tunnel shield excavator 1. In this case, the angle of the sheath pipe 31 with respect to the main tunnel is determined so that the shield excavator can be installed near the open end 31a of the sheath pipe 31. Next, as shown in FIG. 4, the shield digging ta1 and the pushing device 9 are set in this order so as to face the blind plate 32 attached to the open end 31a of the sheath tube 31. In this case, the shield excavator 1 is
2, and a pair of support pieces 33 attached in the upper width direction of this truck prevent the excavator 1 from rolling (see FIG. 11). Then, a reaction wall 34 is strongly constructed of concrete or the like in contact with the base end of the main pushing device 9 to receive the reaction force when the shield tunneling machine is propelled.

次に、サヤ管31の開口端31aを閉塞する盲板32を
取外すと共に、第5図に示す如く元押し油圧ジヤツキ1
3を適宜ストロークだけ伸長させてシールド掘進機1の
先端部をサヤ管31内へ挿入し、再度開口端31aを閉
塞する。そして、サヤ管31とシールド掘進機1との間
に形成されたクリアランス部へ樹脂或いは貧配分コンク
リートよりなる充填材35を注入し、この部分を所定の
硬度に固める。後述する如く、これを掘進していくこと
により、シールド掘進機に無理な片側応力が付加される
ことなく円滑に地盤側に掘り進むことが可能となる。従
って、上記充填材35の強度は地盤G或いは地盤改良部
29の強度とほぼ同程度にすることが望ましい。
Next, the blind plate 32 that closes the open end 31a of the sheath pipe 31 is removed, and the main push hydraulic jack 1 is removed as shown in FIG.
3 by an appropriate stroke, the tip of the shield tunneling machine 1 is inserted into the sheath tube 31, and the open end 31a is closed again. Then, a filler material 35 made of resin or poorly distributed concrete is injected into the clearance part formed between the sheath pipe 31 and the shield excavator 1, and this part is hardened to a predetermined hardness. As will be described later, by digging this, it becomes possible to smoothly dig toward the ground side without applying unreasonable unilateral stress to the shield excavator. Therefore, it is desirable that the strength of the filler 35 be approximately the same as the strength of the ground G or the ground improvement portion 29.

次に、元押し油圧ジヤツキ13を伸長しつつシールド掘
進機1を駆゛動させて掘削を開始すると共に、元押し油
圧シリンダ13を伸長させて充填材35中を掘進してゆ
く。元押し油圧ジヤツキ13の全ストローク分掘進した
ならば第6図に示す如く元押し油圧ジヤツキ13を縮退
させてこれをリセットし、次に、この元押し台車12上
に中押し装置16を載置して再度元押し油圧ジヤツキ1
3を伸長させて掘進を開始する。そして、元押し油圧ジ
ヤツキ13が全ストローク伸長したならば、再度これを
リセットし、今麿は元押し台車12上に環状の推進管1
5をセットする。そして、以後の掘進は元押し油圧ジヤ
ツキ13の全ストローク伸長、リセットを繰り返しなが
ら第7図に示す如(、順次推進管15・・・を連続的に
接続して行くことにより行なう。シールド掘進l!1と
中押し装置16は連続して進行して行き、中押し油圧ジ
ヤツキ18を適宜伸長することによりこの押し台20に
接する掘進機1を前進させて先行掘削を行なうと共に、
元押し装置9により元押しを行なうことにより連結され
た推進管15・・・全体を順次正大して行く。これによ
り、掘進Ia1は地盤改良部29を貫通して地盤G中に
掘り進んでゆく。
Next, the shield excavator 1 is driven while extending the main push hydraulic jack 13 to start excavation, and at the same time, the main push hydraulic cylinder 13 is extended to dig into the filling material 35. After digging the entire stroke of the main push hydraulic jack 13, the main push hydraulic jack 13 is retracted and reset as shown in FIG. 6, and then the intermediate push device 16 is placed on this main push cart 12. Then press the hydraulic jack 1 again.
Extend 3 and start digging. Then, when the main push hydraulic jack 13 has extended its full stroke, it is reset again and the annular propulsion pipe 1 is placed on the main push truck 12.
Set 5. Then, subsequent excavation is carried out by repeatedly extending the full stroke of the main push hydraulic jack 13 and resetting it, as shown in FIG. !1 and the intermediate push device 16 advance continuously, and by appropriately extending the intermediate push hydraulic jack 18, the excavator 1 in contact with the push platform 20 is advanced to perform advance excavation.
The entire connected propulsion tubes 15 are sequentially enlarged by pushing with the pushing device 9. As a result, the excavation Ia1 penetrates the ground improvement portion 29 and digs into the ground G.

掘進方向の設定は、掘進機1の油圧ジヤツキ8にストロ
ーク差を設けることにより前側シールドフレーム2aの
屈曲角度を変化させて所望する方向に掘進する(第9図
参照ン。また、掘進方向の修正は、中押し装置16の中
押し油圧ジヤツキ18・・・にストローク差を設けるこ
とにより行なわれ、これらの組み合せで所望の推進方向
に確実に進めて行く。
The digging direction is set by providing a stroke difference in the hydraulic jack 8 of the excavation machine 1 to change the bending angle of the front shield frame 2a and digging in the desired direction (see Fig. 9). This is done by providing a stroke difference between the intermediate push hydraulic jacks 18 of the intermediate push device 16, and the combination of these makes it possible to reliably advance in the desired direction of propulsion.

一方、このようにして、一連の掘進作業が行なわれてい
る間に、到達基地25においては、前記発進基地24に
設けたと同様にして到達用サヤ管36が取付けられ(第
8図参照)、この中に充填材を装填して掘進機の到達を
持っている。そして、必要距離だけ掘削した掘進I11
はその掘進方向を徐々に変えつつ到達用サヤ管36内に
まで掘り進み、最終的にその開口端31aから掘進機1
の先端を霧出してバイパストンネル22の掘削を完了す
る。
On the other hand, while a series of excavation operations are being carried out in this manner, the reaching sheath pipe 36 is installed at the reaching base 25 in the same manner as that installed at the starting base 24 (see FIG. 8). Load the filler into this and have the excavator reach it. Then, excavation I11 was carried out by excavating the required distance.
The excavator 1 excavates into the reaching sheath pipe 36 while gradually changing its excavation direction, and finally excavates the excavator 1 from its open end 31a.
The tip of the bypass tunnel 22 is sprayed out to complete the excavation of the bypass tunnel 22.

バイパストンネル22が複数必要ならば、前記と同様な
操作を順次繰り返して複数のトンネルを掘削する。第1
5図は以上のような方法により、本トンネル21に沿っ
て複数のバイパストンネル22・・・を形成した状態を
示す斜視図である。このようにして、本トンネル21と
バイパストンネル22との断面積の総和により必要断面
積以上を確保し、本トンネル21内の所定の箇所Pで或
いは、これに並設したバイパストンネル22.23内で
ケーブル等のジヨイントを行なうことになる。
If a plurality of bypass tunnels 22 are required, the same operations as described above are sequentially repeated to excavate the plurality of tunnels. 1st
FIG. 5 is a perspective view showing a state in which a plurality of bypass tunnels 22 are formed along the main tunnel 21 by the method described above. In this way, the sum of the cross-sectional areas of the main tunnel 21 and the bypass tunnel 22 is larger than the required cross-sectional area, and a predetermined point P in the main tunnel 21 or in the bypass tunnel 22 or 23 installed in parallel thereto is secured. You will need to joint the cables etc.

一方、再度本トンネル内に回収されたシールド掘進m’
+及び中押し装置16は分解されて、再度利用されるこ
とになる。
On the other hand, the shield excavation m' recovered in the main tunnel again
+ and the middle push device 16 will be disassembled and used again.

尚、上記実施例にあっては、掘進ta1の発進基地24
と到達基地25にそれぞれサヤ管を溶接接続して設けた
が、これに限定されず、例えばヒユーム管などを押管工
法により取付けるようにしてもよい。
In the above embodiment, the starting base 24 of the excavation ta1
Although sheath pipes are welded to and connected to the reach base 25, the present invention is not limited to this, and for example, a Huyume pipe or the like may be attached using the push pipe construction method.

また、上記実施例は元押し装置により全体を押し込むい
わゆる押管工法であるが、トンネル系が大きい場合には
バイパストンネル構築方法を従来のセグメントを組みな
がら推進するシールド機械による方法も可能である。
Furthermore, although the above embodiment is a so-called push pipe construction method in which the entire tunnel is pushed in using a pusher, if the tunnel system is large, a bypass tunnel construction method using a conventional shield machine that advances the tunnel while assembling segments is also possible.

[発明の効果コ 以上要するに本発明方法は、すでに形成された本トンネ
ル内の所定の箇所に、その必要断面積を確保する際に、
その上流側と下流側とを結んでシールド掘進機でもって
バイパストンネルを形成することによりこの断面積と本
トンネルとの断面積との総和が上記必要断面積以上とな
るようにしたので、従来必要とされた立坑を不要にでき
、工期の短縮化及び工事費の削減化を達成できるばかり
でなく、バイパストンネルの掘削場所が地上の条件に左
右されないので設計の自由度を増すことができるという
優れた作用効果を発揮することができる。
[Effects of the Invention] In short, the method of the present invention has the following advantages when securing the necessary cross-sectional area at a predetermined location within the main tunnel that has already been formed.
By connecting the upstream side and the downstream side and forming a bypass tunnel using a shield tunneling machine, the sum of the cross-sectional area of this tunnel and the cross-sectional area of the main tunnel is greater than the required cross-sectional area, so it is possible to This technology not only eliminates the need for vertical shafts, shortens the construction period and reduces construction costs, but also increases the degree of freedom in design because the bypass tunnel excavation location is not affected by ground conditions. It is possible to exhibit the following effects.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第8図は本発明方法を示す工程図であり、第
1図は本トンネルを示す縦断面図、第2図は第1図中■
−■線矢視断面図、第3図は地盤改良部にサヤ管を取付
けた状態を示す平面図、第4図はサヤ管にシールド掘進
機をセットした状態を示す平面図、第5図はサヤ管内に
充填材を装填した状態を示す平面図、第6図はシールド
掘進機と元押し装置との間に中押し装置を取付ける状態
を示す平面図、第7図はバイパストンネル掘削中のシー
ルド掘進機を示す平面図、第8図はシールド掘進機が到
達基地に到達した状態を示す平面図、第9図はシールド
掘進機を示す縦断面図、第10図は同部分断面平面図、
第11図は元押し装置を示す側面図、第12図は同部分
断面平面図、第13図は中押し装置を示す側断面図、第
14図は同部分断面平面図、第15図は多数のバイパス
トンネルが形成された本トンネルを示す斜視図である。 尚、1はシールド掘進機、9は元押し装置、1・6は中
押し装置、21は本トンネル、22.23はバイパスト
ンネル、24゛は発進基地、25は到達基地、31はサ
ヤ管、Pは所定の箇所である。 特許出願人  東 京 電 力 株式会社石川島播磨重
工業株式会社 代理人弁理士 絹  谷  信  雄 第1図 第7図 第8図 第1ON 第11図        第12図 第13図          第14図第15図
Figures 1 to 8 are process diagrams showing the method of the present invention, Figure 1 is a longitudinal cross-sectional view showing the main tunnel, and Figure 2 is a
3 is a plan view showing the condition where the pod pipe is attached to the ground improvement section, 4 is a plan view showing the state where the shield excavator is set on the pod tube, and 5 is the sectional view taken along the -■ line. A plan view showing the state in which filler is loaded into the sheath pipe, Fig. 6 is a plan view showing the state in which the intermediate push device is installed between the shield excavator and the main push device, and Fig. 7 shows the shield excavation during bypass tunnel excavation. 8 is a plan view showing the state in which the shield tunneling machine has reached the destination base; FIG. 9 is a vertical sectional view showing the shield tunneling machine; FIG. 10 is a partial sectional plan view of the same;
Fig. 11 is a side view showing the main pushing device, Fig. 12 is a partial sectional plan view of the same, Fig. 13 is a side sectional view showing the intermediate pushing device, Fig. 14 is a partial sectional plan view of the same, and Fig. 15 is a partial sectional plan view of the main pushing device. FIG. 2 is a perspective view showing a main tunnel in which a bypass tunnel is formed. In addition, 1 is the shield excavator, 9 is the main push device, 1 and 6 are the middle push devices, 21 is the main tunnel, 22.23 is the bypass tunnel, 24゛ is the starting base, 25 is the destination base, 31 is the sheath pipe, P is a predetermined location. Patent applicant Tokyo Electric Power Company Ishikawajima-Harima Heavy Industries Co., Ltd. Agent Nobuo Kinutani Figure 1 Figure 7 Figure 8 Figure 1 ON Figure 11 Figure 12 Figure 13 Figure 14 Figure 15

Claims (1)

【特許請求の範囲】[Claims] 電力ケーブル等の布設されル本トンネル内の所定の箇所
に、上記ケーブルのジョイント部等を収容するためにそ
の必要断面積を確保するに際し、上記本トンネル内の所
定の箇所を迂回して、上記所定の箇所の上流側と下流側
との間を、その径が上記本トンネルの内径よりも小径の
シールド掘進機により掘削してバイパストンネルを形成
し、上記本トンネルの断面積と、上記バイパストンネル
の断面積との総和が上記必要断面積以上となるようにし
たことを特徴とするバイパストンネル工法。
When securing the necessary cross-sectional area to accommodate the joints, etc. of the cables at predetermined locations within the main tunnel where power cables, etc. are laid, the above-mentioned A bypass tunnel is formed by excavating between the upstream side and the downstream side of a predetermined location using a shield excavator whose diameter is smaller than the inner diameter of the main tunnel, and the cross-sectional area of the main tunnel and the bypass tunnel are A bypass tunnel construction method characterized in that the total sum with the cross-sectional area of is equal to or larger than the above-mentioned required cross-sectional area.
JP15266584A 1984-07-23 1984-07-23 Bypass tunnel construction method Granted JPS6131594A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15266584A JPS6131594A (en) 1984-07-23 1984-07-23 Bypass tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15266584A JPS6131594A (en) 1984-07-23 1984-07-23 Bypass tunnel construction method

Publications (2)

Publication Number Publication Date
JPS6131594A true JPS6131594A (en) 1986-02-14
JPH0468440B2 JPH0468440B2 (en) 1992-11-02

Family

ID=15545409

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15266584A Granted JPS6131594A (en) 1984-07-23 1984-07-23 Bypass tunnel construction method

Country Status (1)

Country Link
JP (1) JPS6131594A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291316A (en) * 2013-06-14 2013-09-11 中国水电顾问集团成都勘测设计研究院 Large-scale underground cavern group arrangement design method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59495A (en) * 1982-06-24 1984-01-05 日立建機株式会社 Shield drilling machine

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59495A (en) * 1982-06-24 1984-01-05 日立建機株式会社 Shield drilling machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291316A (en) * 2013-06-14 2013-09-11 中国水电顾问集团成都勘测设计研究院 Large-scale underground cavern group arrangement design method

Also Published As

Publication number Publication date
JPH0468440B2 (en) 1992-11-02

Similar Documents

Publication Publication Date Title
CN109026035B (en) Tunnel annular variable cross section expanding excavation method
KR20050093749A (en) The method of dual excavating for a tunnel and its apparatus
JPS6131594A (en) Bypass tunnel construction method
JP4083336B2 (en) How to build a tunnel
JP3170215B2 (en) Pipe burial method
JP3308916B2 (en) Ring cable insertion device for shield segment
JP3350679B2 (en) Tunnel lining segment and construction method
JPH06264698A (en) Method for constructing tunnel
JP3616898B2 (en) Method for joining underground structures using propulsion device
JPH0868293A (en) Underground tunnel joint method and segment
JP2863492B2 (en) Propulsion method, excavation device and propulsion device
KR200376414Y1 (en) Structure main pipe construction to establish tunnel formation tunnel structrue
JP3703638B2 (en) Construction method of multi-strip pipes for underground cables such as electric power
JPH0369438B2 (en)
JPH0468188A (en) Execution method of tunnel widening section
JPH0462299A (en) Larger section tunnel and construction method thereof
JPH1163299A (en) Execution method of multi-conduit pipe and multi-conduit pipe
JP2516582B2 (en) Tunnel construction method
JP3875230B2 (en) Shield excavator for branch tunnel construction
JP3162348B2 (en) Steel segment and shield tunnel excavation method for tunnel lining
KR20030005651A (en) Pipe laying apparatus
JPH04140400A (en) Shield excavator
JPH1018757A (en) Method of constructing pipe roof, coupling pipe and excavating device
JP3789572B2 (en) Tunnel digging device and tunnel digging method
JP3713094B2 (en) Connection method of existing underground pipe and new pipe by shield method

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term