JP3162348B2 - Steel segment and shield tunnel excavation method for tunnel lining - Google Patents

Steel segment and shield tunnel excavation method for tunnel lining

Info

Publication number
JP3162348B2
JP3162348B2 JP05789899A JP5789899A JP3162348B2 JP 3162348 B2 JP3162348 B2 JP 3162348B2 JP 05789899 A JP05789899 A JP 05789899A JP 5789899 A JP5789899 A JP 5789899A JP 3162348 B2 JP3162348 B2 JP 3162348B2
Authority
JP
Japan
Prior art keywords
segment
tunnel
steel
shield
lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP05789899A
Other languages
Japanese (ja)
Other versions
JP2000257395A (en
Inventor
民夫 山岸
Original Assignee
有限会社タム・テック
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 有限会社タム・テック filed Critical 有限会社タム・テック
Priority to JP05789899A priority Critical patent/JP3162348B2/en
Publication of JP2000257395A publication Critical patent/JP2000257395A/en
Application granted granted Critical
Publication of JP3162348B2 publication Critical patent/JP3162348B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はシールド式トンネル
掘削工法に関し、特に小口径のトンネルを掘削するに適
したシールド式掘削工法、並びにその工法において使用
されるトンネル覆工用鋼性セグメントに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a shielded tunnel excavation method, and more particularly to a shielded excavation method suitable for excavating a small-diameter tunnel, and a steel segment for tunnel lining used in the method.

【0002】[0002]

【従来の技術】従来下水道などの管路系を建設するに当
たっては、管路が小径の場合には地上から開削した溝内
に管体を埋設する方法が経済的であるが、本管などの大
径の管路の場合には、土砂の掘削量が多くなるため地上
の交通への影響が大きく、また環境に対する汚染も著し
くなるので、トンネル掘削による管路建設が選択される
ことが多かった。
2. Description of the Related Art Conventionally, in constructing a pipeline system such as a sewer, if the pipeline has a small diameter, it is economical to bury a pipe body in a trench cut out from the ground. In the case of large-diameter pipelines, the amount of excavation of earth and sand increases, which greatly affects the traffic on the ground. .

【0003】ところで、このような管路網の建設が必要
な市街地等の地盤は、強度が十分でないことが多く、幹
線となる大径の管路は、シールド式トンネル掘削工法に
よって建設されるのが普通であった。しかし、シールド
式トンネル掘削工法は、トンネルの径が2m以下となる
と、狭いトンネル内での覆工の作業性が低下するため
に、掘進速度が制限されてしまうという問題があった。
[0003] By the way, the ground in an urban area or the like where the construction of such a pipeline network is necessary is often insufficient in strength, and a large-diameter pipeline serving as a trunk line is constructed by a shield tunnel excavation method. Was normal. However, the shield tunnel excavation method has a problem that when the diameter of the tunnel is 2 m or less, the workability of lining in a narrow tunnel is reduced, and the excavation speed is limited.

【0004】[0004]

【発明が解決しようとする課題】本発明は、径が2m以
下というような小口径のトンネルを建設するに際し、掘
進速度が制限されることなく、効率的にトンネルの建設
を行うことができる、新しいシールド式トンネル掘削工
法を提供しようとするものであり、更にかかるシールド
式トンネル掘削工法を実施するに使用する、新しいトン
ネル覆工用鋼性セグメントを提供することを目的とす
る。
SUMMARY OF THE INVENTION According to the present invention, when constructing a small-diameter tunnel having a diameter of 2 m or less, the tunnel can be efficiently constructed without limiting the excavation speed. It is an object of the present invention to provide a new shield tunnel excavation method, and to provide a new steel segment for tunnel lining used for carrying out such a shield tunnel excavation method.

【0005】[0005]

【課題を解決するための手段】本発明のトンネル覆工用
の鋼性セグメントは、鋼板で形成した筒体の内側面に、
軸に平行な複数のビーム材を軸に対して回転対称かつ略
等間隔に設けると共に、該ビーム材と直交する弧状リブ
材で構成された環状補強部材を該筒体の内周に沿って設
けたことを特徴とする。
According to the present invention, a steel segment for tunnel lining is provided on an inner surface of a cylindrical body formed of a steel plate.
A plurality of beam members parallel to the axis are provided rotationally symmetric with respect to the axis and at substantially equal intervals, and an annular reinforcing member formed of an arcuate rib member orthogonal to the beam member is provided along the inner periphery of the cylindrical body. It is characterized by having.

【0006】更にまた、本発明のトンネル覆工用の鋼性
セグメントを使用するシールド式トンネル掘削工法は、
シールド式掘削機を用いて地盤内にトンネルの掘削と覆
工とを行うに当たり、前記シールド式掘削機を推進して
形成された掘削機後部空間内に、略長方形状の鋼板を巻
き丸めてなる切り割り筒状鋼板の内側面に長さ方向に平
行な複数のビーム材を該切り割りの対向端位置を含めて
略等間隔に設けてなるセグメント部材を導入し、次いで
該セグメント部材の内側空間に拡張装置を導入して、該
セグメント部材の外径をトンネル覆工体の外径と一致さ
せると共に該切り割りの対向端部を結合して筒体に整形
し、更に該筒体の内周に沿って複数の弧状リブ材を組み
立ててなる環状補強部材を設けて請求項1に記載の鋼性
セグメントを形成し、該鋼性セグメントを隣接する既設
セグメントと結合したのち前記シールド式掘削機を推進
して掘削を進め、続いて上記の一連の工程を反復するこ
とを特徴とするものである。
Further, the shield tunnel excavation method using the steel segment for tunnel lining according to the present invention comprises:
In performing excavation and lining of a tunnel in the ground using a shielded excavator, a substantially rectangular steel plate is wound and rolled in an excavator rear space formed by propelling the shielded excavator. A plurality of beam members parallel to the longitudinal direction are introduced into the inner surface of the split tubular steel plate at a substantially equal interval including a position of the opposite end of the cut . An expansion device is introduced into the inner space, the outer diameter of the segment member is made to match the outer diameter of the tunnel lining body, and the opposite ends of the split are joined to form a cylinder. An annular reinforcing member formed by assembling a plurality of arc-shaped rib members along a circumference is provided to form a steel segment according to claim 1, and the steel segment is connected to an adjacent existing segment, and then the shield type excavator is provided. To promote drilling , Followed by those characterized by repeating the series of steps described above.

【0007】[0007]

【発明の実施の形態】以下、図面に基づいて、本発明の
シールド式トンネル掘削工法を詳細に説明する。図1〜
図4に、本発明のシールド式トンネル掘削工法を実施中
のトンネルの様子を示すが、3は、地盤1中にトンネル
2を掘削するシールド式のトンネル掘削機であって、3
1は掘削機やジャッキ32などを備えた掘削部である。
そして掘削部31の後方には、可撓性連結部33を介し
てセグメント組立部34が結合されており、掘進方向の
修正が可能であるように構成されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The shield tunnel excavation method of the present invention will be described below in detail with reference to the drawings. Figure 1
FIG. 4 shows the state of the tunnel during the execution of the shield tunnel excavation method of the present invention. Reference numeral 3 denotes a shield tunnel excavator that excavates the tunnel 2 in the ground 1.
Reference numeral 1 denotes an excavation unit provided with an excavator, a jack 32, and the like.
A segment assembling section 34 is connected to the rear of the excavating section 31 via a flexible connecting section 33, so that the excavating direction can be corrected.

【0008】また4はトンネル2の壁面の覆工部を構成
するユニットとなる、本発明の鋼性セグメントである
が、この鋼性セグメント4は、鋼板からなる断面が略円
形の筒体41と、筒体41の内側面に、軸に対して回転
対称かつ略等間隔に設けた軸に平行な複数のビーム材4
2と、このビーム材42と直交するように弧状リブ材4
3aや43bで構成して、筒体41の内周に沿って設け
た複数の環状補強部材43とからなるものである。
Reference numeral 4 denotes a steel segment of the present invention, which is a unit constituting a lining portion of the wall surface of the tunnel 2. The steel segment 4 includes a cylindrical body 41 made of a steel plate and having a substantially circular cross section. A plurality of beam members 4 which are rotationally symmetrical with respect to the axis and are provided at substantially equal intervals on the inner surface of the cylindrical body 41 are parallel to the axis.
2 and an arc-shaped rib material 4 orthogonal to the beam material 42.
3a and 43b, and a plurality of annular reinforcing members 43 provided along the inner periphery of the cylindrical body 41.

【0009】このような鋼性セグメント4は、トンネル
掘削機3の後部空間、特にセグメント組立部34を中心
とした空間内で、セグメント部材4aと弧状リブ材43
a、43bとから組み立てられる。ここで用いられるセ
グメント部材4aは、図5に示すように、略長方形状の
鋼板を巻き丸めた切り割り筒状鋼板40の内側面に、例
えば溶接やボルト止め等によって、複数のビーム材42
を略等間隔で平行に設けたものである。そして、筒状に
整形するときに結合される切り割りの対向端部と、弧状
リブ材43a、43b・・・を取り付ける予定の開口端
位置や中間位置等とには、それぞれボルトなどの締結部
材4cの取り付け孔40aが設けてあり、更に必要に応
じて鋼性セグメント4と地盤1との間隙に充填する生コ
ンクリートのためのコンクリート注入孔40b等を設け
ておいてもよい。
Such a steel segment 4 is provided in the rear space of the tunnel excavator 3, particularly in the space centered on the segment assembling section 34, with the segment member 4 a and the arc-shaped rib material 43.
a and 43b. As shown in FIG. 5, the segment member 4a used here is provided with a plurality of beam members 42 on the inner surface of a cut tubular steel plate 40 obtained by winding a substantially rectangular steel plate by, for example, welding or bolting.
Are provided in parallel at substantially equal intervals. The opposite ends of the slits to be joined when shaping into a cylindrical shape and the opening end positions and intermediate positions where the arc-shaped rib members 43a, 43b... Are to be attached are respectively provided with fastening members 4c such as bolts. Mounting holes 40a, and if necessary, concrete injection holes 40b for ready-mixed concrete filling the gap between the steel segment 4 and the ground 1 may be provided.

【0010】このようなセグメント部材4aは、設置予
定のトンネルの形状に合わせて工場で作成され、組み立
て現場まで搬入されるが、セグメント組立部34内に搬
入したセグメント部材4aは、図6に示すような油圧プ
レス5などの拡張装置をセグメント部材4aの中心部に
導入し、複数の伸縮アーム51を均等に伸長させる。そ
うするとセグメント部材4aは拡張して円筒状に整形さ
れるので、図7に示すように、切り割りの対向端部の
側に取り付けたビーム材42の外側に他方の対向端部が
重なるので、双方の対向端部の間にシール部材4bを挟
み込み、ボルトなどの締結部材4cで結合して筒体41
が得られる。
Such a segment member 4a is prepared in a factory according to the shape of the tunnel to be installed, and is carried to the assembly site. The segment member 4a carried into the segment assembling section 34 is shown in FIG. An expansion device such as the hydraulic press 5 is introduced into the center of the segment member 4a, and the plurality of telescopic arms 51 are extended uniformly. Then since the segment member 4a is shaped into a cylindrical shape to expand, as shown in FIG. 7, of the opposing ends of the cut-split
The other opposing end is outside the beam material 42 attached to the side
Since they overlap with each other , the sealing member 4b is sandwiched between the two opposing ends , and connected with a fastening member 4c such as a bolt to form the cylindrical body 41b.
Is obtained.

【0011】こうして図8に示すような、内側面に複数
のビーム材42が固着された筒体41が得られるが、こ
こで筒体41内から油圧プレス5を撤去する。それに続
いて筒体41の内側面に複数の環状補強部材43を、ボ
ルトなどの締結部材4cを用いて、ビーム材42と直交
するように内周にそって固着して設ける。かかる環状補
強部材43としては、図9に示すような、筒体41の開
口端部を補強するための弧状リブ材43aを組み立てた
ものと、図10に示すような、筒体41の中央部分を補
強するための弧状リブ材43bを組み立てたものを、例
として挙げることができるが、これに限られるものでは
ない。
As shown in FIG. 8, a cylindrical body 41 having a plurality of beam members 42 fixed to the inner surface is obtained. Here, the hydraulic press 5 is removed from the cylindrical body 41. Subsequently, a plurality of annular reinforcing members 43 are provided on the inner side surface of the cylindrical body 41 along the inner circumference so as to be orthogonal to the beam member 42 by using a fastening member 4c such as a bolt. As the annular reinforcing member 43, an annular rib member 43a for reinforcing the opening end of the cylindrical body 41 as shown in FIG. 9 and a central portion of the cylindrical body 41 as shown in FIG. Can be cited as an example, but the present invention is not limited to this.

【0012】上記のように、筒体41の内側面にビーム
材42と環状補強部材43とを固着して組み立てた鋼性
セグメント4を、ジャッキ32を用いて既設の鋼性セグ
メント4に圧着し、それぞれの開口端部に取り付けた環
状補強部材43を、シール部材4dを間に挟んで相互に
密着させた上、図11に示すように、ボルトなどの締結
部材4cを用いて結合することにより、鋼性セグメント
4の組立及び設置が完了する。
As described above, the steel segment 4 assembled by fixing the beam member 42 and the annular reinforcing member 43 to the inner surface of the cylindrical body 41 is press-bonded to the existing steel segment 4 using the jack 32. The annular reinforcing members 43 attached to the respective open end portions are brought into close contact with each other with the sealing member 4d interposed therebetween, and then connected by using a fastening member 4c such as a bolt as shown in FIG. The assembly and installation of the steel segment 4 are completed.

【0013】その後、必要に応じて新設の鋼性セグメン
ト4内には、掘削した土砂の搬出や資材の搬入などのた
めの軌道などを延設し、トンネル掘削機3前面の地盤の
掘削と土砂等の搬出を行うと共に、ジャッキ32及び補
助ビーム35などを用いてトンネル掘削機3を推進す
る。このようにして鋼性セグメント4の長さ約1個分だ
け掘進したのち、トンネル掘削機3の掘削部31、可撓
性連結部33、及びセグメント組立部34の内部空間を
清掃し、次のセグメント部材4aを搬入し、前記と同様
にして鋼性セグメント4の組み立てを反復し、トンネル
の建設を進める。
Thereafter, if necessary, a track for carrying out the excavated earth and sand and carrying in materials is extended into the newly constructed steel segment 4, and excavation of the ground in front of the tunnel excavator 3 and earth and sand are performed. And the like, and the tunnel excavator 3 is propelled using the jack 32, the auxiliary beam 35, and the like. After the steel segment 4 has been dug by about one length in this manner, the internal space of the excavation part 31, the flexible connection part 33, and the segment assembly part 34 of the tunnel excavator 3 is cleaned, and The segment member 4a is carried in, the assembly of the steel segment 4 is repeated in the same manner as described above, and the construction of the tunnel is advanced.

【0014】こうして設置された鋼性セグメント4の位
置から、トンネル掘削機3のセグメント組立部34が離
れたのち、必要に応じて、鋼性セグメント4に設けたコ
ンクリート注入孔40bを介して、鋼性セグメント4と
地盤1との間隙に生コンクリートを注入し、或いは鋼性
セグメント4の内側に型枠などを設置して、鋼性セグメ
ント4と型枠の間に生コンクリートを充填するなどし
て、強靱な覆工体を備えたトンネルを完成することがで
きる。
After the segment assembly 34 of the tunnel excavator 3 is separated from the position of the steel segment 4 thus installed, if necessary, the steel is inserted through a concrete injection hole 40b provided in the steel segment 4. By injecting ready-mixed concrete into the gap between the steel segment 4 and the ground 1 or installing a formwork or the like inside the steel segment 4 to fill the space between the steel segment 4 and the formwork with ready-mixed concrete. Thus, a tunnel having a tough lining can be completed.

【0015】[0015]

【発明の効果】本発明のシールド式トンネル掘削工法に
よれば、鋼板を用いて工場で製作されたセグメント部材
や弧状リブ材などをトンネル内に搬入し、現場で組み立
てた鋼性セグメントでトンネルの覆工を行うので、小径
のトンネル内の狭い空間内でも極めて効率的に覆工作業
を進めることができ、しかも長尺の鋼性セグメントを用
いることにより、トンネルの掘削に要する時間に対する
覆工に要する時間の比率を、大幅に低下させることが可
能で、工期の短縮と共に工事費用の低減が達成できる効
果がある。
According to the shield tunnel excavation method of the present invention, a segment member or an arc-shaped rib material manufactured at a factory using a steel plate is carried into the tunnel, and the steel segment assembled on site is used for the tunnel. Because the lining is used, the lining work can be performed very efficiently even in a narrow space in a small-diameter tunnel. The ratio of the required time can be greatly reduced, which has the effect of shortening the construction period and reducing the construction cost.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のシールド式トンネル掘削工法におけ
る、トンネル覆工用鋼性セグメントを設置する前の、シ
ールド式掘削機付近のトンネルの断面図である。
FIG. 1 is a cross-sectional view of a tunnel near a shield-type excavator before a steel segment for tunnel lining is installed in a shield-type tunnel excavation method of the present invention.

【図2】本発明のシールド式トンネル掘削工法におけ
る、トンネル覆工用のセグメント部材を搬入したとき
の、シールド式掘削機付近のトンネルの断面図である。
FIG. 2 is a cross-sectional view of a tunnel near a shield type excavator when a segment member for tunnel lining is carried in the shield type tunnel excavation method of the present invention.

【図3】本発明のシールド式トンネル掘削工法におけ
る、セグメント部材を伸長させて筒体に整形したとき
の、シールド式掘削機付近のトンネルの断面図である。
FIG. 3 is a cross-sectional view of a tunnel near a shield-type excavator when a segment member is elongated and shaped into a cylindrical body in a shield-type tunnel excavation method of the present invention.

【図4】本発明のシールド式トンネル掘削工法におけ
る、トンネル覆工用鋼性セグメントを完成したときの、
シールド式掘削機付近のトンネルの断面図である。
FIG. 4 is a diagram showing a state in which a steel segment for tunnel lining is completed in the shield tunnel excavation method of the present invention.
It is sectional drawing of the tunnel near a shield type excavator.

【図5】本発明のトンネル覆工用鋼性セグメントの組立
用材料であるセグメント部材の外観斜視図である。
FIG. 5 is an external perspective view of a segment member which is a material for assembling the steel segment for tunnel lining according to the present invention.

【図6】本発明のトンネル覆工用鋼性セグメントの組立
用材料であるセグメント部材を伸長させるための、油圧
プレスの外観斜視図である。
FIG. 6 is an external perspective view of a hydraulic press for extending a segment member that is a material for assembling the steel segment for tunnel lining according to the present invention.

【図7】本発明のトンネル覆工用鋼性セグメントの組立
用材料であるセグメント部材を整形して得た筒体の、結
合部分を拡大した外観斜視図である。
FIG. 7 is an external perspective view of a cylindrical body obtained by shaping a segment member, which is a material for assembling a steel segment for a tunnel lining according to the present invention, in which a joining portion is enlarged.

【図8】本発明のトンネル覆工用鋼性セグメントの組立
用材料であるセグメント部材を整形して得た筒体の、部
分外観斜視図である。
FIG. 8 is a partial external perspective view of a cylindrical body obtained by shaping a segment member which is a material for assembling a steel segment for tunnel lining according to the present invention.

【図9】本発明のトンネル覆工用鋼性セグメントの組立
用材料である弧状リブ材のうち、筒体開口部用の環状補
強部材に用いるものの外観斜視図であり、それぞれ
(A)は前側を、(B)は外側を示す図である。セグメ
ント部材の、外観斜視図である。
9 is an external perspective view of an arcuate rib material used for assembling the steel segment for tunnel lining according to the present invention, which is used for an annular reinforcing member for an opening of a cylindrical body, and FIG. (B) is a diagram showing the outside. It is an external appearance perspective view of a segment member.

【図10】本発明のトンネル覆工用鋼性セグメントの組
立用材料である弧状リブ材のうち、筒体中央位置用の環
状補強部材に用いるものの、外観斜視図である。
FIG. 10 is an external perspective view of an arcuate rib material used for assembling the steel segment for tunnel lining according to the present invention, which is used for an annular reinforcing member for a central position of a cylindrical body.

【図11】本発明のトンネル覆工用鋼性セグメントの隣
接したもの相互を結合した構造の一部を示す、部分外観
斜視図である。
FIG. 11 is a partial external perspective view showing a part of a structure in which adjacent ones of the steel segments for tunnel lining of the present invention are connected to each other.

【符号の説明】[Explanation of symbols]

1 地盤 2 トンネル 3 トンネル掘削機 31 掘削部 32 ジャッキ 33 可撓性連結部 34 セグメント組立部 35 補助ビーム 4 鋼性セグメント 4a セグメント部材 4b シール部材 4c 締結部材 4d シール部材 40 切り割り筒状鋼板 40a 取り付け孔 40b コンクリート注入孔 41 筒体 42 ビーム材 43 環状補強部材 43a 弧状リブ材 43b 弧状リブ材 5 油圧プレス 51 伸縮アーム DESCRIPTION OF SYMBOLS 1 Ground 2 Tunnel 3 Tunnel excavator 31 Excavation part 32 Jack 33 Flexible connection part 34 Segment assembling part 35 Auxiliary beam 4 Steel segment 4a Segment member 4b Seal member 4c Fastening member 4d Seal member 40 Split tubular steel plate 40a Mounting hole 40b Concrete injection hole 41 Cylindrical body 42 Beam material 43 Annular reinforcing member 43a Arc-shaped rib material 43b Arc-shaped rib material 5 Hydraulic press 51 Telescopic arm

Claims (7)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 鋼板で形成した筒体の内側面に、軸に平
行な複数のビーム材を軸に対して回転対称かつ略等間隔
に設けると共に、該ビーム材と直交する弧状リブ材で構
成された環状補強部材を該筒体の内周に沿って設けたこ
とを特徴とするトンネル覆工用鋼性セグメント。
1. A plurality of beam members parallel to an axis are provided on the inner side surface of a cylindrical body formed of a steel plate at rotationally symmetrical and substantially equal intervals with respect to the axis, and are constituted by arcuate rib members orthogonal to the beam members. A steel segment for tunnel lining, characterized in that said annular reinforcing member is provided along the inner periphery of said tubular body.
【請求項2】 前記筒体の長さにそって前記環状補強部
材の複数個を順次に設けてなる、請求項1に記載のトン
ネル覆工用鋼性セグメント。
2. The steel segment for tunnel lining according to claim 1, wherein a plurality of the annular reinforcing members are sequentially provided along a length of the cylindrical body.
【請求項3】 前記筒体の開口端部に前記環状補強部材
を設けてなる、請求項1又は2に記載のトンネル覆工用
鋼性セグメント。
3. The tunnel lining according to claim 1, wherein the annular reinforcing member is provided at an open end of the cylindrical body.
Steel segment of.
【請求項4】 シールド式掘削機を用いて地盤内にトン
ネルの掘削と覆工とを行うに当たり、前記シールド式掘
削機を推進して形成された掘削機後部空間内に、略長方
形状の鋼板を巻き丸めてなる切り割り筒状鋼板の内側面
に長さ方向に平行な複数のビーム材を該切り割りの対向
端位置を含めて略等間隔に設けてなるセグメント部材を
導入し、次いで該セグメント部材の内側空間に拡張装置
を導入して、該セグメント部材の外径をトンネル覆工体
の外径と一致させると共に該切り割りの対向端部を結合
して筒体に整形し、更に該筒体の内周に沿って複数の弧
状リブ材を組み立ててなる環状補強部材を設けて請求項
1に記載の鋼性セグメントを形成し、該鋼性セグメント
を隣接する既設セグメントと結合したのち前記シールド
式掘削機を推進して掘削を進め、続いて上記の一連の工
程を反復することを特徴とする、シールド式トンネル掘
削工法。
4. When excavating and lining a tunnel in the ground using a shield type excavator, a substantially rectangular steel plate is formed in a rear space of the excavator formed by propelling the shield type excavator. A plurality of beam members parallel to the length direction on the inner surface of the cylindrical steel plate
The segment members provided at substantially equal intervals including the end position are introduced, and then the expansion device is introduced into the inner space of the segment member so that the outer diameter of the segment member matches the outer diameter of the tunnel lining body. claim together by combining the opposite ends of said cut-split shaped into the cylindrical body, further provided with an annular reinforcing member made by assembling a plurality of arcuate ribs material along the inner periphery of the tubular member
Forming a steel segment according to 1 above, joining the steel segment with an adjacent existing segment, and then propelling the shield type excavator to perform excavation, and subsequently repeating the above series of steps. The shield tunnel excavation method.
【請求項5】 前記セグメント部材の切り割りの対向端
部を、シール部材を介して結合する、請求項4に記載の
シールド式トンネル掘削工法。
5. The shield tunnel excavation method according to claim 4, wherein opposing ends of the segment members are connected via a seal member.
【請求項6】 前記鋼性セグメントを隣接する既設セグ
メントにシール部材を介して結合する、請求項4又は5
に記載のシールド式トンネル掘削工法。
6. The steel segment is connected to an adjacent existing segment via a sealing member.
Shield tunnel excavation method described in 1.
【請求項7】 前記鋼性セグメントとその内面側に打設
された補強コンクリートとが、一体化した覆工体を形成
する、請求項4乃至6のいずれかに記載のシールド式ト
ンネル掘削工法。
7. The shield tunnel excavation method according to claim 4, wherein the steel segment and the reinforced concrete cast on the inner surface thereof form an integrated lining body.
JP05789899A 1999-03-05 1999-03-05 Steel segment and shield tunnel excavation method for tunnel lining Expired - Fee Related JP3162348B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP05789899A JP3162348B2 (en) 1999-03-05 1999-03-05 Steel segment and shield tunnel excavation method for tunnel lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP05789899A JP3162348B2 (en) 1999-03-05 1999-03-05 Steel segment and shield tunnel excavation method for tunnel lining

Publications (2)

Publication Number Publication Date
JP2000257395A JP2000257395A (en) 2000-09-19
JP3162348B2 true JP3162348B2 (en) 2001-04-25

Family

ID=13068821

Family Applications (1)

Application Number Title Priority Date Filing Date
JP05789899A Expired - Fee Related JP3162348B2 (en) 1999-03-05 1999-03-05 Steel segment and shield tunnel excavation method for tunnel lining

Country Status (1)

Country Link
JP (1) JP3162348B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104675413B (en) * 2015-02-16 2017-03-08 济南轨道交通集团有限公司 A kind of tunnel duct piece rounding device and its using method

Also Published As

Publication number Publication date
JP2000257395A (en) 2000-09-19

Similar Documents

Publication Publication Date Title
JP2816397B2 (en) Method of expanding and reducing diameter of tunnel
JPH0765455B2 (en) Construction method for branch / joint of shield tunnel and temporary bulkhead construction device for branch / joint
JP4183470B2 (en) Underground structure and its construction method
JP2788953B2 (en) Structure of tunnel structure
JP3966334B2 (en) Method for forming communication part of parallel shield tunnel and its communication part structure
JP4750568B2 (en) Tunnel junction construction method and tunnel junction structure
JP3162348B2 (en) Steel segment and shield tunnel excavation method for tunnel lining
JPH10227199A (en) Construction method of large sectional tunnel
JP2002220991A (en) Partition wall installed in main-tunnel shield tunnel and construction method therefor
JPH04319198A (en) Construction method of tunnel
JP3765048B2 (en) How to build a tunnel
JP2770112B2 (en) Ground improvement method in shield excavation
JPH0462299A (en) Larger section tunnel and construction method thereof
JP3584416B2 (en) Tunnel and its construction method
JPH07324595A (en) Inner concrete form and secondary lining method for shield tunnel of internal water pressure compliance type
JP2019124048A (en) Connection structure and connection method between pipe roof and start side tunnel
JPH11117686A (en) Segment corresponding to opening covered with resin on inner surface
JPH0868293A (en) Underground tunnel joint method and segment
JPH05287983A (en) Construction of underground space having long and large diametral dimension
JP3153887B2 (en) Joining method of shield tunnel
JP2018178593A (en) Underground wall construction method
JP3567399B2 (en) Large section tunnel and its construction method
JP3178357B2 (en) Construction method of large section tunnel
JP4451016B2 (en) Tunnel laying replacement method
JP2746866B2 (en) Drilling device for propulsion method and propulsion method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees