JPS61286417A - Cofferdam structure - Google Patents

Cofferdam structure

Info

Publication number
JPS61286417A
JPS61286417A JP12618485A JP12618485A JPS61286417A JP S61286417 A JPS61286417 A JP S61286417A JP 12618485 A JP12618485 A JP 12618485A JP 12618485 A JP12618485 A JP 12618485A JP S61286417 A JPS61286417 A JP S61286417A
Authority
JP
Japan
Prior art keywords
floating body
piles
construction
cofferdam
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12618485A
Other languages
Japanese (ja)
Inventor
Kentaro Yamada
健太郎 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP12618485A priority Critical patent/JPS61286417A/en
Publication of JPS61286417A publication Critical patent/JPS61286417A/en
Pending legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

PURPOSE:To shorten the term of construction and need no sea-bottom dredging after a cofferdam is removed, by a method wherein a ballast can be contained in a floating body, and wherein piles are housed on the side sections of the floating body, and wherein the cofferdam is constructed to be hung from the piles. CONSTITUTION:A floating body 1 is taken in tow to the site of a cofferdam, and a ballast is contained in the floating body 1 there, and the floating body 1 is sunk. After that, piles 2, 2a are supported by the side sections of the floating body 1, and at the same time, the piles are driven to the sea-bottom, and the floating body 1 is served as a supporting guide when the piles are driven. When removed, the piles 2, 2a are respectively taken out of the ends in order, and after the work for taking out is completed, the floating body 1 is made to float and is moved to the following construction site. As a result, the construction is facilitated, and the term of the construction is shortened, and the removal can be facilitated, and so the piles can be used repeatedly.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、水中に構造物や基礎を作る時、作業に先立
ってその周囲の水をせき止める堤防等の仮締切構造物に
関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a temporary coffering structure such as an embankment that dams water around the structure or foundation prior to construction of the structure or foundation underwater.

〔従来の技術〕[Conventional technology]

従来、海面に設置される堤防等の仮締切構造物は、第2
間断面図に示すように、タイロッド(101)で雨間が
連結され、且つ海底Qoo)に打込まれた鋼矢板(10
2) (xoza)の間に、土砂(103)を埋め込む
ことにより構築されている。
Conventionally, temporary cofferdam structures such as embankments installed on the sea surface are
As shown in the cross-sectional view, the steel sheet piles (10
2) It is constructed by burying earth and sand (103) between (xoza).

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかし、その施工工事としては、まず鋼矢板(102)
 (xoza)を二重に打込み、これらの鋼矢板(10
2) (102m)の間に土砂(103)をある程度投
入した上で、タイロッド(101)をその間に固定し、
更に土砂(103)を入れることにより構築される。
However, as for the construction work, first the steel sheet pile (102)
(xoza) and these steel sheet piles (10
2) After putting a certain amount of earth and sand (103) between (102m) and fixing the tie rod (101) between them,
It is constructed by further adding earth and sand (103).

反対に仮締切を撤去する場合は、前記鋼矢板(102)
 (xoza)間の土砂(103)を掘り出し、タイロ
ッド(101)を取外した後、更に残りの海中土砂(1
oa)を取り出して、次に該鋼矢板(102) (lo
2a)  −を抜き取り、最後に仮締切の海底(100
)部分に残った土砂(103)を浚渫して終了していた
On the other hand, when removing the temporary cofferdam, the steel sheet pile (102)
After digging out the earth and sand (103) between (xoza) and removing the tie rod (101),
oa) and then the steel sheet pile (102) (lo
2a) Remove - and finally remove the temporary cofferdam (100
) The remaining soil (103) was dredged and completed.

このように従来の仮締切の施行及び撤去に関する土木工
事は、工事手順が多く、工期も長くか力することになり
、又、撤去時の海中土砂(103)の取り出し、及び浚
渫工事等の際には海洋汚染の虞れもある等の問題も生じ
ていた。
In this way, conventional civil engineering work related to the enforcement and removal of temporary cofferdams involves many construction procedures and requires a long construction period. There were also problems such as the risk of marine pollution.

本発明は以上の問題を解決するためなされたもので、水
中に仮締切を作る際、土木工事を大幅に減少させて工期
の短縮を実現でき、仮締切撤去後の海底浚渫も不要にす
ることが可能な新たな仮締切構造物を提供せんとするも
のである。
The present invention has been made to solve the above problems, and it is possible to significantly reduce the civil engineering work and shorten the construction period when constructing a temporary cofferdam underwater, and also eliminate the need for seabed dredging after the temporary cofferdam is removed. The aim is to provide a new temporary cofferdam structure that is capable of

〔問題点を解決するための手段〕[Means for solving problems]

第1図は本発明に係る仮締切構造物の構造を示しており
、該構造物は浮体(1)と、パイル(2) (2a)と
を有している。
FIG. 1 shows the structure of a temporary cofferdam structure according to the present invention, and the structure has a floating body (1) and a pile (2) (2a).

前記浮体11)は、海水等のバラストをその内部に収容
することができる構造物であり、仮締切を付設しようと
する範囲に応じて適当な長さを有するものが良い。
The floating body 11) is a structure capable of accommodating ballast such as seawater, and preferably has an appropriate length depending on the area in which the temporary cofferdam is to be attached.

前記パイル(2) (2a)は、浮体(1)側部に昇降
自在に支持格納され、そこ力)ら垂下されて、海底に打
込まれる鋼矢板等の鋼杭である。
The pile (2) (2a) is a steel pile such as a steel sheet pile that is supported and stored on the side of the floating body (1) so as to be able to rise and fall, and is suspended from there and driven into the seabed.

〔作 用〕 以上の仮締切構造物は次のようにして使用される。まず
、浮体(1)を仮締切現場まで曳航し、そこで該浮体(
1)内にバラストを収容せしめ、沈下させる。そしてパ
イル(2) (21L)を浮体(1)側部で支持しなが
ら、これらを海底に向けて打込む。このようにパイル(
2) (2a)の間にある浮体(1)は、該パイル(2
) C2&>の運搬に供することができると共に、打込
み時にこれらを支持ガイドするものとなり、又、打込み
完了後はパイル(2) (2Jk)の間に詰め込む土砂
等と同様な内容物となるものである。しかして。
[Function] The above temporary cofferdam structure is used as follows. First, the floating body (1) is towed to the temporary cofferdam site, and there the floating body (1) is towed to the temporary cofferdam site.
1) Place the ballast inside and let it sink. Then, while supporting the pile (2) (21L) on the side of the floating body (1), these are driven toward the seabed. Pile like this (
2) The floating body (1) located between the piles (2a)
) It can be used to transport C2 &>, and it will support and guide them during driving, and after driving is completed, it will become the same content as earth and sand packed between piles (2) (2Jk). be. However.

これらを撤去する場合は以上の操作と反対の手順で行な
い、浮体(1)浮上後、次の工事現場に移動せしめるこ
とになる。
When removing these, the procedure described above is reversed, and after the floating body (1) has surfaced, it will be moved to the next construction site.

〔実施例〕〔Example〕

第3図は本発明の仮締切構造物の一実施例を示している
。同図iこおいて本発明は浮体αqと、パイル(ホ)e
ηにより構成されている。
FIG. 3 shows an embodiment of the temporary cofferdam structure of the present invention. In the figure i, the present invention consists of a floating body αq and a pile (E)
It is composed of η.

浮体部は不要になった船舶の船体を利用しており、内部
に多量の海水を貯蔵できるバラストタンクと%咳海水の
吸排水設備を備えている。又この浮体αOの両舷平行部
には、前記パイル(7)(財)をその両舷に格納せしめ
ておき、又該パイルmQηを打込む時にガイドとなる格
納ガイド部αlaが装備されている。
The floating body uses the hull of a ship that is no longer needed, and is equipped with a ballast tank that can store a large amount of seawater and a system for absorbing and draining seawater. In addition, the pile (7) (goods) is stored on both sides of the floating body αO, and a storage guide part αla is installed to serve as a guide when driving the pile mQη. .

前記パイル(ホ)?では夫々鋼矢板からなり、これらの
側辺を相互lこ摺動可能に複数連結せしめた状態にして
いる。そして、これらのパイル(1)91は前記格納ガ
イド部α1)(6)により浮体部の両舷で垂下可能な状
態に格納されている。
Said pile (ho)? Each of these is made of steel sheet piles, and a plurality of these sides are connected so that they can slide relative to each other. These piles (1) 91 are stored in a hanging state on both sides of the floating body part by the storage guide parts α1) and (6).

上記本実施例の構造物は、浮上させたまま仮締切現場ま
で曳航し、そこで前記浮体αGのバラストタンク内に吸
排水設備により海水をバ、ラスト水として張り込ませ、
該浮体部を沈下着底させる。バラストタンク内が海水で
いっばいになった後、浮体uG両舷側ζこ杭打機を設置
し、第4図に示すように格納ガイド部αで(2)に格納
されているパイル(7)?やを端より順に海底(loo
)+こ打込んでその施工を完了するり又−撤去する時は
パイル翰(財)を夫々端から順次抜き上げて行き、この
抜き上げ作業完了後、海水をバラストタンク内から排水
させて浮体αOを浮上せしめる。そして次の工事現場ま
で移動させる。
The structure of this embodiment is towed while floating to the temporary cofferdam site, and there, seawater is filled as last water into the ballast tank of the floating body αG using suction and drainage equipment,
The floating part is allowed to sink to the bottom. After the inside of the ballast tank is completely filled with seawater, a pile driver is installed on both sides of the floating uG, and the pile (7) stored in (2) is installed in the storage guide section α as shown in Figure 4. ? Starting from the end, the bottom of the ocean (loo
) When driving in the pile to complete the construction or remove it, pull out the pile ferrules (property) one by one from each end, and after completing this pulling out, drain the seawater from the ballast tank and remove the floating structure. Let αO float. Then move it to the next construction site.

〔発明の効果〕〔Effect of the invention〕

以上説明してきたように本発明の構造物によれば、これ
を海底に付設せしめる際、パラスティング及びパイルの
打込み/抜き上げのみの手順で良いので、施工が簡単(
こできて工期の短縮につながり、又、海洋汚染の問題も
生じないという優れた効果を有している。更に上述のよ
うに設置工事が容易な他、移動も簡単にできるため、何
回も繰り返し使用できるという利点も有している。
As explained above, according to the structure of the present invention, when attaching it to the seabed, only the steps of driving/pulling out parasting and piles are required, so construction is easy (
This has the excellent effect of shortening the construction period and also eliminating the problem of marine pollution. Furthermore, as mentioned above, it is easy to install and can be moved easily, so it has the advantage of being able to be used many times.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の構成を示す説明図、第2図は従来の仮
締切構造物の付設状態を示す概略図、第3図は本発明の
一実施例を示す斜視図、第4図は本実施例の付設状態を
示す概略図である。 図中、(1) (10)は浮体、(2) (2a) (
20) (21)はパイル、(11) (12)は格納
ガイド部、(100)は海底% (101)はタイロッ
ド、(102) (10ム)は鋼矢板、(103)は土
砂を各示す。 特許出願人  日本鋼管株式会社 第  1   図 12図 第  3  図 第4図
Fig. 1 is an explanatory diagram showing the configuration of the present invention, Fig. 2 is a schematic diagram showing the attached state of a conventional temporary cofferdam structure, Fig. 3 is a perspective view showing an embodiment of the present invention, and Fig. 4 is FIG. 2 is a schematic diagram showing an attached state of this embodiment. In the figure, (1) (10) are floating bodies, (2) (2a) (
20) (21) indicates pile, (11) (12) indicates storage guide section, (100) indicates seabed percentage, (101) indicates tie rod, (102) (10mm) indicates steel sheet pile, and (103) indicates earth and sand. . Patent applicant Nippon Kokan Co., Ltd. No. 1 Fig. 12 Fig. 3 Fig. 4

Claims (1)

【特許請求の範囲】 内部にバラストを収容可能な浮体と、該 浮体側部に格納され又そこから垂下される パイルとを有することを特徴とする仮締切 構造物。[Claims] A floating body that can accommodate ballast inside and a floating body that can accommodate ballast inside. Stored on the side of the floating body and suspended from it A temporary cofferdam characterized by having a pile Structure.
JP12618485A 1985-06-12 1985-06-12 Cofferdam structure Pending JPS61286417A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12618485A JPS61286417A (en) 1985-06-12 1985-06-12 Cofferdam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12618485A JPS61286417A (en) 1985-06-12 1985-06-12 Cofferdam structure

Publications (1)

Publication Number Publication Date
JPS61286417A true JPS61286417A (en) 1986-12-17

Family

ID=14928766

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12618485A Pending JPS61286417A (en) 1985-06-12 1985-06-12 Cofferdam structure

Country Status (1)

Country Link
JP (1) JPS61286417A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014088721A (en) * 2012-10-31 2014-05-15 Meiwa Industries Ltd Cut-off wall member for irrigation channel repair, and cofferdam method for irrigation channel repair
CN105586977A (en) * 2016-02-03 2016-05-18 中交第三航务工程局有限公司宁波分公司 Method for diversion construction of closure gap of steel cofferdam under open sea unshielded condition by down-penetrating method
CN105714837A (en) * 2016-02-03 2016-06-29 中交第三航务工程局有限公司宁波分公司 Diversion construction method for up-pull-method open sea no-cover steel cofferdam closure gap

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014088721A (en) * 2012-10-31 2014-05-15 Meiwa Industries Ltd Cut-off wall member for irrigation channel repair, and cofferdam method for irrigation channel repair
CN105586977A (en) * 2016-02-03 2016-05-18 中交第三航务工程局有限公司宁波分公司 Method for diversion construction of closure gap of steel cofferdam under open sea unshielded condition by down-penetrating method
CN105714837A (en) * 2016-02-03 2016-06-29 中交第三航务工程局有限公司宁波分公司 Diversion construction method for up-pull-method open sea no-cover steel cofferdam closure gap

Similar Documents

Publication Publication Date Title
US20020018696A1 (en) Submersible modular dike
US2050727A (en) Caisson belt apparatus and method
JPH11323872A (en) Remodeling method of sheet pile type quay
JPS61286417A (en) Cofferdam structure
US4360291A (en) Subsea foundation
CN115823351A (en) Method for installing submarine pipeline at shoal section and method for designing installation parameters
JPS58143023A (en) Caisson for pile supporting type breakwater
KR0130745B1 (en) Construction method of port district structure at the poor subsoil
JPH0551918A (en) Operation caisson
JPS6340024A (en) Pile-type caisson work
CN112779967B (en) Construction method for sea-land connecting section of sewage sea area discharge pipe
JP2745097B2 (en) Construction method of low temperature liquefied gas underground tank
JPH07292648A (en) Construction of artificial island
RU2465408C1 (en) Method to construct and repair water conduits and headers of shallow waste water on bottom of rivers and water reservoirs
JP2827536B2 (en) Sinking method for submerged boxes
JP3069822B2 (en) Installation method of intake water discharge pipe
JPH01121410A (en) Driving work of vertical drain in soft ground
JPS59106611A (en) Laying work of water sealing sheet
RU2565118C2 (en) Method to dismantle manifold pipeline
JPS58138805A (en) Construction of coffering revetment work
JPS5820329B2 (en) Artificial island for oil drilling in frozen waters
JPH0340169B2 (en)
KR20240074169A (en) A doupling device of the barge and regulation of floatation of fabric
JPH08184022A (en) Method of aerial reclamation construction
JP2802837B2 (en) Submerged tunnel installation method