JPH08184022A - Method of aerial reclamation construction - Google Patents

Method of aerial reclamation construction

Info

Publication number
JPH08184022A
JPH08184022A JP6338821A JP33882194A JPH08184022A JP H08184022 A JPH08184022 A JP H08184022A JP 6338821 A JP6338821 A JP 6338821A JP 33882194 A JP33882194 A JP 33882194A JP H08184022 A JPH08184022 A JP H08184022A
Authority
JP
Japan
Prior art keywords
ground
landfill
reclamation
zone
revetment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6338821A
Other languages
Japanese (ja)
Inventor
Kazuo Mishima
三島和生
Hiroyasu Tsutsumi
博恭 堤
Kazuto Yoshikoshi
吉越和人
Yuji Onishi
大西雄二
Yuichiro Someba
染葉祐一郎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP6338821A priority Critical patent/JPH08184022A/en
Publication of JPH08184022A publication Critical patent/JPH08184022A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins

Landscapes

  • Processing Of Solid Wastes (AREA)
  • Revetment (AREA)

Abstract

PURPOSE: To enable reclamation having high quality, and to facilitate maintenance after completion by a method wherein a reclamation zone is coffered, water in the zone is drained, the ground is exposed, the ground is improved and the inside of a coffering is reclaimed. CONSTITUTION: Cut-off steel sheet-piles 7, 7 are driven to an improved field ground 6 as a revetment section 2 single or doubly, and the outer circumference of a reclamation zone A is coffered. A rubble-stone 13 is also charged on the outsides of the coffering sheet-piles 7 and the insides as required, and covering stone and precast concrete armour blocks are installed, thus constituting a revetment. All drainage in the reclamation zone A is conducted and the ground 1 is exposed, and a weak stratum is improved by using a stabilizer, etc. A deep well is installed as necessary, and spring water treatment and consolidation promotion are executed. The inside of a coffering zone is reclaimed through the same construction method as a method of banking construction on a land section.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、止水性護岸または仮
締切りの構築が可能な水深、基礎地盤ともに浅い水域の
埋立てに採用可能な気中埋立て工法に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an air reclamation method which can be used for reclamation of a shallow water area for both water depth and foundation ground where a water stop revetment or temporary cutoff can be constructed.

【0002】[0002]

【従来の技術】海上人工島の建設等に採用されている従
来の埋立て工法は、水中に土砂投棄を行って、一律な地
盤高さまで海面より盛る築島によるものであった。
2. Description of the Related Art The conventional landfill method used for the construction of artificial islands on the sea is based on Tsukishima, which involves dumping earth and sand into the water to a uniform ground level above the sea level.

【0003】[0003]

【発明が解決しようとする課題】このような水中埋立て
工法では次のような課題を有する。 基礎地盤の沈下時間の延長または地盤改良の増加。 水中埋立てに伴う埋立て地盤の強度不足と液状化の
危険性、及び地盤改良の増加。 水中への土砂投棄による水質の汚濁や生態系の破
壊。 不良土埋立てによる埋立地盤の品質低下と早期利用
の困難さ。 築島と建築物の平行作業ができないことによる工期
の延長。 地下施設構築における山止め、再掘削などの手戻り
作業。
The underwater landfill method as described above has the following problems. Extend the settlement time of the foundation ground or increase the ground improvement. Insufficient strength of landfill due to underwater landfill, risk of liquefaction, and increase in ground improvement. Water pollution and ecosystem destruction due to the dumping of sediment into the water. Deterioration of landfill board quality due to bad soil reclamation and difficulty of early use. Extension of the construction period due to the inability to work parallel between Tsukishima and the building. Repair work such as mountain stopping and re-drilling in the construction of underground facilities.

【0004】この発明の目的は、埋立てを土砂の水中投
棄によらず、陸上部と同様な盛土工法の採用により施工
することができ、これにより水中埋立て工法における上
記課題の解決を可能とする新たな気中埋立て工法を提供
することにある。
An object of the present invention is that landfill can be constructed not by dumping earth and sand into water but by adopting the same embankment construction method as that used on land, which makes it possible to solve the above problems in the underwater landfill construction method. To provide a new air reclamation method.

【0005】[0005]

【課題を解決するための手段】上記目的によるこの発明
は、埋立区域の締切りを行い、締切り内の排水を行って
埋立区域の地盤を出現させ、その現地盤の地盤改良を行
ってから締切り内の埋立てを行う、というものである。
According to the present invention for the above object, the landfill area is closed, the drainage within the deadline is performed to make the ground in the landfill area appear, and the ground of the site ground is improved before the deadline is reached. The landfill will be carried out.

【0006】[0006]

【作 用】上記工法では、排水により出現した現地盤に
土砂を転圧しつつ埋め立て可能なため、十分締固められ
た沈下の少ない地盤を造成することができる。また埋立
土の先行加重のため現地盤の圧密沈下促進と支持力向上
が図れることから地盤改良が少なく済む。さらに埋立て
完了後に水を戻すことにより浮力で埋立土の重量が低減
し、圧密沈下量減少と圧密時間短縮が可能となり、埋立
地盤が早期に利用できる。一方埋立土を水中投棄しない
ため埋立区域周辺の水質汚濁も低減するようになる。
[Working] With the above method, since the soil that has emerged from the drainage can be reclaimed while compacting the soil, it is possible to create a well-compacted ground with less subsidence. In addition, since the landfill soil is loaded in advance, it is possible to promote consolidation and settlement of the local soil and improve bearing capacity. Furthermore, by returning water after the landfill is completed, the weight of the landfill soil can be reduced by buoyancy, and the amount of consolidation settlement and the consolidation time can be shortened, and the landfill site can be used early. On the other hand, since the landfill soil is not dumped underwater, water pollution around the landfill area will be reduced.

【0007】[0007]

【実施例】図1から図9は、人工島を埋立てる場合を施
工例として工程順に示すものである。
EXAMPLES FIGS. 1 to 9 show a process sequence of a case where an artificial island is to be reclaimed, in the order of steps.

【0008】護岸部分地盤改良工程(図1) 止水性護岸または仮締切りとその補強の構築が可能な地
形の水域が埋立区域として設定され、その水域の地盤1
の地質が軟弱で護岸部分2の地盤沈下が長期にわたる場
合や、軟弱過ぎて護岸部分2が構築できない場合には、
先ず埋立区域Aの護岸部分2となる水底の地盤改良を行
う。ただし、水域の地盤が良質な場合や長期間の地盤沈
下時間を確保可能な場合には、水底の地盤か改良を省略
することができる。
Revetment Partial Ground Improvement Process (Fig. 1) The water area of the terrain where the water revetment or temporary deadline and its reinforcement can be constructed is set as the landfill area, and the ground 1 of the water area is set.
If the geology of is weak and the ground subsidence of the revetment part 2 is for a long time, or if the revetment part 2 is too soft to build,
First, the ground improvement of the water bottom which becomes the revetment part 2 of the landfill area A is performed. However, if the ground in the water area is of good quality or long-term land subsidence time can be secured, the improvement of the ground at the bottom of the water can be omitted.

【0009】この地盤改良は、作業船3を使用して所要
本数のバーチカルドレーン杭4を一定間隔ごとに打設す
る。地盤改良時には汚濁防止幕5を作業船3から施工中
の杭の周囲水中に張り設けて、舞い上がった土砂による
海水の汚濁を防止する。このバーチカルドレーン杭4の
造成により軟弱層の圧密が促進され、支持力が向上して
護岸部分2の現地盤6の強度が増加する。
In this ground improvement, the work boat 3 is used to drive a required number of vertical drain piles 4 at regular intervals. At the time of ground improvement, the pollution prevention curtain 5 is stretched from the work boat 3 to the surrounding water of the pile under construction to prevent the seawater from being polluted by the rising sand. By constructing the vertical drain pile 4, the consolidation of the soft layer is promoted, the supporting force is improved, and the strength of the field board 6 of the revetment portion 2 is increased.

【0010】締切り矢板打設工程(図2) 護岸部分2となる地盤改良した現地盤6に止水性の鋼矢
板7を一重または二重に打設して、埋立区域Aの外周締
切りを行う。上記鋼矢板7の打設は、沖側に停泊位置さ
せたクレーン付台船8の櫓から鋼矢板7を吊り下ろし、
バイブロハンマーまたは油圧ハンマー9により現地盤6
に打ち込んで行う。
Shutoff sheet pile driving step (FIG. 2) A water-stopping steel sheet pile 7 is struck in a single or double manner on the ground-improved site 6 which becomes the revetment portion 2, and the outer circumference of the landfill area A is shut off. In order to place the steel sheet pile 7, the steel sheet pile 7 is hung from the turret of the crane-equipped barge 8 that is anchored offshore.
Vibro hammer or hydraulic hammer 9
Type in.

【0011】締切り中詰め工程(図3) 二重の鋼矢板で締切り行った場合には、打ち込み完了部
分の内外の鋼矢板7をタイロッド10により一定間隔ご
とに連結したのち、ガット船11で運んできた中詰め土
砂12または捨石を鋼矢板7間に投入し、これにより水
密に締切りを行う。
Deadline filling process (Fig. 3) When the double steel sheet pile is used for shutting, the steel sheet piles 7 inside and outside the portion where the driving is completed are connected by the tie rods 10 at regular intervals and then carried by the gut ship 11. The resulting filled sand 12 or rubble stones are put into the space between the steel sheet piles 7 to make a watertight cutoff.

【0012】締切り補強工程(図4) さらに消波及び締切り安定のため、締切り矢板の沖側に
捨石13を投入し、その上に被覆石,消波ブロックを据
え付けて護岸14となす。場合によっては、内側にも捨
石または土砂で押さえ盛土を行って安定性を確保する。
Closure Reinforcement Step (FIG. 4) In order to further dissipate the waves and stabilize the seizure, a rubble 13 is put on the offshore side of the cut-off sheet pile, and a covering stone and a wave-dissipating block are installed thereon to form a revetment 14. In some cases, rubble stones or earth and sand may be applied to the inside for embankment to ensure stability.

【0013】埋立区域の現地盤不良土改良工程(図5) 締切った埋立区域内の全ての排水を行って地盤1を出現
させ、軟弱層をスタビライザー15等を使用して地盤改
良する。また湧水処理,圧密促進を目的とするディープ
ウイル16を、必要に応じて設置する。
On-site ground soil improvement process in the landfill area (FIG. 5) All the drainage in the closed landfill area is performed to expose the ground 1, and the soft layer is improved by using the stabilizer 15 or the like. In addition, a deep virus 16 for the purpose of treating spring water and promoting consolidation is installed if necessary.

【0014】埋立区域の現地盤改良工程(図6) 軟弱層の厚い場所には圧密沈下,支持力向上を目的に、
バーチカルドレーンなどの地盤改良杭17を杭打機18
により施工する。
On-site board improvement process in the landfill area (Fig. 6) For the purpose of consolidation settlement and improvement of bearing capacity in the thick soft layer,
Ground improvement piles 17 such as vertical drains are piled into the pile driver 18
Install by.

【0015】埋立て工程(図7) 現地盤の改良を完了したのち、土運搬船で運搬してきた
埋立土砂19を揚土船20で締切り内に揚土して埋立て
を行う。この際の埋立土砂は山土のみに限らず不良土を
含む建設発生土でもよく、不良土は良質な砂質土と交互
にサンドイッチ状にブルドーザー21により敷均し、充
分に転圧する。
Landfilling process (FIG. 7) After the improvement of the on-site board is completed, the landfilled sand 19 transported by the soil carrier is unloaded by the hoisting ship 20 into the deadline for landfilling. The landfilled sand at this time is not limited to mountain soil, but may be construction-generated soil containing defective soil, and the defective soil is laid by the bulldozer 21 alternately in a sandwich with high-quality sandy soil and sufficiently compacted.

【0016】施設構築工程(図8) 締切り内の埋立てと同時に人工島関連施設22の構築を
開始する。施設の構築は水底の地盤状況に応じて直接基
礎23または杭基礎24を基本とする。
Facility construction process (FIG. 8) Construction of the artificial island-related facility 22 is started at the same time as the landfill within the deadline. The construction of the facility is based on the direct foundation 23 or the pile foundation 24 depending on the ground condition of the water bottom.

【0017】締切り矢板撤去工程(図9) 埋立てを完了したのち、必要に応じて上記締切り矢板を
撤去する。この撤去後に護岸ブロック25との上部工2
6とを構築する。撤去しない場合には仮締切り矢板上に
護岸ブロックと上部工を構築する。これらの完成をもっ
て埋立ての全工程の完了となる。
Closing Sheet Pile Removal Step (FIG. 9) After the landfill is completed, the cutting sheet pile is removed if necessary. Superstructure with revetment block 25 after this removal 2
Build 6 and. If not removed, a revetment block and superstructure will be built on the temporary cut-off sheet pile. With these completions, all landfill processes will be completed.

【0018】なお、この工法の適用は予定地が水深、基
礎地盤ともに浅い場所であれば同様に行い得るので、こ
の発明は特に島部外周等のの埋立てに制限されるもので
はない。
Since this method can be applied in the same manner if the planned site is shallow in both the water depth and the foundation ground, the present invention is not particularly limited to landfilling of the outer periphery of the island or the like.

【0019】[0019]

【発明の効果】この発明は上述のように、埋立区域の締
切りを行ったのち、締切り内を排水して陸上部と同様な
盛土工法で埋立てを施工できることから、下記効果を奏
する。
As described above, the present invention has the following effects because the landfill area can be closed and then the landfill can be drained and the landfill can be constructed by the same embankment construction method as the land portion.

【0020】・ 締切り内を排水してから転圧して一層
づつ埋立てるため、埋立て地盤の改良が不要で沈下量の
少ない高品質な埋立てができる。従って完成後の維持管
理が少なくなり、また埋立地盤の早期利用が可能とな
る。 ・ 埋立て土砂量が増加する気中埋立てによる先行荷重
のため、現地盤の圧密度が促進され、地盤改良が不要ま
たは少なく済む。 ・ 締切り内を排水してから埋立てを行うので、水中へ
の土砂投棄による場合に比べて水質汚濁が少なくなり、
水質変化による埋立区域周辺の環境や漁業への影響も殆
ど無くなる。 ・ 建設発生土等の不良土の使用が可能となる。また埋
立工と施設構築との同時施工ができるため工事短縮を図
ることができる。 ・ 施設構築のための山留工、二次掘削工が不要にな
り、また施設基礎杭が不要または短く済む。
Since the deadline is drained and then compacted, landfilling is performed one by one, the landfill does not need to be improved and high-quality landfilling with less subsidence can be performed. Therefore, the maintenance work after completion is reduced, and the landfill board can be used early.・ Because of the preceding load due to air reclamation, which increases the amount of landfilled sand, the pressure density of the on-site ground is promoted, and ground improvement is unnecessary or less necessary.・ Since the deadline is drained before landfilling, water pollution is reduced compared to when dumping sand into the water.
The impact on the environment and fisheries around the landfill area due to changes in water quality will almost disappear.・ It is possible to use bad soil such as construction soil. In addition, since land reclamation work and facility construction can be done at the same time, the work can be shortened.・ No need for mountain retaining work and secondary excavation work for facility construction, and no or short facility foundation piles.

【図面の簡単な説明】[Brief description of drawings]

【図1】 この発明の気中埋立て工法における護岸部分
地盤改良工程図である。
FIG. 1 is a process diagram of revetment partial ground improvement in the air reclamation method of the present invention.

【図2】 締切り矢板打設工程図である。FIG. 2 is a process diagram of placing a cutoff sheet pile.

【図3】 締切り中詰め工程図である。FIG. 3 is a deadline filling process diagram.

【図4】 締切り補強工程図である。FIG. 4 is a deadline reinforcement process diagram.

【図5】 埋立区域の現地盤不良土改良工程図である。FIG. 5 is a process diagram for improving the on-site bad soil in the landfill area.

【図6】 埋立区域の現地盤改良工程図である。FIG. 6 is a process diagram for improving the on-site board in the landfill area.

【図7】 埋立て工程図である。FIG. 7 is a landfill process diagram.

【図8】 施設構築工程図である。FIG. 8 is a facility construction process chart.

【図9】 締切り矢板撤去工程図である。FIG. 9 is a process drawing of removing a cutoff sheet pile.

【符号の説明】[Explanation of symbols]

1 埋立区域の地盤 2 護岸部分 4 バーチカルドレーン杭 6 護岸部分の現地盤 7 止水性の鋼矢板 12 中詰め土砂 13 捨て石 14 護岸 17 地盤改良 1 Ground in reclaimed area 2 Revetment part 4 Vertical drain pile 6 Local plate of revetment part 7 Water-stop steel sheet pile 12 Filling sand 13 Discarded stone 14 Revetment 17 Ground improvement

───────────────────────────────────────────────────── フロントページの続き (72)発明者 大西雄二 東京都港区芝浦一丁目2番3号清水建設株 式会社内 (72)発明者 染葉祐一郎 東京都港区芝浦一丁目2番3号清水建設株 式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Yuji Onishi 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Co., Ltd. (72) Inventor Yuichiro Someba 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction stock company

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 埋立区域の締切りを行い、締切り内の排
水を行って埋立区域の地盤を出現させ、その現地盤の地
盤改良を行ってから締切り内の埋立てを行うことを特徴
とする気中埋立て工法。
1. A method for closing a landfill area, draining the landfill area to expose the ground in the landfill area, improving the ground on the site, and then landfilling the landfill area. Medium landfill method.
JP6338821A 1994-12-29 1994-12-29 Method of aerial reclamation construction Pending JPH08184022A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6338821A JPH08184022A (en) 1994-12-29 1994-12-29 Method of aerial reclamation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6338821A JPH08184022A (en) 1994-12-29 1994-12-29 Method of aerial reclamation construction

Publications (1)

Publication Number Publication Date
JPH08184022A true JPH08184022A (en) 1996-07-16

Family

ID=18321769

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6338821A Pending JPH08184022A (en) 1994-12-29 1994-12-29 Method of aerial reclamation construction

Country Status (1)

Country Link
JP (1) JPH08184022A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010137813A3 (en) * 2009-05-26 2011-03-17 O Kwang Sik Method for forming reclaimed land within seawall and construction equipment thereof
CN102168411A (en) * 2010-02-25 2011-08-31 浙江大学 Construction method of rubble mounding for sea-reclamation
CN116043884A (en) * 2022-12-19 2023-05-02 保利长大工程有限公司 Construction method for constructing island by using flexible cofferdam of offshore anchor ingot

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010137813A3 (en) * 2009-05-26 2011-03-17 O Kwang Sik Method for forming reclaimed land within seawall and construction equipment thereof
CN102449239A (en) * 2009-05-26 2012-05-09 吴广植 Method for forming reclaimed land within seawall and construction equipment thereof
CN102168411A (en) * 2010-02-25 2011-08-31 浙江大学 Construction method of rubble mounding for sea-reclamation
CN116043884A (en) * 2022-12-19 2023-05-02 保利长大工程有限公司 Construction method for constructing island by using flexible cofferdam of offshore anchor ingot

Similar Documents

Publication Publication Date Title
Porbaha et al. State of the art in deep mixing technology: part II. Applications
US6139225A (en) Method for building an underground continuous wall
Rasmussen Concrete immersed tunnels—Forty years of experience
JPH08184022A (en) Method of aerial reclamation construction
Troughton The design and performance of foundations for the Canary Wharf development in London Docklands
KR100621410B1 (en) Dry Construction Method of Underwater Structure Using Watertight Caisson
CN111663493A (en) Repairing and reinforcing method suitable for block wharf after foundation damage
EP1004707B1 (en) Process for deepening and/or reinforcing, consolidating or renovating a quay wall constructed along a water basin
Polańska et al. Barriers of Low Permeability to Water–Technical Solutions
JP3579807B2 (en) Method of reducing lateral pressure on underground structures in aerial landfill method
KR20020089691A (en) The construction method of cassion basis using a coagulant
RU2745313C1 (en) Method for reconstruction of the way with pioneer fill with a shear filler
JP2002038465A (en) Excavation, solidification, and replacement method for foundation
JP3510366B2 (en) How to build underwater structures
Degen et al. Offshore Stone Columns-Equipment, Quality Control and Outlook for Future Applications
JP2000248527A (en) Earthquake resistant reinforcing method for existing structure
Bell et al. Control of groundwater by exclusion
JPH1161775A (en) Method for repair and improvement of harbor and river civil engineering structure
Lambrechts What Lurks Below: The Geotechnical Intrigue of Boston’s Back Bay
JPH0376371B2 (en)
JPH10114957A (en) Method of sand boiling-preventive construction in excavation work of shaft, etc.
Feremans et al. HISTORICAL QUAY WALL RENOVATION IN ANTWERP, BELGIUM
CN111997008A (en) Construction method for underwater non-blasting demolition of reserved rock ridge
Bambrick Construction of an Island
Dauncey et al. Chapter 10 Engineering design and construction