JPS61282519A - Horizontal joint placement work of underwater concrete - Google Patents

Horizontal joint placement work of underwater concrete

Info

Publication number
JPS61282519A
JPS61282519A JP12439585A JP12439585A JPS61282519A JP S61282519 A JPS61282519 A JP S61282519A JP 12439585 A JP12439585 A JP 12439585A JP 12439585 A JP12439585 A JP 12439585A JP S61282519 A JPS61282519 A JP S61282519A
Authority
JP
Japan
Prior art keywords
concrete
layer
joint
binders
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP12439585A
Other languages
Japanese (ja)
Other versions
JPH0454765B2 (en
Inventor
Kunijiro Matsushita
松下 邦治郎
Hideo Toyoizumi
豊泉 秀雄
Jinzou Sonoyama
園山 尋三
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP12439585A priority Critical patent/JPS61282519A/en
Publication of JPS61282519A publication Critical patent/JPS61282519A/en
Publication of JPH0454765B2 publication Critical patent/JPH0454765B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

PURPOSE:To strongly form horizontal joints of concrete by a method in which when placed concrete is unhardened, many joint binders are spread and buried, and after the concrete is hardened, the next concrete is driven. CONSTITUTION:Concrete 3 for the first layer is driven on the bottom ground under water. When the concrete 3 is unhardened, many joint binders 4 of a block form are spread unformly from water surface 6 in a cassson 1 and the lower half portions of the binders 4 are buried into the surface layer of the concrete 3. After the concrete 3 is hardened, concrete 5 for the second layer is placed on the concrete 3 and the joint binders 4. The shearing strength of the joint portions of the concretes 3 and 5 can thus be greatly increased by the keying effect of the joint binders 4.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、水中コンクリートの水平打継目を強固に施
工することができる水平打継目施工法に関するものであ
る。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a horizontal pour joint construction method that can firmly construct horizontal pour joints in underwater concrete.

〔従来技術〕[Prior art]

従来、水中コンクリートの水平打継目施工法としては、
(1)水底地盤上に打設された第1層のコンクリートの
表面に沿って潜水作業者かはつシ装置を移動して、その
コンクリートの表面の目荒し処゛理すなわち粗面形成処
理を行ない、次に第1層のコンクリートの上に第2層の
コンクリートを打設する方法、(2)予め組立てた補強
筋を第1層のコンクリートに埋設すると共にその補強筋
を第1層のコンクリートの表面から突出させ、次に第、
1層のコンクリートの上に第2層のコンクリートを打設
する方法、(3)第1層のコンクリートが硬化する前に
、潜水作業者が高圧水噴射装置を第1層のコンクリート
の表面に沿って移動して、そのコンクリートの表面に高
圧水を噴射することによシ粗面を形成し、次に第1層の
コンクリートの上に第2層のコンクリートを打設する方
法等が知られている。
Conventionally, the horizontal pour joint construction method for underwater concrete is as follows:
(1) A diving worker or a hammering device is moved along the surface of the first layer of concrete poured on the underwater ground to roughen the surface of the concrete, that is, to form a rough surface. (2) burying the reinforcing bars assembled in advance in the first layer of concrete, and then placing the reinforcing bars on top of the first layer of concrete; protrude from the surface of the
A method for placing a second layer of concrete on top of the first layer of concrete. (3) Before the first layer of concrete hardens, a diver uses a high-pressure water jet device along the surface of the first layer of concrete. There is a known method in which a rough surface is formed by moving the concrete and spraying high-pressure water onto the surface of the concrete, and then pouring a second layer of concrete on top of the first layer of concrete. There is.

しかし、前記例れの方法の場合も潜水作業を必要とする
ので1作業員の安全性に問題があると共に作業能率が悪
いという問題があり、さらに第1層のコンクリートの表
面に傾斜や不陸があると。
However, in the case of the above-mentioned method, there are problems with the safety of one worker and poor work efficiency as it requires diving work, and furthermore, the surface of the first layer of concrete is sloped and uneven. There is.

前記(1)(3)の方法の場合は、はつシ装置や高圧水
噴射装置の移動作業を行ないにりく、前記(2)の方法
の場合は、第1層のコンクリートの表面の不陸や傾斜を
見込んで、補強筋の高さを太き目に設定したシ、部分的
に変更する必要があるので、不経済または煩雑である。
In the case of methods (1) and (3) above, there is no need to move the removal equipment or high-pressure water injection equipment, and in the case of method (2) above, it is difficult to move the surface of the first layer of concrete. The height of the reinforcing bars is set thick in consideration of the slope and slope, but it is uneconomical and complicated because it is necessary to partially change the height of the reinforcing bars.

また前記(11の方法の場合は、目荒し処理を行なうと
第1層のコンクリートの表面にスライムが堆積するので
、そのスライムを除去する必要があるが、そのスライム
除去作業は煩雑であり、さらに大水深のときは目荒し処
理およびスライム除去作業が困難である。
In addition, in the case of method 11 mentioned above, slime accumulates on the surface of the first layer of concrete when roughening treatment is performed, so it is necessary to remove the slime, but the slime removal work is complicated, and When the water is deep, roughening and slime removal work is difficult.

前記(2)の方法の場合は、多量の鉄筋材を必要とする
ので不経済であると共に、煩雑な鉄筋組立作業を必要と
し、さらに大水深で広い面積の打継ぎに実施すると、施
工能率゛が極めて悪いという問題がある。
In the case of method (2) above, it is uneconomical because it requires a large amount of reinforcing bars, and it also requires complicated reinforcing bar assembly work.Furthermore, when it is applied to connecting large areas in deep water, the construction efficiency decreases. The problem is that it is extremely bad.

また前記(3)の方法の場合は、高王水を硬化前のコン
クリートの表面に噴射すると、粗骨材が弛んで打継ぎ面
が弱化する恐れがある。
In addition, in the case of method (3) above, if high aqua regia is injected onto the surface of concrete before hardening, there is a risk that the coarse aggregate will loosen and the pour joint surface will become weakened.

〔発明の目的、構成〕[Purpose and structure of the invention]

この発明は前述の問題を有利に解決できる水中コンクリ
ートの水平打継目施工法を提供することを目的とするも
のであって、この発明の要旨とするところは、水底地盤
上に第1層のコンクリート3を打設し、その第1層のコ
ンクリート6が未硬化状態のとき、多数の打継目結合材
4を散布して、その打継目結合材4の下半部を前記第1
層のコンクリート6に貫入埋設し、その第、1層のコン
クリート6が硬化したのち、その第1層のコンクリ−ト
ロおよび打継目結合材4の上に第2層のコンクリート5
を打設することを特徴とする水中コンクリート→→→の
水平打継目施工法にある。
The purpose of this invention is to provide a method for constructing horizontal pour joints for underwater concrete that can advantageously solve the above-mentioned problems. 3 is poured, and when the first layer of concrete 6 is in an uncured state, a large number of pouring seam binding materials 4 are sprinkled, and the lower half of the pouring seam binding material 4 is poured into the first layer of concrete 6.
After the first layer of concrete 6 has hardened, a second layer of concrete 5 is placed on top of the first layer of concrete and the joint bonding material 4.
This is a method of horizontally pouring joints for underwater concrete→→→, which is characterized by pouring .

〔実施例〕〔Example〕

次にこの発明を図示の例によって詳細に説明する。 Next, the present invention will be explained in detail using illustrated examples.

図面は大型ケーソンにおける水中底版コンクリートを複
数層に分けて打設する場合の実施例を示すものであって
、まず第1図および第2図に示すように、断面円形また
はほぼ楕円形のコンクリート製大型ケーソン1を、その
ケーソン1の下部が水底地盤2の所定深さに達するまで
沈設すると共に、ケーソン1の上端部を水面6から突出
させ。
The drawing shows an example of pouring concrete for the underwater bottom of a large caisson in multiple layers; A large caisson 1 is sunk until the lower part of the caisson 1 reaches a predetermined depth in the water bottom ground 2, and the upper end of the caisson 1 is made to protrude from the water surface 6.

かつケーソン1内の地盤を掘削して平坦な掘削面7を形
成する。
Then, the ground inside the caisson 1 is excavated to form a flat excavation surface 7.

次に第3図に示すように、ケーソン1の近くにおいて水
底地盤2上に作業足場架台8を設置し、その作業足場架
台8にコンクリートポンプ9を載置し、そのコンクリー
トポンプ9の吐出口にホース10を介して接続されたト
レミー管11を、ケーソン1内に配置してクレーン12
によシ吊下支持し、前記ケーソン1内の掘削面7上に水
中で第1層のコンクリート3を打設する。
Next, as shown in FIG. 3, a working scaffolding frame 8 is installed on the underwater ground 2 near the caisson 1, a concrete pump 9 is placed on the working scaffolding frame 8, and the discharge port of the concrete pump 9 is placed on the working scaffolding frame 8. The tremie pipe 11 connected via the hose 10 is placed inside the caisson 1 and moved to the crane 12.
The first layer of concrete 3 is placed on the excavated surface 7 in the caisson 1 under water.

第1層のコンクリート3の打設が完了したのち、そのコ
ンクリート6が未硬化状態にあるうちに、$4図に示す
ように、粗骨材または比較的小さいコンクリートブロッ
ク等からなる多数の塊状打継目結合材4をケーソン1内
の水面乙の上方から均等に分散して散布し、その打継目
結合材4の下半部(約半分)を前記第1層のコンクリー
ト3の表面側に貫入埋設させる。なお打継目結合材4を
水中の所定高さから散布してもよい。
After the first layer of concrete 3 has been poured, while the concrete 6 is still in an uncured state, a large number of lumps of coarse aggregate or relatively small concrete blocks, etc., are poured as shown in Figure 4. Spread the seam binding material 4 evenly from above the water surface B in the caisson 1, and embed the lower half (approximately half) of the seam binding material 4 into the surface side of the first layer of concrete 3. let Note that the seam binding material 4 may be sprayed from a predetermined height underwater.

次に第1層のコンクリート3が硬化して、前記打継目結
合材4がそのコンクリート3に強固に固定されたのち、
第、5図に示すように、再びトレミー管11をケーソン
1内に配置してクレーン12によシ吊下支持し、前記第
1層のコンクリート6および打継目結合材4の上に第2
層のコンクリート5を打設する。
Next, after the first layer of concrete 3 has hardened and the pour joint binding material 4 has been firmly fixed to the concrete 3,
As shown in FIG. 5, the tremie pipe 11 is placed inside the caisson 1 again, suspended and supported by the crane 12, and a second
Layer concrete 5 is poured.

このようにして第1層のコンクリート6の上に第2層の
コンクリート5を打継ぐと、それらのコンクIJ−) 
3 、5の間に介在された多数の打継目結合材4のキー
効果によって打継目箇所に充分なせん断耐力が確保され
る。
When the second layer of concrete 5 is poured on top of the first layer of concrete 6 in this way, those concrete IJ-)
Sufficient shear strength is ensured at the joint by the key effect of the large number of joint binding materials 4 interposed between the joints 3 and 5.

次にこの発明を実施する場合の打継目結合材4の散布方
法および散布時期の決定法の一例について説明する。
Next, an example of a method of dispersing the seam binding material 4 and a method of determining the time of dispersion when carrying out the present invention will be described.

まず打継目箇所の単位面積当たシの打継目結合材量を事
前に決定し、クラムノ々ケットによシ一定量の打継目結
合材を水面上の所定位置に運び、次に一定の落差を保っ
て打継目結合材を水中の未硬化コンクリートに向かって
散布する。このようにすると1重量、比重9寸法が揃っ
ている打継目結合材は水中を一定速度で落下し、未硬化
コンクリート中にほぼ一定深さまで貫入される。
First, the amount of seam bonding material per unit area of the seam joint is determined in advance, a certain amount of seam bonding material is transported to a predetermined position above the water surface using a clam socket, and then a certain amount of head is Spray the joint binder onto the uncured concrete in the water. In this way, the joint binders, which have a uniform weight of 1 and a specific gravity of 9, fall through the water at a constant speed and penetrate into the uncured concrete to a substantially constant depth.

また打継目結合材の散布の時期は、打設するコンクリー
トの配合によって一異なるので、事前に打継目結合材の
散布時期を決定する必要がある。次にその決定法の例に
ついて説明する。
Furthermore, since the timing of spraying the joint binding material varies depending on the composition of the concrete to be poured, it is necessary to determine the timing of spraying the joint binding material in advance. Next, an example of the determination method will be explained.

まず水底地盤上に打設するコンクリートと同配合のコン
クリートを、水を収容した2つの容器の底部に打設し、
経過時間ごとに次の計測を行なう。
First, concrete of the same mix as the concrete that will be poured on the underwater ground is poured into the bottoms of two containers containing water.
Perform the following measurements at each elapsed time.

(1)一方の容器内の水中に打継目結合材を散布し、そ
の時の貫入深さを計測する。この時、落差を実際の施工
時と等しくするか、またはコンクリートへの着底速度を
施工時の計算で求められる打継目結合材の着底速度と等
しくなるようにする。
(1) Spread the seam binding material into the water in one container and measure the penetration depth at that time. At this time, either the head is made equal to that during actual construction, or the speed at which the concrete sinks to the bottom is made equal to the speed at which the joint bonding material sinks to the bottom calculated during construction.

(2)他方の容器のコンクリートについては、公知のブ
ロクター貫入試験を実施する。
(2) For the concrete in the other container, conduct a known broctor penetration test.

前記(1) (2)の計測値から、ゾロフタ−貫入抵抗
値に対する打継目結合材の貫入量を知ることができる。
From the measured values in (1) and (2) above, it is possible to know the amount of penetration of the seam bonding material relative to the Zolofter penetration resistance value.

したがって、施工時には、打設するコンクリートを容器
に採取して、ゾロフタ−貫入抵抗値を適時計測し、所定
貫入深さが得られる打継目結合材の散布時期を決定する
Therefore, during construction, the concrete to be poured is collected in a container, the Zolofter penetration resistance value is measured at appropriate times, and the timing of spraying the joint bonding material to obtain a predetermined penetration depth is determined.

なお前記(1)および(2)の計測法のうち、−何れか
一方のみを行なって打継目結合材の散布時期を決定して
もよい。
Incidentally, of the measurement methods (1) and (2) above, only one of - may be performed to determine the timing of spraying the seam binding material.

前記実施例はこの発明を第1層のコンクリート6と第2
層のコンクリート5との打継目部に実施した例であるが
、この発明は3層以上のコンクリートの打継目部にも同
様にして実施することができる。またこの発明は護岸の
ための水中コンクリートの打設にも実施することができ
る。
The above embodiments demonstrate that the present invention can be applied to the first layer of concrete 6 and the second layer of concrete.
Although this is an example in which the present invention is applied to a joint between concrete layers 5 and 5, the present invention can be similarly applied to a joint between three or more layers of concrete. Furthermore, the present invention can also be applied to pouring underwater concrete for seawalls.

ケーソン内で打継目結合材を散布する場合は、散布する
部分の全周がケーソンの側壁により囲まれているので、
海域の水流の影響を受けることなく打継目結合材を均一
に散布することができるが、水流の速い場所で打継目結
合材を散布する場合は、水上から水流の影響が少ない深
さまで延長するホラノミ付き鋼管等のガイド管を使用し
、打継目結合材を前記ホラノミ内に投入してガイド管を
経て散布すればよい。
When spraying seam bonding material inside a caisson, the entire circumference of the area to be sprayed is surrounded by the side walls of the caisson, so
It is possible to uniformly spread the seam binding material without being affected by water currents in the sea, but when spraying seam binding material in areas with fast water currents, use a hollow chisel that extends from above the water to a depth where it is less affected by water currents. Using a guide pipe such as a steel pipe with a steel pipe, the joint binding material may be introduced into the hollow chisel and dispersed through the guide pipe.

〔発明の効果〕〔Effect of the invention〕

この発明によれば、水底地盤上に第1層のコンクリート
6を打設し、その第1層のコンクリート6が未硬化状朝
のとき、多数の打継目結合材4を散布して、その打継目
結合材4の下半部を前記第1層のコンクリート乙に貫入
埋設し、その第1層のコンクリート3が硬化したのち、
その第1層のコンクリート3および打継目結合材4の上
に第2層のコンクリート5を打設するので、前記第1層
のコンクリート3および第2層のコンクリート5・の双
方にわたって貫入埋設された多数の打継目結合材4のキ
ー効果によって、第1層のコンクIJ 。
According to this invention, when the first layer of concrete 6 is poured on the underwater ground and the first layer of concrete 6 is still unhardened, a large number of pouring joint binders 4 are sprinkled on the concrete 6, The lower half of the joint binding material 4 is penetrated and buried in the first layer of concrete B, and after the first layer of concrete 3 has hardened,
Since the second layer of concrete 5 is placed on top of the first layer of concrete 3 and the pour joint bonding material 4, the concrete 5 of the first layer is penetrated and buried over both the first layer of concrete 3 and the second layer of concrete 5. Due to the key effect of the large number of joints 4, the first layer of conc IJ.

ト3と第2層のコンクリート5との打継目箇所のせん断
耐力を著しく強化することができ、かつ水面の上方ま念
は水中の所定高さから打継目結合材4を第1層のコンク
リニド乙の上面に散布するだけでよいので、大水深の打
継目施工においても。
It is possible to significantly strengthen the shear strength at the joint between the concrete 5 of the first layer and the concrete 5 of the first layer. You only need to spray it on the top surface, so it can be used for construction of joints in deep water.

施工能率が良くかつ経済的であると共に、潜水作業を必
要としないので安全であシ、さらに第1層のコンクリー
ト3の表面に不陸や傾斜がある場合でも容易に施工する
ことができる。また施工能率が良いので工期を短縮する
ことができ、特に打継ぎ面が広い場合あるいは打継ぎ層
数が多い場合に有利であシ、さらに水平打継目部の処理
に特別な設備を必要としないので施工費を安くする。こ
とができる等の効果が得られる。
It is efficient and economical in construction, is safe as it does not require diving work, and can be easily constructed even when the surface of the first layer of concrete 3 is uneven or sloped. In addition, the construction efficiency is high, so the construction period can be shortened, which is especially advantageous when the splicing surface is wide or there are many spliced layers.Furthermore, special equipment is not required for processing horizontal splicing joints. This reduces construction costs. Effects such as being able to do this can be obtained.

【図面の簡単な説明】[Brief explanation of drawings]

図面はこの発明の一実施例を示すものであって。 第1図はケーソンを水底地盤に沈設した状態を示す縦断
側面図、第2図はケーソンの平面図、第3図はケーソン
内の掘削面上に第1層のコンクリートを打設している状
態を示す縦断側面図、第4図は第1層のコンクリートの
表面部に打継目結合材の下半部を貫入埋設した状態を示
す縦断側面図。 第5図は第1層のコンクリートおよび打継目結合材の上
に第2層のコンクリートを打設している状態を示す縦断
側面図である。 図において、1はケーソン、2は水底地盤、6は第1層
のコンクリート、4は打継目結合材、5は第2層のコン
クリート、8は作業足場架台、9はコンクリートポンプ
、10はホース、11はトレミー管、12はクレーンで
ある。 第1図 第2図
The drawings show one embodiment of the invention. Figure 1 is a vertical cross-sectional side view showing the caisson sunk into the underwater ground, Figure 2 is a plan view of the caisson, and Figure 3 is the state in which the first layer of concrete is placed on the excavated surface of the caisson. FIG. 4 is a vertical side view showing a state in which the lower half of the joint bonding material has been penetrated and buried in the surface of the first layer of concrete. FIG. 5 is a longitudinal sectional side view showing a state in which a second layer of concrete is placed on the first layer of concrete and pour joint binding material. In the figure, 1 is the caisson, 2 is the underwater ground, 6 is the first layer of concrete, 4 is the joint bonding material, 5 is the second layer of concrete, 8 is the work scaffolding frame, 9 is the concrete pump, 10 is the hose, 11 is a tremie tube, and 12 is a crane. Figure 1 Figure 2

Claims (1)

【特許請求の範囲】[Claims] 水底地盤上に第1層のコンクリート3を打設し、その第
1層のコンクリート3が未硬化状態のとき、多数の打継
目結合材4を散布して、その打継目結合材4の下半部を
前記第1層のコンクリート3に貫入埋設し、その第1層
のコンクリート3が硬化したのち、その第1層のコンク
リート3および打継目結合材4の上に第2層のコンクリ
ート5を打設することを特徴とする水中コンクリートの
水平打継目施工法。
When the first layer of concrete 3 is cast on the underwater ground and the first layer of concrete 3 is in an uncured state, a large number of pour joint binders 4 are sprinkled on the lower half of the pour seam binders 4. After the first layer of concrete 3 has hardened, a second layer of concrete 5 is poured on top of the first layer of concrete 3 and pour joint binding material 4. A horizontal pour joint construction method for underwater concrete.
JP12439585A 1985-06-10 1985-06-10 Horizontal joint placement work of underwater concrete Granted JPS61282519A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12439585A JPS61282519A (en) 1985-06-10 1985-06-10 Horizontal joint placement work of underwater concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12439585A JPS61282519A (en) 1985-06-10 1985-06-10 Horizontal joint placement work of underwater concrete

Publications (2)

Publication Number Publication Date
JPS61282519A true JPS61282519A (en) 1986-12-12
JPH0454765B2 JPH0454765B2 (en) 1992-09-01

Family

ID=14884365

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12439585A Granted JPS61282519A (en) 1985-06-10 1985-06-10 Horizontal joint placement work of underwater concrete

Country Status (1)

Country Link
JP (1) JPS61282519A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6462517A (en) * 1987-09-01 1989-03-09 Morinaga Gumi Kk Continuous placement of concrete underwater

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6462517A (en) * 1987-09-01 1989-03-09 Morinaga Gumi Kk Continuous placement of concrete underwater

Also Published As

Publication number Publication date
JPH0454765B2 (en) 1992-09-01

Similar Documents

Publication Publication Date Title
CN107447765A (en) Side slope construction supported with framed anchor construction
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN108330902B (en) Construction method for cast-in-situ lower cross beam of high-pile wharf
CN107268634A (en) Deep basal pit waist rail construction typified form system
CN203924116U (en) Portable side wall formwork jumbo
CN109648696A (en) Side slope precast lattice beam of reinforcing bar connection and preparation method thereof and construction method
Rajapakse Construction engineering design calculations and rules of thumb
CN107905609A (en) Underground people's air defense construction method
CN105332386B (en) Structure construction method for tower crane foundation serving as basement bottom plate
CN108118689B (en) Prefabricated underground diaphragm wall capable of being partially recycled, lifting appliance and construction method
CN209669857U (en) A kind of variable diameters steel reinforcement cage enlarged footing anchor pole anti-floating or pressure bearing pile
JPS61282519A (en) Horizontal joint placement work of underwater concrete
CN108221955B (en) Prefabricated underground diaphragm wall capable of being recycled integrally, lifting appliance and construction method
CN110258600A (en) A kind of vertical cofferdam construction engineering method suitable for deep water waters
CN110468729A (en) A kind of frame bridge construction method
CN110453592A (en) A kind of bearing platform construction process within the scope of prefabricated stand column
CN206753488U (en) A kind of artificial digging pile reaming auxiliary equipment
CN102535493B (en) Method for constructing inverted type foundation beam
JP3676441B2 (en) Pit and construction method of basement using it
JPS6354093B2 (en)
JPH0833002B2 (en) Construction method of large block made of concrete
CN207062956U (en) A kind of deep basal pit waist rail construction typified form system
CN114045742B (en) Construction method of bridge abutment of large-span inverted siphon pipe bridge
JPH011828A (en) Top-shaped block for ground stabilization and its installation method
JP3752238B2 (en) Structure construction method and structure