JPS6095103U - extraction turbine plant - Google Patents

extraction turbine plant

Info

Publication number
JPS6095103U
JPS6095103U JP18580783U JP18580783U JPS6095103U JP S6095103 U JPS6095103 U JP S6095103U JP 18580783 U JP18580783 U JP 18580783U JP 18580783 U JP18580783 U JP 18580783U JP S6095103 U JPS6095103 U JP S6095103U
Authority
JP
Japan
Prior art keywords
bleed
pipe
air
pressure
turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP18580783U
Other languages
Japanese (ja)
Inventor
北沢 守一
Original Assignee
株式会社東芝
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社東芝 filed Critical 株式会社東芝
Priority to JP18580783U priority Critical patent/JPS6095103U/en
Publication of JPS6095103U publication Critical patent/JPS6095103U/en
Pending legal-status Critical Current

Links

Landscapes

  • Control Of Turbines (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【図面の簡単な説明】[Brief explanation of the drawing]

、 第1図は従来の抽気タービンの全体構成を示す系統
図、第2図は本考案に係る抽気タービンの一実施例によ
る全体構成を示す系統図、第3図は本考案に係る抽気タ
ービンの他の実施例による全体構成を示す系統図、第4
図は本考案に係る抽気タービンのさらに他の実施例によ
る全体構成を示す   5系統図である。′ 1.20・・・ボイラ、2,21・・・高中圧タービン
、3.25・・・4’t、4.27・・・低圧タービン
、5.26・・・第1抽気管、6,45・・・造水プラ
ント、7,28・・・集合ヘッダ、8,44・・・第2
抽気管、9,38・・・抽気加減弁、10・・・設定器
、11・・・加算器、12.39・・・信号増幅器、2
2・・・主蒸気管、23・・・高温再熱管、29・・・
発電機、4o・・・比較器、41・・・ヘッダ圧力検出
器、42・・・信号機、43・・・ヘッダ圧設定器、4
4・・・第2抽気管、  −45・・・造水プラント。
, Figure 1 is a system diagram showing the overall configuration of a conventional extraction turbine, Figure 2 is a system diagram showing the overall configuration of an embodiment of the extraction turbine according to the present invention, and Figure 3 is a system diagram showing the overall configuration of an extraction turbine according to the present invention. System diagram showing the overall configuration according to another embodiment, No. 4
The figure is a five-system diagram showing the overall configuration of still another embodiment of the extraction turbine according to the present invention. '1.20...Boiler, 2,21...High and intermediate pressure turbine, 3.25...4't, 4.27...Low pressure turbine, 5.26...First extraction pipe, 6 , 45... Water desalination plant, 7, 28... Collective header, 8, 44... Second
Bleed pipe, 9, 38... Bleed control valve, 10... Setting device, 11... Adder, 12.39... Signal amplifier, 2
2... Main steam pipe, 23... High temperature reheat pipe, 29...
Generator, 4o...Comparator, 41...Header pressure detector, 42...Signal, 43...Header pressure setting device, 4
4...Second air bleed pipe, -45...Water production plant.

Claims (1)

【実用新案登録請求の範囲】 1 タービン段落群の途中で開口する抽気管により抽気
された抽気量を抽気加減弁により制御して抽気圧を調圧
し、この調圧された油気を上記抽気管を介して工業プラ
ントへ供給する抽気タービンプラントにおいて、上記抽
気管の工業プラント側に抽気圧を検出する圧力検出器を
設け、この圧力検出器にて検出された工業プラント側の
抽気圧に応じて上記抽気加減弁の開度を適宜制御して抽
気圧を調圧し、工業プラントの需要量に対応した抽気量
を工業プラントへ供給するようにしたことを特徴とする
抽気タービンプラント。 2 抽気管は、ボイラで発生した蒸気を高中圧タービン
へ案内する主蒸気管に連結管を介して接続され、この連
結管に蒸気流量を制御する調整弁が介装されると共に、
上記連結管との接続箇所より上流側の抽気管に逆止弁を
介装し、ボイラで発生した主蒸気の一部を上記抽気管を
介して工業プラント側へ供給するようにした実用新案登
録請求の範囲第1項に記載の抽気タービンプラント。 3 抽気管は、ボイラで再熱された蒸気を高中圧タービ
ンへ案内する高温再熱管に接続管を介して接続され、こ
の接続管に蒸気流量を制御する調整弁が介装されると共
に、上記接続管との接続箇所より上流側の抽気管”に逆
止弁を介装し、ボイラで再熱された再熱蒸気の一部を上
記抽気管を介して工業プラント側へ供給するようにした
実用新案登録請求の範囲第1項に記載の抽気タービンプ
ラント。 4 圧力検出器は、抽気管の工業プラント側に接  、
続されて複数の工業プラントへ抽気を分配する集合ヘッ
ダに設置された実用新案登録請求の範囲第1項に記載の
抽気タービンプラント。 5 主蒸気管は途中分岐して高中圧タービンを迂   
・回し、この高中圧タービンより排出される蒸気をボイ
ラへ還流させる低温再熱管の途中に接続された高圧バイ
パス管を有し、この高圧バイパス管の途中に蒸気流量を
制御する高圧バイパス弁を介装した実用新案登録請求の
範囲第2項に記載の抽気タービンプラント。
[Claims for Utility Model Registration] 1. The amount of air extracted by an air bleed pipe opened in the middle of a turbine stage group is controlled by an air bleed adjustment valve to regulate the extraction pressure, and the regulated oil is sent to the air bleed pipe. In a bleed turbine plant that supplies air to an industrial plant via a bleed pipe, a pressure detector is installed on the industrial plant side of the bleed pipe to detect the bleed pressure, and the pressure is adjusted according to the bleed pressure detected by this pressure detector on the industrial plant side. A bleed air turbine plant characterized in that the bleed air pressure is regulated by appropriately controlling the opening degree of the bleed air regulating valve, and an amount of bleed air corresponding to the amount demanded by the industrial plant is supplied to the industrial plant. 2. The bleed pipe is connected via a connecting pipe to the main steam pipe that guides the steam generated in the boiler to the high-intermediate pressure turbine, and this connecting pipe is equipped with a regulating valve that controls the steam flow rate.
Registration of a utility model in which a check valve is installed in the bleed pipe upstream from the point where it connects with the connecting pipe, and a part of the main steam generated in the boiler is supplied to the industrial plant through the bleed pipe. An extraction turbine plant according to claim 1. 3. The bleed pipe is connected via a connecting pipe to a high temperature reheat pipe that guides the steam reheated in the boiler to the high and intermediate pressure turbine, and this connecting pipe is equipped with a regulating valve that controls the steam flow rate, and the above-mentioned A check valve was installed in the bleed pipe upstream from the connection point with the connecting pipe, and a portion of the reheated steam reheated by the boiler was supplied to the industrial plant through the bleed pipe. The bleed air turbine plant according to claim 1 of the utility model registration claim. 4. The pressure detector is connected to the industrial plant side of the bleed pipe,
The bleed air turbine plant according to claim 1, which is installed in a collection header that is connected to a plurality of industrial plants and distributes bleed air to a plurality of industrial plants. 5 The main steam pipe is branched midway to bypass the high and intermediate pressure turbine.
- A high-pressure bypass pipe is connected to the middle of the low-temperature reheat pipe that returns the steam discharged from the high- and intermediate-pressure turbine to the boiler. The extraction turbine plant according to claim 2 of the utility model registration claim.
JP18580783U 1983-12-02 1983-12-02 extraction turbine plant Pending JPS6095103U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18580783U JPS6095103U (en) 1983-12-02 1983-12-02 extraction turbine plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18580783U JPS6095103U (en) 1983-12-02 1983-12-02 extraction turbine plant

Publications (1)

Publication Number Publication Date
JPS6095103U true JPS6095103U (en) 1985-06-28

Family

ID=30401512

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18580783U Pending JPS6095103U (en) 1983-12-02 1983-12-02 extraction turbine plant

Country Status (1)

Country Link
JP (1) JPS6095103U (en)

Similar Documents

Publication Publication Date Title
US6134891A (en) Method and device for quick power regulation of a power station system
US4870823A (en) Low load operation of steam turbines
JPS6095103U (en) extraction turbine plant
GB994766A (en) Improvements in and relating to steam power plant
US4862692A (en) Supercritical pressure once-through boiler
GB946406A (en) Improvements in or relating to steam power installations including forced-flow, once-through boilers
CA1227985A (en) Method of and apparatus for controlling steam vent volume of moisture separator reheaters
US3175541A (en) Automatic feedwater control system and method of operating same
JPS6062604A (en) Reheater heating steam system of power generating plant
JPH04252807A (en) Steam turbine power generation plant
JPH0454204A (en) Control device for gas-extraction and condensation type turbine
JP2504939Y2 (en) Boiler level controller
JPS5847203Y2 (en) Steam turbine rotor cooling system
JP2863645B2 (en) Feedwater flow control system for an exhaust gas reburning combined cycle power plant
JPS60108509A (en) Steam turbine protecting device in combined cycle plant
JPS591805U (en) Reheat turbine bypass device
JPS60152004U (en) Turbine bypass temperature reduction control device
JPS59217403A (en) Method of controlling flow rate of condensation
GB851754A (en) Improvements in heat generating and utilising plants
JPS5944506B2 (en) Geothermal steam turbine control device
JPS5991403U (en) Steam turbine control device
JPS6069218A (en) Turbine bypass system
JPH01187304A (en) Steam turbine control device
JPS6288111U (en)
JPS59144309U (en) steam desuperheater