JPS60126429A - Installing method of caisson - Google Patents

Installing method of caisson

Info

Publication number
JPS60126429A
JPS60126429A JP23332483A JP23332483A JPS60126429A JP S60126429 A JPS60126429 A JP S60126429A JP 23332483 A JP23332483 A JP 23332483A JP 23332483 A JP23332483 A JP 23332483A JP S60126429 A JPS60126429 A JP S60126429A
Authority
JP
Japan
Prior art keywords
caisson
weight
water
cell
weight cell
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP23332483A
Other languages
Japanese (ja)
Other versions
JPS6143494B2 (en
Inventor
Kenro Tomonaga
朝長 賢郎
Haruo Yamamoto
山本 治生
Toshiyuki Toba
鳥羽 俊行
Kiyomi Aikawa
清実 相河
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP23332483A priority Critical patent/JPS60126429A/en
Publication of JPS60126429A publication Critical patent/JPS60126429A/en
Publication of JPS6143494B2 publication Critical patent/JPS6143494B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)

Abstract

PURPOSE:To ensure weight which is capable of resisting against an external force produced during installation and to stabilize a caisson during installation, by a method wherein weight cells are temporarily placed on the sunk caisson, and sea water is poured in the tank part of the weight cell. CONSTITUTION:A caisson 1 is installed in a position as water is poured in chambers 5 in the caisson 1, weight cells 2 are placed on the caisson 1, water is poured into a tank part 4 of the weight cell 2, and weight, which is capable of resisting against an external force produced during installation. Sand is charged in a chamber 6 in the caisson 1 through a through-hole 3 in the weight cell 2, and after filling sand is charged, water in the weight cells 2 is drained. After drainage is completed, the weight cells 2 is transported to other caisson, which is intended to be installed, with the aid of a crane ship.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は護岸工、防波機工等のケーソンを用いた海洋
構造物の施工におけるケーソンの据付は工法、特にケー
ソン工事において問題となるケーソン据付は直後の安定
性確保ζこ関するものである。
[Detailed Description of the Invention] [Field of Industrial Application] This invention relates to a method for installing caisson in the construction of offshore structures using caisson such as seawall construction and breakwater construction, especially caisson installation which is a problem in caisson construction. This is related to ensuring stability immediately after.

〔発明の背景および目的〕[Background and purpose of the invention]

ケーソンを用いた海洋構造物の施工において、ケーソン
を所定の位置に沈設した直後の状態は、風、波浪などの
外力が作用するため非常に不安定である。
In the construction of offshore structures using caisson, the state immediately after the caisson is sunk in a predetermined position is extremely unstable due to the action of external forces such as wind and waves.

このため従来の技術では中詰砂の充填を急速に行なうこ
とにより、ケーソン自体の重量を増加させ、この重量に
よる摩擦力で外力に抵抗させることが行なわれている。
For this reason, in the prior art, the weight of the caisson itself is increased by rapidly filling the caisson with sand, and the frictional force generated by this weight is used to resist external forces.

しかし、中詰砂の充填については規模が大きくなればな
る程、砂の量が多くなり、急速に充填することが難しく
なる。
However, when it comes to filling with sand, the larger the scale, the larger the amount of sand, and the more difficult it becomes to fill it quickly.

そこで、この発明では沈設したケーソン上にウェイトセ
ルを仮置し、この中に海水等の水を注入することによっ
て所要重量を確保し、施工時の安定を図っている。
Therefore, in this invention, a weight cell is temporarily placed on top of the sunken caisson, and water such as seawater is injected into the cell to ensure the required weight and to ensure stability during construction.

〔発明の構成〕[Structure of the invention]

この発明において使用するウェイトセルはりンク部と貫
通孔とを有するもので、鋼、コンクリートまたは合成樹
脂等を用いて製作することができる。なお、このウェイ
トセルはケーソンの各室の平面形状に合わせて製作し、
複数個を連結して一体化して使用することもできる。
The weight cell used in this invention has a link portion and a through hole, and can be manufactured using steel, concrete, synthetic resin, or the like. In addition, this weight cell is manufactured according to the planar shape of each chamber of the caisson.
It is also possible to connect a plurality of pieces and use them as one unit.

施工においては所定位置に沈設したケーソン上に上述の
ウェイトセルを載置し、ウェイトセルのタンク部に海水
等の水を注入してウェイトセル部分の電縫を確保し、こ
の重量で外力に抵抗させる。このようにして初期の段階
でケーソンを安定させ、安定させた状態で中詰砂等正こ
よるケーソンの中詰めを行なう。このケーソンの中詰め
および必要な水抜きは上述したウェイトセルの貫通孔を
通して行なう。中詰めが完了したらウェイトセルは不要
となり、内部に注入した水を排出し、次のケーソン据付
のために移動させる。
During construction, the above-mentioned weight cell is placed on top of a caisson that has been sunk in a predetermined position, and water such as seawater is injected into the tank of the weight cell to secure the electric resistance welding of the weight cell, and this weight is used to resist external forces. let In this way, the caisson is stabilized at an early stage, and in a stable state, the caisson is filled with filling sand or the like. Filling of the caisson and necessary water drainage are carried out through the through holes of the weight cells mentioned above. Once the filling is complete, the weight cell will no longer be needed, and the water injected into it will be drained and moved for the next caisson installation.

〔実施例〕〔Example〕

次に図示した実施例について説明する。 Next, the illustrated embodiment will be described.

第1図、第5図、および第6図は据付は予定0)’T−
ソ71上に多数のウェイトセル2を載置した状態を示し
たものである。ウェイトセル2はケーソン1の各室の平
面形状に合わせて製作してあり、各ウェイトセル2の上
部間をボルトで結合するなどして一体となる。
Figures 1, 5, and 6 are scheduled for installation.
This figure shows a state in which a large number of weight cells 2 are placed on a saw 71. The weight cells 2 are manufactured to match the planar shape of each chamber of the caisson 1, and are integrated by connecting the upper portions of each weight cell 2 with bolts.

第2図、第7図、および第8図はウェイトセル2の一例
を示したもので、貫通孔3とその回りのタンク部4とか
らなっている。貫通孔3は円形または矩形であり、ケー
ソン1の内部の水抜き及び中詰砂の投入に使用する。な
お、第7図および第8図に示した実施例ではウェイトセ
ル2を骨組となる形鋼と鋼板で製作し、貫通孔5部分に
は鋼管を用いている。
FIG. 2, FIG. 7, and FIG. 8 show an example of the weight cell 2, which consists of a through hole 3 and a tank portion 4 around it. The through hole 3 is circular or rectangular and is used for draining water from the inside of the caisson 1 and for filling with sand. In the embodiments shown in FIGS. 7 and 8, the weight cell 2 is made of a shaped steel frame and a steel plate, and the through hole 5 is made of a steel pipe.

第5図および第4図は施工の様子を示したもので、−第
3図はクレーン船でケーソン1上に複数個一体化したウ
ェイトセル2を載置するところ、第4図はウェイトセル
2の貫通孔3を通してケーソン1内に中詰砂を充填して
いるところである。
Figures 5 and 4 show the construction process, - Figure 3 shows a crane ship loading a plurality of integrated weight cells 2 onto the caisson 1, and Figure 4 shows the weight cells 2. Filling sand is being filled into the caisson 1 through the through hole 3.

施工手順は次のようになる。The construction procedure is as follows.

■ 製作ヤードで完成されたケーソン1を所定の位置に
注水しながら据え付ける。
■ Install caisson 1, which was completed in the fabrication yard, in the designated position while pouring water into it.

■ 次ζこ据え付けたケーソン1上にウェイトセル2を
クレーン船で設置する。
■ Next, use a crane ship to install weight cell 2 on top of caisson 1.

■ ウェイトセル2のタンク部4に海水を注水し、施工
時の外力に抵抗できる重量を確保する。
■ Fill the tank part 4 of the weight cell 2 with seawater to ensure a weight that can resist external forces during construction.

■ 貫通孔3からケーソン1の内部に砂を投入する。■ Inject sand into the caisson 1 through the through hole 3.

■ 中詰砂投入完了後、ウェイトセル2内の水を排水す
る。
■ After filling in the sand, drain the water in the weight cell 2.

■ 排水完了後、任意の時期にクレーン船でウェイトセ
ル2を他の設置予定ケーソンに運搬する。
■ After the drainage is completed, weight cell 2 will be transported to another caisson to be installed using a crane ship at any time.

〔発明の効果〕〔Effect of the invention〕

この発明のケーソンの据付は工法は上述の構成からなり
、次のような利点、特徴を有する。
The caisson installation method of the present invention has the above-mentioned configuration and has the following advantages and features.

■ ウェイトセルの移動、据付けと海水の注排水で構成
される単純な作業からなり、ケーン゛ ン施工時の安定
確保が短時間でなされる。
■ It consists of simple work consisting of moving and installing the weight cell and pouring seawater in and out, ensuring stability during cane construction in a short time.

■ 従って、従来ネックとなっていた中詰砂充填の施ニ
スピードの緩和が可能である。
■ Therefore, it is possible to reduce the sand filling speed, which has been a problem in the past.

■ また、材料費としてはウェイトセル以外は海水を利
用するため安価である。
■ Also, material costs are low because seawater is used for everything except the weight cell.

■ ウェイトセルは繰り返し使用でき経済的である。■ Weight cells can be used repeatedly and are economical.

【図面の簡単な説明】[Brief explanation of drawings]

図面はこの発明の実施例を示したもので、第1図はケー
ソン上にウェイトセルを載置した状態を示す斜視図、第
2図はウェイトセルの斜視図、第3図および第4図は施
工の様子を示す正面図、第5図はケーソン上にウェイト
セルを載置した状態を示す平面図、第6図は同じく正面
図、第7図はウェイトセルの平面図(右半分は横断面図
)、第8図は第7図のI−1[4図である。 1・・ケーソン、2・・ウェイトセル、5・・貫通孔、
4・・タンク部、5・・室。 第1図 第2図 第3図 第5図 2 ・ 回置−・ 開園田園 ・ ・ 回向−′ ・−回回回 ・ 2 i、’j 1 第4図
The drawings show an embodiment of the present invention; FIG. 1 is a perspective view showing a weight cell placed on a caisson, FIG. 2 is a perspective view of the weight cell, and FIGS. Fig. 5 is a front view showing the construction process, Fig. 5 is a plan view showing the weight cell placed on the caisson, Fig. 6 is the same front view, and Fig. 7 is a plan view of the weight cell (the right half is a cross section). Figure), Figure 8 is Figure I-1 [4 of Figure 7]. 1. Caisson, 2. Weight cell, 5. Through hole,
4. Tank section, 5. Room. 1 2 3

Claims (2)

【特許請求の範囲】[Claims] (1)所定位置に沈設したケーソン上にタンク部と貫通
孔とを有するウェイトセルを載置し、該ウェイトセルの
タンク部に水を注入してウェイトセル部分の重量を確保
し、前記貫通孔からケーソン内部に中詰めを行なった後
、ウェイトセル内の水を排出してウェイトセルを移動す
ることを特徴とするケーソンの据付は工法。
(1) A weight cell having a tank part and a through hole is placed on a caisson sunk in a predetermined position, water is injected into the tank part of the weight cell to secure the weight of the weight cell part, and the through hole is The caisson installation method is characterized by filling the inside of the caisson with water, then draining the water inside the weight cell and moving the weight cell.
(2) ウェイトセルは鋼製、コンクリート製または合
成樹脂製である特許請求の範囲第1項記載のケーソンの
据付は工法。
(2) The caisson installation according to claim 1 is a construction method in which the weight cell is made of steel, concrete, or synthetic resin.
JP23332483A 1983-12-09 1983-12-09 Installing method of caisson Granted JPS60126429A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23332483A JPS60126429A (en) 1983-12-09 1983-12-09 Installing method of caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23332483A JPS60126429A (en) 1983-12-09 1983-12-09 Installing method of caisson

Publications (2)

Publication Number Publication Date
JPS60126429A true JPS60126429A (en) 1985-07-05
JPS6143494B2 JPS6143494B2 (en) 1986-09-27

Family

ID=16953352

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23332483A Granted JPS60126429A (en) 1983-12-09 1983-12-09 Installing method of caisson

Country Status (1)

Country Link
JP (1) JPS60126429A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528551A (en) * 2019-08-08 2019-12-03 中交第二航务工程局有限公司 The W-shaped excavation sinking construction method of open caisson
CN110644517A (en) * 2019-08-29 2020-01-03 中交第二航务工程局有限公司 Open caisson bulkhead partition integrated excavation adjusting method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110528551A (en) * 2019-08-08 2019-12-03 中交第二航务工程局有限公司 The W-shaped excavation sinking construction method of open caisson
CN110644517A (en) * 2019-08-29 2020-01-03 中交第二航务工程局有限公司 Open caisson bulkhead partition integrated excavation adjusting method

Also Published As

Publication number Publication date
JPS6143494B2 (en) 1986-09-27

Similar Documents

Publication Publication Date Title
JPS60126429A (en) Installing method of caisson
JPS61216915A (en) Construction of breakwater structure
JPS60215924A (en) Settlement of steel skeleton for underwater foundation structure
CA1205642A (en) Marine structure constructing method
JPH039252B2 (en)
JPH1046597A (en) Execution work method of steel shell caisson
JP3132846B2 (en) Construction method of pile type offshore structure
JPH1171718A (en) Method for reinforcing construction of underwater part of existing bridge pier
JP2576891B2 (en) Girder block with wing and its breakwater construction method
JPS55119812A (en) Filling method of precast embankment
JPS6128625A (en) Construction of marine concrete structure on sea
JPH056602B2 (en)
JP3808552B2 (en) Form for constructing underwater caisson, underwater caisson and construction method thereof
JPH027959Y2 (en)
JPS62202125A (en) Underwater foundation work using steel plate shell
JP2815470B2 (en) Buoyancy-adjustable movable support construction method
JPH0336367B2 (en)
JPH0258631A (en) Execution of caisson
JPH0588326B2 (en)
JPS6260544B2 (en)
JPH0423686B2 (en)
JPS60159224A (en) Method of installing caisson
JPH0489917A (en) Executing method for rubble mound
JPS58138832A (en) Caisson levee and construction thereof
JPH03110218A (en) Installation of caisson