JP2815470B2 - Buoyancy-adjustable movable support construction method - Google Patents

Buoyancy-adjustable movable support construction method

Info

Publication number
JP2815470B2
JP2815470B2 JP21522590A JP21522590A JP2815470B2 JP 2815470 B2 JP2815470 B2 JP 2815470B2 JP 21522590 A JP21522590 A JP 21522590A JP 21522590 A JP21522590 A JP 21522590A JP 2815470 B2 JP2815470 B2 JP 2815470B2
Authority
JP
Japan
Prior art keywords
support
shoring
buoyancy
formwork
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP21522590A
Other languages
Japanese (ja)
Other versions
JPH0497008A (en
Inventor
啓一 大村
茂樹 喜瀬
信之 柴原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP21522590A priority Critical patent/JP2815470B2/en
Publication of JPH0497008A publication Critical patent/JPH0497008A/en
Application granted granted Critical
Publication of JP2815470B2 publication Critical patent/JP2815470B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、水上に突出する杭頭上にコンクリート製の
水上構造物を構築するに際しての、浮力調整式可動支保
工による工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a buoyancy-adjustable movable shoring method for constructing a concrete floating structure on a pile head projecting above the water.

〔従来の技術〕[Conventional technology]

水上から突出する杭群の頭部に海洋プラットフォーム
や桟橋などの水上構造物を施工するにあたっては、型枠
の他に、この型枠を支承するための支保工が必要とな
る。
When constructing a floating structure such as an offshore platform or a pier on the head of a pile group that protrudes from the water, in addition to the formwork, a shoring for supporting the formwork is required.

この際、水上面は直接の支持面にはならないから、従
来は杭にブラケットを取付けて型枠を支持するか、ある
いは作業船を施工現場の直下に位置せしめ、次に作業船
に搭載した支持装置の上面を利用して支保工および型枠
の組立てを行って、杭の頭部よりも高位置で水上構造物
を施工した後、この構築した水上構造物を降下して杭頭
部に据え付ける施工方法が一般に知られている。
At this time, since the water surface does not directly support the surface, conventionally, a bracket is attached to the pile to support the formwork, or the work boat is positioned directly below the construction site and then mounted on the work boat. Use the upper surface of the equipment to assemble the shoring and formwork, construct the floating structure at a position higher than the head of the pile, and then lower the constructed floating structure and install it on the pile head Construction methods are generally known.

〔発明が解決しようとする課題〕 しかしながら、上記のような従来の施工方法には以下
に示すような問題点が存在する。すなわち、 (イ)支保工が小型なものでないと組立、解体が容易で
ない。しかし小型の支保工では重量物を支えることがで
きないので、梁・スラブ等を一体化打設することができ
ない。
[Problems to be Solved by the Invention] However, the conventional construction method as described above has the following problems. That is, (a) Assembling and dismantling are not easy unless the support is small. However, since small supports cannot support heavy objects, beams, slabs, and the like cannot be integrally cast.

(ロ)杭間の設置間隔が変化するところに、どこにでも
対応できるような支保工形式がない。
(B) Where the spacing between piles changes, there is no form of support that can be used anywhere.

(ハ)型枠の組外しは海上作業(船上作業)に依らねば
ならないので多大の作業時間と労力を要する上、作業者
が転落する恐れもあり、非常に高い危険性を伴う。
(C) Since the removal of the formwork must depend on the offshore work (ship work), it requires a great amount of work time and labor, and there is a risk that the worker may fall down, which is very dangerous.

(ニ)海上作業での型枠や支保工の組立、解体、移動の
各作業に多大の手数を要するため、施工能率が極めて低
い。
(D) Since the work of assembling, disassembling and moving the formwork and the shoring work at sea requires a great deal of work, the construction efficiency is extremely low.

(ホ)この工法では、低潮位で波浪の穏やかな時を選ん
で作業が行われるため、気象状況に大きく左右され、ま
た作業時間も短く、時間に制限される。
(E) In this method, the work is performed at a low tide when the waves are calm, so that the work is greatly affected by the weather conditions, and the work time is short and limited.

(ヘ)杭表面は海水等に対する防蝕処理が施されている
ので、杭に溶接加工等ができないため、杭自身からの支
保形式(ブラケット方式)が採れなくなる。
(F) Since the pile surface is subjected to corrosion treatment against seawater or the like, the pile cannot be welded or the like, so that the pile itself cannot be supported (bracket type).

(ト)波浪による損傷を防ぐため、部材数の減少を図る
必要があるが、支保工が小型化する点に対して設計上、
矛盾する。
(G) In order to prevent damage due to waves, it is necessary to reduce the number of members.
Contradict.

この発明は、上記のような従来の問題点にかんがみて
なされたものであって、浮力調整式可動支保工を用いる
等により、上記課題を解決することを目的としている。
The present invention has been made in view of the above-described conventional problems, and has as its object to solve the above-mentioned problems by using a buoyancy-adjustable movable supporter.

〔課題を解決するための手段〕[Means for solving the problem]

この発明は上記目的を達成するために、杭間隔の異な
る水上コンクリート構造物の施工にあたり、水の出し入
れにより浮力調整可能な大型支保工を杭間の所定位置へ
浮上曳航し、該大型支保工を所定高さに吊上げて吊り鋼
棒により杭頭吊り金物に固定した後、この大型支保工上
に小型支保工及び梯子状支保工を取付けて型枠受け支保
工を組立て、しかる後に該型枠受け支保工上に型枠を架
設固定してコンクリート打設を行い、所定養生期間経過
後、前記各支保工を解組して水面に降下させ、浮力を利
用して次架設場所へ浮上曳航する浮力調整式可動支保工
による工法としたものである。
In order to achieve the above object, the present invention, in the construction of a floating concrete structure having a different pile interval, a large shoring capable of adjusting the buoyancy by taking in and out of water, levitating and towing to a predetermined position between the piles, After being lifted to a predetermined height and fixed to the pile head suspension with a hanging steel rod, a small support and a ladder-like support are attached on this large support, and a form receiving support is assembled. After the prescribed curing period has elapsed, the shoring is disassembled and lowered to the surface of the water, and the buoyancy of levitation and towing to the next erection location using buoyancy It is a construction method using adjustable movable supports.

〔作用〕[Action]

この発明は、上記のような構成となっていて、大型支
保工は浮力を利用して運搬するために、陸送に比べて大
型化でき、且つ浮上曳航するため杭間隔の狭い場所へで
も配設可能である。また、クレーン等で所定高さに吊上
げられた上記大型支保工は杭頭吊り金物に吊り鋼棒によ
って固定されるので、防食処理を施した杭表面に傷をつ
けることはない。
The present invention is configured as described above, and large supports can be transported using buoyancy, so that they can be made larger in size than land transportation, and can be installed even in places where the spacing between piles is small for floating towing. It is possible. In addition, since the large-sized shoring lifted to a predetermined height by a crane or the like is fixed to the pile head hanging metal by a hanging steel rod, the surface of the anticorrosion-treated pile is not damaged.

このように吊上げ、固定された大型支保工を縦材とす
ると、これらの縦材上に例えばH型鋼を素材とする小型
支保工を横材として固定し、さらにこの小型支保工上に
梯子状支保工を取付けることにより、所要形状に応じた
型枠受け支保工を組立てることができる。次いで、この
支保工上に予め製作された型枠を載置固定し、コンクリ
ート打設を行うことにより、杭と一体化したコンクリー
ト構造物が構築される。
When the large supports thus lifted and fixed are used as vertical members, small supports made of, for example, H-section steel are fixed as horizontal members on these vertical members, and a ladder-like support is further mounted on the small supports. By attaching the work, it is possible to assemble the form receiving support work according to the required shape. Next, a pre-manufactured formwork is placed and fixed on this support, and concrete is cast, whereby a concrete structure integrated with the pile is constructed.

以上のように組合せ部材が少なく且つ堅固なので、コ
ンクリート硬化までの波浪、強風等の外力に対する安全
性が高い。また型枠の解組に際しては、前記各支保工を
部分的に組立てた状態で水面に降下し、浮力を利用して
次の架設場所へ浮上曳航して配設することができる。以
上のような工法により、従来のように型枠や支保工の組
立、解体、移動の各作業に多大の手間を要することな
く、且つ作業の危険性も大幅に減少することができる。
As described above, since the number of combined members is small and firm, safety against external forces such as waves and strong winds until concrete hardens is high. Further, when dismantling the formwork, each of the supports can be lowered to the surface of the water in a state where the supports are partially assembled, and can be disposed by surfacing and towing to the next erection location using buoyancy. According to the above-described construction method, each work of assembling, disassembling, and moving the formwork and the shoring work does not require much labor as in the related art, and the danger of the work can be greatly reduced.

〔実施例〕〔Example〕

以下、この発明を図面を参照して説明する。第1〜8
図は本発明の一実施例を説明するための図である。
Hereinafter, the present invention will be described with reference to the drawings. First to eighth
The figure is a diagram for explaining an embodiment of the present invention.

第1図は実施例である浮力調整式可動支保工による工
法概念を示す斜視図である。また、この工法の手順は第
8図に略示するごとく行われる。
FIG. 1 is a perspective view showing the concept of a construction method using a buoyancy-adjustable movable support according to an embodiment. The procedure of this method is performed as schematically shown in FIG.

第1図に本発明の構成上の特徴をなす支保工について
説明する。図において、全体をなす型枠受け支保工は、
支保工A及び支保工Bよりなる。また支保工Aは陸上に
おいて加工製作した鋼管で、縦材としての大型支保工11
と、これらを連結する小型支保工12及びこの小型支保工
12上に縦材21と横材22とにより形成された梯子状部材が
取付けられて構成される。この際、大型支保工11は全体
のバランスを考慮して水の出し入れにより浮力を調節し
必要に応じた姿勢に調整する。なお、大型支保工11には
後述のごとく吊上げるときの吊りバンド11aが所要位置
に取付けられている。
FIG. 1 illustrates a supporting structure which is a structural feature of the present invention. In the figure, the entire formwork support is
It consists of Shoring A and Shoring B. Shoring A is a steel pipe machined and manufactured on land.
And the small shoring 12 that connects them and this small shoring
A ladder-like member formed by a vertical member 21 and a horizontal member 22 is mounted on the structure 12. At this time, the large shoring 11 adjusts the buoyancy by taking in and out the water in consideration of the overall balance, and adjusts the posture as needed. The large support 11 is provided with a suspending band 11a at a required position for lifting as described later.

支保工Bは縦材31、横材32を組合わせて梯子状部材を
形成するとともに、大型支保工11を連結する。
The shoring B forms a ladder-like member by combining the vertical members 31 and the horizontal members 32 and connects the large shoring 11.

上記の支保工A,Bの上面には型枠を受けるためのステ
ンレス鋼板等を素材とした桁底型枠ブレート13が設けら
れている。
A girder bottom form plate 13 made of a stainless steel plate or the like for receiving the form is provided on the upper surfaces of the supports A and B.

次に型枠Cはコンクリート硬化後、脱型可能とするた
めにC1,C2,C3,C4のように4分割できるスラブ型枠Ca
び中抜型枠部Cbよりなっている。すなわち、スラブ型枠
Caは第5図に示すように縦材41、横材42、斜材43、成形
面44からなっている。コンクリート重量は成形面44より
縦材、横材、斜材等を介して支保工A,Bに支承される。
型枠Cを解体時、4分割するための中抜型枠部Cbは縦材
45、横材46、成形面47、固定金具48からなっていて、ス
ラブ型枠Caとの固定は固定金具48とクリップで行う。
Then mold C after concrete curing, has become more C 1, C 2, C 3, slab form can 4 divided as C 4 C a and the medium cutting die frame portion C b to allow demolding . That is, slab formwork
C a is composed of fifth Tatezai 41 as shown in FIG, crosspiece 42, diagonal member 43, the molding surface 44. The concrete weight is supported by the supports A and B from the forming surface 44 via vertical members, horizontal members, diagonal members and the like.
Dismantling the mold C, 4 cutting die frame portion C b in for splitting Tatezai
45, cross member 46, the molding surface 47, consist of a fixed bracket 48, fixed to the slab form C a is carried out in the clip and mounting brackets 48.

次に、本発明による水中構造物の工法につき順序を追
って説明する。先ず、第4図に示すように、杭頭上に設
けた結構材60の所定位置に杭頭吊り金物50を取付ける。
次に第8図に示すように、陸上で製作した大型支保工
11を浮上曳航し、現場の杭間に運搬する。その他の部材
は台船等で運搬する。大型支保工11を杭間所定位置へ配
置したら、これを曳船から結構材60上のクレーンに盛替
え(同図)、吊り上げて吊り鋼棒51を杭頭吊り金物50
に固定する。その他、前述のごとく小型支保工12、支保
工B等を大型支保工11に固定し、型枠受け支保工の架設
を完了する(同図)。次に陸上で組まれた型枠Cを台
船にて運搬し、結構材60上のクレーンにて吊り込み、支
保工A,Bと固定して型枠の架設を完了する(同図,第
5図)。次いで組立てられた支保工、型枠内に鉄筋を組
み、コンクリートを打設し、水上構造物を構築する。こ
の水上構造物の重量は、吊り鋼棒51にて吊り金物50、結
構材60、杭1,2へと荷重される。
Next, the method of constructing an underwater structure according to the present invention will be described step by step. First, as shown in FIG. 4, a pile head suspension metal fitting 50 is attached to a predetermined position of a structural member 60 provided on the pile head.
Next, as shown in Fig. 8, a large shoring made on land
11 is towed up and transported between piles at the site. Other members are transported by barges. When the large support 11 is placed at a predetermined position between the piles, the shoring is changed from a tugboat to a crane on the structural member 60 (the same figure).
Fixed to In addition, the small shoring 12, the shoring B, etc. are fixed to the large shoring 11 as described above, and the erection of the form receiving shoring is completed (the same figure). Next, the formwork C assembled on land is transported by a barge, suspended by a crane on the structural member 60, fixed to the supports A and B, and the erection of the formwork is completed (FIG. 5). Next, rebar is assembled in the assembled shoring and formwork, concrete is poured, and a floating structure is constructed. The weight of the floating structure is applied to the hanging hardware 50, the structural member 60, and the stakes 1 and 2 by the hanging steel rods 51.

次に、所定の養生期間経過後、概ね架設の逆工程を辿
って脱型、解体を以下のごとく行う。先ず、支保工A,B
を型枠Cの吊り点より仮吊りする。大型支保工11の吊り
鋼棒51を切断し(第8図,第6図)、両端のチューン
ブロックにて左右の動きを調整しながら、静かに水中に
吊り降ろす。このとき大型支保工11の一方の浮力を大き
く、他方の浮力を小さくすると、第6図に示すごとく姿
勢(イ)から(ロ)へ、又姿勢(イ)から(ロ)へ、
(ロ)から(ハ)へ調整し曳出しに都合のよい姿勢とし
て次の架設場所へ曳航する。小型支保工,支保工Bは第
7図に示すように上記と同様に水上へ降ろし、フロータ
70に乗せ次架設場所へ曳航する。
Next, after a lapse of a predetermined curing period, the mold is removed and dismantled as follows, generally following the reverse process of the erection. First, Shoring A, B
Is temporarily suspended from the suspension point of the form C. The suspended steel rod 51 of the large-sized support 11 is cut (FIGS. 8 and 6), and is gently suspended in the water while adjusting left and right movements by the tune blocks at both ends. At this time, if the buoyancy of one of the large supports 11 is increased and the buoyancy of the other is decreased, the posture (a) is changed from (a) to (b) and the posture (a) is changed from (b) as shown in FIG.
Adjust from (b) to (c) and tow to the next erection site in a posture convenient for withdrawal. As shown in FIG. 7, the small shoring and the shoring B are dropped on the water in the same manner as described above,
Put it on 70 and tow to the next erection site.

また、型枠Cは第8図,に示すように、中抜型枠
部Cbをスラブ開口部より金物等で叩打して落下せしめ、
4分割スラブC1〜C4はIボルトにロープを掛けてそれぞ
れ降下し、フロータに乗せて運搬する。
Further, the mold C, as shown in Figure 8, allowed dropping medium trimming die frame portion C b by tapping with hardware such as from slab openings,
4 divided slab C 1 -C 4 are lowered respectively by multiplying the rope I bolt, carrying put the floater.

なお、第2図は型枠受け支保工の実施例であって、第
3図は第2図の支保工上に架設する型枠の配列を示す。
なお、図中のX−1〜X−5,Z−2〜Z−5は設計、施
工等の基準線、寸法数字は実施例のものである。
FIG. 2 shows an embodiment of the form support shoring, and FIG. 3 shows an arrangement of the form erection erected on the support of FIG.
In the drawings, X-1 to X-5 and Z-2 to Z-5 are reference lines for design, construction, etc., and the dimensional figures are those of the embodiment.

以上の工程を繰り返し行って所定のブロック単位毎に
(第2,3図)水上構造物を順次構築していく。
By repeating the above steps, the floating structures are sequentially constructed for each predetermined block unit (FIGS. 2 and 3).

〔発明の効果〕〔The invention's effect〕

以上説明したように、本発明によれば以下に示すよう
な多くの効果が得られる。すなわち、 (1) 梁、スラブコンクリートの一体化打設が可能で
あり、高品質の水上構造物が構築できる。
As described above, according to the present invention, many effects as described below can be obtained. That is, (1) Beams and slab concrete can be integrally cast and a high-quality floating structure can be constructed.

(2) 大型支保工は浮力を利用して運搬するので、従
来の陸送する場合に比べて大型化が可能で、さらに浮力
により姿勢が調整できるので杭間隔の狭い場所にも適用
可能である。
(2) Large supports can be transported using buoyancy, so they can be made larger than conventional land transport, and can be adjusted in position by buoyancy, so they can be applied to places with narrow pile spacing.

(3) 陸上で組立てるので精度の良い部材となり、水
上構造物の仕上げ精度が向上する。
(3) Since it is assembled on land, it becomes a high-precision member, and the finishing accuracy of a floating structure is improved.

(4) セパレータ等の埋込み金物がないため、その部
分からの腐蝕、劣化等が生じない。
(4) Since there is no embedded metal such as a separator, corrosion, deterioration, and the like do not occur from that portion.

(5) 組合せ部材が少なくかつ堅固なので、コンクリ
ート硬化までの間の波浪、強風等の外力に対する安全性
が高い。
(5) Since the number of combined members is small and firm, safety against external forces such as waves and strong winds until concrete hardens is high.

(6) 組合せ部材が簡略化されているので熟練工等の
作業員が少なくて済むと同時に水上での作業が減り、作
業の安全性が向上する。
(6) Since the combination members are simplified, the number of workers such as skilled workers is reduced, and at the same time, work on water is reduced, and work safety is improved.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本発明に係る浮力調整式可動支保工による工法
概念図、第2図は支保工の実施例の平面図、第3図は第
2図の支保工上に架設する型枠の配列平面図、第4図は
実施例工法による支保工A,Bの取付図、第5図は型枠取
付け後、コンクリート打設した状態を示す図、第6図は
支保工Aの解体を示す図、第7図は支保工Bの解体を示
す図、第8図は本発明に係る工法を〜の順に示した
説明図である。 1,2……杭、11……大型支保工、12……小型支保工、50
……杭頭吊り金物、51……吊り鋼棒、A,B……型枠受け
支保工、C……型枠。
FIG. 1 is a conceptual view of a construction method using a buoyancy-adjustable movable shoring according to the present invention, FIG. 2 is a plan view of an embodiment of the shoring, and FIG. 3 is an arrangement of a formwork erected on the shoring in FIG. FIG. 4 is a plan view, FIG. 4 is a mounting view of the shoring A, B by the embodiment method, FIG. 5 is a view showing a state in which concrete is cast after the formwork is mounted, and FIG. FIG. 7 is a view showing the disassembly of the shoring B, and FIG. 8 is an explanatory view showing the method of the present invention in the order of. 1,2 …… pile, 11 …… large shoring, 12 …… small shoring, 50
... Pile head hanging hardware, 51 ... Hanging steel bars, A, B ... Formwork support, C ... Formwork.

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平1−198914(JP,A) 特開 昭63−156108(JP,A) (58)調査した分野(Int.Cl.6,DB名) E02B 17/00 - 17/08────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A-1-198914 (JP, A) JP-A-63-156108 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E02B 17/00-17/08

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】杭間隔の異なる水上コンクリート構造物の
施工にあたり、水の出し入れにより浮力調整可能な大型
支保工を杭間の所定位置へ浮上曳航し、該大型支保工を
所定高さに吊上げて吊り鋼棒により杭頭吊り金物に固定
した後、この大型支保工上に小型支保工及び梯子状支保
工を取付けて型枠受け支保工を組立て、しかる後に該型
枠受け支保工上に型枠を架設固定してコンクリート打設
を行い、所定養生期間経過後、前記各支保工を解組して
水面に降下させ、浮力を利用して次架設場所へ浮上曳航
することを特徴とする浮力調整式可動支保工による工
法。
In the construction of a floating concrete structure having different pile intervals, a large shoring capable of adjusting buoyancy by taking in and out of water is floated and towed to a predetermined position between the piles, and the large shoring is lifted to a predetermined height. After fixing to the pile head suspension with the hanging steel rod, the small support and the ladder-like support are mounted on this large support, and the form receiving support is assembled. Thereafter, the form receiving is supported on the form receiving support. The buoyancy adjustment is characterized in that concrete is fixed and erected, and after a predetermined curing period has elapsed, each of the supports is disassembled and lowered to the surface of the water, and buoyancy is used to surfacing and towing to the next erection site. Construction method with movable support.
JP21522590A 1990-08-14 1990-08-14 Buoyancy-adjustable movable support construction method Expired - Lifetime JP2815470B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21522590A JP2815470B2 (en) 1990-08-14 1990-08-14 Buoyancy-adjustable movable support construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21522590A JP2815470B2 (en) 1990-08-14 1990-08-14 Buoyancy-adjustable movable support construction method

Publications (2)

Publication Number Publication Date
JPH0497008A JPH0497008A (en) 1992-03-30
JP2815470B2 true JP2815470B2 (en) 1998-10-27

Family

ID=16668782

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21522590A Expired - Lifetime JP2815470B2 (en) 1990-08-14 1990-08-14 Buoyancy-adjustable movable support construction method

Country Status (1)

Country Link
JP (1) JP2815470B2 (en)

Also Published As

Publication number Publication date
JPH0497008A (en) 1992-03-30

Similar Documents

Publication Publication Date Title
CN107882055A (en) A kind of construction method of blower fan cushion cap
US4080916A (en) Maritime platform assemblies
JP2815470B2 (en) Buoyancy-adjustable movable support construction method
EP0029428B1 (en) Apparatus for and method of transporting prefabricated plants
CN110644510B (en) Construction method of pier steel cofferdam
CA1318512C (en) Method and apparatus for constructing seawalls and docks
CN115059026A (en) Construction method for reversely hoisting cast-in-place bridge deck slab by supporting steel beam on top of sluice pier
JPH056601B2 (en)
EP0029044B1 (en) A method of carrying out slip form casting of concrete structures under water and apparatus for carrying out the method
JP4602840B2 (en) Method of forming a calm water area for work
JPH0726531A (en) Building method of maritime landing bridge
JP2003064632A (en) Floating girder material for timbering of underwater and waterborne structure
JPH08158341A (en) Joining structure of pile and beam
TWI763400B (en) Construction method of pier face plate
JP3951809B2 (en) Construction method of swash plate dyke
US4527926A (en) Method for building a protective wall when constructing an underwater base
CN115075273B (en) Reinforced concrete prefabricated pouring jacket cofferdam and construction method
JP3311226B2 (en) Construction method of wave-break water-permeable breakwater
JP3140401B2 (en) Floating member, underwater / overwater construction method and underwater / overwater construction method for formwork support
JPH11229404A (en) Construction of bridge foundation in deep water
JP3170670B2 (en) Construction method for floating structures
JPH08120657A (en) Cereation of artificial water-surface ground
JPH06240637A (en) Mounting method of molding frame
JP2980003B2 (en) Floating formwork and construction method using floating formwork for quay construction
JP2953818B2 (en) Construction method for deep water structures

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20090814

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20090814

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100814

Year of fee payment: 12

EXPY Cancellation because of completion of term