JPS5965108A - Principal rafter-shaped steel dam and its construction - Google Patents
Principal rafter-shaped steel dam and its constructionInfo
- Publication number
- JPS5965108A JPS5965108A JP17565182A JP17565182A JPS5965108A JP S5965108 A JPS5965108 A JP S5965108A JP 17565182 A JP17565182 A JP 17565182A JP 17565182 A JP17565182 A JP 17565182A JP S5965108 A JPS5965108 A JP S5965108A
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- reinforcing bars
- gassho
- frames
- box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
- E02B7/02—Fixed barrages
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
Abstract
Description
【発明の詳細な説明】
この発明は、砂防や提防、あるいは擁壁として構築され
る重力式の鋼製合掌堰堤とその構築方法に関する。従来
、この種の堰堤として、鉄筋コンクリートによるものと
、鋼製箱枠によるものとがあるが、鉄筋コンクリートに
よる堰堤は多くの仮設資材と人手とを必要とするため工
事費が嵩みかつ工期が長びく欠点があった。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a gravity-type steel gassho dam that is constructed as an erosion control, a protection wall, or a retaining wall, and a method for constructing the same. Conventionally, this type of dam has been made of reinforced concrete or made of steel box frame, but dams made of reinforced concrete require a lot of temporary materials and manpower, which increases construction costs and takes a long time. was there.
一方、鋼製箱枠による堰堤は中詰石として、人力では持
てないようなきわめて重くて大粒の砕石を大量に使用す
るため砕石の詰込み作業がきわめて面倒であった。また
、この種の砕石は一般に高価なため工事費が嵩むことが
避けられなかった。On the other hand, dams made of steel box frames use a large amount of extremely heavy and large crushed stones that cannot be lifted by hand, making the filling process extremely troublesome. Furthermore, since this type of crushed stone is generally expensive, it was inevitable that construction costs would increase.
この発明は前記従来の問題点を解消するために提案され
たもので、砂防や堤防あるいは擁壁をきわめて簡単かつ
短期間に、しかも廉価に構築することができる畑製合掌
堰堤を提供することを目的とする。This invention was proposed in order to solve the above-mentioned conventional problems, and aims to provide a field-made gassho dam that allows erosion control, embankments, or retaining walls to be constructed extremely easily, in a short period of time, and at low cost. purpose.
以下、この発明を図示する一実施例によって説明すると
、鋼製合掌堰堤1は複数本の基礎フレーム2と、基礎鉄
筋3と、梁フレーム4と、梁鉄筋5と、合掌鉄筋6と複
数枚の遮閉パネル7とから断面略梯形の箱8を構成し、
この頭8内に土砂や砕石を充填することによシ構成され
ている。Hereinafter, this invention will be explained with reference to an illustrated embodiment. The steel gassho dam 1 includes a plurality of foundation frames 2, foundation reinforcing bars 3, beam frames 4, beam reinforcing bars 5, gassho reinforcing bars 6, and a plurality of A box 8 having a substantially trapezoidal cross section is constructed from the shielding panel 7,
It is constructed by filling the head 8 with earth and sand or crushed stones.
基礎フレーム2はH形鋼よシ形成され、堰堤の構築地盤
面に基礎フレーム20幅方向に適宜間隔離して布設され
ている。布設された基礎フレーノ・2は、アンカーボル
ト等で地盤に適当にアンカーされている。The foundation frame 2 is formed of H-shaped steel, and is laid on the construction ground surface of the dam at appropriate intervals in the width direction of the foundation frame 20. The laid foundation Freno-2 is appropriately anchored to the ground with anchor bolts, etc.
左右基礎フレーム2,2間には、ねじ鉄筋よシなる複数
本の基礎鉄筋3が基礎フレーム2の長手方向に所定間隔
おきに布設され、その両端部は基礎フレーム2,2のウ
ェブ2a、2aK貫通させ、基礎鉄筋3の貫通部分には
固定ナツト9,9が螺着されでいる。Between the left and right foundation frames 2, 2, a plurality of foundation reinforcing bars 3, such as screw reinforcement bars, are laid at predetermined intervals in the longitudinal direction of the foundation frame 2, and both ends thereof are connected to the webs 2a, 2aK of the foundation frames 2, 2. Fixing nuts 9, 9 are screwed into the penetrating portions of the foundation reinforcing bars 3.
梁フレーム4は山形釧より形成され、左右基礎フレーノ
、2,2の直上部に左右基礎フレーム2゜2間の間隔よ
り小幅な間隔で布設されている。The beam frame 4 is formed of a chevron-shaped piece, and is installed directly above the left and right foundation frames 2, 2 at intervals narrower than the interval between the left and right foundation frames 2.2.
布設された梁フレーム4,4はII形鋼等の形鋼よりな
る柱フレーノ、10 、10によって基礎フレーム2,
2にそれぞれ連結されている。柱フレーA I Old
、arRフレーム2および梁フレーノ、4の長手方向両
端部に内側に若干傾斜しで立設され、その上下両端部は
基礎フレーム2および梁フレーノ・4にボルトナツト等
で連結されている。また、左右柱フレーム10.10間
には、複数本の格子鉄筋12が布設され、格子鉄筋12
0両端部は、左右柱フレーム10.10に貫通させ、格
子鉄筋12の貫通部分にはナツトが螺着されている。左
右梁フレーム4,4間には、ねじ鉄筋よりなる複数本の
梁鉄筋5が梁フレーノ・4の長手方向に所定間隔おきに
布設され、千〇両錨1部は梁フ1/−ム4゜4の垂直フ
ランジ4a、4aK貫通させ、梁鉄筋5の貫通部分には
固定ナツト9.9が螺着されている。The installed beam frames 4, 4 are connected to the foundation frame 2 by the column fleno, 10, made of section steel such as II section steel.
2 are connected to each other. Pillar Flare A I Old
, arR frame 2 and the beam flanges 4 are erected at both ends in the longitudinal direction with a slight inclination, and both upper and lower ends thereof are connected to the foundation frame 2 and the beam beams 4 with bolts and nuts. In addition, a plurality of lattice reinforcing bars 12 are installed between the left and right column frames 10 and 10, and the lattice reinforcing bars 12
Both ends of the lattice reinforcing bars 12 are passed through the left and right column frames 10 and 10, and nuts are screwed into the penetrating portions of the lattice reinforcing bars 12. Between the left and right beam frames 4, 4, a plurality of beam reinforcing bars 5 made of threaded reinforcing bars are laid at predetermined intervals in the longitudinal direction of the beam flange 4. The vertical flanges 4a and 4aK of 4° are passed through, and fixing nuts 9.9 are screwed into the portions through which the beam reinforcing bars 5 pass.
基礎フレーム2と梁フレーム4間には、ねじ鉄筋よりな
る複数本の合掌鉄筋6が基礎フレーム2および梁フレー
ム4の長手方向に所定間隔おきに、内側に若干傾斜して
立設され、その上下両端部は基礎フレーム2の7ランジ
2bおよび梁フレーム4の水平フランジ4bに貫通させ
、合掌鉄筋60貫通部分には、固定ナツト9,9が螺着
されている。なお、合掌鉄筋6を梁フレーム4に連結す
るには、梁フレーム4の水平フランジ4bに略り字型の
切欠部4Cを形成し、こめ切欠部4Cに合掌鉄筋6の上
端部を貫通させ、その貫通部分に固定ナツト9を螺着す
る。Between the foundation frame 2 and the beam frame 4, a plurality of gassho reinforcing bars 6 made of threaded reinforcing bars are erected at predetermined intervals in the longitudinal direction of the foundation frame 2 and the beam frame 4, slightly tilted inward. Both ends are passed through the 7 langes 2b of the foundation frame 2 and the horizontal flange 4b of the beam frame 4, and fixing nuts 9, 9 are screwed into the portions where the gassho reinforcing bars 60 pass through. In addition, in order to connect the gassho reinforcing bars 6 to the beam frame 4, an abbreviated notch 4C is formed in the horizontal flange 4b of the beam frame 4, and the upper end of the gassho reinforcing bars 6 is passed through the temple notch 4C. A fixing nut 9 is screwed into the penetrating portion.
また、基礎フレーム2と梁フレーム4間には石綿スレー
ト板、合成樹脂板、波形鎖板、コンクリート板あるいは
ファイバーコンクリート板等からなる遮閉パネル7が取
付けられている。Further, a shielding panel 7 made of an asbestos slate board, a synthetic resin board, a corrugated chain board, a concrete board, a fiber concrete board, or the like is attached between the foundation frame 2 and the beam frame 4.
遮閉パネル7は、その幅方向並びに上下方向に順次突き
合せながら設置され、そのおのおのは、フックボルト1
1によって合掌鉄筋6に固定されている。The shielding panels 7 are installed while facing each other sequentially in the width direction and the vertical direction, and each of the shielding panels 7 has a hook bolt 1.
1 to the gassho reinforcing bars 6.
このように構成された断面略梯形の箱8内に砕石や土砂
14が充填されている。なお、箱8は実施例t44図で
示すように外側と内側とに二重にtlり成することによ
って強度を著しく高めることができる1、この場合、内
側の箱8内には現場で発生する切込み砂利等の土砂を充
填し、外側の箱8内罠をよ砕石(玉石)を充填すれば、
砕石の節約化並びに土砂の流失を防止することができる
。また、砕石や土砂の自重によって左右合掌鉄筋6,6
が外方に膨出するようであれば左右合掌鉄筋6,6を複
数本のフープ鉄筋15で緊結する。The box 8 having a substantially trapezoidal cross section configured in this manner is filled with crushed stones and earth 14. In addition, the strength of the box 8 can be significantly increased by double-layering it on the outside and inside as shown in Figure t44 of the embodiment. If you fill the trap with cut gravel or other earth and sand, and fill the trap inside the outer box 8 with crushed stone (cobblestone),
It is possible to save on crushed stone and prevent soil from being washed away. In addition, due to the weight of crushed stones and earth, the left and right gassho reinforcement bars 6, 6
If it bulges outward, the left and right gassho reinforcing bars 6, 6 are tied together with a plurality of hoop reinforcing bars 15.
この上うな構成において、施工に際してれ、まず基礎フ
レーム2.2を堰堤の掘削地盤面に基礎フレーム2の長
手方向に適宜連結しながらほぼ平行に布設し、アンカー
ボルト等で地盤に適当に固定する。In such a configuration, during construction, first, the foundation frame 2.2 is installed on the excavated ground surface of the dam approximately parallel to the foundation frame 2 while appropriately connecting the foundation frame 2 in the longitudinal direction, and is appropriately fixed to the ground with anchor bolts, etc. .
次に、左右基礎フレーA 2 + 2間に複数本の基礎
鉄筋3を設置する。基礎鉄筋3は、その両端部を基礎フ
レーム2,2のウェブ2fL、2aに貫通させ、その貫
通部分に固定ナツト9,9を螺着することによって固定
する。基礎フレーム2.2を連結するには、基礎フレー
ム2,2の突合せ部のウェブ2a側部およびフランジ2
b側部に連結プレー)13.13をそれぞれ添わせ、こ
の連結プレート13.13とウェブ2aおよびフランジ
2bに基礎鉄筋3および合掌鉄筋6の端部を貫通させ、
その貫通部分に固定ナツト9を螺着する。Next, a plurality of foundation reinforcing bars 3 are installed between the left and right foundation frames A 2 + 2. The foundation reinforcing bars 3 are fixed by having both ends thereof penetrate the webs 2fL, 2a of the foundation frames 2, 2, and screwing fixing nuts 9, 9 into the penetrating portions. To connect the foundation frames 2.2, the sides of the web 2a and the flange 2 of the butt part of the foundation frames 2, 2 are connected.
Connecting plates) 13.13 are attached to the b side, and the ends of the foundation reinforcing bars 3 and gassho reinforcing bars 6 are passed through the connecting plates 13.13, the web 2a, and the flange 2b,
A fixing nut 9 is screwed into the penetrating portion.
次に、合掌鉄筋6を建てこみ、合掌鉄筋6の下端部は基
礎フレーム2の7ランジ2bに貫通させ、その貫通部分
に固定ナツト9を螺着することにより固定する。合掌鉄
筋6を建てこむ場合、複数本の合掌鉄筋6を軽藪形鋼等
からなる連結部材で連結してユニット化し、これをクレ
ーンで吊って建てこむようにすれば、作業の簡略化が図
れる。建てこみ直後の合掌鉄筋6はその内側に鋼管から
なる支保工を組立て、との支保工にたてかけて支持する
。Next, the gassho reinforcing bars 6 are built in, and the lower ends of the gassho reinforcing bars 6 are passed through the seven lunges 2b of the foundation frame 2, and fixed by screwing the fixing nuts 9 into the penetrating portions. When erecting gassho reinforcing bars 6, the work can be simplified by connecting a plurality of gassho reinforcing bars 6 into a unit by connecting members made of light bush-shaped steel or the like, and hoisting this unit with a crane. Immediately after erection, the gassho reinforcing bars 6 are supported by assembling a support made of steel pipes on the inside thereof, and leaning against the support.
次に、合掌鉄筋6の上端部に梁フレーム4を布設し、合
掌鉄筋6上端部は梁フレーム4の切欠部4cVc貫通さ
せ、合掌鉄筋6の貫通部分には固定ナツト9を螺着する
。また、左右梁フレーム4゜4間には梁鉄筋5を布設し
、罰鉄筋5の両端部は左右梁フレーム4,4の垂直フラ
ンジ4a、4aに貫通させ、梁鉄筋50貫;F(部分に
は固定ナツト9.9を螺着する。Next, a beam frame 4 is installed on the upper end of the gassho reinforcing bar 6, the upper end of the gassho reinforcing bar 6 passes through the notch 4cVc of the beam frame 4, and a fixing nut 9 is screwed into the penetrating portion of the gassho reinforcing bar 6. In addition, a beam reinforcing bar 5 is laid between the left and right beam frames 4°4, and both ends of the fine reinforcing bar 5 are passed through the vertical flanges 4a, 4a of the left and right beam frames 4, 4, and 50 pieces of beam reinforcing bar; Screw on the fixing nut 9.9.
次に、連間パネル′1をその幅方向および上下方向に順
次突き合せながら設置し、そのおのおのはフックポル)
11によって合掌鉄筋6に固定する。Next, install the continuous panels '1 one after another in the width direction and vertical direction, each with a hook pole).
11 to fix it to the gassho reinforcing bars 6.
なお、連間パネル7として在来のコンクリートブロック
を使用することもできる。この場合、コンクリートブロ
ックはコンクリートブロックの孔内に合掌鉄筋6を挿通
して設置する。Note that a conventional concrete block can also be used as the continuous panel 7. In this case, the concrete block is installed by inserting gassho reinforcing bars 6 into the holes of the concrete block.
次に、構成された断面略梯形の箱8内に砕石や土砂14
を充填する。なお、建てこみ直後の合掌鉄筋6を支持す
る支保工l、鋼管等を用いた場合、埋殺しとし、そのう
ち支保工の水平部tjはその両端部を構築された鋼製合
掌堰vI−1の側面より突出させて流水路として使用す
ることもできる。Next, crushed stones and earth 14 are placed in a box 8 having a roughly trapezoidal cross section.
Fill it. In addition, if shoring l, steel pipes, etc. are used to support the gassho reinforcing bars 6 immediately after erection, they will be buried, and the horizontal parts tj of the shorings will have both ends attached to the constructed steel gassho weir vI-1. It can also be used as a flow channel by protruding from the side.
次に、この鋼製合掌堰堤の他の実施例として、第9図に
例示する構造について説明すると、複数本の基礎フレー
ム2を堰堤の幅方向に適宜間隔離して布設し、基礎フレ
ーム2,2相互は基礎鉄筋3にて連結されて、基礎部分
を構成している。Next, as another example of this steel gassho dam, the structure illustrated in FIG. 9 will be described. A plurality of foundation frames 2 are installed at appropriate intervals in the width direction of the dam, and the foundation frames 2, 2 They are connected to each other by foundation reinforcing bars 3 to form a foundation part.
基礎フレーム2の上部には、上下、左右に複数段及び複
数列の梁フレーム4を梁鉄筋5と合掌鉄筋6にて上下、
左右に、ボルト・ナツトを用いて連結している。On the top of the foundation frame 2, beam frames 4 in multiple stages and rows are installed vertically and horizontally using beam reinforcing bars 5 and gassho reinforcing bars 6.
The left and right sides are connected using bolts and nuts.
この場合、第9図にて図示するごとく、堰堤の断面にお
いては、梁鉄筋5と合掌鉄筋6がやや格子状に形成され
、格子の各交点の内、その一部又は全部に梁フレーム4
を用いて、堰堤全体の剛性を高めることができる。In this case, as shown in FIG. 9, in the cross section of the dam, the beam reinforcing bars 5 and gassho reinforcing bars 6 are formed in a somewhat lattice shape, and beam frames 4 are formed at some or all of the intersection points of the lattice.
can be used to increase the rigidity of the entire dam.
また、堰堤の下部より上部に上がるに従って、合掌鉄筋
6の本数を減少させることにより、堰堤断面をやや断面
階段状の梯形の箱体を形成することが可能である。Further, by decreasing the number of gassho reinforcing bars 6 from the lower part of the dam to the upper part, it is possible to form a trapezoidal box with a slightly stepped cross section of the dam.
なお、この場合、梁フレーム4と基礎フレー、ム2を同
じ材料を用いることにより、形成することも可能であり
、必要な0、下部に基礎フレーム2と梁フレーノ・4を
密に配設し、上部は粗に配設してもよい7、
#fT l g図tよ、包製合掌堰堤全体をこの発明に
従って実施した場合の一5′1!施例に゛C1外部に連
間パネルを配設した堰堤であるが、内部を図示するため
、部分的に連間パネルを除いた状態にて示17ている。In this case, it is also possible to form the beam frame 4, the foundation frame, and the beam frame 2 by using the same material, and the foundation frame 2 and the beam frame 4 can be arranged closely at the bottom of the necessary 0. , the upper part may be arranged roughly 7, #fT lg Figure t, 15'1 when the entire envelope gassho dam is implemented according to the present invention! In this example, C1 is a dam with a continuous panel disposed outside, but in order to illustrate the inside, the continuous panel is partially removed from the drawing 17.
なお、第3図、第4図に図示する断面略梯形の箱体の2
重’I’A造において、内部および外部が完全に分離さ
れた重複的な構造でも又、iコじ鉄筋等にて相互に連結
されている複合的なイ1¥造でもよい。In addition, 2 of the boxes having a roughly trapezoidal cross section shown in FIGS. 3 and 4.
In heavy-duty I'A construction, it may be a redundant structure in which the interior and exterior are completely separated, or it may be a composite I-1 structure in which the interior and exterior are interconnected by means of reinforcing bars or the like.
第9図のような堰堤断面においては、堰堤内部の合掌鉄
筋6に連間パネルを随時設けることにより、2重、3重
のJ罠堤を4苦成することも可能であり、この場合の堰
堤は、各々相方にねじ鉄筋、詳しくは、梁鉄筋5と基礎
鉄筋3にて連結しているので、多重に形成された’F(
堤1j、複合的に形成された構造の堰堤である。In the cross section of the dam as shown in Figure 9, it is possible to construct four double or triple J-trap dams by installing continuous panels on the gassho reinforcing bars 6 inside the dam. The dam is connected to each other by threaded reinforcing bars, specifically beam reinforcing bars 5 and foundation reinforcing bars 3, so multiple 'F(
Embankment 1j is a dam with a complex structure.
この発明は、以上のtlり成よりなるので次の効果が期
待できる。Since this invention consists of the above tl components, the following effects can be expected.
■ 構造がきわめて単純であるから工事の簡略化、省力
化並びに工期の大幅な短縮化が図れる。■ Since the structure is extremely simple, construction work can be simplified, labor can be saved, and the construction period can be significantly shortened.
■ 箱は形鋼、鉄筋、石綿スレート等の連間パネル等、
すべて在来のもので構成され、かつ箱の中には高価な砕
石の代りに現場で大量に発生する土砂を充填することが
できるので、工事費の大幅な低廉価が図れる。■ The box is made of continuous panels made of shaped steel, reinforcing bars, asbestos slate, etc.
The box is constructed entirely from local materials, and the box can be filled with earth and sand generated in large quantities on site instead of expensive crushed stone, making it possible to significantly reduce construction costs.
■ 重力式堰堤としては、理想的な梯形断面に構築され
ているので構造的にもきわめて安定している。。■ As a gravity-type dam, it is constructed with an ideal trapezoidal cross-section, making it extremely stable structurally. .
■ よってこの考案によれば、砂防や堤防あるいは擁壁
をきわめて簡単かつ確実にしかもきわめて廉価に構築す
ることができる。■Thus, according to this invention, erosion control, embankments, or retaining walls can be constructed extremely easily, reliably, and at an extremely low cost.
■ ネジ鉄筋と基礎フレーム、梁フレームを相互に連結
することにより構成された堰堤のため、現場の地形に応
じて容易に構築が可能である。■ Since the dam is constructed by interconnecting threaded reinforcing bars, foundation frames, and beam frames, it can be easily constructed according to the topography of the site.
第1図は銅製合掌堰堤の斜視図、第2図は千の縦断面図
、第3図は鋼製合掌堰堤の箱の側面図、第4I¥Iは(
(1製合掌堰堤の斜視「イ1、−は5図は〕、(礎フレ
ームと基礎鉄筋および合掌鉄筋との連結状輯を示す酬視
図、第6図は梁フレームと梁鉄筋および合掌鉄筋との連
結状か1を示す斜視図、第7図は基礎フレームの連結部
を示す斜視図、第8図trl連間パネルの[包封状態を
示す断面図1,6.’; 9図は他の実施例の梁フレー
)1、鉄筋の配置状j、i14図、第10図tよぞの堰
堤の斜視図である。
l・・鋼?V合掌堰堤、2・・:q6 y猷フレー・人
、3・・基η)き鉄筋、4・・梁71ノー人、5・・梁
鉄筋、(i・・合掌鉄筋、
7・・連間パネル、8・・箱、
9・ ・固定ナツト、1()・・柱フレー ノ・、Jl
・・フツクボ/I<1・、12・・フープ鉄筋、13・
・連結プレート、14・・砕石や土砂、15、・フープ
鉄筋。Figure 1 is a perspective view of the copper gassho dam, Figure 2 is a vertical cross-sectional view of the steel gassho dam, Figure 3 is a side view of the box of the steel gassho dam, and No. 4I\I is (
(A perspective view of the Gassho Weir made by No. 1. Figure 5 is a perspective view of the Gassho Weir made by Manufacturer No. 1. Fig. 7 is a perspective view showing the connecting part of the foundation frame, Fig. 8 is a cross-sectional view showing the enclosed state of the trl continuous panel; Beam frame of other embodiments) 1. Reinforcing bar arrangement j, i Fig. 14, Fig. 10 Fig. 10 is a perspective view of the dam from t.・Person, 3. Reinforcing bar with base η), 4. Beam 71 no person, 5. Beam reinforcing bar, (i. Gassho reinforcing bar, 7. Connecting panel, 8. Box, 9. Fixing nut. , 1()... Column Freno..., Jl
・・Futsukubo/I<1・, 12・・Hoop reinforcing bar, 13・
・Connection plate, 14. Crushed stone and earth, 15. Hoop reinforcing bar.
Claims (4)
複数の基礎フレームと、その上部に、上下・左右に各々
複数の梁フレームを並設し、左右に並設した梁フレーム
は梁鉄筋にて連結し、上下に並設した梁フレームは、下
部の基礎フレームに一端を連結してなる合掌鉄筋にて連
結することにより形成した略箱状の箱体内に土石を充填
したことを特徴とする鋼製合掌堰堤。(1) A plurality of foundation frames are connected by a plurality of foundation reinforcing bars and installed in parallel, and on top of the foundation frames, a plurality of beam frames are installed in parallel vertically and horizontally, and the beam frames installed in parallel on the left and right are beams. The beam frames are connected by reinforcing bars and placed vertically in parallel, and one end is connected to the lower foundation frame using gassho reinforcing bars.The beam frames are connected by gassho reinforcing bars, which form a roughly box-shaped box body that is filled with earth and stones. A steel gassho dam.
方が鉄筋にて代用された特許請求の範囲第1項記載の鋼
製合掌堰堤。(2) The steel gassho dam according to claim 1, wherein either or both of the beam frame and the foundation frame are replaced with reinforcing bars.
レーム相互を複数本の基礎鉄筋にて連結して、箱体下面
部を形成すると共に、上記下面部直上部に、複数本の梁
フレームを並設し、並設した梁7レーム相互を複数本の
梁鉄筋にて連結して、箱体上面部を形成し、この上面部
と下面部を複数の合掌鉄筋にて連結して。、箱体中部を
形成し、この箱体内部に土石を充填して堰堤を構築する
ことを特徴とする銀製合掌堰堤構築方法。(3) A plurality of foundation frames are installed in parallel, and the foundation frames installed in parallel are connected to each other with a plurality of foundation reinforcing bars to form the lower surface of the box. The beam frames are installed side by side, and the 7 parallel beams are connected to each other with multiple beam reinforcing bars to form the upper surface of the box body, and the upper and lower surfaces are connected with multiple gassho reinforcing bars. . , a method for constructing a silver gassho dam, characterized by forming a central part of the box body, and building the dam by filling the inside of the box with earth and stones.
は重複的に構築する特#′r請求の範囲第3項記載のf
Ki4製合掌堰堤栴築方法。(4) A feature of constructing a box having a substantially trapezoidal cross section in a complex or overlapping manner such as double or triple.
Ki4 gassho dam construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17565182A JPS5965108A (en) | 1982-10-06 | 1982-10-06 | Principal rafter-shaped steel dam and its construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17565182A JPS5965108A (en) | 1982-10-06 | 1982-10-06 | Principal rafter-shaped steel dam and its construction |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5965108A true JPS5965108A (en) | 1984-04-13 |
JPS613929B2 JPS613929B2 (en) | 1986-02-05 |
Family
ID=15999818
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP17565182A Granted JPS5965108A (en) | 1982-10-06 | 1982-10-06 | Principal rafter-shaped steel dam and its construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5965108A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10351909B2 (en) | 2005-06-15 | 2019-07-16 | Complete Genomics, Inc. | DNA sequencing from high density DNA arrays using asynchronous reactions |
-
1982
- 1982-10-06 JP JP17565182A patent/JPS5965108A/en active Granted
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10351909B2 (en) | 2005-06-15 | 2019-07-16 | Complete Genomics, Inc. | DNA sequencing from high density DNA arrays using asynchronous reactions |
Also Published As
Publication number | Publication date |
---|---|
JPS613929B2 (en) | 1986-02-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9388561B2 (en) | Modular construction mold apparatus and method for constructing concrete buildings and structures | |
US4015379A (en) | In-ground swimming pool and apparatus and method for constructing same | |
KR100510092B1 (en) | A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it | |
JPH10152998A (en) | Earthquake-resistant reinforcing structure of existing building | |
US4519730A (en) | Method for constructing underground structure | |
JPS5965108A (en) | Principal rafter-shaped steel dam and its construction | |
RU2275456C2 (en) | Sheet piling | |
JP3778392B2 (en) | Basic block | |
JPH09195438A (en) | Precast concrete plate and reinforcing structure of building | |
JP2536376B2 (en) | Foundation structure of shed for road protection | |
JPS6054459B2 (en) | Slope protection method | |
JPS642727B2 (en) | ||
JP3138129B2 (en) | Reverse beam construction method and driving beam side formwork | |
JPS61102911A (en) | Steel cell | |
JP3406370B2 (en) | Horizontal shaft construction method | |
JPH02266016A (en) | Structural process of underground concrete body of building | |
JPH0492021A (en) | Foundation structure of building and construction method thereof | |
JP4045623B2 (en) | Construction method of reinforced concrete underground floor and underground structure constructed by this method | |
GB2152973A (en) | Method of building a cavity structure in an embankment | |
JPS63277342A (en) | Reverse execution of underground story | |
JP2003027505A (en) | Structure and structure of crossing part of structural members | |
JPH073821A (en) | Construction of footing beam and earthen floor slab on bearing slab foundation concrete | |
JPH0960492A (en) | Structure and execution method for timbering wall | |
KR101125547B1 (en) | Steel composite rahmen shaped structure and construction method of assembly type rahmen structure using the same | |
JP2023131678A (en) | New building block form block, concrete structure and construction method of concrete foundation |