JPS5955963A - Method and apparatus for raising power transmission tower - Google Patents

Method and apparatus for raising power transmission tower

Info

Publication number
JPS5955963A
JPS5955963A JP16724782A JP16724782A JPS5955963A JP S5955963 A JPS5955963 A JP S5955963A JP 16724782 A JP16724782 A JP 16724782A JP 16724782 A JP16724782 A JP 16724782A JP S5955963 A JPS5955963 A JP S5955963A
Authority
JP
Japan
Prior art keywords
tower
steel tower
raising
temporary
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP16724782A
Other languages
Japanese (ja)
Other versions
JPH0418110B2 (en
Inventor
内田 勝征
俊樹 近藤
永井 幹雄
辻井 隆雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chubu Electric Power Co Inc
Aichi Electric Co Ltd
Original Assignee
Chubu Electric Power Co Inc
Aichi Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chubu Electric Power Co Inc, Aichi Electric Co Ltd filed Critical Chubu Electric Power Co Inc
Priority to JP16724782A priority Critical patent/JPS5955963A/en
Publication of JPS5955963A publication Critical patent/JPS5955963A/en
Publication of JPH0418110B2 publication Critical patent/JPH0418110B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)
  • Transmitters (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は、設に設置されている架空電線路の鉄基地上部
全体を架線状態の候嵩上げする工法及び同装置に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method and apparatus for raising the entire upper part of an iron base of an overhead power line installed in an overhead line.

既設鉄塔間の電線の−高さを周辺の建築物の高層化に対
処して高くする場合及び電力需要の増大等に伴って鉄塔
金高くし増設する場合、鉄塔を新規に建替えることは、
仮鉄塔の建設用地、建設費用、労力、送電停止等の諸問
題があって容易に実施することが出来ないことから、本
発明では、既設鉄塔に於ける基礎脚部外側に仮性塔柱を
垂直設置せしめ当該仮性塔柱に夫々一体的に固設せる油
圧ジ車 ヤッキ部の一体動作によシ、既設鉄塔の地上部下方に差
渡した鉄塔受梁の各外端部に固設したロッドを昇降動せ
しめ、該鉄塔受梁より下方に於いて前記基礎部から分断
せる鉄塔地上部を、特に垂直姿勢を損なうことなく持上
げ移動後、嵩上げ脚部ユニットを分断鉄基地上部底部に
連結設置せしめ、必要により更に仮定着せる嵩上げ脚部
ユニットに栴度妖塔受梁全差渡し、再び垂直姿勢を損な
うことなく持上げ移動後、上部を連結せる第2嵩上↓ げ脚部ユニット全前記基礎脚部に定着せしめようにする
嵩上げ工法及び同装置の提供を目的とするものである。
When increasing the height of electric wires between existing steel towers to cope with the rise of surrounding buildings, or when increasing the height of steel towers due to increased electricity demand, etc., rebuilding a new steel tower requires:
Since it is not possible to easily implement a temporary tower due to various problems such as land, construction cost, labor, power outage, etc., in the present invention, temporary tower pillars are installed vertically on the outside of the foundation legs of the existing tower. The rods fixed to the outer ends of the tower support beams extending below the ground of the existing tower are installed by the integrated operation of the hydraulic wheel jack parts that are fixed integrally to the temporary tower pillars. After lifting and moving the above-ground part of the steel tower which is moved up and down and separated from the foundation below the steel tower support beam without particularly damaging its vertical posture, the raised leg unit is connected and installed at the bottom of the upper part of the separated iron base, If necessary, attach the entire raised leg unit to the raised leg unit, and after lifting and moving again without damaging the vertical posture, connect the upper part of the second raised leg unit to the base leg. The object of the present invention is to provide a method and device for raising the surface to make it more stable.

本発明の嵩上げ工法及び同装置を添附図面に従って説明
するに、既設鉄塔(1)(第1図)に対し、鉄塔基礎脚
部(2)を(第1.14図)を含むその外側部分に例え
ば各脚部間の二本の直交対角線上に十文字形態等適宜補
強基礎を行う新設基礎部(8)を形成(第2.15図)
シ、該新設基礎部(8)に各仮性塔柱(6)全垂直設置
せしめ、該仮性塔柱(6)に嵩上げ装置(6)全装設せ
しめる(第6図)。この嵩上げ装置(6)は第9〜11
図に示してお夛、例えば既設鉄塔(1)の各角部外方に
夫々81i、せる夫々の仮性塔柱(6)の上方部に固設
せるジヤツキ受ブラケット(7)に掛架支持せるジヤツ
キ受梁(8)の適宜位置の上面に定着せしめるジヤツキ
台座(9)’z介して各センターホール屋油圧ジヤツキ
部叫ヲ一体制御すべく油圧系路を連結設置する(第9.
1o図)。一方鉄塔(1)下方部に差渡し設置する鉄塔
受梁(11)は平行敷設乃至井桁形状に積重する等任意
の形態とし、その外端部には、前記油圧ジヤツキ部σ0
)の操作により上下動自任なるロッド(12)の下端部
(12a)が夫々定着せしめられており、油圧ジヤツキ
部1.10)の制御操作に基因して昇降動すべく形成さ
れている(第11図)。
To explain the raising construction method and device of the present invention according to the attached drawings, for an existing steel tower (1) (Fig. 1), the tower foundation leg (2) is attached to the outer part including (Fig. 1.14). For example, a new foundation (8) is formed on the two orthogonal diagonals between each leg, with appropriate reinforcement foundations such as a cross shape (Figure 2.15).
6. Each temporary tower column (6) is fully vertically installed on the new foundation (8), and the raising device (6) is fully installed on the temporary tower column (6) (Fig. 6). This raising device (6) is the 9th to 11th
As shown in the figure, for example, it is suspended and supported by a jack bracket (7) fixed to the upper part of each temporary tower column (6) placed outside each corner of the existing steel tower (1) at a distance of 81i. Hydraulic system lines are connected and installed in order to integrally control the hydraulic jack parts of each center hall through a jack pedestal (9)'z fixed on the upper surface of the jack support beam (8) at an appropriate position (No. 9).
Figure 1o). On the other hand, the steel tower support beam (11) installed across the lower part of the steel tower (1) can be of any arbitrary configuration, such as being laid parallel or stacked in a cross-shaped shape, and the outer end has the above-mentioned hydraulic jack part σ0.
), the lower ends (12a) of the rods (12) are fixed, respectively, and are formed to move up and down based on the control operation of the hydraulic jack (1.10). Figure 11).

aS>は分断鉄塔地上部(1a)の嵩上げ工程に於ける
垂直姿勢保持装置であシ、第12図に示す如く同鉄塔地
上部(1a)に於ける少くとも上下二位置にて上方及び
下方水平腕杆α6)(161,57)1,17)’を一
体固設し、該両外端に例えば上下二体を一組とする各支
えローラーμ5)(ll全夫々固設する。該各支えロー
ラーは、第10図に示す如く各仮性塔柱(6)の支持枠
(財)に於けるコーナー筋交い)の中央部に一体設置せ
るl型鋼製案内レール−の内壁面に接合配設されている
。上記の如く少くとも上下二位置にて設ける上方及び下
方水平腕杆u6)(t5)、σ7川6を第13図に示す
如く直交する二本の対角線上に夫々設けて一対とするこ
とが望ましい。
aS> is a vertical posture holding device used in the process of raising the ground part (1a) of the divided steel tower, and as shown in Fig. 12, it holds the upper and lower positions of the above ground part (1a) of the tower at least in two positions. Horizontal arm rods α6) (161, 57) 1, 17)' are integrally fixed, and each support roller μ5) (ll, which is a set of two upper and lower bodies, for example, is fixed at both outer ends. The support rollers are connected to the inner wall surface of the L-shaped steel guide rail, which is installed integrally in the center of the corner brace of the support frame of each temporary tower column (6), as shown in Figure 10. has been done. As mentioned above, it is desirable that the upper and lower horizontal arm rods u6) (t5) and σ7 rivers 6 are provided at least in two positions, upper and lower, and are provided as a pair on two orthogonal diagonal lines as shown in Fig. 13. .

分断鉄塔地上部(1a)の上昇移動時に、上記の如き上
下二位置に夫々設けた各支えローラー(ト)(191は
、相互にテコ反力作用をもたらし、各仮性塔柱(6)に
予じめ設定された垂直線上に怒って案内支持されるので
、傾斜姿勢になることは無く且つ支えローラーμ5)(
19)の回動によシ円滑移動が得られる。
When the above-ground part of the divided steel tower (1a) moves upward, the supporting rollers (191) provided at the upper and lower two positions as described above exert a lever reaction force on each other, and each temporary tower pillar (6) is pre-loaded. Since it is guided and supported on a preset vertical line, it will not be in an inclined position and the support roller μ5) (
Smooth movement is obtained by the rotation of 19).

仮性塔柱(51に、上記嵩上げ装置(6)を設置後、基
礎脚部(2)を分断し、嵩上げ装置(6)を作動せしめ
て、分断状態にある鉄塔地上部(1a)は鉄塔受梁辿の
上昇移動に関連して皇直姿勢を損なうことなく円滑に上
方へ移動せしめられる。先づ第1段階としての嵩上げ所
望長例えば4〜5mの分離空間(ISa)を形成後、第
1嵩上げ脚部ユニツ)(14a)を組立て形成して、そ
の上面は鉄塔地上部(1a)の分断底部と連結し、同下
面は前記分断基4a脚部(2)に一体固設した新設基礎
部(4)に連結設置して第1嵩上げ工程を行うものであ
る。更に第2段階として嵩上げ高位を例えば4〜5m延
長せしめたい場合には、前記第1嵩上げ工程終了後、そ
れに続き、第1嵩上げ脚部ユニッ) (14,a)に再
度高上げ装置(6)の鉄塔受梁辿を差渡し設置せしめて
(第5図)、前記新設基礎部(8)の基礎部(4)との
連結部全分断して嵩上げ装置(6)の稼動によシ、第1
嵩上げ脚部ユニツ)(14a)ヲ一体化した鉄塔地上部
(1a)は2度目の分M9間(13b)を形成する(第
6図)。該空間に第2嵩上げ脚部ユニッ) (14b)
 i組立て形成して、前記の工程と同様その上下面を連
結せしめて、第2嵩上げ工程を終了しく第7図)、仮性
塔柱(6)を撤去することにより、当初の鉄塔高位(T
l)は、第1嵩上げ工程を径ることにより、同高位は(
T2)に変動出来、必要により更に、第2嵩上げ工程を
経ることにより1同高位は(TI)に変動可能となる(
第8図)。
After installing the above-mentioned raising device (6) on the temporary tower column (51), the foundation legs (2) are divided, the raising device (6) is activated, and the above-ground part (1a) of the tower in the divided state is raised to the tower support. In connection with the upward movement of the beam, it can be smoothly moved upward without impairing the imperial posture.First, after forming a separation space (ISa) with a desired height of e.g. 4 to 5 m as the first step, the first The raised leg unit) (14a) is assembled and formed, the upper surface of which is connected to the divided bottom part of the above-ground part of the steel tower (1a), and the lower surface of which is connected to the new foundation part that is integrally fixed to the leg part (2) of the divided base 4a. (4) is connected and installed to perform the first raising step. Furthermore, if it is desired to extend the raised height by 4 to 5 m as a second step, after the first raising step is completed, the first raising leg unit (14, a) is again fitted with the raising device (6). (Fig. 5), the connection between the new foundation (8) and the foundation (4) is completely severed, and the raising device (6) is activated. 1
The above-ground part of the steel tower (1a) that is integrated with the raised leg unit (14a) forms the second section M9 (13b) (Fig. 6). A second raised leg unit) (14b) is placed in the space.
i Assemble and form, connect the upper and lower surfaces in the same way as in the previous step, and complete the second raising step (Fig. 7). By removing the temporary tower column (6), the original height of the tower (T
l), by going through the first raising process, the same height becomes (
It can be changed to T2), and if necessary, by going through the second raising process, the 1st height can be changed to (TI) (
Figure 8).

本発明は上記の如く、既設鉄塔(1)の基礎脚部(2)
を含む新設基礎部(8)を外方に形成し、該基礎部に仮
性塔柱(5)全垂直設置せしめ、該仮性塔柱に、嵩上げ
装置1(6)を設置せしめていることにより、鉄塔(1
)の外方空間に於いて嵩上げ装置(6)を設けることが
出来るので、設置作業性が頗ぶる簡易且つ迅速に行い得
、嵩上げ装置(6)全形成する油圧ジヤツキ部(至)が
夫々前記仮性塔柱(6)に一体設置されていることから
分断鉄塔地上部(1a)を持上げ支持する鉄塔受梁μm
)はその各外端部を一体動する油圧ジヤツキ部qO)の
操作により一体的に昇降動し、垂直姿勢保持装置itμ
s)によシ垂直姿勢を損なうことなく移動するので、鉄
塔地上部(1a)の持上げ姿勢上の安定性に優れる嵩上
げ工法であって、第1嵩上げ工程の後、更に必要により
第2嵩上げ工程に進行する作業性も極めて簡易且つ迅速
であり、安全且つ確実な嵩上げ作業をもたらす優れた発
明である。
As described above, the present invention provides a foundation leg (2) of an existing steel tower (1).
By forming a new foundation part (8) including the outside, a temporary tower column (5) is completely vertically installed on the foundation part, and a raising device 1 (6) is installed on the temporary tower column, Steel tower (1
) Since the raising device (6) can be provided in the outer space of the Since it is installed integrally with the temporary tower column (6), the steel tower support beam that lifts and supports the above-ground part of the divided steel tower (1a) μm
) are integrally moved up and down by the operation of hydraulic jacks qO) that move their respective outer ends integrally, and the vertical posture holding device itμ
s) It is a raising method that has excellent stability in the lifting posture of the above-ground part (1a) of the steel tower because it moves without damaging the vertical posture, and after the first raising step, a second raising step is performed if necessary. This is an excellent invention that is extremely easy and quick to proceed with the work, and brings about safe and reliable raising work.

【図面の簡単な説明】[Brief explanation of the drawing]

第1〜8図は本発明工法に於ける作業順序を示す正面図
であって、第9〜11図は嵩上げ装置を示し、第9図は
油圧ジヤツキ部を示す部分拡大正面図、第10図は同平
面図、第11図は鉄塔受梁を示す同図、第12図は垂直
姿勢保持装置の側面図、第16図は同平面図、第14図
は第1図A−A線断面図、第15図は第2図B−B線断
面図である。 (1)鉄  塔  (2)基礎脚部 (8)新設基礎部   (4)新設基礎脚部(6)仮性
塔柱   (6)嵩上げ装置(7)ジヤツキ受ブラケッ
ト  (8)  ジヤツキ受梁(9)ジヤツキ台座  
   1.1o1  油圧ジヤツキ部σ1)鉄塔受梁 
 (12)口 ・ソ ド(18)  分 離 窒 間 
    (6)嵩上げ脚部ユニットψン 垂直姿勢保持
装置    (16)σ7)上下の水平腕杆U3X19
)  支えローラー     □□□支  持  枠母
)コーナー筋交    −案内レールσ)鉄塔の高位 出願人  中部峨力株式会社 外1名
Figures 1 to 8 are front views showing the work order in the construction method of the present invention, Figures 9 to 11 show the raising device, Figure 9 is a partially enlarged front view showing the hydraulic jack part, and Figure 10. is the same plan view, FIG. 11 is the same figure showing the steel tower support beam, FIG. 12 is a side view of the vertical posture holding device, FIG. 16 is the same plan view, and FIG. 14 is a sectional view taken along the line A-A in FIG. , FIG. 15 is a sectional view taken along the line B--B in FIG. 2. (1) Steel tower (2) Foundation legs (8) Newly installed foundation (4) Newly installed foundation legs (6) Temporary tower column (6) Raising device (7) Jacket support bracket (8) Jacket support beam (9) Jyatsuki pedestal
1.1o1 Hydraulic jack part σ1) Steel tower support beam
(12) Mouth/Sodo (18) Separation Nitoma
(6) Raised leg unit ψ Vertical posture holding device (16) σ7) Upper and lower horizontal arm rods U3X19
) Support roller □□□ Support Frame base) Corner bracing - Guide rail σ) High-ranking applicant for the steel tower: Chubu Oriki Co., Ltd. and 1 other person

Claims (2)

【特許請求の範囲】[Claims] (1)既設鉄塔に於ける外側に垂直設置された仮性た鉄
塔受梁に固設せるロッドを介して垂直姿勢を損なうこと
なく円滑な持上げ移動に伴う分離空間に、嵩上げ脚部ユ
ニツlr組立て形成し、その上面を鉄塔地上部の分断底
部と連結し、同下面は分断基礎部に連結設置することt
−特徴とする送電鉄塔の嵩上げ工法。
(1) Assembling and forming the raised leg unit lr in the separated space that allows for smooth lifting and movement without compromising the vertical posture through rods that are fixed to the temporary tower support beam installed vertically on the outside of the existing steel tower. The upper surface shall be connected to the divided bottom part of the above-ground part of the steel tower, and the lower surface shall be connected to the divided foundation part.
-Characteristic method for raising the height of transmission towers.
(2)既設鉄塔に於ける外側に仮性塔柱を垂直設置せし
め、該仮性塔柱に、油圧ジヤツキ部を固設、シ、鉄塔地
上部に差渡す鉄塔受梁を固設せる口・ンドにて昇降動自
在に連結形成すると共に、仮性塔柱の支持枠に設置した
案内レールに接合する支えローラーを両端に形成した上
下方の水平腕杆を固設する垂直姿勢保持装置をも構成し
たこと全特徴とする送電鉄塔の嵩上げ装置。
(2) A temporary tower column is installed vertically on the outside of the existing steel tower, a hydraulic jack part is fixed to the temporary tower column, and a bridge is installed at the opening/end where the steel tower support beam to be passed to the above-ground part of the steel tower is fixed. A vertical posture holding device is also constructed in which upper and lower horizontal arm rods are fixedly connected to each other so as to be able to move up and down freely, and the upper and lower horizontal arm rods have support rollers at both ends that are connected to guide rails installed on the support frame of the temporary tower column. A device for raising the height of power transmission towers with all its features.
JP16724782A 1982-09-25 1982-09-25 Method and apparatus for raising power transmission tower Granted JPS5955963A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16724782A JPS5955963A (en) 1982-09-25 1982-09-25 Method and apparatus for raising power transmission tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16724782A JPS5955963A (en) 1982-09-25 1982-09-25 Method and apparatus for raising power transmission tower

Publications (2)

Publication Number Publication Date
JPS5955963A true JPS5955963A (en) 1984-03-31
JPH0418110B2 JPH0418110B2 (en) 1992-03-26

Family

ID=15846183

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16724782A Granted JPS5955963A (en) 1982-09-25 1982-09-25 Method and apparatus for raising power transmission tower

Country Status (1)

Country Link
JP (1) JPS5955963A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004076781A1 (en) 2003-02-25 2004-09-10 Oehme Hermann R System for erecting a wind power plant
KR101310013B1 (en) * 2011-12-30 2013-09-24 경북대학교 산학협력단 Erection apparatus by using hydraulic jack
ES2672256A1 (en) * 2018-02-08 2018-06-13 Sociedad Española de Montajes Industriales S.A. (SEMI, S.A.) Tower construction procedure (Machine-translation by Google Translate, not legally binding)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5598580A (en) * 1979-01-20 1980-07-26 Toukiyuu Souden Kensetsu Kk Method of and apparatas for raising steel tower
JPS55145280A (en) * 1979-04-28 1980-11-12 Niigata Engineering Co Ltd Method of constructing pylon

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5598580A (en) * 1979-01-20 1980-07-26 Toukiyuu Souden Kensetsu Kk Method of and apparatas for raising steel tower
JPS55145280A (en) * 1979-04-28 1980-11-12 Niigata Engineering Co Ltd Method of constructing pylon

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004076781A1 (en) 2003-02-25 2004-09-10 Oehme Hermann R System for erecting a wind power plant
KR101310013B1 (en) * 2011-12-30 2013-09-24 경북대학교 산학협력단 Erection apparatus by using hydraulic jack
ES2672256A1 (en) * 2018-02-08 2018-06-13 Sociedad Española de Montajes Industriales S.A. (SEMI, S.A.) Tower construction procedure (Machine-translation by Google Translate, not legally binding)

Also Published As

Publication number Publication date
JPH0418110B2 (en) 1992-03-26

Similar Documents

Publication Publication Date Title
JP2003328323A (en) Construction method of tower structure
JPS5955963A (en) Method and apparatus for raising power transmission tower
JP2539150B2 (en) Bridge erection equipment
JP3988937B2 (en) Steel tower raising method
JP2979039B2 (en) Large space building construction equipment
JPH071195U (en) Steel frame erection equipment
JPH1061193A (en) Method of building steel frame structure and device therefor
JPH0932120A (en) Method of construction of structure
JPS5840121Y2 (en) Support stand for pile erection
JP2872886B2 (en) Construction lift equipment
JP2629441B2 (en) High-rise building construction method
JP2515361Y2 (en) Lifting device for construction
JP2854389B2 (en) Steel construction method
JP2776128B2 (en) Lifting device for building frame
JPH0791904B2 (en) Push-up device
JP2590671B2 (en) Construction method of steel frame using overhead crane frame
JP3318133B2 (en) How to build artificial ground
JP3125205B2 (en) Construction method of temporary side wall
JPS604321B2 (en) Bridge girder construction equipment
JPH0537876U (en) Tower crane climbing jig
JP3715378B2 (en) Automatic roof raising device and method of building a building by raising the roof
JP3139854B2 (en) Collapse prevention frame
JP2791749B2 (en) Method and apparatus for lifting up top-level frame for structure construction
JP2881503B2 (en) Temporary strut for stroke pole
JP2876991B2 (en) Steel frame method for high-rise buildings