JP2979039B2 - Large space building construction equipment - Google Patents

Large space building construction equipment

Info

Publication number
JP2979039B2
JP2979039B2 JP2284376A JP28437690A JP2979039B2 JP 2979039 B2 JP2979039 B2 JP 2979039B2 JP 2284376 A JP2284376 A JP 2284376A JP 28437690 A JP28437690 A JP 28437690A JP 2979039 B2 JP2979039 B2 JP 2979039B2
Authority
JP
Japan
Prior art keywords
pillar
temporary
jack
large space
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2284376A
Other languages
Japanese (ja)
Other versions
JPH04161566A (en
Inventor
憲衛 幸村
勉 前之原
雄太郎 仁科
今朝美 丸山
暁男 鳥羽
芳明 林田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP2284376A priority Critical patent/JP2979039B2/en
Publication of JPH04161566A publication Critical patent/JPH04161566A/en
Application granted granted Critical
Publication of JP2979039B2 publication Critical patent/JP2979039B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、例えば体育館、格納庫、倉庫のような大空
間建物の構築装置に関する。
Description: TECHNICAL FIELD The present invention relates to an apparatus for constructing a large space building such as a gymnasium, a hangar, and a warehouse.

[従来の技術] 従来、この種の大空間建物の構築方法としては、第8
図(A)〜(E)に示すように、 A.建物の所定位置に本設柱9を立設し、 B.該本設柱9の間に仮設柱10を組み立て、 C.これらの本設柱9および仮設柱10上にトラス架構屋根
11を構築し、 D.仮設柱11上のジャッキ12をジャッキダウンして仮設柱
10を該仮設柱11から切り離し、仮設柱11を仮想線状態か
ら実線状態のように本設柱9に受けさせ、 E.仮設柱11を解体撤去して、大空間建物を完成させる
か、 あるいは、第9図(A)〜(E)に示すように、 A.まず仮設柱13を組み立て、 B.トラス架構屋根14を地上で組み上げ、 C.該トラス架構屋根14を仮設柱13上に取り付けたリフト
アップ用ジャッキ15によりリフトアップし、 D.リフトアップしたトラス架構屋根14の下に本設柱16を
立設した後、トラス架構屋根14をリフトダウンして本設
柱16上に固定架設し、 E.仮設柱13を解体撤去して、大空間建物を完成させてい
た。
[Prior Art] Conventionally, as a method of constructing this kind of large space building, there is an eighth method.
As shown in FIGS. (A) to (E), A. Standing pillars 9 are erected at predetermined positions in the building, B. Temporary pillars 10 are assembled between the pillars 9, C. Truss frame roof on erection column 9 and temporary column 10
D. Jacking down the jack 12 on the temporary pillar 11 and jacking down the temporary pillar
10) is separated from the temporary pillar 11, the temporary pillar 11 is received by the main pillar 9 from the virtual line state to the solid line state, and E. The temporary pillar 11 is dismantled and removed to complete a large space building, or As shown in FIGS. 9 (A) to 9 (E), A. First, a temporary column 13 is assembled, B. A truss frame roof 14 is assembled on the ground, and C. The truss frame roof 14 is mounted on the temporary column 13. D. Lift up with the lift-up jack 15 and D. After the main pillar 16 is erected below the lifted truss frame roof 14, the truss frame roof 14 is lifted down and fixed on the main pillar 16. E. The temporary pillars 13 were dismantled and removed to complete the large space building.

[発明が解決しようとする課題] しかしながら、上記従来の大空間建物の構築方法のう
ち前者のジャッキダウン工法は、トラス架構屋根を高所
で組み立てるため、危険作業となるばかりでなく工期が
長くなって不経済となる等の問題点があり、一方、後者
のリフトアップ工法は、仮設柱がトラス架構屋根の全荷
重を支えるために大規模となり、工期や工費の点で無駄
が多い等の問題点があった。
[Problems to be Solved by the Invention] However, the jack-down method, which is the former method of constructing a large space building, is not only dangerous work but also requires a long construction time because the truss frame roof is assembled at a high place. On the other hand, the latter lift-up method has a problem in that the temporary columns are large in scale to support the entire load of the roof of the truss frame, and there are many wastes in terms of the construction period and construction costs. There was a point.

本発明は、上記従来の問題点を解決するためになされ
たもので、その目的とするところは、仮設柱を小規模化
して工費を節約すると共に工期も短くすることができ、
安全性および品質管理を向上せしめることのできる大空
間建物の構築装置を提供するものである。
The present invention has been made in order to solve the above-mentioned conventional problems, and the object thereof is to reduce the construction cost by reducing the size of the temporary pillars and shorten the construction period,
An object of the present invention is to provide a large space building construction apparatus capable of improving safety and quality control.

[課題を解決するための手段] 本発明の大空間建物の構築装置は、建物の適宜位置に
立設した本設柱の頂部に取り付けられ、地上で組み上げ
たトラス架構屋根をリフトアップするためのリフトアッ
プ用ジャッキと、該本設柱を補強支持する架設柱と、該
架設柱と本設柱との間に介挿されるジャッキダウン用の
支持ジャッキと、から構成されることを特徴とする。
[Means for Solving the Problems] A large space building construction apparatus according to the present invention is mounted on the top of a main pillar erected at an appropriate position in a building, and lifts a truss frame roof assembled on the ground. It is characterized by comprising a lift-up jack, a erection column for reinforcingly supporting the main column, and a jack-down support jack inserted between the erection column and the main column.

[実施例] 以下、本発明の一実施例について図面を参照しながら
説明する。
Hereinafter, an embodiment of the present invention will be described with reference to the drawings.

第1図において、1は本設柱であって、構築すべき建
物の四隅に立設される。本実施例の本設柱1はトラス柱
であるが、本発明はこれに限定するものではなく、鋼
柱、プレート柱等の鉄骨柱、鉄筋コンクリート柱、鉄骨
鉄筋コンクリート柱のいずれであってもよい。
In FIG. 1, reference numeral 1 denotes a main pillar, which is erected at four corners of a building to be constructed. Although the main pillar 1 of the present embodiment is a truss pillar, the present invention is not limited to this, and may be any of a steel pillar such as a steel pillar, a plate pillar, a reinforced concrete pillar, or a steel reinforced concrete pillar.

2は補強用仮設柱であって、第2図からも明らかなよ
うに、支持ジャッキ3を介して本設柱1を補強する。
Reference numeral 2 denotes a temporary reinforcing column, which reinforces the main column 1 via a support jack 3 as is apparent from FIG.

また、上記本設柱1の頂部にはリフトアップ用ジャッ
キ4が取り付けられる。
A lift-up jack 4 is attached to the top of the main pillar 1.

5はリフトアップ用仮設柱であって、上記本設柱1の
中間位置に必要に応じて設置される。該リフトアップ用
仮設柱5の頂部には、第3図に示すように、リフトアッ
プ用ジャッキ6が取り付けられる。
Reference numeral 5 denotes a temporary lifting column, which is installed at an intermediate position of the main column 1 as necessary. As shown in FIG. 3, a lift-up jack 6 is attached to the top of the temporary lift-up column 5.

上記本設柱1および仮設柱2,5の構築後、あるいはこ
れらの構築作業と併行して、第4図に示すように、トラ
ス架構屋根7を地上で組み上げる。該トラス架構屋根7
は、第5図からも明らかなように、立体トラス構造とな
っているが、大スパンの架構に十分耐え得るような構造
であればいずれでもよく、これに限定するものではな
い。
After or along with the construction of the main pillar 1 and the temporary pillars 2 and 5, as shown in FIG. 4, the truss frame roof 7 is assembled on the ground. The truss frame roof 7
Has a three-dimensional truss structure, as is clear from FIG. 5, but may be any structure as long as it can sufficiently withstand a large span frame, and is not limited thereto.

トラス架構屋根7の地組みが完了すると、上記リフト
アップ用ジャッキ4から吊り降ろした吊上げワイヤー8
の下端部をトラス架構屋根7の端部に緊結し、リフトア
ップ用ジャッキ4によりトラス架構屋根7をリフトアッ
プする。
When the framing of the truss frame roof 7 is completed, the lifting wires 8 suspended from the lift-up jacks 4
Of the truss frame roof 7 is lifted up by the lift-up jack 4.

第6図に示すように、トラス架構屋根7がリフトアッ
プされて本設柱1の頭部に取り付け固定されると、該本
設柱1およびトラス架構屋根7は大空間の架構建物とし
て一体化される。
As shown in FIG. 6, when the truss frame roof 7 is lifted up and fixed to the head of the main column 1, the main column 1 and the truss frame roof 7 are integrated as a large space frame building. Is done.

本設柱1とトラス架構屋根7が一体化されると、本設
柱1を補強支持している支持ジャッキ3をジャッキダウ
ンして、補強用仮設柱2を本設柱1から切り離し、トラ
ス架構屋根7の全荷重を本設柱1に移し替える。
When the main pillar 1 and the truss frame roof 7 are integrated, the support jack 3 that reinforces and supports the main pillar 1 is jacked down, the temporary reinforcing pillar 2 is separated from the main pillar 1, and the truss frame The entire load on the roof 7 is transferred to the main pillar 1.

この仮設時の状態から本設時の荷重の移し替えは、荷
重伝達が円滑になるよう2工程となり、その方法には、
リフトアップ用ジャッキ4を解放してから支持ジャッキ
3のジャッキダウンを行う方法と、逆に支持ジャッキ3
のジャッキダウンを行ってからリフトアップ用ジャッキ
4を解放する方法があり、いずれの方法でもよい。
The transfer of the load at the time of the permanent installation from the state at the time of the temporary installation is performed in two steps so that the load can be smoothly transmitted.
A method of releasing the lift-up jack 4 and then jacking down the support jack 3 and, conversely, a method of supporting the jack 3
And then releasing the lift-up jack 4, any method may be used.

続いて、本設柱1から切り離された補強用仮設柱2を
解体撤去すると同時にリフトアップ用仮設柱5も解体撤
去して、第7図に示すような、大空間建物を構築する。
Subsequently, the temporary pillars 2 for reinforcement separated from the main pillars 1 are dismantled and removed, and at the same time, the temporary pillars 5 for lift-up are also dismantled and removed, thereby constructing a large space building as shown in FIG.

[発明の効果] 1) リフトアップ用の柱として本設柱を利用できるよ
うにしたこと、そして本設柱を主体とし、仮設柱は本設
柱を補強して補助的に使用するようにしたので、仮設柱
を小規模化することができると共に、仮設柱の組み立て
及び解体撤去が簡素化されるので、工費を低減せしめる
と共に工期を短縮化することができる。
[Effects of the Invention] 1) The main pillar can be used as a lift-up pillar, and the main pillar is mainly used, and the temporary pillar is used as a supplemental use by reinforcing the main pillar. Therefore, the size of the temporary pillar can be reduced, and the assembling and dismantling of the temporary pillar can be simplified, so that the construction cost can be reduced and the construction period can be shortened.

2) トラス架構屋根を地上で組み立てるため、高所作
業が少なくなり、特に強風時などに作業の安全が確保で
きる。
2) Since the truss frame roof is assembled on the ground, work in high places is reduced, and work safety can be ensured especially in strong winds.

3) 仮設柱に過大な荷重がかからないため、仮設柱の
基礎も簡素化することができ、本設柱の基礎のみを設計
の上で考慮すればよい。
3) Since an excessive load is not applied to the temporary column, the foundation of the temporary column can be simplified, and only the foundation of the permanent column needs to be considered in the design.

4)荷重の伝達が2工程となり、一度に大きな荷重伝達
をしないで、安全性と精度の確認ができる。
4) The load is transmitted in two steps, and safety and accuracy can be confirmed without transmitting a large load at once.

5)本設時の状態と仮設時の応力状態がほぼ似ているた
め、本設鉄骨トラスを少なくすることができる。
5) Since the state at the time of the permanent installation and the stress state at the time of the temporary installation are substantially similar, the number of the steel trusses provided at the time of permanent installation can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

第1図は本設柱と補強用仮設柱の構築状態を示す施工説
明図、第2図は補強用仮設柱による本設柱の補強状態を
示す斜視図、第3図はリフトアップ用仮設柱の斜視図、
第4図はトラス架構屋根の地組み状態を示す施工説明
図、第5図は第4図の平面図、第6図はリフトアップ状
態を示す施工説明図、第7図は大空間建物の施工完了状
態を示す側面図、第8図(A)〜(E)及び第9図
(A)〜(E)は、各々従来の構築方法の施工説明図で
ある。 1……本設柱、2……補強用仮設柱、3……支持ジャッ
キ、4……リフトアップ用ジャッキ、5……リフトアッ
プ用仮設柱、6……リフトアップ用ジャッキ、7……ト
ラス架構屋根、8……吊りワイヤー。
1 is a construction explanatory view showing a construction state of a permanent pillar and a reinforcing temporary pillar, FIG. 2 is a perspective view showing a reinforcement state of the permanent pillar by a reinforcing temporary pillar, and FIG. 3 is a temporary lifting pillar. Perspective view of the
Fig. 4 is a construction explanatory view showing the trussed roof structure, Fig. 5 is a plan view of Fig. 4, Fig. 6 is a construction explanatory view showing the lift-up state, and Fig. 7 is the construction of a large space building. FIGS. 8 (A) to (E) and FIGS. 9 (A) to 9 (E) are side views showing the completed state, and are each an explanatory view of the construction of the conventional construction method. DESCRIPTION OF SYMBOLS 1 ... Main pillar, 2 ... Temporary column for reinforcement, 3 ... Support jack, 4 ... Jack for lift-up, 5 ... Temporary column for lift-up, 6 ... Jack for lift-up, 7 ... Truss Frame roof, 8 ... hanging wire.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 林田 芳明 神奈川県川崎市中原区上丸子天神町318 (58)調査した分野(Int.Cl.6,DB名) E04G 21/14 E04B 1/19 ────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Yoshiaki Hayashida 318 Tenjincho, Kamimaruko, Nakahara-ku, Kawasaki City, Kanagawa Prefecture (58) Fields investigated (Int.Cl. 6 , DB name) E04G 21/14 E04B 1/19

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】建物の適宜位置に立設した本設柱の頂部に
取り付けられ、地上で組み上げたトラス架構屋根をリフ
トアップするためのリフトアップ用ジャッキと、該本設
柱を補強支持する架設柱と、該架設柱と本設柱との間に
介挿されるジャッキダウン用の支持ジャッキと、から構
成されることを特徴とする大空間建物の構築装置。
1. A jack for lifting up a truss frame roof mounted on the ground, which is attached to the top of a main pillar erected at an appropriate position in a building, and an erection for reinforcingly supporting the main pillar. An apparatus for constructing a large space building, comprising: a pillar; and a jack-down support jack inserted between the erected pillar and the main pillar.
JP2284376A 1990-10-24 1990-10-24 Large space building construction equipment Expired - Lifetime JP2979039B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2284376A JP2979039B2 (en) 1990-10-24 1990-10-24 Large space building construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2284376A JP2979039B2 (en) 1990-10-24 1990-10-24 Large space building construction equipment

Publications (2)

Publication Number Publication Date
JPH04161566A JPH04161566A (en) 1992-06-04
JP2979039B2 true JP2979039B2 (en) 1999-11-15

Family

ID=17677788

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2284376A Expired - Lifetime JP2979039B2 (en) 1990-10-24 1990-10-24 Large space building construction equipment

Country Status (1)

Country Link
JP (1) JP2979039B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018115427A (en) * 2017-01-16 2018-07-26 株式会社大林組 Construction method of roof frame

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102337782B (en) * 2010-07-27 2013-08-07 北京星河模板脚手架工程有限公司 Lift system for constructing truss platform on top of tall and large space
CN105064697A (en) * 2015-07-15 2015-11-18 安徽跨宇钢结构网架工程有限公司 Roof grid elevating method
CN107355003B (en) * 2017-06-15 2020-04-07 上海二十冶建设有限公司 Modular construction method of large-span ultra-wide overweight truss
CN110512875A (en) * 2019-08-19 2019-11-29 北京市机械施工有限公司 A kind of method for improving of large-span truss structure
CN110924693A (en) * 2019-12-17 2020-03-27 北京首钢建设集团有限公司 Method for mounting large-span steel frame by using temporary support jig
CN112320553B (en) * 2020-10-28 2023-09-22 浙江精工钢结构集团有限公司 Lifting installation method and lifting tool for peripheral cantilever structure of cylinder

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018115427A (en) * 2017-01-16 2018-07-26 株式会社大林組 Construction method of roof frame

Also Published As

Publication number Publication date
JPH04161566A (en) 1992-06-04

Similar Documents

Publication Publication Date Title
JP2928948B2 (en) Construction method of large span roof
JP2979039B2 (en) Large space building construction equipment
JP2945917B2 (en) Construction method of large space building
JPH10331272A (en) Construction method of reinforced concrete columns, core walls, top layer wall beams and slabs
JPH1061193A (en) Method of building steel frame structure and device therefor
JP2942879B2 (en) Temporary house for all-weather construction
JPH05133016A (en) Peripheral supporting self-rising type building engineering method
US3435583A (en) Method of forming buildings
JP3066460B2 (en) How to build a tower
JP2858891B2 (en) Construction method of large span dome roof
JP3241896B2 (en) Steel frame stair hang down method
JPH0718743A (en) Construction method for large span domelike roof
JP3239154B2 (en) Lift-up device for all-weather temporary roof
JP2876991B2 (en) Steel frame method for high-rise buildings
JPH0518132A (en) Jack-up type construction method for steel structure such as tower type stereoscopic parking lot
JPS6282175A (en) Construction method for height increasing rebuilding while existing building is operated
JP3125205B2 (en) Construction method of temporary side wall
JP2946372B2 (en) Construction method of structure
JPH1181679A (en) Construction for building
JP2761527B2 (en) How to build structures
JPH0781323B2 (en) Building construction method
JP2785112B2 (en) All-weather construction method for high-rise buildings
JPH06101280A (en) Erection method
JP3124152B2 (en) Collapse prevention frame
JPH084120A (en) Building construction method