JPS5944407A - Prestressed concrete bridge constructing apparatus - Google Patents

Prestressed concrete bridge constructing apparatus

Info

Publication number
JPS5944407A
JPS5944407A JP15373882A JP15373882A JPS5944407A JP S5944407 A JPS5944407 A JP S5944407A JP 15373882 A JP15373882 A JP 15373882A JP 15373882 A JP15373882 A JP 15373882A JP S5944407 A JPS5944407 A JP S5944407A
Authority
JP
Japan
Prior art keywords
formwork
bridge
feed
girders
prestressed concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15373882A
Other languages
Japanese (ja)
Other versions
JPH0114370B2 (en
Inventor
三藤 重剛
石塚 敬之
仲佐 俊之
正 岡野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP15373882A priority Critical patent/JPS5944407A/en
Publication of JPS5944407A publication Critical patent/JPS5944407A/en
Publication of JPH0114370B2 publication Critical patent/JPH0114370B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は、あらかじめ施工された橋脚間に、プレストレ
ストコンクリート橋梁の上部工を区分ごとに施工するた
めの装置に係るものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an apparatus for constructing the superstructure of a prestressed concrete bridge section by section between piers that have been constructed in advance.

プレストレストコンクリート橋梁構築工法において従来
から使用されている装置は、橋梁上部工上に設けられる
送り桁に、前後の型枠装置をそれぞれ吊り枠を介して懸
垂装備したものであるが、この装置によって施工される
橋梁としては、その上部工の構造形式が一室の箱桁橋が
主であり、施工可能な幅員は最大でも15メートルが限
度である。
The equipment traditionally used in the prestressed concrete bridge construction method is one in which the front and rear formwork devices are suspended from the feed girder installed on the bridge superstructure via hanging frames. The main bridges to be built are box girder bridges with a single-room superstructure, and the width that can be constructed is limited to 15 meters at the most.

ところが、最近、道路橋などで一室の二連箱桁橋または
一室と二室の二連箱桁橋のように、大幅員のものの施工
が多くなり、それらの橋梁を一括施工することの必要性
が増している。
However, recently, there has been an increase in the construction of road bridges with large widths, such as double box girder bridges with one room or double box girder bridges with one room and two rooms, and it has become difficult to construct these bridges all at once. The need is increasing.

本発明は、上記の如き実状に鑑み、大幅員の橋梁の一括
施工が可能なプレストレストコンクリート橋梁構築装置
を提供しようとするものである。
In view of the above-mentioned circumstances, the present invention aims to provide a prestressed concrete bridge construction device that is capable of constructing large-scale bridges all at once.

次に本発明の構成を図面に示された一実施例について説
明する。
Next, the configuration of the present invention will be described with reference to an embodiment shown in the drawings.

図面(第1図〜第5図)において、1は施工を完了した
部分のプレストレストコンクリートの橋梁、2はその部
分の橋脚、3は次に橋梁を構築する部分の橋脚であって
、この橋脚3は橋梁の施工に先だってあらかじめ施工さ
れるものであり、橋脚3を中心として、その前方および
後方に向けて区分ごとにプレストレストコンクリートの
橋梁4が順次施工される。橋梁1および橋梁4は一定の
二連箱桁橋を構成するものである。5は一対の送り桁で
あって、この一対の送り桁5は、前記施工を完了した部
分の橋梁1および一部施工中の橋梁4の上部工上に、前
後3基の架台6によって支持されており、一対の送り桁
5は一定の間隔をおいて並設されている。各架台6は受
梁7、滑動梁および所要基数の油圧ジヤツキ8等によっ
て構成されており、架台6は送り桁5を橋軸方向、橋軸
直角方向および上下方向にそれぞれ移動し支持すると共
に、ウェブ間隔の変化にも枕材を挿入することにより容
易に対応し得るようになっている。9は吊り枠であって
、この吊り枠9は、基枠10の上部にアーチ状枠11を
取付けてなるものであり、吊り枠9は前記一対の送り桁
5上にそれと直交する方向に跨架され、かつ基枠10は
油圧ジヤツキおよびローラを備えた複数の移動台車12
を介して一対の送り桁5に移動および固定が自在にでき
るように支持されている。上記吊り枠9の両端部は一対
の送り桁5の両側方に張出しており、吊り枠9の両側張
出し部には4箇所8本のアイパー13によって型枠装置
14が懸垂装備されている。型枠装置14は、内型枠1
5と外型枠16によって構成されている。その内型枠1
5は一般の型枠支保工であって、区分ごとの橋梁施工の
都度組立てられ、解体されるものである。外型枠16は
、両側および中央の主桁17を複数の縦桁18で連結し
た枠組みに、底型枠19と側方型枠20を装備したもの
である。外型枠16の主桁17は4分割され、その各部
をそれぞれビン21により結合して一体としており、そ
の中央で左右両側に割れ、さらにそれぞれが2つに折た
たみ可能となっている。吊り枠9内に設置された複数基
のウィンチ22はその折たたみ操作用である。外型枠1
6の底型枠19は平床形状となっており、側方型枠20
は底型枠19上を自由に移動して装着することができる
ようになっている。23は複数の吊り鋼棒であって、コ
ンクリート打設時に外型枠16の底型枠19を吊り枠9
に吊る補強材である。
In the drawings (Figures 1 to 5), 1 is the part of the prestressed concrete bridge that has been completed, 2 is the pier of that part, and 3 is the pier of the part where the bridge will be constructed next. is constructed in advance prior to the construction of the bridge, and prestressed concrete bridges 4 are sequentially constructed for each section, centering on the piers 3, toward the front and rear of the piers. Bridge 1 and bridge 4 constitute a fixed double box girder bridge. 5 is a pair of feed girders, and this pair of feed girders 5 is supported by three mounts 6 in the front and rear on the superstructure of the bridge 1 where the construction has been completed and the bridge 4 which is partially under construction. The pair of feed girders 5 are arranged side by side at a constant interval. Each frame 6 is composed of a support beam 7, a sliding beam, a required number of hydraulic jacks 8, etc., and the frame 6 moves and supports the feed girder 5 in the direction of the bridge axis, the direction perpendicular to the bridge axis, and the vertical direction, respectively. Changes in web spacing can be easily accommodated by inserting pillow material. Reference numeral 9 denotes a hanging frame, and this hanging frame 9 is formed by attaching an arch-shaped frame 11 to the upper part of a base frame 10. The base frame 10 is supported by a plurality of movable carts 12 equipped with hydraulic jacks and rollers.
It is supported by a pair of feed girders 5 via the support so that it can be moved and fixed freely. Both end portions of the hanging frame 9 extend on both sides of the pair of feed girders 5, and a formwork device 14 is suspended from the both side projecting portions of the hanging frame 9 by means of eight eyepers 13 at four locations. The formwork device 14 includes an inner formwork 1
5 and an outer formwork 16. Inner formwork 1
5 is a general formwork support, which is assembled and dismantled each time a bridge is constructed for each section. The outer formwork 16 is a framework in which main girders 17 on both sides and the center are connected by a plurality of longitudinal girders 18, and a bottom formwork 19 and side formworks 20 are provided. The main girder 17 of the outer formwork 16 is divided into four parts, each of which is joined by a bin 21 to form a single body, which is split into left and right sides at the center, and furthermore, each part can be folded into two. A plurality of winches 22 installed within the hanging frame 9 are used for folding operations. Outer formwork 1
The bottom formwork 19 of No. 6 has a flat floor shape, and the side formwork 20
can be mounted by freely moving on the bottom formwork 19. Reference numeral 23 denotes a plurality of hanging steel rods, which connect the bottom formwork 19 of the outer formwork 16 to the hanging frame 9 during concrete pouring.
It is a reinforcing material that is hung on.

なお、送り桁5および吊り枠7にはトロリーホイスト用
レール24.25が設けられ、それぞれに必要なトロリ
ーホイストが設置される。型枠装置14は前後にそれぞ
れ1基ずつ設けられている。
Note that trolley hoist rails 24 and 25 are provided on the feed girder 5 and the hanging frame 7, and necessary trolley hoists are installed on each of them. One formwork device 14 is provided at the front and back.

紙上の如く構成された装置によりプレストレストコンク
リート橋梁を施工するには、施工を完了した橋梁1の上
部工から一対の送り桁5を次に橋梁を施工する橋脚3上
に移動させ、この一対の送り桁5に吊り枠9を介して懸
垂装備した前後の型枠装置14を用いて、橋脚3を中心
とし、橋軸方向Km梁4の上部工を前後1区分を張出し
施工する。以後、上記同様の工程を繰返して各区分ごと
に順次橋梁4の上部工を張出し施工し、既設橋梁1の先
端の閉合部およびそれに対応する片持部分を完成させる
To construct a prestressed concrete bridge using the device configured as shown in the paper, a pair of feed girders 5 are moved from the superstructure of the bridge 1 that has been completed onto the piers 3 on which the bridge will be constructed next, and the pair of feed girders 5 are Using the front and rear formwork devices 14 suspended from the girder 5 via the suspension frame 9, a superstructure of a beam 4 of Km in the bridge axis direction is constructed by overhanging the front and rear sections, centering on the pier 3. Thereafter, the same steps as described above are repeated to sequentially extend and construct the superstructure of the bridge 4 for each section, thereby completing the closing section at the tip of the existing bridge 1 and the corresponding cantilever section.

ところで、一対の送り桁5は、橋梁上部工上に一定間隔
をおいて並設されており、この一対の送り桁5にその両
側方に張出す吊り枠9を介して型枠装置14が′IN!
!垂装備されているので、型枠装置14が例えば−室の
二連箱桁橋や一室と二室の二連箱桁橋を施工するもので
あっても、これを安定かつ安全な姿勢に保持することが
でき、橋軸直角方向に40メートルにも及ぶ型枠装置1
4を懸垂装備することができる。したがって、橋梁上部
工の最大幅員が38メ一トル程度までの一括施工が可能
である。
By the way, a pair of feed girders 5 are arranged side by side at a constant interval on the bridge superstructure, and a formwork device 14 is attached to the pair of feed girders 5 via hanging frames 9 extending on both sides thereof. IN!
! Since the formwork device 14 is vertically mounted, it can be kept in a stable and safe position even if the formwork device 14 is to construct, for example, a two-chamber box girder bridge or a one-chamber and two-chamber double box girder bridge. Formwork device 1 that can hold up to 40 meters in the direction perpendicular to the bridge axis
4 can be equipped with suspension. Therefore, it is possible to construct bridge superstructures up to a maximum width of about 38 meters at once.

また、型枠装[14においては、その外型枠16゜の底
型枠19が平床形状となっているので、側方型枠20の
取付は位置を自由に変更することができる。このため、
道路橋のランプ部のように、橋梁上部工の幅員が大きく
異なり、かつウェブ位置が急変化するものであっても、
これに対応して施工することができる。底型枠19を平
床形状とし6一 たことは、その型枠としての残余部分を作業床に利用で
きる。
Further, in the formwork [14], since the bottom formwork 19 of the outer formwork 16° has a flat floor shape, the mounting position of the side formworks 20 can be changed freely. For this reason,
Even if the width of the bridge superstructure varies greatly and the web position changes suddenly, such as the ramp section of a road bridge,
Construction can be done accordingly. The fact that the bottom formwork 19 is shaped like a flat bed allows the remaining part of the formwork to be used as a work floor.

なお、外型枠16は中央から公印1して左右両側に折た
たむような構造になっているので、ラーメン橋脚のよう
な橋軸直角方向に幅の広い大橋脚であっても、型枠装置
14をそのまま通過させることができ、橋梁施工の作業
性が大いに向上する。
The outer formwork 16 is structured so that it can be folded from the center to the left and right sides, so even if it is a large pier such as a rigid-frame pier that is wide in the direction perpendicular to the bridge axis, the formwork device 14 can be passed through as is, greatly improving the workability of bridge construction.

さらに、一対の送り桁5のほかに吊り枠9にもトロリー
ホイスト用レール25を設けて、トロリーホイストを装
備したことKより、各種作業を行いやすくし、能率の向
上をはかることができる。
Furthermore, in addition to the pair of feed girders 5, the hanging frame 9 is also provided with trolley hoist rails 25, and by equipping the trolley hoist, various operations can be performed more easily and efficiency can be improved.

これを要するに、本発明は、あらかじめ施工された橋脚
間に、プレストレストコンクリート橋梁を区分ごとに施
工するための装置であって、橋梁上部工上に一定間隔を
おいて並設される一対の送り桁を設け、該一対の送り桁
上に、それと直交しかつ橋軸方向に移動および固定が自
在にできる吊り枠を設置し、上記吊り枠の両側張出し部
に型枠装置を@佃装備したものであるから、型枠装置を
大幅員のものとしても、これを吊り枠を介して一部7一 対の送り桁に安定した姿勢で安全に懸垂装備することが
でき、例えば道路橋などで一室の二連箱桁橋または一室
と二基の二連箱桁橋のように、大幅員の橋梁を一括施工
することができるうえ、その作業性および作業能率の向
上をはかることができる。
In summary, the present invention is an apparatus for constructing a prestressed concrete bridge section by section between piers that have been constructed in advance, and which includes a pair of feed girders that are installed in parallel at regular intervals on the bridge superstructure. A suspension frame is installed on the pair of feed girders, and a suspension frame that is orthogonal thereto and can be freely moved and fixed in the bridge axis direction, and formwork devices are equipped on both side overhangs of the suspension frame. Therefore, even if the formwork equipment is large in size, it can be safely suspended in a stable posture from a pair of feed girders via a hanging frame. It is possible to construct large bridges at once, such as double box girder bridges or double box girder bridges with one room and two units, and it is possible to improve workability and efficiency.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本発明に係るプレストレストコンクリート橋梁構
築装置の一実施例を示すものであって、第1図は全体の
側面図、第2図は一部の断面図、第3図は同上側面図、
第4図は型枠装置の外型枠を左右両側に折たたんだ状態
を示す断面図、第5図は同上側面図である。 1・・・橋梁、2.3・・・橋脚、4・・・橋梁、5.
5・・・一対の送り桁、6・・・架台、9・・・吊り枠
、13・・・アイバー、14・・・型枠装置、15・・
・内型枠、16・・・外型枠、19・・・底型枠、20
・−・側方型枠特許出願人 清水建設株式会社
The drawings show an embodiment of the prestressed concrete bridge construction apparatus according to the present invention, in which Fig. 1 is an overall side view, Fig. 2 is a partial sectional view, and Fig. 3 is a side view of the same.
FIG. 4 is a cross-sectional view showing a state in which the outer formwork of the formwork device is folded on both left and right sides, and FIG. 5 is a side view of the same. 1... Bridge, 2.3... Pier, 4... Bridge, 5.
5... Pair of feed girders, 6... Frame, 9... Hanging frame, 13... Eye bar, 14... Formwork device, 15...
・Inner formwork, 16... Outer formwork, 19... Bottom formwork, 20
・−・Side formwork patent applicant Shimizu Corporation

Claims (2)

【特許請求の範囲】[Claims] (1)あらかじめ施工された橋脚間に、プレストレスト
コンクリート橋梁(P、C橋梁)の上部工を区分ごとに
施工するための装置であって、橋梁上部工上に一定間隔
をおいて並設される一対の送り桁を設け、該一対の送り
桁上に、それと直交しかつ橋軸方向に移動および固定が
自在にできる吊り枠を設置し、上記吊り枠の両側張出し
部に型枠装置を懸垂装備したことを特徴とするプレスト
レストコンクリート橋梁構築装置。
(1) A device for constructing the superstructure of prestressed concrete bridges (P and C bridges) section by section between piers that have been constructed in advance, and is installed in parallel at regular intervals on the bridge superstructure. A pair of feed girders is provided, and on the pair of feed girders, a hanging frame that is perpendicular to the feed girders and that can be freely moved and fixed in the bridge axis direction is installed, and a formwork device is suspended from the overhangs on both sides of the hanging frame. Prestressed concrete bridge construction equipment characterized by:
(2)型枠装置は、内型枠と外型枠とで構成し、外型枠
の底型枠を平床形状としたことを特徴とする特許請求の
範囲第1項記載のプレストレストコンクリート橋梁構築
装置。 1−
(2) Prestressed concrete bridge construction according to claim 1, wherein the formwork device is composed of an inner formwork and an outer formwork, and the bottom formwork of the outer formwork has a flat floor shape. Device. 1-
JP15373882A 1982-09-03 1982-09-03 Prestressed concrete bridge constructing apparatus Granted JPS5944407A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15373882A JPS5944407A (en) 1982-09-03 1982-09-03 Prestressed concrete bridge constructing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15373882A JPS5944407A (en) 1982-09-03 1982-09-03 Prestressed concrete bridge constructing apparatus

Publications (2)

Publication Number Publication Date
JPS5944407A true JPS5944407A (en) 1984-03-12
JPH0114370B2 JPH0114370B2 (en) 1989-03-10

Family

ID=15569017

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15373882A Granted JPS5944407A (en) 1982-09-03 1982-09-03 Prestressed concrete bridge constructing apparatus

Country Status (1)

Country Link
JP (1) JPS5944407A (en)

Also Published As

Publication number Publication date
JPH0114370B2 (en) 1989-03-10

Similar Documents

Publication Publication Date Title
US3571835A (en) Apparatus for concreting multiple section structures, particularly bridge supports of reinforced or prestressed concrete
JP2010059748A (en) Apparatus and method for constructing bridge girder
CN107201719B (en) Viaduct anti-collision wall template hoisting transfer machine and anti-collision wall construction method
JP3845619B2 (en) Column head construction method
JPH08165613A (en) Erection method of bridge beam
JP2000087316A (en) Method and device for construction of floor slab
JPS5944407A (en) Prestressed concrete bridge constructing apparatus
JP2009179999A (en) Erection apparatus for constructing capital, method of constructing movable work vehicle using part of the same, and method of overhanging bridge
JP3790229B2 (en) Bridge construction method and bridge construction apparatus
GB1509440A (en) Movable formwork for building of bridge structures
JP4080070B2 (en) Floor slab construction method and apparatus
JPS6041165B2 (en) Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections.
JP2552997B2 (en) Bridge girder construction method and its equipment
JP2000087314A (en) Method and device for construction of floor slab
JPH0689527B2 (en) Construction work vehicle for PC cable-stayed bridge
CN217629466U (en) Corrugated steel web plate lifting system for bridge
JP2000170122A (en) Erection method of concrete girder and its device
JPH0114369B2 (en)
CN212454446U (en) Anchor section trolley is widened to tunnel both sides
JPS60258311A (en) Construction of high structure
JP3657544B2 (en) Construction work vehicle
JPS60192009A (en) Moving type mold frame construction method of slab of high bridge
JPH07102524A (en) Method for building concrete cable-stayed bridge and form supporting truck using the same
JPS61169507A (en) Under support type construction working vehicle
JP3318133B2 (en) How to build artificial ground