JPS60258311A - Construction of high structure - Google Patents

Construction of high structure

Info

Publication number
JPS60258311A
JPS60258311A JP11253884A JP11253884A JPS60258311A JP S60258311 A JPS60258311 A JP S60258311A JP 11253884 A JP11253884 A JP 11253884A JP 11253884 A JP11253884 A JP 11253884A JP S60258311 A JPS60258311 A JP S60258311A
Authority
JP
Japan
Prior art keywords
floor slab
block
girder
group
gate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11253884A
Other languages
Japanese (ja)
Other versions
JPH0336362B2 (en
Inventor
原田 雅男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd filed Critical Hazama Gumi Ltd
Priority to JP11253884A priority Critical patent/JPS60258311A/en
Publication of JPS60258311A publication Critical patent/JPS60258311A/en
Publication of JPH0336362B2 publication Critical patent/JPH0336362B2/ja
Granted legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は′、在来線の直上に更に高架構造物を構築する
施工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a construction method for constructing an elevated structure directly above a conventional railway line.

(従来技術とその問題点) 従来、営業線などの直上の高架構造物を構築する施工方
法としては、在来線を跨いで移動可能な作業構台を設け
、この上に支保工、型枠を組み場所打ちコンクリート打
設により施工するか、または施工場所から離れた作業基
地において製作されたブレキャスト部材を施工済の高架
構造物上または沿道を利用して施工場所まで運搬し、大
型クレーンにて吊り上げ組立てるなどの方法が知られて
いる0 しかしこrらの施工方法では、場所打ちコンクリートで
施工する場合には営業線直上で支保工および凰枠の組立
て、解体、鉄筋組立、コンクリート打設などの一連の繰
返し作業となるため、運行車栢に対する危険要因が多く
、安全性の確保が難しく、またプレキャスト部材を用い
′fc施工法ではプレキャスト部材の長距離運搬および
施工場所での重量物量シ上げ、移動などの作業において
安全性確保の対象範囲が広くなり、また場所打ちコンク
リート方法に較べてコスト高となる欠点がある。
(Prior art and its problems) Conventionally, the construction method for constructing elevated structures directly above commercial lines, etc. has been to set up a movable work platform that straddles the conventional line, and then install shoring and formwork on top of this. Construction is carried out by pouring concrete in place, or pre-cast members manufactured at a work base remote from the construction site are transported to the construction site on an already constructed elevated structure or along the roadside, and then transported using a large crane. Methods such as lifting and assembling are known. However, when using cast-in-place concrete, these construction methods involve assembling and dismantling shoring and roof frames directly above the service line, assembling reinforcing bars, and pouring concrete. As this is a series of repeated operations, there are many dangers to the operating vehicles, making it difficult to ensure safety.Furthermore, the 'FC construction method using precast members requires long-distance transportation of precast members and lifting of heavy materials at the construction site. This method has the disadvantage that the scope of ensuring safety during operations such as transportation is broader, and the cost is higher than that of cast-in-place concrete methods.

(発明の目的) 本発明は、従来の施工方法の欠点を解決するものであり
、在来線の直上に既設構造物を利用して床版を組立て、
こ扛を順次送出し、門型架台を使用して構築することに
より、安全にして施工効率のよい高架構造物構築の施工
方法を提供するものである。
(Object of the invention) The present invention solves the drawbacks of conventional construction methods, and involves assembling a floor slab using an existing structure directly above a conventional railway line.
The present invention provides a construction method for constructing an elevated structure that is safe and efficient in construction by sequentially sending out the bridges and constructing the structure using a gate-shaped frame.

(発明の構成) 本発明は、在来営業路線を跨ぎ床版吊上げ装置および床
版移動用ガーダ−の昇降引込み装置を備えた路線に平行
に敷設したレール上を走行する門型架台を使用して、先
ず前記路線の両側部に並行して立設さnる支柱群に支え
らnた床版よりなる第1ブロツクの構造物を構築したの
ちついで該構造物上にて隣接する第2ブロツクの床版を
築造するとともに第2ブロツクの支柱群を立設し、該支
柱群上に第1ブロツクに継合する床版移動用ガーダ−を
載置し、該ガーダ−上にて前記床版を支柱群上の所定位
置まで移動し、前記門型架台にて床版を吊上げたのち昇
降引込み装置によりガーダ−を床版吊下げに支障のない
位置まで移動し、床版を吊下げ支柱群上に載架して第2
ブロツクの構造物を構築する工程を順次繰返して高架構
造物を構築することを特徴とする高架構造物の施工方法
である。
(Structure of the Invention) The present invention uses a gate-shaped frame that straddles a conventional business route and runs on a rail that is installed parallel to the route and is equipped with a floor slab lifting device and a floor slab moving girder elevating and retracting device. First, a first block structure consisting of a floor slab supported by a group of pillars erected in parallel on both sides of the line was constructed, and then an adjacent second block structure was constructed on top of the structure. At the same time, a group of pillars for the second block is erected, a girder for moving the floor slab to be connected to the first block is placed on the group of pillars, and the floor slab is moved on the girder. After moving the girder to a predetermined position on the column group and hoisting the deck using the gate-shaped frame, move the girder using the elevating and retracting device to a position where there is no problem with hanging the deck, and then hang the deck and place it on the column group. Place the second one on top.
This method of constructing an elevated structure is characterized in that the elevated structure is constructed by sequentially repeating the steps of building a block structure.

(発明の実施例) 本発明の一実施例を図面により説明すると。(Example of the invention) An embodiment of the present invention will be described with reference to the drawings.

第1図および第3図は施工方法を説明する側面図でめシ
、第2図(A) 、 (B)は第1図のA−AおよびB
−B工り見た正面図、第4図(A)、(B)。
Figures 1 and 3 are side views for explaining the construction method, and Figures 2 (A) and (B) are A-A and B of Figure 1.
- Front view of B construction, Figures 4 (A) and (B).

(C)は第3図C−Cより見た正面図で7おり、施工順
序を説明する図面である。
(C) is a front view seen from FIG. 3 CC, and is a drawing for explaining the construction order.

先ず第1図、第2図(A)、(B)において5は在米の
営業路線であシ、鉄道または自動車道である。1,1′
は門型架台であり、本実施例にては2セツト使用さn1
門型架台l、1′は路線5を跨ぎ路線5の外側に平行に
敷設されたレール2上に載置さtている。門型架台1,
1′は、横桁3には複数台の油圧シリンダにより作動す
る床版(イ)上げ装置4を1脚柱3′には後述する床版
移動用ガーダ−17をブラケット6′上に収納する昇降
引込み装置6とを備えている。なお該昇降引込み装置6
は該床版移動用ガーダ−17を支柱15上にて支承調節
する昇降ジヤツキ7と脚柱3′側に移動させる引き込み
ジヤツキ8より構成さnている。
First, in Fig. 1, Fig. 2 (A), and (B), 5 is a business route in the United States, either a railroad or a motorway. 1,1'
is a gate-shaped frame, and two sets are used in this example.
The gate-shaped frames 1 and 1' are placed on a rail 2 which is laid parallel to the outside of the line 5 and straddles the line 5. Gate type mount 1,
1', a floor slab (a) lifting device 4 operated by a plurality of hydraulic cylinders is mounted on the crossbeam 3, and a girder 17 for moving the floor slab, which will be described later, is stored on the bracket 6' on the one-leg pillar 3'. It is equipped with an elevating and lowering retracting device 6. Note that the lifting/lowering retracting device 6
is composed of an elevating jack 7 for supporting and adjusting the floor slab moving girder 17 on the pillar 15, and a retracting jack 8 for moving it toward the pillar 3'.

先ず高架構造物構築の始点の位置に第1ブロツクの構造
物11が門型架台1,1′お工び其の他のクレーンなど
によシ構築さnる。この第゛1−ブロックの構造物11
は門型架台l、1′の跨間に路l1li!5の両側部に
並行して一足間隔に立設さnる支柱群12およびこの支
柱群12の上面に築造載架さする床版13よりなってい
る。
First, the structure 11 of the first block is constructed at the starting point of the construction of the elevated structure using gate-shaped frames 1, 1' and other cranes. This first block structure 11
The road l1li! is located between the gate-shaped frames l and 1'. It consists of a group of columns 12 erected parallel to both sides of the column 5 at one-foot intervals, and a floor slab 13 placed on the upper surface of the column group 12.

この第1ブロツクの構造物11を基点として、ついで路
線5に沿い隣接する第2ブロツクの構造物14の支柱群
15が立設さn、併行して第1ブロツクの構造物11上
で第2ブロツクの構造物140床版16が築造さnる。
Using the structure 11 of the first block as a base point, the column group 15 of the adjacent structure 14 of the second block is then erected along the route 5, and in parallel, a second column is placed on the structure 11 of the first block. A block structure 140 and a floor slab 16 are constructed.

支柱群15の立設および床版16の築造に引続き1対の
床版移動用ガーダ−17が載架さnる。該ガーダ−17
は支柱群15上に載架さnた昇降引込装置6の昇降ジヤ
ツキ7を介して支柱群15上に載置さnlその後端部1
8は第1ブロツクの構造物11の床版13の先端に継合
し、昇降ジヤツキ7を調節して床版移動用ガーダ−17
の上面は床版1301面と同一平面に保たn1脚柱3′
との間に転倒防止装置9が取付けらn床版移動用ガーダ
−17の垂直度が保たしる。ついで床版16は複数台の
移動台車19に載置さn1第2ブロツク側に牽引移動さ
A。
Following the erection of the column group 15 and the construction of the floor slab 16, a pair of floor slab moving girders 17 are mounted. The girder 17
The rear end portion 1 is placed on the support group 15 via the lifting jack 7 of the lifting retraction device 6 placed on the support group 15.
8 is connected to the tip of the floor slab 13 of the structure 11 of the first block, and by adjusting the lifting jack 7, a girder 17 for moving the floor slab is connected.
The upper surface of the n1 pedestal 3' is kept on the same plane as the floor slab 1301 surface.
An overturn prevention device 9 is installed between the floor slab moving girder 17 to maintain the verticality of the floor slab moving girder 17. Next, the floor slab 16 is placed on a plurality of movable carts 19 and pulled to the n1 second block side A.

第3図の如く第2ブロツクの支柱群15の所定位置まで
運搬される0 床版16の据付位置が確認されると、床版16は門型架
台1,1′の床版吊上げ装置4にエクー旦吊支さn、(
第4図(A)参照)ついで前記の床版移動用ガーダ−1
7は転倒防止装置9が取外さn昇降引込み装置6の引込
みジヤツキ8により支柱群15および床版13から外さ
れて脚柱3′側に引込まf床版16の吊下に支障がない
門型架台1,1′の脚柱3′のブラケット6′上に預け
らnる。(第4図(B)参照)引続き第4図((C)の
ように床版16は支柱群15上に吊下げらn接合さnて
第2ブロツクの構造物14が完成する。
As shown in Fig. 3, the floor slab 16 is transported to the predetermined position of the column group 15 of the second block. Once the installation position of the floor slab 16 is confirmed, the floor slab 16 is moved to the floor slab lifting device 4 of the gate-shaped frame 1, 1'. Ekudan Suspended n, (
(See Figure 4 (A)) Next, the above-mentioned floor slab moving girder 1
7 is a gate where the fall prevention device 9 is removed n is removed from the column group 15 and the floor slab 13 by the retracting jack 8 of the elevating and retracting device 6 and is retracted to the pedestal 3' side f which does not hinder the hanging of the floor slab 16 It rests on the bracket 6' of the pedestal 3' of the mold stand 1, 1'. (See FIG. 4(B)) Subsequently, as shown in FIG. 4(C), the floor slab 16 is suspended on the column group 15 and joined together to complete the structure 14 of the second block.

同様の方法によシ第3ブロック、第4ブロツク・・・の
構造物を構築し、なお各高架構造物のブロック間は更に
門型架台1,1′によQ連結桁20が順次連結さn1連
続した高架構造物が構築さnる0 (発明の効果) 以上説明した如く本発明の施工方法は、隣接する既設の
構造物を利用し、床版を組立て、こnを床版移動用ガー
ダ−を利用し所定の位置まで移動し、設置する方法を採
用しており、従つて場所打ちコンクリートでありながら
プレキャストと同一の効果を得ることができ、また設置
のための大型クレーン等は必要とせず、在来営業線の車
輛往来に何ら影響を及はさず、安全にして効率よく高架
構造物を構築できる施工方法である。なおこの施工方法
はコンクリート構造床版に止まらず鋼構造縦通桁を有す
る床版に対しても適用可能である。
Structures for the third block, fourth block, etc. were constructed in the same manner, and between the blocks of each elevated structure, Q connecting girders 20 were successively connected by gate-shaped frames 1 and 1'. (Effects of the Invention) As explained above, the construction method of the present invention utilizes adjacent existing structures to assemble floor slabs, and uses these to move the floor slabs. We use a girder to move and install the product to the specified location, so even though it is cast-in-place concrete, it can achieve the same effect as precast, and does not require a large crane etc. for installation. This is a construction method that allows for the construction of elevated structures safely and efficiently without any impact on vehicle traffic on conventional service lines. Note that this construction method is applicable not only to concrete structural deck slabs but also to deck slabs with steel structural longitudinal girders.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の施工方法を説明する側面図、第2図(
A)、(B)は第1図のA−AおよびB−Bより見た正
面図、第3図は本発明の施工方法を説明する側面図、第
4図(A−)、(B)、(C)は第3図のC−Cより見
た正面図であり、施工順序を説明する図面である。 1.1′・・・門型架台 2・・・レール 3・・・門
型架台の横桁 3′・・・門型架台の脚柱 4・・・床
版吊上げ装置 5・・・路線 6・・・昇降引込み装’
鵞6’・・・ブラケット 7・・・昇降ジヤツキ8・・
・引込みジヤツキ 9・・・転倒防止装置11・・・第
1ブロツクの構造物 12.15・・・支柱群 13.
16・・・床版 14・・・第2フ。 ロックの構造物 17・・・床版移動用ガータ゛−19
・・・移動台車 20・・・連結桁用 願 人 株式会
社 間 組 代理人 弁理士 高 雄次部 j
Figure 1 is a side view explaining the construction method of the present invention, Figure 2 (
A) and (B) are front views seen from A-A and B-B in Figure 1, Figure 3 is a side view explaining the construction method of the present invention, and Figures 4 (A-) and (B). , (C) is a front view seen from CC in FIG. 3, and is a drawing for explaining the construction order. 1.1'... Gate type mount 2... Rail 3... Cross beam of the gate type mount 3'... Pillar of the gate type mount 4... Floor slab lifting device 5... Line 6 ... Lifting retraction device'
Goose 6'... Bracket 7... Lifting jack 8...
- Retraction jack 9... Fall prevention device 11... Structure of the first block 12.15... Support column group 13.
16... Floor slab 14... 2nd floor. Lock structure 17...Garter for moving the floor slab-19
...Moving trolley 20...For connecting girder Applicant Hazama Co., Ltd. Agent Patent attorney Yujibe Taka j

Claims (1)

【特許請求の範囲】[Claims] 在来営業路線を跨ぎ床版吊上げ装置および床版移動用ガ
ーダ−の昇降引込み装置を備えた路線に平行に敷設した
レール上を走行する門型架台を使用して、先ず前記路線
の両側部に並行して立設さnる支柱群に支えらnた床版
工りなる第1ブロツクの構造物を構築したのち該構造物
上にて隣接する第2ブロツクの床版を築造するとともに
第2ブロツクの支柱群を立設し、該支柱群上に第1ブロ
ツクに継合する床版移動用ガーダ−を載置し、該ガーダ
−上にて前記床版を支柱群上の所定位置まで移動し、前
記門型架台にて床版を吊上げたのち昇降引込み5置によ
りガーダ−を床版吊下げに支障のない位置まで移動し、
床版を吊下げ支柱群上に載架して第2ブロツクの構造物
を構築する工程を順次繰返して高架構造物を構築するこ
とを特徴とする高架構造物の施工方法。
Using a gate-shaped frame running on rails laid parallel to the route, which is equipped with a floor slab lifting device and a girder elevating and retracting device for moving the floor slab, straddling the conventional business route, first, the bridge was installed on both sides of the route. After constructing the structure of the first block, which is a floor slab supported by a group of columns erected in parallel, the floor slab of the adjacent second block is constructed on top of the structure, and the second block is constructed. A group of pillars of the block is erected, a girder for moving the floor slab to be connected to the first block is placed on the group of pillars, and the floor slab is moved to a predetermined position on the group of pillars on the girder. Then, after hoisting the floor slab using the gate-shaped frame, move the girder to a position where it does not interfere with the suspension of the floor slab by raising and lowering the girder in 5 positions.
A method of constructing an elevated structure, which comprises constructing the elevated structure by sequentially repeating the steps of mounting the floor slab on a group of hanging supports to construct a second block structure.
JP11253884A 1984-06-01 1984-06-01 Construction of high structure Granted JPS60258311A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11253884A JPS60258311A (en) 1984-06-01 1984-06-01 Construction of high structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11253884A JPS60258311A (en) 1984-06-01 1984-06-01 Construction of high structure

Publications (2)

Publication Number Publication Date
JPS60258311A true JPS60258311A (en) 1985-12-20
JPH0336362B2 JPH0336362B2 (en) 1991-05-31

Family

ID=14589148

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11253884A Granted JPS60258311A (en) 1984-06-01 1984-06-01 Construction of high structure

Country Status (1)

Country Link
JP (1) JPS60258311A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020225A (en) * 1999-07-05 2001-01-23 Mitsubishi Heavy Ind Ltd Erection method of bridge and equipment therefor
JP2012117219A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct
JP2012117216A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct
JP2012117217A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct
JP2012117218A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020225A (en) * 1999-07-05 2001-01-23 Mitsubishi Heavy Ind Ltd Erection method of bridge and equipment therefor
JP2012117219A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct
JP2012117216A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct
JP2012117217A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct
JP2012117218A (en) * 2010-11-29 2012-06-21 Railway Technical Research Institute Construction structure of composite viaduct and construction method of composite viaduct

Also Published As

Publication number Publication date
JPH0336362B2 (en) 1991-05-31

Similar Documents

Publication Publication Date Title
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN107201719B (en) Viaduct anti-collision wall template hoisting transfer machine and anti-collision wall construction method
JP3579897B1 (en) Construction method of split bridge type traffic route and split bridge type traffic route
JP5184248B2 (en) Construction method of level crossing
WO2022142193A1 (en) Construction method for large-span thin-wall concrete sound barrier pouring trolley
JP2006028881A (en) Self-propelled pc floor slab erecting machine and pc floor slab erecting method
JP3025227B2 (en) Bridge construction method
JPS60258311A (en) Construction of high structure
CN110331672A (en) Across the pier bale handle holder device in bridge side position and its simple and fast construction method
CN205501840U (en) A braced system for construction of overpass cast -in -situ box girder
JP3349463B2 (en) How to install additional girder
CN212426772U (en) Suspended bracket system for cast-in-place bridge deck of steel plate composite beam
CN211772863U (en) Temporary fixing structure for multilayer municipal interchange ramps
JPH10204830A (en) Method for bridging bridge girder
JPS62185905A (en) Moving type mold frame construction method of slab of high bridge
KR102247200B1 (en) Method for carrying out replacement of an upperstructure of a bridge
JP3873101B2 (en) Equipment for placing slabs
JP2003147705A (en) Constructing method for divided bridge body type traffic road
JPS5894504A (en) Mold frame moving type constructing process of high bridge slab
JPH0312172B2 (en)
JPH0649810A (en) Method of removing bridge crossbeam
CN115679969A (en) Cover plate pouring method based on erection of portal frame body
JPH11293628A (en) Hung scaffold assembling method for bridge
JPH0426377B2 (en)
JPS62288260A (en) Moving type mold frame construction method of high bridging slab