JPS59432A - Correction for deviation of buried pipe - Google Patents

Correction for deviation of buried pipe

Info

Publication number
JPS59432A
JPS59432A JP57108885A JP10888582A JPS59432A JP S59432 A JPS59432 A JP S59432A JP 57108885 A JP57108885 A JP 57108885A JP 10888582 A JP10888582 A JP 10888582A JP S59432 A JPS59432 A JP S59432A
Authority
JP
Japan
Prior art keywords
tube
pipe
buried
sheath
buried pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP57108885A
Other languages
Japanese (ja)
Other versions
JPS611578B2 (en
Inventor
Susumu Iketani
進 池谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUSO GIKEN KK
Original Assignee
FUSO GIKEN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUSO GIKEN KK filed Critical FUSO GIKEN KK
Priority to JP57108885A priority Critical patent/JPS59432A/en
Publication of JPS59432A publication Critical patent/JPS59432A/en
Publication of JPS611578B2 publication Critical patent/JPS611578B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground

Abstract

PURPOSE:To safely correct the deviation of buried pipes without affecting objects on the ground surface by a method in which the discharge of soil, the take- out of pipe, embedment, and correction are made in the inside of a sheath tube fitted on the outside of the deviated portion of the buried pipe. CONSTITUTION:In case where a buried pipe 3 leading from a starting pit 1 to an arrival pit 2 is deviated vertically by a level difference H at one place, for example, a sheath tube 4 of an inside diameter corresponding to the total sum of the outside diameter (d) of the tube 3, the level difference H, and the excess spaces S1 and S2 in the upper and lower sides is penetrated into the pit 1 by a propulsory device 5, the soil between the tubes 4 and 3 is discharged, the deviated portion of the tube 3 is completely covered with the tube 4, and the tube 3 is taken out. The tube 3 is returned into the tube 4, placed on a regulating material 13 below the tube 4, and straightly connected to the remaining tube 3. Then, a filling material 14 is packed into the space around the tube 3 to fix the tube 3. Thereby, the deviation of the tube 3 can be safely and highly accurately corrected.

Description

【発明の詳細な説明】 その中で埋設管の5ねりを修正する各操作を順次に11
って、地上物に何等影響なく安全な埋設管の修正を行う
方法に関する。
[Detailed description of the invention] Therein, each operation for correcting the 5 torsions of the buried pipe is sequentially performed in 11 steps.
This article relates to a method for safely repairing underground pipes without affecting anything above ground.

近年、上下水道,電力ケーブル,挿入管,ガス管等を地
上物や地下の地盤に影響なく埋設する工事は益々増加し
、之tこ伴い各種の工法が開発され、手掘式の一般ヒュ
ーム管推進工法.機$1[の小口径推進工法.セミシー
ルド工法,w4管削進工法等が多く行われているが、何
れの工法【こおいても、施工中又は施行完了後トこlj
lll iすると、埋設した管が上下或は左右にうねっ
ていることがあり、特1・こ上下水道の場合は、落差に
よる自然流水であるため、管.路の5ねりの許容範囲が
□程度と非常に高い精度が要求される000 ため、埋設された管路に前記許容範囲以上の5ねりがあ
ると使いものにならないから、これを修正しな叶ればな
らないものであるが、現在その修正手段としては、埋設
管のうねり部を履う土に対して薬剤を注入し、地盤を固
めて作業員が埋設管の中トこ入シ、管を割るか、、溶断
するかして埋設管を取出し、管路端から新しい管を押し
込んで管の取り出された部分へ別の管を移動させて並び
の修正を行うか、又は埋設管の上部を開削して管を取り
出し、管を戻した後並びを修正して再び埋め戻す方法に
よシ修正したものであるが、前者の場合は地上物には影
響なく修正出来るが、薬注により固化させた地盤は工事
中1こ崩壊して人命にかかわる事故を起す危険性が高く
、又、後者の場合は河川や鉄道、建造物の下等の開削が
許されない場合には、施工することが出来ない現状であ
るため、当業界では゛ 地上物に影響を及ぼす開削を行
わず、地盤中において安全が保証された状態で埋設管の
5ねり修正が行える方法の完成が強く望まれていた。
In recent years, the number of construction works to bury water and sewage systems, power cables, insertion pipes, gas pipes, etc. without affecting above-ground structures or the underground ground has been increasing.As a result, various construction methods have been developed. Propulsion method. Small-diameter propulsion method for machine $1. Semi-shield construction method, W4 pipe cutting method, etc. are often used, but in both construction methods
In this case, buried pipes may undulate up and down or from side to side. Since the tolerance range for the 5-curvature of the pipeline is approximately □, very high accuracy is required, so if the buried pipeline has 5-curvatures that exceed the above-mentioned tolerance range, it will be unusable, so this must be corrected. However, the current method for correcting this problem is to inject chemicals into the soil that covers the undulating parts of the buried pipe, harden the ground, and then have workers dig into the buried pipe and break it. Or, remove the buried pipe by fusing it, push a new pipe from the end of the pipe, and move another pipe to the removed part to correct the alignment, or cut the top of the buried pipe. The method was to take out the pipes, put them back in, correct the alignment, and then fill them back in again.In the former case, the correction could be made without affecting anything above ground, but it was hardened by pouring chemicals. There is a high risk of the ground collapsing during construction and causing an accident involving human life, and in the latter case, construction cannot be carried out if excavation under rivers, railways, buildings, etc. is not allowed. Due to the current situation, there has been a strong desire in the industry for the completion of a method that can perform 5-curvature correction of buried pipes while ensuring safety in the ground, without requiring excavation that would affect above-ground objects.

本発明なこ関する埋設管の5ねり修正方法は、前述の要
望を満すためになされたもので、うねりを生じた埋設管
を鞘管に包容させて、この鞘管の中で排土、管の取り出
し、管の戻しと修正、空隙充填を行うことにより、地上
物に影響のない埋設管の修正を安全に行える方法を提供
することを目的とするものである。
The method for correcting the 5-curvature of a buried pipe, which is related to the present invention, was made to satisfy the above-mentioned requirements, and involves enclosing a buried pipe with a undulation in a sheath pipe, removing earth from the pipe within the sheath pipe, and The purpose of the present invention is to provide a method for safely repairing buried pipes without affecting above-ground objects by taking out the pipe, returning and repairing the pipe, and filling the void.

即ち、この方法は、地中の埋設管シこ上下又は左右の5
ねりを生じてその修正を必要とするときは、この埋設管
の外側へうねり部を包容し得る大とさの鞘管を、管路の
一端から押し込んでその中C・こ侵入した十等は管路外
へ排出させ、鞘管Pこ包容された埋設管は端部から順々
eこ取出してうねり部の終端のもの迄取り出されたとき
、取り出した埋設管を鞘管内へ戻し、調整部材により各
埋設管が真直ぐに接る様に位置決めして残存埋設管へ順
次接続して行き、修正後の埋設管と鞘管との隙間へ填隙
材を充填して、埋設管を固定、し、修正を完了するもの
であるから、全作業を鞘管により地盤の崩壊を防止させ
た安全な状態において行い得るから、危険性の高い地中
作業の安全が完壁に保証されて、然も、この方法は鞘管
による地盤保Npこより、地表に何等工事の影響を及ぼ
さないため、河川、鉄道、構造物の下での修正が問題な
〈実施出来るものである。
In other words, this method can be used to connect underground pipes up and down or left and right.
When a bend occurs and it needs to be corrected, a sheath pipe large enough to accommodate the undulation is pushed into the outside of the buried pipe from one end of the pipe, and C. The buried pipes are discharged to the outside of the pipe line, and the buried pipes enclosed in the sheath pipe P are taken out one after another from the end until they reach the end of the undulating part. Position each buried pipe so that it touches straight and connect it to the remaining buried pipe one by one.Fill the gap between the repaired buried pipe and the sheath pipe with a gap filler to fix the buried pipe. Since the modification is completed, all work can be done in a safe condition with the sheath pipe preventing the ground from collapsing, so the safety of highly dangerous underground work is completely guaranteed. Since this method does not affect the ground surface in any way due to the ground protection by the sheath pipe, it is possible to carry out corrections under rivers, railways, and structures.

更に、この方法は、埋設管の外に鞘管が存在するため、
その内部から排土すれば、鞘管の管壁がガイドとなり、
埋設管を戻して調整部材により残存管、修正管と真直ぐ
に接ぐ作業も簡単に行われるだけでなく、施工完了後は
、鞘管と填隙材とが埋設管を二重被覆するため、修正部
が補強されて地震等により再びうねりを生じたシ、崩壊
を起したりするおそれがない特有の効果を奏するもので
ある。
Furthermore, in this method, since there is a sheath pipe outside the buried pipe,
If you remove soil from inside, the wall of the sheath pipe will serve as a guide.
Not only is it easy to return the buried pipe and connect it straight to the remaining pipe and the repaired pipe using the adjustment member, but after the construction is completed, the buried pipe is double coated with the sheath pipe and the gap filling material, making it easy to repair the pipe. This has the unique effect of being reinforced so that there is no risk of it undulating or collapsing again due to earthquakes, etc.

次に本発明tこ関する方法を図面に基いて詳細に説明す
る。
Next, a method related to the present invention will be explained in detail with reference to the drawings.

図面第1図をこ示す様に発進チル1から到達坑2迄埋設
管3を埋設し、埋設途中か、埋設完了後に同図tこ示す
様【こ測量機aを用いて測量して、埋設管3をこ図面を
こ示す様なうねり部(このうねりは図示の様に一方向へ
一個所だけの単純なものではなく、何個所かに方向の違
ううねりが生ずることが多いが、便宜上単純tこ表わし
である)が認められれば、そのうねり量換言すれば、埋
設管3の高低差I]を計測し、埋設管3の外径dに前記
の高低差Hと、上下の余剰スペースS。
As shown in Figure 1 of the drawing, a buried pipe 3 is buried from the starting chill 1 to the arrival hole 2. The pipe 3 has an undulating portion as shown in the drawing (this undulation is not a simple one in one direction as shown in the figure, but often has several undulations in different directions, but for convenience, it is shown in a simple manner) If the amount of waviness (in other words, the height difference I of the buried pipe 3) is recognized, the outside diameter d of the buried pipe 3 is calculated by adding the above-mentioned height difference H and the surplus space S above and below. .

とSZとを合ま1した内径りの図面第一図に示す様な鞘
管4を準噛し、この鞘管4を前記うねり部に近い方の境
、例えば、発進★IL1から従来公知の推進機5を用い
て圧入すると共トこ、この鞘管4と埋設管3との間へ侵
入して来る土を、図面第4図に示す様に鞘管4に装着し
た遮板61こ開口する噴射ノズル7から水ジェツトを噴
射して崩しつつ、前記遮板6に開口させた吸引管8によ
り吸引させて外部へ排出するか、又は、図面第り図に示
す様tこ遮板6に注水管9と排水管lOよを開口させる
と共に、オーガ11を貫通させて、注水管9から注水し
つつ、図面第g図に示す様にオーガ11により土を掘削
してオーガ覆筒12tこより外部へ排出させ、排水は排
水管10により外部へ排出させれば、土により支持され
ていた埋設管3が遊離状態となるから、この遊離埋設管
3を一端から発進チル1へ恥シ出し、所定長さの鞘管4
が端末名圧入されれ・ば、鞘管4を接ぎ足して更に圧入
を行いながら、鞘4管4内へ侵入する土を外部へ排出し
、之に伴い遊離した埋込管3を発進を丸1へ取り出す操
作を続行して、鞘管4の先端が蛇行部の終端を越えたと
き圧入を止め、排土を行って遊離した埋込管3を引出せ
ば、埋込管3は図面第1図eこ示す様にうねり部の終端
より手前のものが総て取り出され、鞘管4内を空洞にす
るから、この状態において、発進抗1へ取り出した埋込
管3を鞘管4内へ戻し、鞘管4の下部f・こ↓メント等
の調整部材13を置いて、この上に埋込管3を乗せ、残
存している埋込管と真直ぐtこ接る様【・こ並びを調整
して、その周シと鞘管4との隙間1・こセメント等の填
隙材14を充填して埋込管3を固定し、この固定された
埋込管3に次の埋込管3を調整部材13により真直ぐ接
がる様に並びを調整して、埋込管3を鞘管4との隙間を
填隙材14により充填する操作を鞘管4の奥端から入口
端迄行えば、鞘管4内に図面第S図に示す埋込管3が真
直ぐに埋設されて、上下水道様″うねシの高低差力゛去
以内と5゛5厳しい条件にも適合する管理設が可能であ
り、然も、この方法は前述の作業を鞘管4により土の崩
壊を防止させつつ、その中において行っため、作業上P
こ全く危険性がなく、又、埋設管3は鞘管4と填隙材と
により二重被覆されて、修正後に曲りを生ずるおそれが
ないものである。
A sheath tube 4 as shown in FIG. When the propulsion device 5 is used to press fit the soil, the soil that enters between the sheath pipe 4 and the buried pipe 3 is removed through the opening of the shielding plate 61 attached to the sheath pipe 4 as shown in Figure 4 of the drawings. Either a water jet is injected from the spray nozzle 7 to break it up, and the shielding plate 6 is sucked through a suction pipe 8 opened in the shielding plate 6 and discharged to the outside. The water injection pipe 9 and the drain pipe 1O are opened, and the auger 11 is penetrated to inject water from the water injection pipe 9, and the soil is excavated by the auger 11 as shown in Figure g of the drawings, and the soil is removed from the auger cover tube 12t. If the wastewater is discharged to the outside through the drain pipe 10, the buried pipe 3 supported by the soil becomes free, so the free buried pipe 3 is brought out from one end to the starting chiller 1, and the drain is discharged to the outside through the drain pipe 10. Length of sheath tube 4
Once the terminal name is press-fitted, the sheath pipe 4 is added and press-fitted further, and the soil that has entered the sheath pipe 4 is discharged to the outside, and the embedded pipe 3 that has come loose due to this is completely removed from the start. 1, and when the tip of the sheath pipe 4 passes the end of the meandering part, stop the press-fitting, remove the earth, and pull out the free buried pipe 3. As shown in Fig. e, all the parts before the end of the undulating part are taken out and the inside of the sheath tube 4 is made hollow.In this state, the embedded tube 3 taken out to the starting shaft 1 is inserted into the sheath tube 4. Place the adjustment member 13 such as the lower part of the sheath tube 4, place the embedded tube 3 on top of it, and align it so that it comes into direct contact with the remaining embedded tube. After adjusting, the gap 1 between the circumference and the sheath tube 4 is filled with a gap filling material 14 such as cement, and the embedded tube 3 is fixed, and the next embedded tube is inserted into this fixed embedded tube 3. 3 so that they are in direct contact with each other using the adjusting member 13, and fill the gap between the embedded tube 3 and the sheath tube 4 with the gap filling material 14 from the inner end of the sheath tube 4 to the inlet end. For example, if the embedded pipe 3 shown in Figure S of the drawing is buried straight inside the sheath pipe 4, it is possible to create a management system that meets the strict conditions of water supply and sewerage systems by keeping the difference in height between the ridges within 50 degrees. However, since this method performs the above-mentioned work inside the sheath pipe 4 while preventing the soil from collapsing, the work P
There is no danger at all, and since the buried pipe 3 is double coated with the sheath pipe 4 and the gap filling material, there is no risk of bending after correction.

次に不発明に関する方法の実施例を説明する。Next, an example of a method related to non-invention will be described.

実施例/ 道路の下に管径がgo順で、総延長がgOmの分水管を
埋設し、埋設完了後に管路を測量すると、管路の一端か
ら20〜30mの範囲内に水平線に対する上りが7gO
maのうねり部が認められた。そこで、この埋設管の外
側へ外径/3 !; Omm 、肉厚/2叫の鋼製鞘管
を一端から圧管 入し、前記埋設管を包容させて鞘管と埋設との八 間へ侵入した土を外部へ排除し、之ンこ伴い遊離した埋
込管を順次に取り出して行き、うねり部の埋設管名歌り
出されたら、空洞となった鞘管の下部へ調整部材として
のセメントを流し、その上へ埋込管を置いて、残存埋込
管と真直ぐ接がる様に並びを調整し、この埋込管と鞘管
との間へ填隙材としてのセメントを詰め、埋込管を固定
して、前記同様の操作によりこの埋込管へ次の埋込管を
真直ぐに接続する操作を順次tこ行った。
Example: Diversion pipes with a diameter of go in order of go and a total length of gOm are buried under a road, and when the pipe is surveyed after the burying is completed, there is an upward slope relative to the horizon within a range of 20 to 30 m from one end of the pipe. 7gO
An undulating part of ma was observed. Therefore, the outside diameter of this buried pipe is /3! Omm, a steel sheath pipe with a wall thickness of 2 mm is inserted into the pipe from one end, and the buried pipe is enclosed, and the soil that has entered the space between the sheath pipe and the buried pipe is expelled to the outside, and the soil is released along with it. Take out the buried pipes one by one, and when the name of the buried pipe in the undulating part is sung, pour cement as an adjustment member into the lower part of the hollow sheath pipe, place the buried pipe on top of it, and Adjust the alignment so that it is in direct contact with the remaining buried tube, fill the space between this buried tube and the sheath tube with cement as a gap filler, fix the buried tube, and perform the same operation as above. The operation of connecting the next implanted tube straight to the implanted tube was performed t times in sequence.

その結果、うねり部の高低差が工以内に納ま000 る埋設管の修正作業を地上物に何等影響なく、安全に約
90時で完了することが出来た。
As a result, we were able to safely complete the repair work on the buried pipe, where the difference in height at the undulating part was within 1,000 hours, without any impact on above-ground structures, in about 90 hours.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は上下f・こうねりを生じた埋設管の断面図。第
2図は本発明tこ関する方法に使用する鞘管と埋込管と
の関係を示す縦断正面図。第3図〜第5図は本発明に関
する方法の施工順序を示す縦断側面図。第4図は鞘管内
の土を水ジェツトと吸引管で排出する場合の一部切欠縦
断側面図。第7図は同上正面図。第g図は鞘管内の土を
オーガで排出する場合の一部切欠縦断側面図。 第り図は同上正面図である。 図中3は埋設管、4は鞘管、13は調整部材、14は填
隙材である。 第 7 第 第 図 第 手続補正書(自制 昭和Sフイ]゛ 7 月/71] 1、事件の表示 昭和57年特許願第10ggg3号 2、発明の名称 埋設管のうねり修正方法 3、補正をする者 事件との関係  特 許 出 願 人 民  名   代 表 者    池  谷   達 
 雄4、代 理 人 明細書中1発明の詳細な説明」の欄 / 明細書中、第9頁下がら7行目pこI−g Omm
 lとあるをr g 00 mm−1と訂正します。 / 同上第10頁下がら/1行目に1−約り。時−1と
あるを1−約90時間」と、?J正します。
FIG. 1 is a cross-sectional view of a buried pipe that is curved upward and downward. FIG. 2 is a longitudinal sectional front view showing the relationship between the sheath tube and the implanted tube used in the method related to the present invention. 3 to 5 are longitudinal sectional side views showing the construction order of the method according to the present invention. FIG. 4 is a partially cutaway longitudinal side view when soil in the sheath pipe is discharged using a water jet and a suction pipe. Figure 7 is a front view of the same as above. Fig. g is a partially cutaway longitudinal side view when soil in the sheath pipe is discharged with an auger. The second figure is a front view of the same as above. In the figure, 3 is a buried pipe, 4 is a sheath pipe, 13 is an adjustment member, and 14 is a gap filler. 7 Figure No. Procedural Amendment (Self-restraint Showa S-F] July/71) 1. Indication of the case 1982 Patent Application No. 10ggg 3 2. Name of the invention Method for correcting undulations in buried pipes 3. Making amendments Relationship with the patent case Patent application People’s name Representative Tatsu Ikeya
Male 4, Agent Column 1 “Detailed explanation of the invention” in the specification / 7th line from the bottom of page 9 in the specification pkoI-g Omm
Correct "l" to "r g 00 mm-1". / Same as above, page 10, bottom, 1st line, 1-about. Hours - 1 and 1 - about 90 hours, ? J Correct.

Claims (1)

【特許請求の範囲】[Claims] 埋設管に生じたうねり部の外側C・こ、該うねり部を許
容し得る鞘管を嵌装し、該鞘管の内部において排土、埋
設管の取り出し、埋設管の戻し、並び修正、空隙充填を
順次トこ行うことを特徴とした埋設管のうねり修正方法
Outside the undulations that have occurred in the buried pipe, a sheath pipe that can accommodate the undulations is fitted, and inside the sheath pipe, earth is removed, the buried pipe is taken out, the buried pipe is returned, alignment is corrected, and gaps are formed. A method for correcting waviness in a buried pipe, characterized by sequentially filling the pipe.
JP57108885A 1982-06-24 1982-06-24 Correction for deviation of buried pipe Granted JPS59432A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57108885A JPS59432A (en) 1982-06-24 1982-06-24 Correction for deviation of buried pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57108885A JPS59432A (en) 1982-06-24 1982-06-24 Correction for deviation of buried pipe

Publications (2)

Publication Number Publication Date
JPS59432A true JPS59432A (en) 1984-01-05
JPS611578B2 JPS611578B2 (en) 1986-01-18

Family

ID=14496057

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57108885A Granted JPS59432A (en) 1982-06-24 1982-06-24 Correction for deviation of buried pipe

Country Status (1)

Country Link
JP (1) JPS59432A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4975134A (en) * 1985-06-14 1990-12-04 The Yokohama Rubber Co. Method for supplying tire constituent material
CN111692423A (en) * 2020-05-13 2020-09-22 坝道工程医院(平舆) Trenchless in-situ deviation rectification design construction method for jacking pipe

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4975134A (en) * 1985-06-14 1990-12-04 The Yokohama Rubber Co. Method for supplying tire constituent material
CN111692423A (en) * 2020-05-13 2020-09-22 坝道工程医院(平舆) Trenchless in-situ deviation rectification design construction method for jacking pipe
CN111692423B (en) * 2020-05-13 2022-01-07 坝道工程医院(平舆) Trenchless in-situ deviation rectification design construction method for jacking pipe

Also Published As

Publication number Publication date
JPS611578B2 (en) 1986-01-18

Similar Documents

Publication Publication Date Title
WO2021109144A1 (en) Modular intelligent dado cast-in-place pile and construction process therefor
US4329083A (en) Methods of laying underground conduits
US4170248A (en) Method for repairing sewer pipes
CN108442370A (en) The broken pile connector processing method of prestressed concrete pipe pile
JPS59432A (en) Correction for deviation of buried pipe
KR101974826B1 (en) The Precast Pile Having Interlocking Secant and The Earth Retaining Wall Method Constructed by It's Continuous Pile
CN214738262U (en) Temporary plugging structure for comprehensive pipe rack
RU2144637C1 (en) Pipe line for transportation of fluid medium and method of its erection
JP3347866B2 (en) How to lay the tunnel footstep
JPS6158640B2 (en)
KR100632971B1 (en) Propulsion method and apparatus for underground donduits
KR102515341B1 (en) the degree structure of the steel pipe for the work equipment in which the dismantlement facilitates
KR20200005841A (en) Rainwater storage tank construction method using top-down method
KR102609258B1 (en) Hybrid collaboration recovering method
JPS603394A (en) Construction of underground connecting measure
CN113932063B (en) Underground pipeline construction process and migration and modification method
KR20180014792A (en) H-beam extraction method used in retaining wall methods
JP2953843B2 (en) Pipe line laying method by non-cutting propulsion method
JPH01198920A (en) Reinforcing method for underground earth guarding wall by earth anchor
KR102191503B1 (en) The Tunnel construction method to use retangular pipe
JP7208840B2 (en) Method for shear reinforcement of reinforced concrete walls
KR200336460Y1 (en) foundation bottom permanent drainage structure using trench and drainage member
JP3923482B2 (en) Underground conduit construction method
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
KR100518460B1 (en) Reinforcement formwork for sewage pipe in civil engineering and road construction