JP2953843B2 - Pipe line laying method by non-cutting propulsion method - Google Patents

Pipe line laying method by non-cutting propulsion method

Info

Publication number
JP2953843B2
JP2953843B2 JP3333291A JP33329191A JP2953843B2 JP 2953843 B2 JP2953843 B2 JP 2953843B2 JP 3333291 A JP3333291 A JP 3333291A JP 33329191 A JP33329191 A JP 33329191A JP 2953843 B2 JP2953843 B2 JP 2953843B2
Authority
JP
Japan
Prior art keywords
pit
pipe
sewage
pits
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP3333291A
Other languages
Japanese (ja)
Other versions
JPH05163890A (en
Inventor
国昭 大西
裕之 関
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui Chemical Co Ltd
Original Assignee
Sekisui Chemical Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui Chemical Co Ltd filed Critical Sekisui Chemical Co Ltd
Priority to JP3333291A priority Critical patent/JP2953843B2/en
Publication of JPH05163890A publication Critical patent/JPH05163890A/en
Application granted granted Critical
Publication of JP2953843B2 publication Critical patent/JP2953843B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Sewage (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は、下水道・上水道等、
地中に埋設する管路の敷設工事に適する非開削推進工法
による管路敷設方法に関するものである。
[Industrial applications] The present invention relates to
The present invention relates to a method of laying a pipeline by an uncutting propulsion method suitable for laying a pipeline buried underground.

【0002】[0002]

【従来の技術】下水道・上水道等、地中に埋設する管路
の敷設工事では、敷設する管路の途中に汚水ます、マン
ホール、掃除口、管路分岐ます等(以下汚水ます等とい
う)を設置するためのピット掘削を要する例が多い。そ
して、これ等各ピットの掘削以外は、道路、建造物等の
ため地上から行なう開削式の管路掘削ができないケース
がある。
[Prior Art] When laying pipes to be buried in the ground, such as sewers and waterworks, sewage, manholes, cleaning outlets, pipe branches, etc. (hereinafter referred to as sewage squirrels, etc.) in the middle of pipes to be laid. In many cases, pit excavation is required for installation. Except for excavation of these pits, there are cases in which open-cut type pipeline excavation performed from the ground cannot be performed due to roads, buildings, and the like.

【0003】上記ケースの場合には、例えば特公昭58
−38598号公報に開示されている「小径管の案内付
埋設管工法」、或は「フローモール工法」と呼ばれてい
る地上から開削しない非開削推進工法によって管路敷設
工事が実施されている。
In the case described above, for example,
Pipe laying work is carried out by a non-cutting propulsion method that does not cut from the ground called the "buried pipe method with small diameter pipe" disclosed in Japanese Patent No. 38598/1996 or the "flow molding method". .

【0004】上記従来技術の概要は、両端および中間に
必要な複数の立坑(ピット)をまず掘削する。次に、先
端ドリルヘッドに流体ジェット推進機構を取付けた掘削
管によって、一端のピットから、途中のピットを次々と
通り他端のピットまでボーリングする。そして、この掘
削管に所定の上水道管、下水道管等を連結して掘進孔内
への管路敷設を行なう工法である。
[0004] The above prior art outlines that a plurality of shafts (pits) required at both ends and in the middle are first excavated. Next, a drilling pipe having a fluid jet propulsion mechanism attached to the tip drill head drills the pits at one end one after another through the pits on the way to the pit at the other end. In this method, a predetermined water supply pipe, a sewer pipe, or the like is connected to the excavation pipe to lay a pipeline in the excavation hole.

【0005】なお上記の工法の基になる非開削推進工法
は、地上からの電子誘導により地中を100メートル程
度の距離までは掘進可能な工法であり、地上から掘削す
るよりコストが安い特徴をも有している。
[0005] The non-digging propulsion method, which is the basis of the above-mentioned method, is a method that can excavate up to a distance of about 100 meters in the ground by electronic guidance from the ground, and is characterized by a lower cost than excavating from the ground. Also have.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、上記従
来の非開削推進工法による管路敷設方法は、掘進装置を
セットした端のピットから例えば15メートルとか20
メートル先の次のピットまでは正確に掘進することがで
きるが、先端ドリルヘッドの重量が大きいため、ピット
部分では先端ドリルヘッドの方向制御が困難であり、次
の、そして更にその先のピットまで連続して掘進する
と、期待した精度での掘進ができないといった問題があ
った。
However, the conventional pipe laying method by the non-cutting propulsion method is, for example, 15 meters or 20 meters from the pit at the end where the excavating device is set.
It is possible to excavate accurately up to the next pit a meter away, but due to the weight of the tip drill head, it is difficult to control the direction of the tip drill head in the pit part, and to the next and further pits There is a problem in that excavation cannot be performed with the expected accuracy when excavating continuously.

【0007】また、ピットごとに、掘進装置を移動しセ
ットし直して掘進作業を実施することは手数と工事日数
の面で問題があった。
[0007] In addition, moving the excavating device for each pit, resetting the excavating device, and performing the excavation work has a problem in terms of labor and work days.

【0008】この発明は、上記従来技術の問題点を解消
するために成されたもので、比較的短い間隔で汚水ます
等を設置するためのピットの掘削を必要とする埋設管路
敷設工事を非開削推進工法によって容易に実施すること
ができる非開削推進工法による管路敷設方法を提供する
ことを目的とするものである。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems of the prior art, and lays a buried pipeline which requires excavation of a pit for installing a sewage basin at a relatively short interval. It is an object of the present invention to provide a pipe laying method by a non-cutting propulsion method which can be easily implemented by a non-cutting driving method.

【0009】[0009]

【課題を解決するための手段】このため、この発明に係
る非開削推進工法による管路敷設方法は、中間にピット
掘削予定個所を挟んでピットを掘削する工程と、前記中
間にピット掘削予定個所を挟んだピット間の地中を非開
削推進工法により掘進して管を敷設する工程と、前記敷
設した管の上方から予定個所に中間のピットを掘削する
工程と、ピット内への所定の作業を実施する工程とより
なることを特徴とする方法によって、前記の目的を達成
しようとするものである。
Therefore, according to the present invention, a pipe laying method using a non-cutting propulsion method according to the present invention includes a step of digging a pit with a pit excavation part in the middle, and a pit excavation part in the middle. A step of digging the underground between the pits sandwiching the pit by a non-cutting propulsion method and laying a pipe, a step of digging an intermediate pit at a predetermined location from above the laid pipe, and a predetermined work in the pit The above-mentioned object is achieved by a method characterized by comprising the step of performing the following.

【0010】[0010]

【作用】上記の構成により、中間にピット掘削予定個所
を挟んでピットを掘削し、掘削されたピット間の地中を
非開削推進工法により掘進してピット間に管を敷設する
ので、従来工法と異なり先端ドリルヘッドの重量が大き
いためにピット部分で先端ドリルヘッドの方向制御が困
難になるといったことがなく、他方のピットまで正確に
地中を掘進し、埋設管を敷設することができる。
According to the above construction, a pit is excavated in the middle of the pit to be excavated, and a pipe is laid between the excavated pits by digging the underground by a non-digging propulsion method. Unlike this, since the weight of the tip drill head is large, it is not difficult to control the direction of the tip drill head in the pit portion, and it is possible to accurately dig into the ground to the other pit and lay a buried pipe.

【0011】そして、管路中間に必要なピットは、埋設
した管の上方から容易に所定個所を掘削することができ
る。そして掘削したピット内に汚水ます等を形成するの
に必要な作業、即ち汚水ます、マンホール、掃除口、管
路分岐ます等に必要な諸作業を実施でき、非開削推進工
法によって埋設管路を完成させることができる。
The pit required in the middle of the pipe can be easily excavated from above the buried pipe. The work required to form sewage pits in the excavated pits, that is, sewage pits, manholes, cleaning ports, pipe branching, etc. can be performed. Can be completed.

【0012】[0012]

【実施例】以下、この発明に係る非開削推進工法による
管路敷設方法を実施例により説明する。図1ないし図4
は、一実施例の工程構成を示す工程説明図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A pipeline laying method according to the present invention will be described below with reference to an embodiment. 1 to 4
FIG. 3 is a process explanatory view showing a process configuration of one embodiment.

【0013】まず、図1に示すように敷設する予定管路
上にピット1,ピット2を掘削する。本実施例は、下水
道管路工事であり、ピット1とピット2とは約80メー
トルの距離があり、その中間には排水ます等を設置する
ための2個所のピット掘削予定個所がある。
First, as shown in FIG. 1, pits 1 and 2 are excavated on a pipeline to be laid. In this embodiment, the pit 1 and the pit 2 are about 80 meters apart from each other, and there are two pit excavation places in the middle of the pit 1 for installing a drainage basin and the like.

【0014】次に、前記従来の非開削推進工法または同
工法に準ずる工法によって、ピット1とピット2の間の
地中を掘進し、下水道管3を敷設する(図2)。
Next, the underground between the pits 1 and 2 is dug by the conventional non-cutting propulsion method or a method similar to the method, and a sewer pipe 3 is laid (FIG. 2).

【0015】必要により、再びピット予定個所を1個所
または複数個所挟んで次のピットを掘削し前記同様にし
て地中を掘進し、下水道管を敷設する。
If necessary, the next pit is excavated again by sandwiching one or a plurality of scheduled pit locations, and the underground is dug in the same manner as described above, and a sewer pipe is laid.

【0016】次に、図3に示すように、掘削したピット
1とピット2の間の汚水ます等の設置予定位置に、敷設
した下水道管3の上方からピット4,5を掘削する。な
お図3は、汚水ます等の設置のためにピット4,5内に
露出している下水道管3を所定寸法だけ切断した状態を
示してある。
Next, as shown in FIG. 3, pits 4 and 5 are excavated from above the laid sewer pipe 3 at a location where the excavated pit 1 and pit 2 are to be installed, such as a sewage pit. FIG. 3 shows a state in which the sewer pipe 3 exposed in the pits 4 and 5 has been cut by a predetermined dimension for installation of a sewage basin or the like.

【0017】そして掘削したピット1,2,4,5内に
汚水ます等を形成するのに必要な作業、即ち汚水ます、
マンホール、掃除口、管路分岐ます等に必要な諸作業を
実施し、埋設管路を完成させる(図4)。
The work required to form sewage pits and the like in the excavated pits 1, 2, 4, and 5, ie, sewage pits,
Perform various operations required for manholes, cleaning openings, pipe branching, etc. to complete the buried pipeline (Fig. 4).

【0018】図5ないし図7は、上記のピットに設置す
る汚水ます等に好適なます本体の例を示した断面図であ
る。
FIGS. 5 to 7 are cross-sectional views showing examples of a main body suitable for a sewage basin or the like installed in the pit.

【0019】図5は、ます本体6の底面を広くして下水
道管3への荷重を低減させた例であり、8は下水道管3
の損傷を防止する保護カバーである。
FIG. 5 shows an example in which the bottom of the main body 6 is widened to reduce the load on the sewer pipe 3.
This is a protective cover that prevents damage to the camera.

【0020】図6は、ます本体6の底面に、下水道管3
の敷設方向と同方向に窪み7を設けて、下水道管3への
荷重を低減できることを特徴としたものである。
FIG. 6 shows a sewage pipe 3 on the bottom of the main body 6.
The recess 7 is provided in the same direction as the laying direction of the sewage pipe, so that the load on the sewer pipe 3 can be reduced.

【0021】図7は、ます本体6の底面に、下水道管3
の敷設方向と同方向に2条の窪み7を設けて、ます本体
6の下方の2本の下水道管3への荷重を低減できること
を特徴としたものである。
FIG. 7 shows that the sewage pipe 3
The two dents 7 are provided in the same direction as the laying direction, and the load on the two sewer pipes 3 below the main body 6 can be reduced.

【0022】図4に示すピット5は、真空弁付き汚水ま
すを設置した例を示してある。真空弁付き汚水ますは、
真空式下水道設備に使用する汚水ますの一種であり、汚
水溜めを有する汚水ます本体6と、該汚水溜め内の汚水
が所定レベルに上昇したとき負圧状態の外部管路と連通
させて汚水を排出する真空弁9を備え、汚水溜めに溜っ
た汚水を負圧の下水道管に放流するための汚水ますであ
る。
The pit 5 shown in FIG. 4 shows an example in which a sewage tank with a vacuum valve is installed. Sewage squirrel with vacuum valve
It is a type of sewage basin used for vacuum sewerage equipment, and is connected to a sewage basin body 6 having a sewage reservoir and an external pipeline in a negative pressure state when the sewage in the sewage reservoir rises to a predetermined level. This is a sewage tank provided with a vacuum valve 9 for discharging and discharging sewage collected in a sewage sump into a negative pressure sewer pipe.

【0023】図8ないし図10は、上記真空弁付き汚水
ますの設置工事の説明図である。
FIG. 8 to FIG. 10 are explanatory views of the installation work of the above-mentioned sewage tank with a vacuum valve.

【0024】まず図8に示すように掘削したピット5内
には下水道管3が露出している。この下水道管3に合流
用分岐管路10を取付ける。本実施例では図9に示すよ
うに45度Yチーズ11を使用して合流用分岐管路10
を接続し立ち上げてある。
First, the sewer pipe 3 is exposed in the excavated pit 5 as shown in FIG. A branch pipe 10 for joining is attached to the sewer pipe 3. In this embodiment, a 45 degree Y cheese 11 is used as shown in FIG.
Is connected and started.

【0025】そして、掘削したピット5の底部分に盛り
土し転圧して下水道管3を覆った後、図10に示すよう
に、ピット5内に真空弁付き汚水ます本体6を載置し、
下水道管3に通ずる合流用分岐管10と真空弁付き汚水
ます内の真空弁9に通ずる接続管12を直接または中間
に連結管を介在させて接続する。
Then, after filling the bottom of the excavated pit 5 and rolling it to cover the sewer pipe 3, the sewage body 6 with a vacuum valve is placed in the pit 5 as shown in FIG.
A branch pipe 10 for merging connected to the sewer pipe 3 and a connecting pipe 12 connected to the vacuum valve 9 in the sewage tank equipped with a vacuum valve are connected directly or in the middle via a connecting pipe.

【0026】その後、真空弁付き汚水ますに汚水を送る
汚水流入管(不図示)および必要な制御用の配管、配線
をし真空弁付き汚水ますに蓋をし、真空弁付き汚水ます
の周囲を埋め戻し整地して、真空弁付き汚水ますの設置
工事を終了する。
After that, sewage inflow pipe (not shown) for sending sewage to the sewage with vacuum valve, necessary control piping and wiring, cover the sewage with vacuum valve and cover the sewage with vacuum valve Landfilling is completed, and the installation work of the sewage tank with vacuum valve is completed.

【0027】なお上記各種管の接続方法は、管の材質に
応じてエレクトロフュージョン継手(EF継手)、RR
接続等各種の方法が利用可能であり、接続方法は適宜選
択して施工できる。
The above-mentioned various pipes can be connected by an electrofusion joint (EF joint), an RR joint or the like depending on the material of the pipe.
Various methods such as connection can be used, and the connection method can be appropriately selected and executed.

【0028】なお、ピット5の底部分への盛り土、転圧
工程を開始するに際して、ピット5内に露出している下
水道管3に前記の保護カバー(不図示)を被せ、盛り
土、転圧作業を留意して行なうことにより、あるいは、
真空弁付き汚水ます本体の底面、管路の直上に当る部分
には窪みを有する構造とし、下水道管3の敷設方向に真
空弁付き汚水ますの底面の窪み方向を合せるようにして
ピット5内に載置する。このとき下水道管3の直上への
盛り土量、突き固めを加減する等して、底面の窪みの内
側に空隙部を形成させる、或は窪みの内側の土圧を低く
させる等して、真空弁付き汚水ますから下水道管3への
荷重の影響を軽減させ、下水道管3の事故を防止するこ
とができる。
When starting the embankment and compaction process on the bottom of the pit 5, the sewer pipe 3 exposed in the pit 5 is covered with the protective cover (not shown), and the embankment and compaction work is performed. By taking into account or
Sewage with vacuum valve The structure that has a depression on the bottom of the main body, just above the pipeline, has a recess, and the direction of the depression on the bottom of the sewage basin with vacuum valve is aligned with the laying direction of the sewer pipe 3. Place. At this time, the volume of the embankment directly above the sewer pipe 3 and the amount of tamping are adjusted to form a void inside the depression on the bottom surface, or the earth pressure inside the depression is reduced, and the vacuum valve is reduced. The effect of the load on the sewer pipe 3 can be reduced because the waste water is attached, and an accident of the sewer pipe 3 can be prevented.

【0029】上記のように、本実施例は、非開削推進工
法の長所を生かして、複数の汚水ます等を有する埋設管
路を効率よく容易に敷設することができる。
As described above, this embodiment makes it possible to efficiently and easily lay a buried pipeline having a plurality of sewage basins, etc., by taking advantage of the non-cutting propulsion method.

【0030】特に、真空式下水道管路は、約150メー
トル毎にリフト部を設け、リフト部とリフト部との間は
0.2%以上の勾配を設けて敷設する必要があり、これ
等のリフト部の掘削形成も前記した排水ます等の一つと
して本発明の非開削推進工法による管路敷設方法を実施
することができる。
In particular, the vacuum type sewer pipes need to be provided with a lift section every about 150 meters, and to be laid with a slope of 0.2% or more between the lift sections. The excavation formation of the lift portion can also be implemented as one of the drainage basins described above, and the pipe laying method by the non-cutting propulsion method of the present invention can be implemented.

【0031】なお、本発明による管路敷設方法は、従来
の自然流下式下水管路等にも利用できることは勿論であ
る。
The pipe laying method according to the present invention can, of course, be applied to a conventional natural flow type sewer pipe or the like.

【0032】[0032]

【発明の効果】以上説明したように、この発明に係る非
開削推進工法による管路敷設方法によれば、中間にピッ
ト掘削予定個所を挟んでピットを掘削し、掘削されたピ
ット間の地中を非開削推進工法により掘進してピット間
に管を敷設するので、従来の非開削推進工法と異なり先
端ドリルヘッドの重量が大きいためにピット部分で先端
ドリルヘッドの方向制御が困難になるといったことがな
く、他方のピットまで正確に地中を掘進し、埋設管を敷
設することができる。
As described above, according to the pipe laying method by the non-cutting propulsion method according to the present invention, a pit is excavated in the middle of a pit excavated portion, and the underground between the excavated pits is excavated. Excavation by the non-cutting propulsion method and laying a pipe between the pits, unlike the conventional non-cutting propulsion method, the weight of the tip drill head is so large that it becomes difficult to control the direction of the tip drill head in the pit portion It is possible to excavate exactly underground to the other pit and lay a buried pipe.

【0033】そして、管路中間に必要なピットは、埋設
した管の上方から容易に所定個所を掘削することができ
る。そして掘削したピット内に汚水ます等を形成するの
に必要な作業、即ち汚水ます、マンホール、掃除口、管
路分岐ます等に必要な諸作業を実施することができ、比
較的短い間隔で汚水ます等を設置するためのピットの掘
削を必要とする埋設管路敷設工事を非開削推進工法によ
って容易に実施することができる。
The pit required in the middle of the pipe can be easily excavated from above the buried pipe at a predetermined location. Then, it is possible to carry out the operations necessary for forming sewage pits, etc. in the excavated pits, that is, various operations required for sewage pits, manholes, cleaning openings, pipe branching, etc. The laying work of a buried pipeline that requires excavation of a pit for installing a masuma or the like can be easily performed by a non-cutting propulsion method.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 一実施例の工程説明図である。(先端ピット
掘削)
FIG. 1 is a process explanatory view of one embodiment. (Excavation of tip pit)

【図2】 一実施例の工程説明図である。(管敷設)FIG. 2 is a process explanatory view of one embodiment. (Pipe laying)

【図3】 一実施例の工程説明図である。(中間ピット
掘削)
FIG. 3 is a process explanatory view of one embodiment. (Excavation of intermediate pit)

【図4】 一実施例の工程説明図である。(汚水ますの
載置)
FIG. 4 is a process explanatory view of one embodiment. (Placement of sewage masu)

【図5】 一実施例の汚水ます本体の断面図である。FIG. 5 is a cross-sectional view of the sewage basin body of one embodiment.

【図6】 一実施例の汚水ます本体の断面図である。FIG. 6 is a cross-sectional view of the sewage basin body of one embodiment.

【図7】 一実施例の汚水ます本体の断面図である。FIG. 7 is a cross-sectional view of one embodiment of the sewage basin body.

【図8】 一実施例の真空弁付き汚水ます設置工事の説
明図である。
FIG. 8 is an explanatory view of a sewage basin installation work with a vacuum valve according to one embodiment.

【図9】 一実施例の真空弁付き汚水ます設置工事の説
明図である。
FIG. 9 is an explanatory view of installation work of a sewage masquerade with a vacuum valve according to one embodiment.

【図10】 一実施例の真空弁付き汚水ます設置工事の
説明図である。
FIG. 10 is an explanatory view of a sewage basin installation work with a vacuum valve according to one embodiment.

【符号の説明】[Explanation of symbols]

1,2,4,5 ピット 3 下水道管 6 ます本体 7 ます本体底面の窪み 8 保護カバー 9 真空弁 10 合流用分岐管 1, 2, 4, 5 Pit 3 Sewer pipe 6 Masuda body 7 Depressed bottom of body 8 Protective cover 9 Vacuum valve 10 Branch pipe for merging

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 FI F16L 1/038 ──────────────────────────────────────────────────続 き Continued on front page (51) Int.Cl. 6 Identification code FI F16L 1/038

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 中間にピット掘削予定個所を挟んでピッ
トを掘削する工程と、前記中間にピット掘削予定個所を
挟んだピット間の地中を非開削推進工法により掘進して
管を敷設する工程と、前記敷設した管の上方から予定個
所に中間のピットを掘削する工程と、ピット内への所定
の作業を実施する工程とよりなることを特徴とする非開
削推進工法による管路敷設方法。
1. A step of excavating a pit with a pit to be excavated in the middle, and a step of laying a pipe by excavating the underground between the pits with the pit to be excavated in the middle by a non-cutting propulsion method A step of digging an intermediate pit from above the laid pipe to a predetermined location, and a step of performing a predetermined operation in the pit.
JP3333291A 1991-12-17 1991-12-17 Pipe line laying method by non-cutting propulsion method Expired - Fee Related JP2953843B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3333291A JP2953843B2 (en) 1991-12-17 1991-12-17 Pipe line laying method by non-cutting propulsion method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3333291A JP2953843B2 (en) 1991-12-17 1991-12-17 Pipe line laying method by non-cutting propulsion method

Publications (2)

Publication Number Publication Date
JPH05163890A JPH05163890A (en) 1993-06-29
JP2953843B2 true JP2953843B2 (en) 1999-09-27

Family

ID=18264457

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3333291A Expired - Fee Related JP2953843B2 (en) 1991-12-17 1991-12-17 Pipe line laying method by non-cutting propulsion method

Country Status (1)

Country Link
JP (1) JP2953843B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3692476B2 (en) * 2002-12-20 2005-09-07 大同機工株式会社 Construction method and dredging member to create a pit in the middle of a running water conduit

Also Published As

Publication number Publication date
JPH05163890A (en) 1993-06-29

Similar Documents

Publication Publication Date Title
US4329083A (en) Methods of laying underground conduits
JP2953843B2 (en) Pipe line laying method by non-cutting propulsion method
KR100333024B1 (en) Grouting Horizontal directional drilling method
KR100632971B1 (en) Propulsion method and apparatus for underground donduits
AU716745B2 (en) Novel draining wall, method for producing same and element implementated thereby
JP3495412B2 (en) Pipe laying method
JP3615594B2 (en) Piping laying method and piping structure
JP2576945B2 (en) Construction method of manhole combined sinking pit and cutting edge to promote sinking
JPS5914667B2 (en) How to lay pipes
JPH1054045A (en) Shaft construction method making use of cylindrical body used for manhole wall and excavation cutting edg body, excavation lubricant supply device and settlement cylindrical body used for manhole wall
WO2005098195A1 (en) Equipment and procedure of coupling socket pipe sections for trenchless laying
JP2773000B2 (en) Leakage prevention method for unused supply pipes
KR20230047673A (en) the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe
JP3724734B2 (en) Underground cavity filling method
JPS6314138B2 (en)
JP3145345B2 (en) Method of laying vacuum sewer pipe and composite pipe for vacuum sewer pipe
JPH0465932B2 (en)
JPS63284324A (en) Burying method of tube
JPH0426680B2 (en)
JPS6332938B2 (en)
JPH05156696A (en) Method for installing house inlet with vacuum valve and house inlet with vacuum valve
JPH10168917A (en) Caisson prefabricated manhole and execution method thereof
JPH0924354A (en) Method for installing impervious sheet
JPH03241196A (en) Earthwork for underground piping
JPH06117176A (en) Settlement shaft common to manhole, its construction and cylindrical settlement shaft block

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees