KR20230047673A - the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe - Google Patents

the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe Download PDF

Info

Publication number
KR20230047673A
KR20230047673A KR1020210130790A KR20210130790A KR20230047673A KR 20230047673 A KR20230047673 A KR 20230047673A KR 1020210130790 A KR1020210130790 A KR 1020210130790A KR 20210130790 A KR20210130790 A KR 20210130790A KR 20230047673 A KR20230047673 A KR 20230047673A
Authority
KR
South Korea
Prior art keywords
steel pipe
work tool
horizontal
propulsion
tool
Prior art date
Application number
KR1020210130790A
Other languages
Korean (ko)
Inventor
조광래
Original Assignee
주식회사 아이언몰
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 아이언몰 filed Critical 주식회사 아이언몰
Priority to KR1020210130790A priority Critical patent/KR20230047673A/en
Publication of KR20230047673A publication Critical patent/KR20230047673A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0621Shield advancing devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • E21D9/11Making by using boring or cutting machines with a rotary drilling-head cutting simultaneously the whole cross-section, i.e. full-face machines

Abstract

본 발명은 도시 기반 시설인 상,하수도관, 전기 및 통신 선로 등의 매설을 위해 소구경의 지하터널을 구축하거나 하수관을 매설할 때 굴착기계를 설치하고 굴진시 발생하는 토사와 암반을 지상으로 배출시키는 통로 역할을 하는 수직형태의 작업구의 구조를 개량한 추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조 및 이의 형성방법에 관한 것으로, 강관 압입기에 의해 지반에 일정 깊이 만큼 수직으로 압입된 강관의 내부를 터파기 실시하여 바닥에 콘크리트를 타설하고 내부에 추진잭과 반력벽을 설치하며, 도달구를 향하여 수평관로를 형성하는 강관의 발진갱구에 엔트런스 패킹을 설치한 수직 작업구에 있어서, 상기 발진갱구에서 계획된 갱도쪽으로 일정한 깊이 만큼 수평으로 강관을 압입하고 상기 강관의 내부를 터파기 실시하여 수직작업구와 교차되는 수평 작업구를 형성하고, 상기 수평 작업구의 내부 끝단 영역에 엔트런스 패킹과 합성수지 차수판을 일정 간격을 두고 설치하여서 됨을 특징으로 한다. The present invention installs an excavation machine when constructing a small-diameter underground tunnel or burying a sewage pipe for burial of urban infrastructure such as water supply and sewer pipes, electricity and communication lines, and discharges soil and rock mass generated during excavation to the ground. It relates to an improved structure of a launching work tool that facilitates the input of a propulsion pipe that has improved the structure of a vertical work tool that serves as a passage and a method of forming the same, In a vertical work tool in which the entrance packing is installed in the launching shaft of a steel pipe that excavates the inside, pours concrete on the floor, installs a propulsion jack and a reaction wall therein, and forms a horizontal pipeline toward the arrival port. A steel pipe is press-fitted horizontally to a certain depth from the launching shaft toward the planned tunnel, and the inside of the steel pipe is excavated to form a horizontal workpiece intersecting with the vertical workpiece, and the entrance packing and synthetic resin order are applied to the inner end area of the horizontal workpiece. It is characterized in that the plates are installed at regular intervals.

Description

추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조 및 이의 형성방법{the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe}The improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe}

본 발명은 도시 기반 시설인 상,하수도관, 전기 및 통신 선로 등의 매설을 위해 소구경 추진공법에 의해 소구경의 지하터널을 구축하거나 하수관을 매설할 때 굴착기계를 설치하고 굴진시 발생하는 토사와 암반을 지상으로 배출시키는 통로 역할을 하는 수직형태의 작업구의 구조를 개량하여 긴 길이의 추진관을 용이하게 작업구를 통해 투입할 수 있도록 한 추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조 및 이의 형성방법에 관한 것이다. The present invention is a small-diameter underground tunnel built by a small-diameter propulsion method for burial of urban infrastructure such as water supply and sewer pipes, electricity and communication lines, or when a sewage pipe is buried, an excavation machine is installed and soil generated during excavation An improved structure of a launching tool that facilitates the insertion of a long propulsion tube by improving the structure of a vertical work tool that serves as a passage for discharging rocks and rocks to the ground so that a long length of propulsion pipe can be easily inserted through the tool and a method of forming the same.

일반적으로 도시 기반시설인 상하수도, 전기및 통신선로, 가스관등의 확보를 위해서는 교통장애를 최소화하고 시공시 소음, 분진, 지반침하가 많이 발생하는 개착식 터널 추진공법 보다 원통형 굴착기 선단부에 장착되어 있는 굴착용 커터 헤드를 회전시켜 지반을 굴착하고, 이수압또는 이토압으로 막장면의 붕괴를 방지하면서 작업구내에 반입시킨 추진관을 유압잭(Jack)으로 터널내부로 압입 연결하는 반복작업으로 터널을 굴착하거나 흄관을 매설하는 비개착식 공법이 주로 사용되고 있다. In general, in order to secure urban infrastructure such as water supply and sewage, electricity and communication lines, and gas pipes, excavation mounted on the tip of a cylindrical excavator is used rather than the open-cut tunnel propulsion method, which minimizes traffic obstacles and generates a lot of noise, dust, and ground subsidence during construction. By rotating the cutter head to excavate the ground, and preventing the collapse of the face with water pressure or soil pressure, the propulsion pipe brought into the work area is press-fitted into the tunnel with a hydraulic jack to connect it. The non-cutting method of burying the Hume pipe is mainly used.

이러한 비개착식 공법은 계획심도까지 지반을 수직 굴착하여 작업구를 형성한 다음 수평의 관로를 형성하는 작업구간 내의 전방에 굴착기를 배치시키고 후방의 반력벽에 유압 추진잭을 설치하여 추진잭에 의해 굴착기를 앞으로 전진 이동시키면서 굴착하고 유압 추진잭을 후방으로 후퇴시킨 상태에서 유압 추진잭과 굴착기의 사이에 추진관을 끼워 넣고 유압 추진잭을 신장시켜 전진 이송시키고 다시 추진잭을 후퇴시켜 다른 추진관을 끼워 연결하는 방식으로 추진관을 순차적으로 연결시켜 관로를 형성하게 된다In this non-cutting method, the ground is vertically excavated to the planned depth to form a work area, and then an excavator is placed in the front within the work area to form a horizontal pipeline, and a hydraulic propulsion jack is installed on the reaction wall at the rear to Excavating while moving the excavator forward, inserting the propulsion pipe between the hydraulic propulsion jack and the excavator in the state of retracting the hydraulic propulsion jack, extending the hydraulic propulsion jack and transporting it forward, and retracting the propulsion jack to move another propulsion pipe. The pipe is formed by sequentially connecting the propulsion pipes in a pinched connection method.

이와같은 추진관의 연결작업은 수직으로 형성한 발진 작업구의 내부에서 이루어지게 되는 데 도심지에서 이루어지는 소구경 터널 구축공법에서는 작업구가 도심지의 주위 환경 등 다양한 여건 등을 고려하여 과도하게 크게 형성할 필요가 없는 적정 크기의 대략 3∼5m 정도 직경으로서 강관을 매설하여 형성하게 된다. The connection work of such a propulsion pipe is performed inside the vertically formed launching work area. In the small-diameter tunnel construction method in the downtown area, the work area needs to be formed excessively large in consideration of various conditions such as the surrounding environment in the downtown area. It is formed by embedding a steel pipe with a diameter of about 3 to 5 m of an appropriate size without a hole.

한편, 발진 작업구의 내부에 투입되어 터널을 형성하는 추진관이 콘크리트관의 내부에 철선이나 철근을 인서트한 흄관의 경우 통상 1.2m 와 2.5m의 길이를 가진 2종류의 규격으로 생산되어 나오고 있으며, 가격면에서는 크게 차이가 없어 실제 현장에서는 2.5m 흄관의 사용을 선호한다. On the other hand, in the case of a Hume pipe in which steel wires or reinforcing bars are inserted into the inside of a concrete pipe in which the propulsion pipe that is put into the inside of the launching tool to form a tunnel is produced in two types of standards, usually 1.2m and 2.5m in length, There is not much difference in price, so the use of 2.5m Hume pipe is preferred in the actual field.

그러나, 직경이 작은 발진 작업구의 경우에는 내부에 설치된 반력벽과 추진잭, 등 각종 설비와 자재 등에 의해 공간이 점유되고 있으므로 지상에서 추진관을 크레인으로 작업구의 내부에 투입하여 수평으로 배치시키기가 용이하지 않은 문제로 인해 길이는 짧으면서 가격이 2.5m 보다 큰 차이가 없는 1.2m 의 흄관을 사용할 수 밖에 없어 시공비가 상승하는 반면에 터널 굴착에 따른 효율성은 떨어지게 되는 문제가 있었다. However, in the case of a launching tool with a small diameter, since the space is occupied by various facilities and materials such as a reaction wall and a propulsion jack installed inside, it is easy to insert the propulsion pipe into the tool from the ground using a crane and place it horizontally. Due to the problem of not doing so, there was a problem in that the length was short and the 1.2m Hume pipe, which had no difference in price more than 2.5m, had to be used, which increased the construction cost while reducing the efficiency of tunnel excavation.

본 발명의 목적은 상기한 문제점을 해소하기 위한 것으로 발진 작업구의 구조를 개량하여 작은 직경의 작업구에서 2.5m의 추진관을 용이하게 연결할 수 있도록 한 추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조 및 이의 형성방법을 제공하는 데 있다. An object of the present invention is to solve the above problems, and by improving the structure of the launching tool, it is possible to easily connect a 2.5m propulsion pipe to a small diameter tool, and to improve the launching tool that facilitates the input of the propulsion pipe. It is to provide a structure and a method of forming the same.

본 발명은 이러한 목적을 달성하기 위한 수단으로, 강관 압입기에 의해 지반에 일정 깊이 만큼 수직으로 압입된 강관의 내부를 터파기 실시하여 바닥에 콘크리트를 타설하고 내부에 추진잭과 반력벽을 설치하며, 도달구를 향하여 수평관로를 형성하는 강관의 발진갱구에 엔트런스 패킹을 설치한 수직 작업구에 있어서, 상기 발진갱구에서 계획된 갱도쪽으로 일정한 깊이 만큼 수평으로 강관을 압입하고 상기 강관의 내부를 터파기 실시하여 수직작업구와 교차되는 수평 작업구를 형성하고, 상기 수평 작업구의 내부 끝단 영역에 엔트런스 패킹과 합성수지 차수판을 일정 간격을 두고 설치하여서 됨을 특징으로 하는 추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조를 제공한다. As a means for achieving this object, the present invention excavates the inside of a steel pipe vertically pressed into the ground by a certain depth by a steel pipe presser, pours concrete on the floor, and installs a propulsion jack and a reaction wall therein, In a vertical work tool in which entrance packing is installed in the launch shaft of a steel pipe forming a horizontal pipeline toward the arrival port, the steel pipe is horizontally pushed in by a certain depth toward the planned tunnel from the launch shaft and the inside of the steel pipe is excavated To form a horizontal work tool that intersects with the vertical work device, and by installing entrance packing and a synthetic resin shielding plate at regular intervals at the inner end region of the horizontal work device, the launching work tool that facilitates the introduction of the propulsion pipe Provides an improved structure.

또한, 수평 작업구가 형성된 주위의 지반에는 그라우트재가 주입되어 그라우팅이 형성된다. In addition, grouting is formed by injecting a grout material into the ground around the horizontal work tools.

또한, 지상의 작업구 설치지점에 설치한 강관압입기로서 강관을 일정깊이로 압입시키고 상기 강관의 내부의 토사를 터파기 작업으로 반출한 후 바닥 콘크리트를 타설하며 발진갱구에 엔트런스 패킹을 설치하여 수직 작업구를 형성하는 단계; In addition, as a steel pipe indenter installed at the work hole installation point on the ground, the steel pipe is press-fitted to a certain depth, the soil inside the steel pipe is taken out by excavation work, the floor concrete is poured, and entrance packing is installed in the launch shaft Forming a vertical work tool;

작업구의 발진갱구 외측의 수평 작업구가 설치되는 지반의 넓은 범위에 걸쳐 지상으로 부터 그라우트재를 강제 주입시켜 그라우팅을 실시하고 지반교란과 지하수 유출에 따른 침하를 방지하여 연약지반의 강도를 보강하는 단계; Grouting is performed by forcibly injecting grout material from the ground over a wide range of the ground where the horizontal work tool outside the launching shaft of the work tool is installed, and reinforcing the strength of the soft ground by preventing subsidence caused by ground disturbance and groundwater runoff. ;

수직 작업구의 강관 내벽에 설치된 엔트런스 패킹의 내측을 따라 강관을 원형으로 절단하여 발진갱구를 형성하고, 이를 통해 소정 길이의 강관을 계획된 관로 방향으로 수평 압입 후 내부를 터파기하여 수직 작업구와 연통되는 수평 작업구를 형성하고, 상기 수평 작업구의 내부 끝단 영역에 엔트런스 패킹과 합성수지 차수판을 간격을 두고 순차적으로 설치하는 단계; The steel pipe is circularly cut along the inside of the entrance packing installed on the inner wall of the steel pipe of the vertical work tool to form a launching shaft, through which a steel pipe of a predetermined length is horizontally pressed in the direction of the planned pipe line, and then the inside is broken to open a horizontal Forming a work tool, and sequentially installing an entrance packing and a synthetic resin shielding plate at intervals at an inner end region of the horizontal work tool;

수평 작업구의 설치가 완료되면 수직 작업구의 내부에 반력벽과 추진잭을 설치하고 굴착기를 투입하여 추진잭에 의해 굴착기를 수평 작업구로 추진시키고 엔트런스 패킹과 합성수지 차수판을 관통하여 굴착을 실시하면서 추진관을 순차적으로 연결하여 관로를 형성하는 단계;When the installation of the horizontal work tool is completed, a reaction wall and a propulsion jack are installed inside the vertical work tool, and the excavator is inserted to propel the excavator to the horizontal work tool by the propulsion jack, and the excavation is carried out while penetrating the entrance packing and the synthetic resin liner plate. Forming a conduit by sequentially connecting the conduits;

로 이루어지는 추진관의 투입을 용이하게 하는 발진작업구의 형성방법을 제공한다. It provides a method of forming a launching tool that facilitates the introduction of a propulsion pipe made of.

이와 같이 본 발명은 수직의 발진 작업구에 굴착심도와 연결되는 수평 작업구를 교차되게 형성함으로써 직경이 작은 발진 작업구에 긴 길이의 추진관을 투입하여 용이하게 연결할 수 있게 함으로써 관로를 형성하는 작업효율을 상승시키고 시공비의 절감과 시공기간을 단축시킬 수 있는 효과가 있다. In this way, the present invention is a work of forming a pipeline by forming a horizontal work tool connected to the depth of excavation in a vertical launch work tool to be crossed so that it can be easily connected by inserting a long length propulsion pipe into a small diameter start work tool. It has the effect of increasing efficiency, reducing construction cost and shortening construction period.

도 (1a)(1b)(1c)(1d)(1e)(1f)(1g)는 본 발명에 따른 시공방법을 순서적으로 도시한 설명도
도 2는 본 발명에 의해 추진관이 연속 연결되는 상태의 확대도
도 3은 도 2의 "A" 부 확대단면도
Figures (1a) (1b) (1c) (1d) (1e) (1f) (1g) are explanatory views sequentially showing the construction method according to the present invention
Figure 2 is an enlarged view of a state in which the propulsion pipe is continuously connected according to the present invention
Figure 3 is an enlarged cross-sectional view of the "A" portion of FIG.

이하, 본 발명의 실시 예를 첨부된 도면을 참조하여 본 발명에 따른 동작 및 작용을 이해하는 데 필요한 부분을 중심으로 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail, focusing on parts necessary for understanding operations and actions according to the present invention with reference to the accompanying drawings.

본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 변형 예들이 있을 수 있음을 이해하여야 한다.Since the embodiments described in this specification and the configurations shown in the drawings are only one of the most preferred embodiments of the present invention and do not represent all of the technical ideas of the present invention, various modifications that can be substituted for them at the time of the present application It should be understood that there may be

본 발명의 실시 예를 설명하면서, 본 발명이 속하는 기술 분야에 익히 알려졌고 본 발명과 직접적으로 관련이 없는 불필요한 기술 내용에 대해서는 본 발명의 요지를 흐리지 않고 더욱 명확한 전달을 위해 설명을 생략한다.While describing the embodiments of the present invention, descriptions of unnecessary technical details that are well known in the technical field to which the present invention pertains and are not directly related to the present invention are omitted for clearer delivery without obscuring the gist of the present invention.

도 1 내지 도 3에 도시된 바와 같이, 본 발명의 추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조는, 강관 압입기에 의해 지반에 일정 깊이 만큼 수직으로 압입된 강관(10)의 내부를 터파기 실시하여 바닥에 콘크리트(11)를 타설하고 내부에 추진잭(12)과 반력벽(13)을 설치하며, 도달구를 향하여 수평관로를 형성하는 강관(10)의 발진갱구(14)에 엔트런스 패킹(15)을 설치한 수직 작업구(50)에 있어서, 상기 발진갱구(14)에서 계획된 갱도쪽으로 일정한 깊이만큼 수평으로 강관(20)을 압입하고 상기 강관(20)의 내부를 터파기 실시하여 수직 작업구(50)와 교차되는 수평 작업구(60)를 형성하고, 상기 수평 작업구(60)의 내부 끝단 영역에 엔트런스 패킹(21)과 합성수지 차수판(22)을 일정 간격을 두고 설치하여서 됨을 특징으로 한다. As shown in FIGS. 1 to 3, the improved structure of the launch tool for facilitating the insertion of the propulsion pipe of the present invention is to open the inside of the steel pipe 10 vertically pressed into the ground by a certain depth by a steel pipe presser. After digging, concrete (11) is poured on the floor, a propulsion jack (12) and a reaction wall (13) are installed inside, and an entry is made to the launching shaft (14) of the steel pipe (10) forming a horizontal pipeline toward the arrival hole. In the vertical work tool 50 with the run packing 15 installed, the steel pipe 20 is horizontally pushed in by a certain depth toward the planned tunnel from the launch shaft 14, and the inside of the steel pipe 20 is excavated to form a horizontal work tool 60 intersecting with the vertical work tool 50, and the entrance packing 21 and the synthetic resin shield plate 22 are spaced apart from each other in the inner end region of the horizontal work tool 60 It is characterized by being installed.

상기 수평 작업구(60)가 형성된 주위의 지반에는 그라우트재가 주입되어 그라우팅(30)이 형성된다. A grout material is injected into the ground around the horizontal work tools 60 to form grouting 30 .

상기 엔트런스 패킹(21)과 합성수지 차수판(22)은 수평 강관(20)의 내벽에 용접된 브라켓(40)에 볼트(41)로서 체결된다. The entrance packing 21 and the synthetic resin shielding plate 22 are fastened with bolts 41 to the bracket 40 welded to the inner wall of the horizontal steel pipe 20.

상기 수평 작업구(60)를 형성하는 강관(20)의 직경은 관로를 형성하는 갱도보다는 충분히 크고 수직 작업구(50)의 직경보다는 적은 직경으로 이루어지며, 그 길이는 추진관을 수평으로 투입 가능하도록 여유를 가지는 적정 길이로 이루어진다. The diameter of the steel pipe 20 forming the horizontal work piece 60 is sufficiently larger than the tunnel forming the pipe and smaller than the diameter of the vertical work piece 50, and the length allows the propulsion pipe to be introduced horizontally. It is made of an appropriate length with a margin to do so.

상기 수평 작업구(60)는 수직 작업구(50)의 발진갱구(14)와 연결되어 교차되는 형태로 수평으로 형성되므로 굴착기를 수직 작업구(50)의 선단에 설치하게 되면 추진잭(12)과의 사이에 충분한 여유 공간이 형성되어 긴 길이의 흄관 즉 추진관을 수직 작업구(50)를 통해 투입하게 되면 수평 작업구(60)에 의해 방향전환을 할 수 있으므로 추진관의 순차적 연결이 용이하게 된다. Since the horizontal work piece 60 is connected to the launch shaft 14 of the vertical work piece 50 and formed horizontally in a crossed shape, when the excavator is installed at the front end of the vertical work piece 50, the propulsion jack 12 When a long Hume pipe, that is, a propulsion pipe, is inserted through the vertical work tool 50 when sufficient free space is formed between the propelling pipe and the vertical work tool 50, the direction can be changed by the horizontal work tool 60, so that the sequential connection of the propulsion pipe is easy. will do

상기 수평 작업구(60)의 내부 끝단 영역에는 합성수지재 차수판(22)이 설치되어 수평 작업구(60)를 설치하는 과정에서 지하수와 굴착토사가 유입되는 것을 차단하게 되고, 상기 합성수지재 차수판(22)의 내측에는 일정간격을 두고 엔트런스 패킹(21)이 설치되어 굴착과정에서 지하수 또는 굴착토사가 유입되지 않도록 차단된다. In the inner end region of the horizontal work tool 60, a synthetic resin water blocking plate 22 is installed to block the inflow of groundwater and excavated soil in the process of installing the horizontal work tool 60, and the synthetic resin water blocking plate Entrance packing 21 is installed at regular intervals on the inside of 22 to block the inflow of groundwater or excavated soil during the excavation process.

이와 같이 본 발명은 수직 작업구(50)에 갱도 방향으로 수평 작업구(60)가 교차되게 설치되어 있으므로 발진 작업구의 내부 공간이 확장되어 수직 작업구(50)의 내부에 설치된 추진잭(12)과 반력벽(13), 각종 굴착장비에 의해 점유되어 좁아진 작업구의 공간을 확보하게 되므로 굴착작업시 2.5m의 흄관을 투입시 수평 작업구(60)에 의해 도 1의 (e)와 같이 경사상태로 반입시켜 방향을 전환할 수 있게 됨에 따라 수평으로 선두추진관에 쉽게 연결 시킬 수 있으므로 작업효율이 상승 되는 효과를 제공하게 되고 또한, 흄관의 비용면에서 절감되는 잇점이 있다. As described above, since the horizontal work tools 60 are installed to cross the vertical work tools 50 in the direction of the tunnel, the internal space of the launch work tools is expanded, so that the propulsion jack 12 installed inside the vertical work tools 50 And the reaction wall 13, and the narrow space occupied by various excavation equipment is secured, so when a 2.5m Hume pipe is input during excavation, the inclined state as shown in FIG. 1 (e) by the horizontal work tool 60 Since it can be easily connected to the head propulsion pipe horizontally as it can be brought in to change the direction, it provides an effect of increasing work efficiency and also has the advantage of reducing the cost of the hume pipe.

본 발명의 작업구의 형성과정은 다음과 같은 단계에 의해 이루어진다. The forming process of the work tool of the present invention is made by the following steps.

제1단계(수직 작업구 형성단계)1st step (formation step of vertical work tool)

지상의 작업구 설치지점에 설치한 강관압입기로서 강관(10)을 일정깊이로 압입시키고 이의 상면에 또 다른 강관(10)을 용접하면서 압입하는 방법으로 소요 깊이 만큼 압입하고 상기 강관(10)의 내부의 토사를 터파기 작업으로 반출한 후 바닥 콘크리트(11)를 타설하며 발진갱구(14)에 엔트런스 패킹(15)을 설치하여 수직 작업구(50)를 형성한다. As a steel pipe indenter installed at the work tool installation point on the ground, the steel pipe 10 is pressed in at a certain depth and another steel pipe 10 is pressed in while welding another steel pipe 10 to the upper surface of the steel pipe 10 as much as the required depth. After the soil inside is taken out by excavation work, the floor concrete 11 is poured, and the entrance packing 15 is installed in the launch shaft 14 to form a vertical work tool 50.

제2단계(그라우팅 단계)Step 2 (Grouting step)

작업구의 발진갱구(14) 외측의 수평 작업구(60)가 설치되는 지반의 넓은 범위에 걸쳐 지상으로부터 그라우트재를 강제 주입시켜 그라우팅(30)을 실시하고 지반교란과 지하수 유출에 따른 침하를 방지하여 연약지반의 강도를 보강하게 된다. Grouting 30 is performed by forcibly injecting grout material from the ground over a wide range of the ground where the horizontal work tool 60 outside the launching shaft 14 of the work tool is installed, and subsidence due to ground disturbance and groundwater leakage is prevented. It reinforces the strength of the soft ground.

제3단계(강관 수평 압입단계)3rd step (steel pipe horizontal press-in step)

수직 작업구(50)의 강관(10) 내벽에 설치된 엔트런스 패킹(15)의 내측을 따라 강관(10)을 원형으로 절단하여 발진갱구(14)를 형성하고, 이를 통해 소정 길이의 강관(20)을 계획된 관로 방향으로 강관압입기를 사용하여 수평으로 압입한다. 강관(20)이 수평으로 압입되면 강관(20)의 내부를 터파기하여 수직 작업구(50)와 연통되는 수평 작업구(60)를 형성하고, 상기 수평 작업구(60)의 내부 끝단 영역에 엔트런스 패킹(21)과 합성수지 차수판(22)을 간격을 두고 순차적으로 설치한다. The steel pipe 10 is circularly cut along the inside of the entrance packing 15 installed on the inner wall of the steel pipe 10 of the vertical work tool 50 to form the launching shaft 14, through which the steel pipe 20 of a predetermined length ) is horizontally pressed in the direction of the planned pipeline using a steel pipe indenter. When the steel pipe 20 is press-fitted horizontally, the inside of the steel pipe 20 is broken to form a horizontal work tool 60 communicating with the vertical tool 50, and an ent is formed in the inner end region of the horizontal tool 60. The run packing 21 and the synthetic resin shielding plate 22 are installed sequentially at intervals.

상기 엔트런스 패킹(21)과 합성수지 차수판(22)은 수평 강관(20)의 내벽에 용접된 브라켓(40)에 볼트(41)로서 체결된다. The entrance packing 21 and the synthetic resin shielding plate 22 are fastened with bolts 41 to the bracket 40 welded to the inner wall of the horizontal steel pipe 20.

상기 합성수지 차수판(22)은 수평 작업구(60)의 형성과정에서 내부로 지하수와 토사가 유입되는 것을 방지하는 것으로 굴착기에 의해 관통되며, 엔트런스 패킹(21)은 굴착작업시 수직 작업구(50)에 설치된 엔트런스 패킹(15)과 함께 추진관의 외주에 밀착되어 지중의 지하수와 토사가 작업구의 내부로 유입되는 것을 방지한다.The synthetic resin water plate 22 is penetrated by an excavator to prevent groundwater and soil from flowing into the inside during the formation of the horizontal work tool 60, and the entrance packing 21 is a vertical work tool during excavation work ( 50) is closely attached to the outer circumference of the propulsion pipe together with the entrance packing 15 installed to prevent ground water and soil from entering the work tool.

제4단계(반력벽과 굴착기 설치)4th stage (reaction wall and excavator installation)

수평 작업구(60)의 설치가 완료되면 수직 작업구(50)의 내부에 반력벽(13)과 추진잭(12)을 설치하고 굴착기를 투입하여 추진잭(12)에 의해 굴착기를 수평 작업구(60)로 추진시키고 엔트런스 패킹(21)과 합성수지 차수판(22)을 관통하여 굴착을 실시하면서 추진관을 순차적으로 연결하여 관로를 형성하게 된다. When the installation of the horizontal work piece 60 is completed, the reaction wall 13 and the propulsion jack 12 are installed inside the vertical work piece 50, and the excavator is put into the horizontal work piece by the propulsion jack 12. (60), and while excavating through the entrance packing 21 and the synthetic resin diaphragm 22, the propulsion pipes are sequentially connected to form a conduit.

이 과정에서 수직 작업구(50)에는 수평 작업구(60)가 교차되게 연통되어 작업구의 내부 공간이 확장되므로서 2.5m 추진관을 투입할 때 방향 전환이 용이하므로 긴 길이의 추진관의 투입 및 설치가 가능하다. In this process, the horizontal work tool 60 is cross-connected with the vertical work tool 50 to expand the internal space of the work tool, so that it is easy to change the direction when inserting the 2.5m propulsion pipe, so that the long length of the propulsion pipe is inserted and installation is possible

이와 같이 형성되는 본 발명은 발진 작업구가 수직 작업구(50)와 수평 작업구(60)가 서로 연통 되는 ㄴ 자 형상을 이루게 되므로 작업구의 공간이 대폭 확장되어 발진 작업구에서 발진 작업과 버력 반출 및 각종 자재의 반입이 편리하고 특히 2.5m의 길이가 긴 추진관의 투입시에도 도 1의 (e)와 같이 추진관의 방향 전환이 가능하여 추진관의 수평 연결이 용이한 효과가 있다. In the present invention formed in this way, since the vertical work tool 50 and the horizontal work tool 60 are in communication with each other, the space of the work tool is greatly expanded, so that the oscillation work and the carrying out of the force are greatly expanded And it is convenient to carry in various materials, and even when a long propulsion pipe of 2.5 m is introduced, the direction of the propulsion pipe can be changed as shown in (e) of FIG. 1, so that the horizontal connection of the propulsion pipe is easy.

10 : 강관 11 : 콘크리트 12 : 추진잭 13 : 반력벽 14 : 발진갱구 15 : 엔트런스 패킹 21 : 엔트런스 패킹 20 : 강관 22 : 차수판 30 : 그라우팅 40 : 브라켓 41 : 볼트 50 : 수직 작업구 60 : 수평 작업구Reference Numerals 10: steel pipe 11: concrete 12: propulsion jack 13: reaction wall 14: launch shaft 15: entrance packing 21: entrance packing 20: steel pipe 22: water shield 30: grouting 40: bracket 41: bolt 50: vertical work hole 60 : horizontal working tool

Claims (3)

강관 압입기에 의해 지반에 일정 깊이 만큼 수직으로 압입된 강관(10)의 내부를 터파기 실시하여 바닥에 콘크리트(11)를 타설하고 내부에 추진잭(12)과 반력벽(13)을 설치하며, 도달구를 향하여 수평관로를 형성하는 강관(10)의 발진갱구(14)에 엔트런스 패킹(15)을 설치한 수직 작업구(50)에 있어서, 상기 발진갱구(14)에서 계획된 갱도쪽으로 일정한 깊이 만큼 수평으로 강관(20)을 압입하고 상기 강관(20)의 내부를 터파기 실시하여 수직 작업구(50)와 교차되는 수평 작업구(60)를 형성하고, 상기 수평 작업구(60)의 내부 끝단 영역에 엔트런스 패킹(21)과 합성수지 차수판(22)을 일정 간격을 두고 설치하여서 됨을 특징으로 하는 추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조. By excavating the inside of the steel pipe 10 vertically pressed into the ground by a steel pipe presser to a certain depth, concrete 11 is poured on the floor, and a propulsion jack 12 and a reaction wall 13 are installed inside, In the vertical work tool (50) in which the entrance packing (15) is installed in the launch shaft (14) of the steel pipe (10) forming a horizontal conduit toward the arrival port, a certain depth from the launch shaft (14) toward the planned tunnel. The steel pipe 20 is press-in horizontally as much as possible and the inside of the steel pipe 20 is excavated to form a horizontal work tool 60 intersecting with the vertical work tool 50, and the inside of the horizontal work tool 60 An improved structure of a launching tool that facilitates the introduction of a propulsion pipe, characterized in that the entrance packing 21 and the synthetic resin shielding plate 22 are installed at regular intervals in the end region. 제 1 항에 있어서, 수평 작업구(60)가 형성된 주위의 지반에는 그라우트재가 주입되어 그라우팅(30)이 형성된 추진관의 투입을 용이하게 하는 발진 작업구의 개량 구조. [Claim 2] The improved structure of the launch tool according to claim 1, wherein a grout material is injected into the ground around the horizontal tool (60) to facilitate the insertion of the propulsion pipe on which the grouting (30) is formed. 지상의 작업구 설치지점에 설치한 강관압입기로서 강관(10)을 일정깊이로 압입시키고 상기 강관(10)의 내부의 토사를 터파기 작업으로 반출한 후 바닥 콘크리트(11)를 타설하며 발진갱구(14)에 엔트런스 패킹(15)을 설치하여 수직 작업구(50)를 형성하는 단계;
작업구의 발진갱구(14) 외측의 수평 작업구(60)가 설치되는 지반의 넓은 범위에 걸쳐 지상으로부터 그라우트재를 강제 주입시켜 그라우팅(30)을 실시하고 지반교란과 지하수 유출에 따른 침하를 방지하여 연약지반의 강도를 보강하는 단계;
수직 작업구(50)의 강관(10) 내벽에 설치된 엔트런스 패킹의 내측을 따라 강관(10)을 원형으로 절단하여 발진갱구(14)를 형성하고, 이를 통해 소정 길이의 강관(20)을 계획된 관로 방향으로 수평 압입 후 내부를 터파기하여 수직 작업구(50)와 연통되는 수평 작업구(60)를 형성하고, 상기 수평 작업구(60)의 내부 끝단 영역에 엔트런스 패킹(21)과 합성수지 차수판(22)을 간격을 두고 순차적으로 설치하는 단계;
수평 작업구(60)의 설치가 완료되면 수직 작업구(50)의 내부에 반력벽(13)과 추진잭(12)을 설치하고 굴착기를 투입하여 추진잭(12)에 의해 굴착기를 수평 작업구(60)로 추진시키고 엔트런스 패킹(21)과 합성수지 차수판(22)을 관통하여 굴착을 실시하면서 추진관을 순차적으로 연결하여 관로를 형성하는 단계;
로 이루어지는 추진관의 투입을 용이하게 하는 발진작업구의 형성방법




As a steel pipe indenter installed at the installation point of the work area on the ground, the steel pipe (10) is pressed in at a certain depth, the earth and sand inside the steel pipe (10) are taken out by excavation work, and then the floor concrete (11) is poured and the launch shaft Forming a vertical work tool 50 by installing an entrance packing 15 in (14);
Grouting 30 is performed by forcibly injecting grout material from the ground over a wide range of the ground where the horizontal work tool 60 outside the launching shaft 14 of the work tool is installed, and subsidence due to ground disturbance and groundwater leakage is prevented. reinforcing the strength of soft ground;
The steel pipe 10 is circularly cut along the inside of the entrance packing installed on the inner wall of the steel pipe 10 of the vertical work tool 50 to form the launch shaft 14, through which the steel pipe 20 of a predetermined length is After horizontally press-fitting in the direction of the pipe, the inside is excavated to form a horizontal work tool 60 communicating with the vertical work tool 50, and the entrance packing 21 and synthetic resin order are placed in the inner end area of the horizontal work tool 60 sequentially installing the plates 22 at intervals;
When the installation of the horizontal work piece 60 is completed, the reaction wall 13 and the propulsion jack 12 are installed inside the vertical work piece 50, and the excavator is put into the horizontal work piece by the propulsion jack 12. Forming a conduit by sequentially connecting propulsion pipes while propelling them with 60 and excavating through the entrance packing 21 and the synthetic resin shielding plate 22;
Method of forming a launching tool that facilitates the introduction of a propulsion tube made of




KR1020210130790A 2021-10-01 2021-10-01 the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe KR20230047673A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210130790A KR20230047673A (en) 2021-10-01 2021-10-01 the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210130790A KR20230047673A (en) 2021-10-01 2021-10-01 the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe

Publications (1)

Publication Number Publication Date
KR20230047673A true KR20230047673A (en) 2023-04-10

Family

ID=85984912

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210130790A KR20230047673A (en) 2021-10-01 2021-10-01 the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe

Country Status (1)

Country Link
KR (1) KR20230047673A (en)

Similar Documents

Publication Publication Date Title
CN109371980B (en) Deep foundation pit enclosure construction method combining spray anchor reverse construction and punched pile
CN101092878B (en) Main duct construction method laid down tunnel structure article
JP3834571B2 (en) Construction method for underground structures
KR102239089B1 (en) Underaround continued wall structure using casing and pile continuous connection and method therefor
JP2008019663A (en) Tunnel construction method
KR20230047673A (en) the improvement structure and this formation method of the oscillation work outlet facilitating the input of the propulsion pipe
JP2007162323A (en) Wall body forming method and wall body
KR101407632B1 (en) Underground auxiliary tunnel structure and construction method for underground auxiliary tunnel structure using presssed pipe
JP3443664B2 (en) Shield shaft reinforcement structure
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
JPH11152986A (en) Protection method for shielding excavation in section covered with thin soil layer
KR100333024B1 (en) Grouting Horizontal directional drilling method
JP4460146B2 (en) Method and equipment for accepting tunnel excavator into reach shaft
KR200305659Y1 (en) manpower tunnel propeller for a concrete pipe
KR102191503B1 (en) The Tunnel construction method to use retangular pipe
JP6009294B2 (en) Manhole construction method using steel circular casing
JPH1163299A (en) Execution method of multi-conduit pipe and multi-conduit pipe
JP3110927B2 (en) Backfill injection method in propulsion method
KR100585430B1 (en) Pipe shove in underground construction
JPH1162466A (en) Receiving method of shield boring machine into arrival shaft, and structure of receiving part of shield boring machine in arrival shaft
KR20220167623A (en) the half exit method of the excavator in which excavation is completed in the underground tunnel excavation
JP6230284B2 (en) Existing pipe renewal method
JPH03241196A (en) Earthwork for underground piping
JP6132672B2 (en) Existing pipe renewal method
CN115726803A (en) Anchor-pull type pipe jacking construction device and construction method thereof

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E601 Decision to refuse application