JPS59233016A - Construction work of continuous underground wall - Google Patents

Construction work of continuous underground wall

Info

Publication number
JPS59233016A
JPS59233016A JP10781783A JP10781783A JPS59233016A JP S59233016 A JPS59233016 A JP S59233016A JP 10781783 A JP10781783 A JP 10781783A JP 10781783 A JP10781783 A JP 10781783A JP S59233016 A JPS59233016 A JP S59233016A
Authority
JP
Japan
Prior art keywords
excavation
wall
jack
underground wall
continuous underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10781783A
Other languages
Japanese (ja)
Other versions
JPH0366450B2 (en
Inventor
Akira Nakanishi
章 中西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP10781783A priority Critical patent/JPS59233016A/en
Publication of JPS59233016A publication Critical patent/JPS59233016A/en
Publication of JPH0366450B2 publication Critical patent/JPH0366450B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To construct a continuous underground wall having excellent water sealing property by a method in which a propelled jack is set toward the direction of excavation in contact with a columnar excavating blade provided toward the direction of excavation, and columnar unit walls are erected as the jack extends or shrinks. CONSTITUTION:Two excavating blades 1 are inserted into pillar-row holes 5 and an excavating blade 11 is set toward the direction of excavation. When a jack 6t set in a fitting groove 2 is extended, the blades 1 bite into the ground and move toward the direction of excavation. A trench is excavated to the width of the blades 1, and then the jack 6 is contracted and removed out of the fitting groove 2. The navel 31 of the unit wall 3 is fitted into the groove 2, and the unit wall 3 is erected into the trench. The same operations are repeated orderly to construct a continuous underground wall.

Description

【発明の詳細な説明】 本発明は連続地中壁の構築工法に関するものである。[Detailed description of the invention] The present invention relates to a construction method for continuous underground walls.

地中に連続した土留め壁を構築する方法として地下連続
壁工法が存在する。
An underground continuous wall construction method exists as a method of constructing a continuous earth retaining wall underground.

この工法は安定液を用いて掘削壁面の崩壊を防止しなが
ら地下に壁状の溝孔を掘削し、これに無筋、鉄筋コンク
リート等の連続した壁体を構築する工法である。
This construction method uses a stabilizing liquid to prevent the excavated wall from collapsing while excavating a wall-shaped trench underground, and then constructing a continuous wall of unreinforced or reinforced concrete.

ところが、この工法には次のような問題がある。However, this method has the following problems.

〈イ〉泥水の処理の為の広いスペースを必要とする。<B> Requires a large space for processing muddy water.

〈口〉泥水の処理施設が必要になり、施工コストが高く
なる。
<mouth> A muddy water treatment facility will be required, which will increase the construction cost.

本発明は以上のような問題を解決する為になされたもの
で、施工コストの低減が可能で、止水性に優れた連続地
中壁の構築方法を提供するこを目的とする。
The present invention has been made to solve the above problems, and an object of the present invention is to provide a method for constructing a continuous underground wall that can reduce construction costs and has excellent water-stopping properties.

すなわち本発明は地中には開削方向に向けて柱状の開削
刃を配置し、この開削刃に接して推進ジヤツキを開削方
向に向けて配置し、推進ジヤツキの伸縮の都度、柱状の
歪体壁を建て込んで順次接合させて構築する、連続地中
壁の構築方法に関するものである。
That is, in the present invention, a columnar cutting blade is arranged underground in the excavation direction, a propulsion jack is placed in contact with this excavation blade and directed in the excavation direction, and each time the propulsion jack expands and contracts, the columnar distortion body wall This relates to a method of constructing a continuous underground wall, which is constructed by erecting and sequentially joining.

次に本発明の工法に使用する構造物について説明する。Next, the structure used in the construction method of the present invention will be explained.

[イ]開削刃 開削刃1は第1図に示すJ:うに鋭利な掘削刃11と、
この掘削刃物11と一体の胴部12で構成する。
[A] Trenching blade The trenching blade 1 is shown in FIG. 1. J: A sharp digging blade 11,
It is composed of a body part 12 that is integrated with this excavating blade 11.

掘削刃物11は二面を交差して形成した断面樹状の柱体
である。
The excavating blade 11 is a column with a tree-like cross section formed by intersecting two sides.

開削刃1の胴部12には長手方向に連続して嵌合溝2を
凹設する。
A fitting groove 2 is continuously provided in the body part 12 of the cutting blade 1 in the longitudinal direction.

開削刃1は開削の後に構造物として利用するためプレキ
ャスト版(以下20版という)等で形成する。
The cutting blade 1 is formed of a precast plate (hereinafter referred to as 20 plate) or the like in order to be used as a structure after cutting.

[口]単体壁 単体壁3は前記開削刃1の嵌合溝2に嵌合して連続した
地中壁を形成するための繋ぎ材である。
[Explanation] Single wall The single wall 3 is a connecting member that fits into the fitting groove 2 of the cutting blade 1 to form a continuous underground wall.

単体壁3は四角柱体の一面に嵌合溝2と等しい幅のほぞ
31を突設し、その裏面にはほぞ31と同じ方向に連続
した接合溝32を凹設して形成する。
The single wall 3 has a tenon 31 of the same width as the fitting groove 2 protruding from one side of a square prism, and a joining groove 32 which is continuous in the same direction as the tenon 31 is recessed and formed on the back side of the tenon 31.

接合溝32はほぞ31の厚さと等しいか僅かに広い寸法
に聞H(l!する。
The joining groove 32 has a dimension equal to or slightly wider than the thickness of the tenon 31.

すなわちほぞ31の突出と接合溝32の開設は同一線上
に形成する。
That is, the protrusion of the tenon 31 and the opening of the joining groove 32 are formed on the same line.

単体壁3も開削刃1と同様に構造物として利用する関係
から、PC版等で形成する。
Since the single wall 3 is also used as a structure like the trench cutting blade 1, it is formed of a PC plate or the like.

次に地中壁の構築方法について説明する。Next, we will explain how to construct underground walls.

[41社列孔の開設 地中壁を築造するライン上に所定の深さのオーガ孔をオ
ーバラップさせて開孔し、柱列孔5を開設する。
[41 Opening of Column Row Holes Auger holes of a predetermined depth are overlapped and opened on the line where the underground wall is to be constructed, and columnar holes 5 are opened.

柱列孔5はラインの全線上に開孔するのではなく、二つ
の開削刃1を内挿できる程度に連続して開設する。
The columnar holes 5 are not opened along the entire line, but are opened continuously to the extent that the two cutting blades 1 can be inserted therein.

[口1開削刃の建込み(第3図) 柱列孔5内には二つの開削刃1を内挿する。[Installation of mouth 1 trench cutting blade (Fig. 3) Two cutting blades 1 are inserted into the columnar holes 5.

このとき各開削刃1は胴部12を対向させそして開削刃
11をそれぞれ左右の開削方向に向(プて配置する。
At this time, each of the cutting blades 1 is arranged so that the body portion 12 faces each other, and the cutting blades 11 are oriented in the left and right cutting directions, respectively.

胴部12と胴部12を対抗さぜた結果、開削刃3− 1間には連続した空間が形成される。As a result of opposing the body parts 12 and 12, the cutting edge 3- A continuous space is formed between the two.

この空間内には開削方向に向けて推進ジヤツキ6を複数
配置する。
In this space, a plurality of propulsion jacks 6 are arranged in the excavation direction.

推進ジヤツキ6は油圧で伸縮する公知の構造のものを採
用する。
The propulsion jack 6 has a known structure that expands and contracts with hydraulic pressure.

[ハ]開削(第4図) 嵌合溝2内に配置した推進ジヤツキ6を伸長させると開
削刃1は地中に食い込んで周囲の土砂を圧迫しながら開
削方向に移動する。
[C] Cutting (FIG. 4) When the propulsion jack 6 placed in the fitting groove 2 is extended, the cutting blade 1 digs into the ground and moves in the cutting direction while compressing the surrounding earth and sand.

その結果推進ジヤツキ6が伸長した距離だけ各開削刃1
が前進する。
As a result, each trench cutting blade 1 is
moves forward.

すなわち各開削刃1の前進距離の総計と等しい距離の開
削が行われる。
That is, cutting is performed for a distance equal to the total forward distance of each cutting blade 1.

また開削刃1を前進させる際、円滑に開削刃1の開削を
行うために予め柱列孔5に接して補助孔51を開孔する
場合もある。
Further, when moving the cutting blade 1 forward, the auxiliary hole 51 may be previously drilled in contact with the columnar hole 5 in order to smoothly perform cutting with the cutting blade 1.

補助孔51の開孔は現場の土質の状態を考慮して適宜決
定する。
The opening of the auxiliary hole 51 is appropriately determined in consideration of the soil condition at the site.

[二]単体壁の建込み(第5図) 推進ジヤツキ6の伸長距離の長さで開削刃1幅4− の溝を開設したら推進ジヤツキ6を縮小さげる。[2] Construction of a single wall (Fig. 5) The length of the extension distance of the propulsion jack 6 is the width of the excavation blade 1 4- After opening the groove, reduce the propulsion jack 6.

縮小を完了したら推進ジヤツキ6を嵌合溝2内から取り
外して撤去する。
When the reduction is completed, the propulsion jack 6 is removed from the fitting groove 2 and removed.

次に両開削刃1の嵌合溝2内に単体壁3のほぞ31を嵌
合させて単体壁3を建込む。
Next, the tenons 31 of the single wall 3 are fitted into the fitting grooves 2 of both cutting blades 1, and the single wall 3 is built.

単体壁3を開削刃1に嵌合する際、はぞ31の開削方向
と平行な側面には市水パツキン4を布設し、接触面の密
着性を向上させる。
When fitting the single wall 3 to the cutting blade 1, a city water packing 4 is laid on the side surface of the groove 31 parallel to the cutting direction to improve the adhesion of the contact surface.

またほぞ31の嵌合の後、嵌合溝2内に残存する空間内
にはモルタルもしくはコンクリートを充填して開削刃1
ど単体壁3の一体化を図る。
After the tenon 31 is fitted, the space remaining in the fitting groove 2 is filled with mortar or concrete,
The purpose is to integrate the single wall 3.

単体壁3を内挿した結果、単体壁3間には接合)R32
が対向した空間が形成される。
As a result of interpolating the single walls 3, there is a joint between the single walls 3) R32
A space is formed in which the two faces face each other.

そしてこの空間内に再び収縮した状態の推進ジヤツキ6
を開削方向に向けて設置する。
And the propulsion jack 6 in a contracted state again in this space
Install it facing the excavation direction.

[ホ]開削 接合溝32内に配置した推進ジヤツキ6を伸長するとそ
の力は単体壁3を介して開削刃1に伝達され、推進ジヤ
ツキ6の伸長した距離だけ開削が進行する。
[E] When the propulsion jack 6 disposed in the cutting joint groove 32 is extended, its force is transmitted to the cutting blade 1 through the single wall 3, and cutting progresses by the distance that the propulsion jack 6 has extended.

開削を完了したらJft進ジVツキ6を撤去し、新たな
単体壁3を継ぎ足しながら再び推進ジヤツキ6をMll
!置して繰り返し開削を行い連続1ノだ地中壁を構築す
る。
After completing the excavation, remove the Jft Suji V Tsuki 6, add a new single wall 3, and install the propulsion jack 6 again.
! By repeatedly excavating and excavating the ground, one continuous underground wall was constructed.

最終的に開削が終了したら単体壁3間に発生する接合溝
32やその他の空間内にモルタルやセメントを充填して
11:水性の高い一体構造の地中壁を完成する。(第6
図) [1へ]その仙の実施例 前記実施例では左右の二方向に開削して地中壁を構築す
る場合について説明したが、一方向に開削して同様な地
中壁を構築する事ができる。
When the excavation is finally completed, the joint grooves 32 and other spaces generated between the single walls 3 are filled with mortar or cement to complete 11: a highly water-based monolithic underground wall. (6th
Figure) [Go to 1] A further example In the above example, the case where an underground wall is constructed by excavating in two directions, right and left, was explained, but it is also possible to construct a similar underground wall by excavating in one direction. I can do it.

本発明はJズ−に説明したようになるから次のような効
果を′M侍する事ができる。
Since the present invention is as explained to J.S., the following effects can be achieved.

〈イ〉従来は開削作業と地中壁の構築作業を独立して行
なっていたが、本願工法の場合は開削作業の際同時に地
中壁が構築される。
<B> Conventionally, excavation work and underground wall construction work were performed independently, but in the present construction method, the underground wall is constructed at the same time as the excavation work.

従って独立して地中壁の構築作業が不要となり効率的な
施工を行うことができる。
Therefore, it becomes unnecessary to construct an underground wall independently, and construction can be carried out efficiently.

〈口〉開削刃は推進ジヤツキの伸長力によって開削され
るので開削中に振動や騒音が発生する心配がまったくな
い。
<Mouth> Since the excavation blade is excavated by the extension force of the propulsion jack, there is no need to worry about vibration or noise occurring during excavation.

〈ハ〉開削刃および単体壁は10版で構成されるのでそ
のまま構造物として利用できる。
<C> Since the excavation blade and single wall are composed of 10 plates, they can be used as a structure as is.

〈二〉開削刃もしくは単体壁と単体壁との間を嵌合させ
、さらにパツキンを配置したので止水効果の高い地中壁
が構築される。
<2> By fitting the trench blade or the single walls together and further arranging the seals, an underground wall with a high water-stopping effect is constructed.

〈ボ〉単体壁間の接合部分に発生する空間内にモルタル
もしくはコンクリートを充15 j−るので一体化した
地中壁を構築する事ができる。
<B> By filling the space created at the joint between single walls with mortar or concrete, it is possible to construct an integrated underground wall.

〈へ〉不安定な地山でも開削の際、開削刃および単体壁
が背面地山を圧迫するので緩みを押えて沈下を防1トシ
、地山の安定を図ることができる。
When excavating even unstable ground, the cutting blade and single wall press against the back ground, suppressing loosening, preventing subsidence, and stabilizing the ground.

くト〉泥水を使用しないので広い施ニスペースを必要と
しない。
〉Since muddy water is not used, a large space is not required.

〈ヂ〉泥水処理施設が不要なので施工コストの低減を図
る事ができる。
〈〈〉Since muddy water treatment facilities are not required, construction costs can be reduced.

〈す〉地下連続壁工法に比べて所要施工設備が簡易であ
る。
(S) Required construction equipment is simpler than the underground continuous wall construction method.

7−7-

【図面の簡単な説明】[Brief explanation of the drawing]

第1図二本発明に使用する構造物の説明図第2図:単体
壁間の接合構造の説明図 第3〜5図:施工状態の説明図 第6図:完成時の地中壁の説明図 1:開削刃     2:1m合溝 3:単体壁     6:推進ジヤツキ出願人    
 大  成  建  設  株  式  会  社9− 8− ■ 回          口 Cv)                で派    
     派 ■ Iフ 脈
Figure 1 2 Explanatory diagram of the structure used in the present invention Figure 2: Explanatory diagram of the joint structure between single walls Figures 3 to 5: Explanatory diagram of the construction state Figure 6: Explanation of the underground wall upon completion Figure 1: Cutting edge 2: 1m groove 3: Single wall 6: Propulsion jack applicant
Taisei Construction Co., Ltd. 9-8- ■ Turnover Cv)
sect■ I-fu vein

Claims (1)

【特許請求の範囲】 地中には開削方向に向けて柱状の開削刃を配冒し、 この開削刃に接して推進ジヤツキを開削方向に向けて配
置し、 推進ジヤツキの伸縮の都度、柱状の単体壁を建て込んで
順次接合させて構築する、 連続地中壁の構築方法
[Scope of Claims] A column-shaped excavation blade is placed underground in the excavation direction, a propulsion jack is placed in contact with the excavation blade and directed in the excavation direction, and each time the propulsion jack expands and contracts, the column-shaped single piece is disposed. A continuous underground wall construction method in which walls are built and joined one after another.
JP10781783A 1983-06-17 1983-06-17 Construction work of continuous underground wall Granted JPS59233016A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10781783A JPS59233016A (en) 1983-06-17 1983-06-17 Construction work of continuous underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10781783A JPS59233016A (en) 1983-06-17 1983-06-17 Construction work of continuous underground wall

Publications (2)

Publication Number Publication Date
JPS59233016A true JPS59233016A (en) 1984-12-27
JPH0366450B2 JPH0366450B2 (en) 1991-10-17

Family

ID=14468783

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10781783A Granted JPS59233016A (en) 1983-06-17 1983-06-17 Construction work of continuous underground wall

Country Status (1)

Country Link
JP (1) JPS59233016A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080265126A1 (en) * 2007-04-20 2008-10-30 Erwin Emil Stoetzer Shuttering element for limiting a trench wall section, shuttering part and method for producing a trench wall in the ground
JP2015117545A (en) * 2013-12-19 2015-06-25 鹿島建設株式会社 Construction method for underground tunnel

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53113109A (en) * 1977-03-12 1978-10-03 Teruo Koi Method and device for drilling square pile hole

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53113109A (en) * 1977-03-12 1978-10-03 Teruo Koi Method and device for drilling square pile hole

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080265126A1 (en) * 2007-04-20 2008-10-30 Erwin Emil Stoetzer Shuttering element for limiting a trench wall section, shuttering part and method for producing a trench wall in the ground
US8348555B2 (en) * 2007-04-20 2013-01-08 Bauer Maschinen Gmbh Formwork element for bounding a trench wall section, formwork part and method for producing a trench wall in the ground
JP2015117545A (en) * 2013-12-19 2015-06-25 鹿島建設株式会社 Construction method for underground tunnel

Also Published As

Publication number Publication date
JPH0366450B2 (en) 1991-10-17

Similar Documents

Publication Publication Date Title
JPS59233016A (en) Construction work of continuous underground wall
JP3860143B2 (en) Excavator for pipe roof and pipe roof construction method using them
JP3194192B2 (en) Open shield method
JP2942874B2 (en) How to join tunnels
JPH0762436B2 (en) Open shield method
JPH0510596U (en) Concrete box for underground structure
JPH06306853A (en) Construction of underground structure
JPH0249896A (en) Open shield method and machine thereof
JPS6062327A (en) Construction of underwater continuous wall
JPS6018769B2 (en) Construction method of underground structure
JPS6248011B2 (en)
JP2876266B2 (en) Sheet pile for underground continuous wall and underground continuous wall method
JP2512898Y2 (en) Concrete box for underground structure
JPH05239833A (en) Method of open-shielding construction and concrete caisson body used therefor
JP3494253B2 (en) Concrete box for underground structure construction
JPS58199925A (en) Construction of underground wall and underground foundation pile with brace
JPH11166229A (en) Groundwater vein restoring method making use of steel pipe column earth retaining wall
JPH05187023A (en) Method of open shielding construction and concrete box body used in the same method
JPS62288214A (en) Wall type bottom-expanded piling work
JPH054490B2 (en)
JPH028084B2 (en)
JPH08218767A (en) Construction method for horizontal slab-shaped structure in ground
JPH1113062A (en) Simplified pneumatic caisson earth retaining construction method
JPH1121877A (en) Restoring method for underground water vein using sheathing wall with steel pipe columns
JPS6145021B2 (en)