JPS59150843A - Building due to shaft assembly wall construction - Google Patents
Building due to shaft assembly wall constructionInfo
- Publication number
- JPS59150843A JPS59150843A JP2055483A JP2055483A JPS59150843A JP S59150843 A JPS59150843 A JP S59150843A JP 2055483 A JP2055483 A JP 2055483A JP 2055483 A JP2055483 A JP 2055483A JP S59150843 A JPS59150843 A JP S59150843A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- frame
- framework
- structural
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Shafts, Cranks, Connecting Bars, And Related Bearings (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
本発明は改良された木造住宅用建築物に関するものであ
る。木造建築物には、我国において従来から採用されて
いた軸組工法建築物および北米において開発され昭和4
9年7月27日付建設省告示を契機として我国に急速に
導入された枠組壁工法建築物の両者が主流となっている
。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an improved wooden residential building. Wooden buildings include the framework construction method traditionally used in Japan and the 4th century wooden construction developed in North America.
Both frame wall construction methods, which were rapidly introduced in Japan following the Ministry of Construction's notification dated July 27, 1999, have become mainstream.
しかしながらこれら従来の建築物には、以下述べるとお
り構造上ならびに施工面の点において欠点を有している
。本発明は上記両建築物の欠点を克服し、かつこれら両
者にはない顕著な作用効果を奏するものである。However, these conventional buildings have drawbacks in terms of structure and construction as described below. The present invention overcomes the drawbacks of both of the above-mentioned buildings, and provides remarkable effects not found in either of them.
従来の軸組工法建築物は周知のとおシ建物の四隅の隅柱
、桁、根太などにより建築現場において寸法出し、切込
などの作業を行い軸組を形成し、先ず屋根組を行−1次
いで各階の床面、壁面の作業を行うという施工方法が採
用されている。まだ、軸組および屋根組を行った後、寸
法精度の調整等のため一旦作業を停止し約二週間程乾燥
させなければならない。したがって、現場作業が長期化
せざるを得ない。また柱、横架材および筋違・火打材な
どの軸組構造のみにより水平荷重ならびに鉛直荷重に耐
えるよう設計されている。その為より太い材木ならびに
欠点のない材木が必要となり、木材資源の稀少化につれ
問題が生じている。即ち、工数ならびに資材の面で上記
欠点を有し、また建築コストの上昇を招く。一方、従来
例の一つたる枠組壁工法建築物は上記軸組構造は存在せ
ず、またその施工方法はプラットフォーム工法と呼ばれ
ているように先づ土台上に一階床枠組を組み、構造用合
板等を打付け、次にこの一階床組を作業台(プラットフ
ォーム)として−階壁枠組を組み、これを建て起こし、
更にこの一階壁組の上に二階床枠組を組み同じく構造用
合板等を打付け、次いでこの二階床組を作業台(プラン
トフオーム)として二階壁組を建て起こし、順次同様の
方法で上の階を建築し、天井枠組、小屋組に至る。また
その構造部材の接合方法は全て釘打である。また構造力
学上は床組および壁組による箱型構造体の面によって水
平・鉛直荷重に耐える設計となっている。従って軸組工
法建築物1c較べ現場における工数は減少するが、下の
階から上の階へと順次施工しなければならないという制
約があり、工期の短縮化に限度がある。また構造的にみ
れば各階は一つの独立した箱であり、これを釘打によっ
て連結しているにすぎない。そして水平荷重は床組から
釘打て連結した下の階の壁組に伝達され、また鉛直荷重
は壁組から下の階の床組に伝達°され最終的に地盤に伝
わる。その為各階の釘打接合という構造、即ち部拐間は
釘打によって連結されているとはいえ、猟に接合部には
空隙が存在するという構造自体、更には釘打作業そのも
のに対する不安は払拭できない。特に応力の集中する隅
柱の設計ならび知その作業が煩雑である。また軸組工法
のように座標軸となる軸が存在せず施工性に問題があり
、これが建築時のみならず完成後も建物全体の寸法精度
の狂いの原因となる。In the conventional framework construction method, the framework is formed by measuring and cutting the four corner pillars, girders, joists, etc. at the construction site, and then the roof is assembled first. The construction method used is to then work on the floors and walls of each floor. After assembling the frame and roof, work must be temporarily stopped and allowed to dry for about two weeks to adjust dimensional accuracy. Therefore, on-site work has to be prolonged. In addition, it is designed to withstand horizontal and vertical loads using only the frame structure, which includes columns, horizontal members, braces, and flint materials. Therefore, thicker lumber and lumber without defects are required, and problems arise as wood resources become rarer. That is, it has the above-mentioned drawbacks in terms of man-hours and materials, and also causes an increase in construction costs. On the other hand, the framework structure described above does not exist in buildings using the frame wall construction method, which is one of the conventional examples, and the construction method is called the platform construction method, in which the first floor frame is first built on the foundation, and the structure is Next, use this first floor floor assembly as a work platform (platform) and construct the floor wall framework, and then erect it.
Furthermore, a second floor frame is built on top of this first floor wall frame, and structural plywood etc. are also nailed down. Next, the second floor frame is erected using this second floor frame as a work platform (plant form), and the upper floor frame is built in the same way. Build the floors, ceiling framework, and roof framework. All of the structural members are joined by nailing. In terms of structural mechanics, the box-shaped structure made up of floor and wall assemblies is designed to withstand horizontal and vertical loads. Therefore, the number of man-hours on site is reduced compared to the frame construction method building 1c, but there is a restriction that construction must be carried out sequentially from the lower floor to the upper floor, and there is a limit to the shortening of the construction period. Structurally, each floor is an independent box, which is simply connected by nails. The horizontal load is transmitted from the floor assembly to the wall assembly on the lower floor, which is connected by nailing, and the vertical load is transmitted from the wall assembly to the floor assembly on the lower floor, and finally to the ground. Therefore, although the structure of each floor is connected by nailing, in other words, even though the sections are connected by nailing, there are gaps in the joints, which eliminates concerns about the structure itself, and even the nailing work itself. Can not. In particular, the work of designing and aligning the corner pillars, where stress is concentrated, is complicated. In addition, unlike the frame construction method, there is no axis that serves as a coordinate axis, which poses problems in construction, and this causes errors in the dimensional accuracy of the entire building not only during construction but also after completion.
一方、本発明は土台、胴差、軒桁、管柱(必要に応じて
通柱)によp軸組を構成し、更にこの軸組に構造用面材
を釘打により張シつけ床組ならびに壁組全構成し、これ
も面としての強度部材。となっている。その為、構造設
計上優れた゛利点を有している。即ち箱型構造体を有す
るが、四隅の隅柱、中間の管柱、土台、胴差、軒桁が軸
組として存するため、水平・鉛直荷重によって生ずる応
力の流れは土佐的に軸組に、かつ副使的には床組、壁組
に流れるが、更にこれら両者によって建築物全体の応力
分布が安定する。On the other hand, in the present invention, a p-shaft is constructed of a foundation, a sill, an eave girder, and a pipe column (through-pillars, if necessary), and a structural panel is further attached to this frame by nailing, and the floor assembly is assembled. In addition, the entire wall structure is constructed, and this is also a strength member as a surface. It becomes. Therefore, it has excellent advantages in terms of structural design. In other words, it has a box-shaped structure, but since the corner pillars at the four corners, the middle pipe pillar, the foundation, the girder, and the eave girder exist as a frame, the flow of stress caused by horizontal and vertical loads is carried out in the frame in the Tosa style. Additionally, the stress flows to the floor and wall assemblies, and both of these stabilize the stress distribution throughout the building.
捷だ耐震・耐風強度も優れたものとなる。更に施工方法
も、軸組を床組および壁組に先行して施工できるので、
軸組完成後、−階床組、二階床組を組み、同時に両階の
壁組を組め、その施′ 工順序は適宜最短手順を選択で
きる。したがって、従来の枠組壁工法建築物の如く、そ
の施工順序を制約されず、丑だ従来の軸組工法建築物で
は、11ξII組拐は勿論のこと砕料や受材の切削(カ
ッティング)も現場作業となっていたのに対し、本発明
では現場におけるこれら作業を殆んど零とすると・とが
出来、その工期を大巾に短縮することができる。更に、
必要に応じて工場で予め人工乾燥される為(含水率15
〜25%)部材強度も高まり、また建物全体の寸法精度
も極めて高いものとなる。従来の軸組工法建築物では、
寸法精度は軸組、即ち軸線の立体的交点によって決まる
が、その重量、材木の乾燥度などの為、屋根組径軸組を
乾燥させても、寸法精度に問題がある。また同じく枠組
壁T法建築物では、座標軸たる軸組が存在しないことと
、その施工順序が下の階から上の階へと制約され、徐々
に建物荷重を支え、かつその重量が変化するため、完成
時の寸法精度の誤差が大きくなる。It also has excellent earthquake and wind resistance. Furthermore, the construction method allows the framework to be constructed before the floor and wall assemblies.
After the framework is completed, the floor assembly and second floor assembly can be assembled, and the walls of both floors can be constructed at the same time, and the shortest construction order can be selected as appropriate. Therefore, unlike conventional framework wall construction buildings, the order of construction is not restricted, and in conventional framework construction construction, not only 11ξII construction but also cutting of crushed materials and receiving materials can be done on-site. However, with the present invention, these on-site operations can be almost eliminated, and the construction period can be greatly shortened. Furthermore,
Because it is artificially dried in advance at the factory as necessary (moisture content 15
~25%) The strength of the members will increase, and the dimensional accuracy of the entire building will also be extremely high. In traditional frame construction method buildings,
Dimensional accuracy is determined by the framework, that is, the three-dimensional intersection of the axes, but due to its weight, dryness of the timber, etc., even if the roof assembly diameter framework is dried, there is a problem in dimensional accuracy. Similarly, in framed wall T-method buildings, there is no frame as a coordinate axis, and the construction order is restricted from lower floors to upper floors, which gradually supports the building load and its weight changes. , the error in dimensional accuracy at the time of completion increases.
これに対し本発明建築物では座標軸たる軸組および施工
順序の制約が比較的少く、床組ならびに壁組によって寸
法精度を維持できるので、建物完成時ならびに使用期間
中の寸法精度は極めて高いものとなっている。On the other hand, in the building of the present invention, there are relatively few restrictions on the frame as the coordinate axis and the construction order, and dimensional accuracy can be maintained by the floor and wall assemblies, so the dimensional accuracy is extremely high upon completion of the building and during the period of use. It has become.
以下、本発明の実施例について説明する。第1図は本発
明建築物の布基礎と一階床組のディテール、第2図は四
二階床組および小屋組ディテールであり、第二3図は比
較のだめの従来例の一つたる枠組壁工法建築物の一階床
組ディテール、第・1図は同じく二階床組および小屋組
ディテール、寸だ第5図(d本発明建築物の−、二階壁
軸組を示すものである。Examples of the present invention will be described below. Figure 1 shows details of the cloth foundation and one-story floor assembly of the building according to the invention, Figure 2 shows details of the 42-story floor assembly and roof assembly, and Figure 23 shows the framework of one of the conventional examples for comparison. Figure 1 shows details of the first-floor floor assembly of a building using the wall construction method, as well as details of the second-floor floor assembly and roof assembly, and Figure 5 (d) shows the second-floor wall framework of the building according to the present invention.
第1図に示すとおり、鉄筋コンクリート布基礎1.に(
d通気用段形スリット3が設けられ、床下換気口を形成
し、同基礎上に土台6が設置される。床根太5. Id
床根太掛け4.上に設置され、更に床根太5.上には構
造用面材9.が張られる。As shown in Figure 1, reinforced concrete cloth foundation 1. To (
d A stepped slit 3 for ventilation is provided to form an underfloor ventilation opening, and a foundation 6 is installed on the same foundation. Floor joists5. Id
Floor joist hanging 4. 5. Installed above and further floor joists. Structural surface material 9. is stretched.
一方、管柱10.は仕口(柱はぞ)7により土台6、と
連結され、管柱に隣接して壁枠組用下枠8゜が設けらル
、アンカーボルト2.が該下枠8.構造用面材5〕、土
台6.および鉄筋コンクリート布基礎1、と全相互に強
固に緊結している。したがって水平構面ば鉄筋コンクリ
ート布基礎1、ならびに土台()によって構成される四
辺形の軸組および土台6ならびに床根太5.に釘打され
た構造用面材1)、の両者によって構成される床組によ
って構造が決まる。12図は二階床組および小屋組ディ
テールであるが、−階管柱10.は、二階床組の四辺形
の軸組を構成する胴差18.と仕口により連結され、該
胴差13には根太受金物15.により二階床根太14.
が設置される。そして該床根太[4,上に構造用面材1
6.が張られている。On the other hand, tube column 10. It is connected to the base 6 by a joint (post) 7, a lower frame 8° for wall framing is provided adjacent to the pipe post, and an anchor bolt 2. is the lower frame 8. Structural surface material 5], foundation 6. and reinforced concrete cloth foundation 1, all of which are firmly connected to each other. Therefore, a horizontal structure consists of a reinforced concrete cloth foundation 1, a quadrilateral framework constituted by a foundation (), a foundation 6, and a floor joist 5. The structure is determined by the flooring made up of both the structural panel 1) nailed to the floor. Figure 12 shows the details of the second-story floor assembly and roof assembly. The trunk difference 18. which constitutes the quadrilateral framework of the two-story floor assembly. and a joist bracket 15. 2nd floor floor joist 14.
will be installed. and said floor joist [4, structural panel 1 on top]
6. is stretched.
したがって水平構面は一階と同じく胴差1:31、床根
太14.ならび妬火打梁(但し図示されていない)てよ
って構成される四辺形の軸組、および胴差13.ならび
に床根太14.に釘打された構造用面材16.の両者に
よって構成される床組にこって構造が決まる。また小屋
組は軒桁200、小屋梁21.ならびに火打梁(但し、
図示されて込ない)によって四辺形の軸組が構成され、
該軒桁20.には二階管柱18が仕口により連結されて
いる。更にこれらの上部に野地板または必要に応じて構
造用面vJ23.を用いた屋根かたる木22.を介して
設置される。したがって水平(屋根)構面ば四辺形の軸
組てよって、あるいは屋根23に構造用面材を用いた場
合には軸組・屋根組によって構造が決定される。Therefore, the horizontal structure is the same as the first floor, with a trunk difference of 1:31 and a floor joist of 14. and a quadrilateral frame consisting of a flint beam (not shown), and a girder 13. and floor joists 14. Structural facing plate nailed to 16. The structure is determined by the floor assembly made up of both. Also, the roof frame has 200 eave girders and 21 roof beams. and flint beams (however,
(not shown) constitutes a quadrilateral framework,
The eave girder 20. A second-story pipe column 18 is connected to the pipe column 18 by a joint. Furthermore, on top of these, sheathing boards or structural surfaces vJ23. 22. installed via. Therefore, in the case of a horizontal (roof) surface, the structure is determined by the quadrilateral framework, or if a structural panel is used for the roof 23, the structure is determined by the framework and roof assembly.
以上のとおり水平構面は−、二階床組とも軸組および構
造用面材による床組によってその構造が決定され、また
小屋組は軸組また床組によって決定されている。これに
対し、従来例の一つたる枠組壁工法建築物では軸組は存
在せず、枠組およびこれに設置された構造用面材による
床面のみがその水平構面の構造を決定している。As mentioned above, the structure of the horizontal structure is determined by the framework and the floor assembly made of structural surface materials for both the two-story floor assembly and the roof assembly, and the structure of the roof assembly is determined by the framework and the floor assembly. On the other hand, in a conventional frame-wall construction building, there is no framework, and only the floor surface made of the framework and structural panels installed on it determines the horizontal structure of the structure. .
即ち、算3図は該建築物の一階床組ディテールであるが
、枠材からなる土台28が布基礎29゜上に設置きれる
。そして土台28.の上面に釘打により枠材たる側根太
27、床根太24.が取付けられ、これら両部材の上面
に構造用面材25゜が同じく釘打により設置される。し
がして枠材から構成されているためアンカーボルト用の
穴を側根太27、床根太24.に設けることが出来ず、
アンカーボルトは床組を土台289、布基礎2)〕、に
固定することが困難である。したがって、水平構面は根
太および構造用面材からなる床面によって構造が決定さ
れる。第4図は同じく二階床組および小屋組ディテール
であるが、枠材たる一階スタノド81.および上枠32
.にょって−階壁面の枠組が構成され、該枠組に構造用
面相(図に示されていない)が釘打されている。That is, the figure 3 shows the detail of the first floor of the building, and the base 28 made of frame material can be installed on the cloth foundation 29 degrees. and base 28. Side joists 27, floor joists 24. are attached, and a structural panel 25° is installed on the upper surface of both members by nailing as well. However, since it is made of frame material, holes for anchor bolts are provided for side joists 27, floor joists 24. It is not possible to set up
It is difficult to fix the floor assembly to the foundation 289, cloth foundation 2) with anchor bolts. Therefore, the structure of the horizontal construction surface is determined by the floor surface made of joists and structural panels. Figure 4 shows the details of the second floor truss and roof truss, but the first floor stanod 81 is the frame material. and upper frame 32
.. A framework for the story wall is constructed and structural facings (not shown) are nailed to the framework.
しかして上枠32の上面には上枠32.同志を補強する
ため頭つなぎ33.が設けられ、該村上面に二階側根太
86.および転び止め35.に狭まれた二階床根太34
.かいずれも釘打によって設置される。そして、これら
根太上面に構造用面材;37が張られる。したが゛って
、二階床組の水平構面には一階と同じく軸組は存在せず
、枠材たる根太および構造用面材から々る床面のみによ
って構造が決定される。更に小屋組も二階床組と同じく
上枠421、頭っなぎ43.上に天井根太44が設けら
れ、この上部に構造用面材46.がたる木45.を介し
て設置される。したがって、水平(屋根)構面は構造用
面材からなる屋−面によって構造が決定される。第3、
第4図から明らかなとおり、全て枠材によって枠Miを
構成し、これに構造用面材全釘打て打ちつけた面構造の
ものであり′、本発明建築物の如く軸組は存せず、また
連結方法は釘打のみであって仕口による連結はない。Therefore, the upper frame 32. Head ties to strengthen comrades 33. is installed, and the second floor side joist 86. is installed on the Murakami surface. and anti-fall35. Second floor floor joists narrowed by 34
.. Both are installed by nailing. Then, a structural panel material 37 is applied to the upper surfaces of these joists. Therefore, like the first floor, there is no framework on the horizontal structure of the second floor, and the structure is determined only by the floor surface from the frame joists and structural panels. Furthermore, the roof frame has a top frame of 421 and a headboard of 43. A ceiling joist 44 is provided above, and a structural panel 46. Gataru tree 45. installed via. Therefore, the structure of the horizontal (roof) surface is determined by the roof surface made of structural surface materials. Third,
As is clear from Fig. 4, it has a surface structure in which the frame Mi is made up of frame materials and all the structural panels are nailed to this, and there is no framework like in the building of the present invention. Also, the connection method is only by nailing, and there is no connection by a shikiguchi.
次に、本発明建築物の実施例の垂直構面たる壁構造につ
いて説明する。第5図は、−1二階壁構造の一つの通り
軸組図であシ(但し、これに張られた構造用面材は示さ
れていない)、他の通りも原則として同様である。隅柱
は−、二階を貫通した通柱51.51゜からなる。但し
、必要な補強を行なった場合は、各階の管柱を胴差を介
して連結しても良い。上端面は軒桁2 U、、−1二階
の境界は胴差130、下端面は土台6である。また開口
部(窓)54の両側は管柱55゜55によって構成ばれ
、更に、通柱5Lと管柱55の中間ならび管柱55:
55.の中間には適宜半柱56が設置されている。更に
適宜間柱52゜53が数句けられている。そしてこれら
柱材および間柱の見付面には構造用面材が開口部を除い
て釘打により設置されている。したがって、垂直構面は
、通柱511、軒桁201、胴差138、土台6、管柱
55.などにより構成された軸組およびこれら部材なら
びに間柱52.53.の見付面に設置された構造用面材
の両者によって構成される壁組によって構造が決定され
ている。Next, a wall structure, which is a vertical structure, of an embodiment of a building according to the present invention will be explained. FIG. 5 is a frame diagram of one of the -1 second floor wall structures (however, the structural panels attached thereto are not shown), and the other streets are basically the same. The corner pillars consist of 51.51° pillars that penetrate through the second floor. However, if necessary reinforcement is performed, the pipe columns on each floor may be connected via a trunk gap. The upper end surface is the eave girder 2U, the boundary between the -1 and second floors is the girder difference 130, and the lower end surface is the foundation 6. Further, both sides of the opening (window) 54 are constituted by tube columns 55° 55, and furthermore, the tube columns 55 and 55 are located between the through column 5L and the tube column 55:
55. A half-post 56 is appropriately installed in the middle. Furthermore, several studs 52 and 53 are installed as appropriate. Structural panels are installed on the exposed faces of these pillars and studs by nailing, except for the openings. Therefore, the vertical structural surface includes the pillars 511, the eave beams 201, the girder difference 138, the foundation 6, the pipe pillars 55, . A framework constituted by these members and studs 52, 53. The structure is determined by the wall structure made up of both the structural panels installed on the facing surface.
一方、従来例の一つたる枠組壁工法建築物では、第:(
、第4図と同様にその壁構造に軸+nは存在せず、壁枠
材からなる枠組と、この見付面に取付けられた構造用面
材からなる壁面のみによってその構造が決定されている
。On the other hand, in a conventional example of a building using the frame wall construction method,
, as in Figure 4, there is no axis +n in the wall structure, and the structure is determined only by the framework made of wall frame materials and the wall surface made of structural panel materials attached to this facing surface. .
以上、本発明の実施例・の説明から明らかなとおり、本
発明は軸組構造に構造用面材を張り付は床組ならびに壁
組を構成することによって建築される建築物である。As is clear from the above description of the embodiments of the present invention, the present invention is a building constructed by attaching structural paneling to a frame structure to form a floor assembly and a wall assembly.
第1図は本発明建築物の布基礎と一階床組ディテール、
第2図は同二階床組と小屋組ディテール、第3図は枠組
壁工法建築物の一階床組ディテール、第4図は同二階床
組および小屋組ディテール、第5図は本発明建築物の−
、二階壁軸組図。
1、・・・・・・鉄筋コノクリート布基礎、2.・・・
・・アンカーボルト、8.・・・・・通気用段形スリッ
ト、4.・・・・・・床根太掛、5.・・・・・・床根
太、6.・・・・・・土台、7・・・・・・柱ホゾ、8
・・・・・下枠、9.・・・・・構造用面材、10゜
・・・・・・柱、11.・・・・・・上枠、13・・・
・・胴差、14.・・・・床根太、15.・・・・・根
太受金物、16.・・・・・構造用面材、17・・・・
・下枠、18・・・・・・柱、19.・・・・・・上枠
、20.・・・・・・軒桁、21.・・・・・・小屋梁
、22.・・たる木、23.・・・・構造用面材、24
.・・・・・床根太、25、・・・・・・構造用面材、
26.・・・・・・下枠、27・・・・・側根太、28
・・・・・・土台、29 ・・・・布基礎、31゜・・
・・・・−階スタノド、32.・・・・・・上枠、33
.・・・・・・頭つなぎ、34.・・・・・・床根太、
85.・・・・・・転び止、3(3・・・側根太、37
・・・・・構造用面材、42.・・・・・上枠、43
.・・・・・頭つなぎ、44.・川・・天井根太、11
5、・・・・・・たる木、46・川・・構造用面材。
特許出願人 株式会社ウンノハウス
弁護士Figure 1 shows the fabric foundation and first-floor floor assembly details of the building according to the invention.
Figure 2 shows details of the second-story floor assembly and roof frame, Figure 3 shows details of the first-floor floor assembly of the frame-wall construction method building, Figure 4 shows details of the same second-story floor assembly and roof frame, and Figure 5 shows the building according to the invention. of-
, second floor wall plan. 1,...Reinforced conocrete cloth foundation, 2. ...
・・Anchor bolt, 8. ...Stepped slit for ventilation, 4.・・・・・・Floor joist hanging, 5.・・・・・・Floor joists, 6. ...Foundation, 7...Pillar tenon, 8
...Bottom frame, 9. ...Structural surface material, 10°...Column, 11. ...Top frame, 13...
・・Torso difference, 14. ...Floor joists, 15. ...Joist support, 16. ...Structural surface material, 17...
・Bottom frame, 18... Pillar, 19. ...Top frame, 20.・・・・・・Eave girder, 21.・・・・・・Rotary beam, 22.・・Tarugi, 23. ... Structural surface material, 24
.. ...Floor joist, 25, ...Structural surface material,
26. ...Bottom frame, 27 ...Side joist, 28
...Foundation, 29 ...Fabric foundation, 31°...
...-Standard, 32. ...Top frame, 33
.. ... head tied, 34. ...floor joists,
85. ...Fall prevention, 3 (3... side joist, 37
... Structural surface material, 42. ...Top frame, 43
.. ...head tied, 44.・River...Ceiling joists, 11
5. ... rafters, 46. river ... structural surface materials. Patent applicant: Unno House Lawyers Co., Ltd.
Claims (1)
面材を張り付は床組ならびに壁組を構成することによっ
て建築される木造建築物。A wooden building constructed by attaching structural facing materials to a frame structure consisting of a foundation, pipe columns, girders, eave girders, and beams to form the floor and wall sections.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2055483A JPS59150843A (en) | 1983-02-12 | 1983-02-12 | Building due to shaft assembly wall construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2055483A JPS59150843A (en) | 1983-02-12 | 1983-02-12 | Building due to shaft assembly wall construction |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS59150843A true JPS59150843A (en) | 1984-08-29 |
Family
ID=12030371
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2055483A Pending JPS59150843A (en) | 1983-02-12 | 1983-02-12 | Building due to shaft assembly wall construction |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS59150843A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100389944B1 (en) * | 2001-04-30 | 2003-07-02 | 김종서 | Parallel preservation time capsule |
JP2018071331A (en) * | 2016-10-26 | 2018-05-10 | 株式会社 ▲高▼▲橋▼監理 | Anchor guide method of two-by-four construction building |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5022806A (en) * | 1973-06-29 | 1975-03-11 | ||
JPS53137522A (en) * | 1977-02-08 | 1978-12-01 | Nippon Jiyuutaku Mokuzai Gijiy | Wooden construction |
JPS556133A (en) * | 1978-06-27 | 1980-01-17 | Toshiba Corp | Combustor |
JPS5544082U (en) * | 1978-09-18 | 1980-03-22 | ||
JPS5681749A (en) * | 1979-11-30 | 1981-07-04 | Matsushita Electric Works Ltd | Shaft frame structure of of building |
-
1983
- 1983-02-12 JP JP2055483A patent/JPS59150843A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5022806A (en) * | 1973-06-29 | 1975-03-11 | ||
JPS53137522A (en) * | 1977-02-08 | 1978-12-01 | Nippon Jiyuutaku Mokuzai Gijiy | Wooden construction |
JPS556133A (en) * | 1978-06-27 | 1980-01-17 | Toshiba Corp | Combustor |
JPS5544082U (en) * | 1978-09-18 | 1980-03-22 | ||
JPS5681749A (en) * | 1979-11-30 | 1981-07-04 | Matsushita Electric Works Ltd | Shaft frame structure of of building |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100389944B1 (en) * | 2001-04-30 | 2003-07-02 | 김종서 | Parallel preservation time capsule |
JP2018071331A (en) * | 2016-10-26 | 2018-05-10 | 株式会社 ▲高▼▲橋▼監理 | Anchor guide method of two-by-four construction building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
SK50082015U1 (en) | Modular frame construction | |
JPH02504533A (en) | building buildings | |
US20220145632A1 (en) | A building truss, system, and construction method | |
US11021866B2 (en) | Building and construction method for same | |
JPS59150843A (en) | Building due to shaft assembly wall construction | |
US4137684A (en) | Building panel | |
JPH05195575A (en) | Panel and framework precut panel built-in construction method | |
RU2826688C1 (en) | Method of constructing wooden frame of building | |
RU2766109C2 (en) | Prefabricated load-bearing structure of flooring and method for its formation | |
JP2961595B2 (en) | Buildings using building frames | |
JPS584968Y2 (en) | beam material | |
JP2519384B2 (en) | Auxiliary surface of wooden prefabricated building | |
JPH01219230A (en) | Construction of new wooden three-story residential-structure | |
JP2828857B2 (en) | Auxiliary surface joint structure of wooden prefabricated building | |
JPH07145639A (en) | Three story house unit building | |
JP3168257B2 (en) | Construction method of wooden house | |
JP2004197406A (en) | Building method of building by framework building construction method | |
JPH0657977B2 (en) | Coupling device for building members | |
JPH10152890A (en) | Building structure of wooden building | |
JPH0430247Y2 (en) | ||
JP2021008796A (en) | Triangular frame architectural structure | |
JPH0124264Y2 (en) | ||
JP2774059B2 (en) | Three-storey unit building | |
JP2008190312A (en) | Slender wood assembly type integral construction method | |
JPS60156835A (en) | Wood building structure |