JP2008190312A - Slender wood assembly type integral construction method - Google Patents
Slender wood assembly type integral construction method Download PDFInfo
- Publication number
- JP2008190312A JP2008190312A JP2007057814A JP2007057814A JP2008190312A JP 2008190312 A JP2008190312 A JP 2008190312A JP 2007057814 A JP2007057814 A JP 2007057814A JP 2007057814 A JP2007057814 A JP 2007057814A JP 2008190312 A JP2008190312 A JP 2008190312A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- building
- foundation
- wall
- ceiling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Foundations (AREA)
- Load-Bearing And Curtain Walls (AREA)
Abstract
Description
一般建築工事General construction
在来工法による建築物及び仮設建築物及び工作物は基礎を築造するため 土工事が終了後、捨てコンクリートに建物の位置の墨出しを行い、基礎コンクリートを流すための型枠を組立て、コンクリート打設前に同基礎にアンカーを設置。しかる後にコンクリートを流して作業を終了。同基礎工事完了後、基礎より上の組立を行い、足場を組立て、これを完成させていたBuildings and temporary buildings and structures by conventional methods are used to build foundations.After earthwork is completed, the position of the building is marked on the discarded concrete, and the formwork for flowing the foundation concrete is assembled, and the concrete is cast. An anchor is installed on the foundation before installation. After that, the concrete is poured to finish the work. After completion of the foundation work, the assembly above the foundation was assembled and the scaffold was assembled and completed.
従来、基礎工事は手間がかかりこれを築造するための熟練した技術が必要であった。
また多くの材料を現場に搬入し、これを熟練工による現地組立が大半であり、在来工法による基礎構造物に前もって埋め込まれたアンカーとこの上に載る上部建築物に同建築物を接続するために空けられた前記アンカーを通す孔との位置の不一致が多いため、場合によっては同アンカーを通す穴をアンカーに合わせて現場でドリル等にて孔を開けていた。また在来基礎のアンカーは上部建築物の土台のみである。土台より上の部分を直接アンカーで接続できない。最近では柱の1部を接続する方法が義務付けられているが、すべてを接続することが出来ない。そのため絶対的な接続強度の不足に陥りやすい欠点があった。Traditionally, the foundation work is time-consuming and requires skill to build it.
In addition, many materials are brought into the field, and this is mostly assembled on the ground by skilled workers. In order to connect the same building to the anchor built in advance in the foundation structure by the conventional construction method and the upper building on it. Since there are many inconsistencies in position with the hole through which the anchor is passed, the hole through which the anchor is passed is aligned with the anchor and drilled on the spot with a drill or the like. In addition, the traditional foundation anchor is only the foundation of the superstructure. The part above the foundation cannot be connected directly with an anchor. Recently, a method of connecting one part of a pillar is obligatory, but not all can be connected. For this reason, there is a drawback that absolute connection strength is likely to be insufficient.
1 基礎工事の簡略化
2 基礎と建物全体の完全接合
3 水平力(地震風圧)による二階床面、三階床面の剛性確保
4 全製品の工場製品化1 Simplification of
本発明の前記ならびにそのほかの目的と新規な特徴は次の説明を添付図面と照らし合わせて読むと、より完全に明らかになるであろう。
ただし、図面はもっぱら解説のためのものであって、本発明の技術的範囲を限定するものではない。The above and other objects and novel features of the present invention will become more fully apparent when the following description is read in conjunction with the accompanying drawings.
However, the drawings are for explanation only and do not limit the technical scope of the present invention.
第一の発明は通常建築物の布基礎の地面から上の垂直部分に相当するところに、工場にて加工製作したH形鉄材を現地で組立てた後、前記H形鉄材の水平部分を支える垂直部材と基礎耐圧版と外周基礎部分とを同時に打設した工作物で、同水平H形鉄材には上部の構造材を取り付けるためのボルトの孔を前もって工場で開けてあり、通常工法の基礎天端の高さ調整工程を省略し、正確且つ強固な基礎工作物を作るための工法。The first invention is a vertical that supports the horizontal part of the H-shaped iron material after assembling the H-shaped iron material processed and manufactured at the factory in the place corresponding to the vertical part above the ground of the fabric foundation of the building. A workpiece in which a member, foundation pressure plate and outer peripheral foundation are placed simultaneously. The horizontal H-shaped iron material has a bolt hole for attaching the upper structural material in advance at the factory. A construction method that eliminates the edge height adjustment process and creates an accurate and strong foundation workpiece.
第二の発明は請求工1の基礎工作物の上に組み立てる木製部材を前もって工場にて孔を開けて、同部材の内、通常建築物では土台にあたる部材を請求工1の基礎工作物にボルトにて取り付け、水平に一段毎に組立、それぞれを長いボルトで上下につなぎ、これを繰り返して1階内側壁を梁下まで積み上げてあげて、完成させ内壁全体を梁、桁の横架材にして、次に前記横架材の上に通常の建築物では梁にあたる部材の代わりに天井の仕上げを兼ねた厚板を、階段を除いた建物面積全体に、長辺を下にして取り付け、続いてこれに900mm前後の間隔を空けて前記厚板の上に、通常建築物では梁のせいにあたる部材の代わりに、厚板を、短辺を下にして取り付け、天井全体に間仕切りを作り、通常建築物では梁の上にあたる部材の代わりに、床板の仕上げを兼ねた厚板を長辺を下にして取り付け、床と天井を一体化した梁を作り、一階内側全体を組み立てた後、建物外側から、前記で組み立てた一階部分に垂直に、二階上部までの長さの外壁部材兼通し柱をボルトにて連続して取り付け、建物外側全体を同部材で囲むように組立て一階部分を完成させた後、二階床に上がりから前記外壁兼通し柱に、一階と同じ部材を今度は内側からボルトで取り付け、一階と同様に壁、天井、床を組み立てる建物を作るための工法In the second invention, a wooden member to be assembled on the foundation work of claimer 1 is drilled in advance at the factory, and a member which is a base in a normal building is bolted to the foundation work of claimer 1 Assemble horizontally and assemble in steps one by one, connect them up and down with long bolts, repeat this and stack the first floor inner wall under the beam, and complete the entire inner wall as a beam and girder horizontal member Next, on the horizontal member, in the normal building, instead of a member that corresponds to a beam, a plank that also serves as a ceiling finish is attached to the entire building area excluding stairs, with the long side down, Instead of a member that is usually the cause of a beam in buildings, a thick plate is attached with the short side down to create a partition on the entire ceiling. In the building, instead of the member on the beam, Install a plank that also serves as a plate finish with the long side down, create a beam that integrates the floor and the ceiling, assemble the entire inside of the first floor, then perpendicular to the first floor part assembled above from the outside of the building Next, the outer wall member and through pillar with a length up to the upper part of the second floor are continuously attached with bolts, the entire outside of the building is surrounded by the same member, and the first floor portion is completed, and then the outer wall The same method as the first floor is attached to the through pillar with bolts from the inside this time, and the construction method to create a building that assembles the walls, ceiling, and floor like the first floor
イ、従来の工法に比べてコンクリート打設が一工程省略できる。コンクリート量が減少する。最初の組立で基礎が正確に築造できる。
ロ、基礎工事が完了した後、上部建築物を組み立てるために前記建築物の位置を示すための測量が不要である。
ハ、土台設置のためにセメント等による再度の基礎コンクリートの天端の凹凸修正が不要である。
ニ、工場製作による鉄製基礎であるため正確である。基礎に合わせて組むだけで正確に木材を組むことが出来る。
ホ、基礎より上の材料が軽量であるため重機が不要である。人手の削減 熟練工が不要、特殊工具等が不要
ヘ、末口10cmの間伐材が使用できる。
以上の説明から明らかなように、本発明にあっては次に列挙する効果が得られる。B) Compared with the conventional method, it is possible to omit one step of placing concrete. The amount of concrete decreases. The foundation can be built accurately in the first assembly.
B) After the foundation work is completed, no surveying is required to indicate the position of the building in order to assemble the upper building.
C. It is not necessary to re-adjust the top and bottom of the foundation concrete with cement etc. for the foundation installation.
D. It is accurate because it is a steel foundation manufactured by a factory. You can assemble wood accurately just by assembling to the foundation.
E. Heavy machinery is unnecessary because the material above the foundation is lightweight. Reduction of manpower No need for skilled workers, no need for special tools, etc.
As is clear from the above description, the present invention has the following effects.
(1)
基礎工事の簡略化 基礎剛性の増加 資材の減少 建物全体一体化による剛性向上(1)
Simplify foundation work Increase foundation rigidity Decrease materials Increase rigidity by integrating the entire building
(2)前記(1)によって、
工期の短縮 工費の大幅な削減 熟練工不要(組立は専門職でなくとも良い)
外部足場不要 建設工事廃材の発生の解消
したがって、(2) According to (1) above,
Shortening construction period Significant reduction in construction cost No need for skilled workers (Assembly may not be a professional job)
No need for external scaffolding
(3)前記(1)によって
新建材や工場生産品の使用を極力抑えることが出来るため、省エネルギーである。
自然素材のため健康住宅である。強固な建築物が熟練工無しでも施工が可能になり、建築単価が下がる。そのことにより建築工事件数の大幅な増加が見込まれる。離島や交通の不便なところでも自力で建てることが出来る。木材使用量の増加によって森林保全に関する産業や活動が活発化する。(3) Since the use of new building materials and factory-produced products can be suppressed as much as possible by the above (1), it is energy saving.
It is a healthy house because of natural materials. A strong building can be constructed without skilled workers, and the unit price of the building is reduced. As a result, the number of construction works is expected to increase significantly. It can be built on its own on remote islands and inconvenient places. Industries and activities related to forest conservation are activated by increasing the amount of timber used.
(4)請求項2
も前記(1)〜(3)と同様な効果が得られる。(4)
The same effects as in the above (1) to (3) can be obtained.
以下図面に示す実施の形態により本説明を詳細に説明する。Hereinafter, the present embodiment will be described in detail with reference to embodiments shown in the drawings.
図1ないし図 に示す本発明を実施するための最良の第1の形態において、
図−1 図11 図13の説明をする。
捨てコンクリートまでは在来の工法にのっとり施工する。捨てコンクリートに建物の位置の墨を出す。1の部材が捨てコンクリートの上に載る位置に鉄製薄板等を重ね、全箇所の高さを同水準にする。同作業完了後建物外周部分の鉄筋を組み立てる。鉄製基礎1から2,3の部材は建物間取りにあわせて直線部分のパーツと建物角部分のパーツに分けてあらかじめ製作する。建物の四方の角部分を水平方向、90度直角に製作して溶接により短辺方向部材と長辺方向部材を相互に剛に接合しておく。鉄筋組立終了後、前記角部分パーツを、捨てコンクリートの上に載せ、墨に合わせて設置する。次にこれに合わせて直線部分パーツを組み合わせボルトで接続する。こうして建物四方の角のパーツと直線部材のパーツを接続すれば建物を組み立てる際の重要課題である直角と水平がおのずからできる。そして各部材全部が組みあがれば基礎鉄材自身の重量により固定する必要はありません。しかる後コンクリートを打設する。同硬化後、強度が出れば2の上に換気パッキン等をのせ、その上に5のアングルを取り付ける。In the first mode for carrying out the present invention shown in FIGS.
1 to 11 will be described.
Until the abandoned concrete, it will be constructed according to the conventional method. Ink the location of the building on the discarded concrete. Stack the steel thin plate etc. on the position where 1 member is thrown away and put on the concrete, and make all the heights the same level. Assemble the reinforcing bars on the outer periphery of the building. The steel foundations 1 to 2 and 3 are pre-fabricated according to the layout of the building, divided into straight parts and building corner parts. The four corners of the building are manufactured in a horizontal direction and 90 degrees perpendicular to each other, and the short side member and the long side member are rigidly joined to each other by welding. After rebar assembly, the corner parts are placed on abandoned concrete and placed in line with the ink. Next, in accordance with this, straight part parts are connected with combination bolts. In this way, if the corner parts of the four sides of the building are connected to the parts of the straight members, the right angle and the horizontal, which are important issues when assembling the building, can be naturally achieved. And if all the parts are assembled, there is no need to fix them by the weight of the basic iron material itself. After that, cast concrete. If the strength is increased after the curing, place a ventilation packing on 2 and attach 5 angles on it.
図1ないし図 に示す本発明を実施するための最良の第1の形態において
図−3の説明をする。
前記5のアングルに、前記基礎のアンカー位置に合わせてあらかじめ孔を空けた土台部材6を載せて17のフクロナットで締め付ける。続いて4の部材の上部に角材等を載せ、先に取り付けた換気パッキンの高さより上に床材が載るよう高さを調節する。同木材の上に薄板ベニヤ等を載せて断熱材が床下に落下しないよう床全体に同薄板ベニヤ等を敷き詰め、その上に断熱材を敷き詰め、さらにその上に厚板長尺床材を置いて下部薄板とビス等で縫合する。FIG. 3 is described in the best mode for carrying out the present invention shown in FIG. 1 to FIG.
A base member 6 having a hole formed in advance according to the anchor position of the foundation is placed on the
図1ないし図 に示す本発明を実施するための最良の第1の形態において図4の説明をする
17のフクロナットに長尺ボルトを2段目に締める高さに合わせた長さに切ってねじ込む。次に内壁兼横架材である6を長尺ボルトに合わせて上から置いて、1段ごとに建物の外周及び間仕切りの開口部以外の壁のあるところに水平に重ねていく。サッシ出入り口等の開口部は建具の寸法にあわせた枠をあらかじめ製作し6の材料を組みながら取り付ける。(屋上に屋根がある場合)これを繰り返し2段目及び3段目まで組み、フクロナットでしめ、前記同様に長尺ボルトを取り付ける。建物角部分は鉄製火打ちを6の部材に仮に取り付け直角を確認しておく。一階全体が組みあがったら前記で取り付けたサッシ外枠にサッシ本体を取り付ける。In the first preferred embodiment for carrying out the present invention shown in FIG. 1 to FIG. 1, a long bolt is cut into a length corresponding to the height at which the second bolt is tightened and screwed into 17 croco nuts illustrated in FIG. . Next, 6 which is an inner wall and horizontal member is placed from the top along the long bolt, and is stacked horizontally on the outer wall of the building and on the wall other than the opening of the partition for each step. For the openings such as the sash doorway, a frame that matches the dimensions of the joinery is manufactured in advance, and 6 materials are assembled. (When there is a roof on the roof) This is repeated and assembled up to the second and third stages, fastened with a fuchsia nut, and a long bolt is attached in the same manner as described above. At the corner of the building, iron fire is attached to the member 6 and the right angle is confirmed. When the entire first floor is assembled, attach the sash body to the sash outer frame attached above.
図1ないし図 に示す本発明を実施するための最良の第1の形態において図−5の説明をする
梁下材8を取り付けたら天井、梁兼用厚板長尺材12を8に載せて桁材10,11を重ねる。10,11の壁内側の欠きこみに合わせてこれに直角に12の梁材を上から嵌め合いする。12の下面と8の上面が接触する部分に接着剤を塗布し8下側より木ビスで留める。
8の部材どうしの水平面の接続はそれぞれの凹凸部分に接着剤を塗布する。続いて木槌等により十分に凹凸部分が密着するまで打撃を与え完全に接合する。次に子梁材13を12に角金物等で直角に取り付けていく。これを繰り返し建物全体の下側部分の作業が完了したら、14の床板、梁兼用長尺厚板をこの上に載せる。前述と同様に14どうしの水平凹凸部分に接着剤を塗布し前記同様連続して接合していく。13上の面と14下の面が接触する部分も同じように接着剤を塗布し、14の上側より木ビスで13に留める。これにより合成梁が完成する。これを繰り返し長尺厚板天井材9と長尺厚板床材14を梁材10と子梁材11の合成梁全体がつながると2階床全体が一体化される。In the first preferred embodiment for carrying out the present invention shown in FIG. 1 to FIG. 5, when the beam lower member 8 described in FIG. The
The connection of the horizontal surfaces of the members of 8 applies an adhesive agent to each uneven part. Subsequently, a hammer is applied until the uneven portion is sufficiently intimately adhered with a mallet or the like to completely join. Next, the sub beam material 13 is attached to 12 at a right angle with a square metal or the like. When this operation is repeated and the work on the lower part of the entire building is completed, 14 floor boards and a long plate for both beams are placed thereon. In the same manner as described above, an adhesive is applied to the 14 horizontal concavo-convex portions and is continuously joined in the same manner as described above. In the same way, the adhesive is applied to the portion where the upper surface of 13 and the lower surface of 14 are in contact with each other. This completes the composite beam. If this is repeated and the long thick plate ceiling member 9 and the long thick plate floor member 14 are connected to the entire composite beam of the
図1ないし図 に示す本発明を実施するための最良の第1の形態において図▲6▼の説明をする。
前記により一階部分の内壁及び間仕切り及び天井床が組みあがったら。外側から7の外壁兼通し柱を18の金物にて6の土台壁兼横架材に取り付ける。この時2階以上の高い部分の孔に18の共まわり防止先付けナットをあらかじめ装着しておく。これを繰り返して建物外壁部材を全て6の土台壁兼横架材に取り付ける。FIG. 6 is explained in the best mode for carrying out the present invention shown in FIGS.
When the inner wall and the partition and the ceiling floor of the first floor part are assembled as described above. 7 outer walls and through columns are attached to 6 base walls and horizontal members with 18 hardware from the outside. At this time, 18 common rotation prevention tip nuts are mounted in advance in the holes in the higher part of the second floor and above. By repeating this, all the building outer wall members are attached to the six base wall and horizontal members.
図1ないし図 に示す本発明を実施するための最良の第1の形態において図7の説明をする。
6の部材を7に、18の共まわり防止先付けナットにボルトで内側から取り付ける。サッシは一階と同じように取り付けていく。FIG. 7 is described in the best mode for carrying out the present invention shown in FIG. 1 to FIG.
The member 6 is attached to the
図1ないし図 に示す本発明を実施するための最良の第1の形態において図8の説明をする。
図4と同じ手順で合成梁及び一体式床天井を組立てる。FIG. 8 will be described in the best mode for carrying out the present invention shown in FIG. 1 to FIG.
Assemble the composite beam and the integrated floor ceiling in the same procedure as FIG.
図1ないし図 に示す本発明を実施するための最良の第1の形態において図9の説明をする。
屋上に屋根がある場合は7の柱に落下防止を施して屋根組みを行う。
ただし、屋上を陸屋根にする場合はこの工程は省かれる。
陸屋根にする場合は勾配を十分にとって防水下地を作り防水をする。9 will be described in the best mode for carrying out the present invention shown in FIGS.
If there is a roof on the roof, the roof is assembled by preventing the 7 pillars from falling.
However, this process is omitted when the roof is made a flat roof.
If you want to make a flat roof, make sure that the slope is sufficient and make a waterproof base.
図1ないし図 に示す本発明を実施するための最良の第1の形態において図10の屋上に屋根がある場合の説明をする。
19の部材を14の上に載せ足元を金物で固定し14の部材でこれを梁方向に平行に連続して組み立てる。次に前記に組み立てた19と14を直角桁方向に木ビス等で取り付ける。次に防水紙を貼り屋根材をとりつけ組立が完了する。次にサッシにガラスを取り付け、防水処理がおわると内部木製建具を取り付けて建築本体工事が完了する。電気配線工事は各階本体組立時に6と7との接触面との間に7の部材の双方の垂直方向にそれぞれの面取りがありこの空間に上部より電線を挿入する。The best mode for carrying out the present invention shown in FIG. 1 to FIG. 1 will be described in the case where there is a roof on the roof of FIG.
19 members are placed on 14 and the feet are fixed with hardware, and the 14 members are continuously assembled in parallel to the beam direction. Next, 19 and 14 assembled as described above are attached with wooden screws or the like in the direction of the right-angle beam. Next, waterproof paper is attached and the roofing material is attached and the assembly is completed. Next, the glass is attached to the sash, and when the waterproof treatment is finished, the internal wooden fitting is attached and the construction work of the building is completed. In the electric wiring work, there are chamfers in the vertical direction of both
次に、図1ないし図 に示す本発明を実施するための異なる形態につき説明する。なおこれらの本発明を実施するための異なる形態の説明に当って、前記本発明を実施するための最良の第1の形態と同一構成部分には同一符号を付して重複する説明を省略する。Next, different modes for carrying out the present invention shown in FIG. 1 to FIG. 1 will be described. In the description of the different modes for carrying out the present invention, the same components as those in the best mode for carrying out the present invention are denoted by the same reference numerals, and redundant description is omitted. .
図 4ないし図に示す本発明を実施するための第2の形態において、前記本発明を実施するための最良の第1の形態と主に異なる点は、
ア、基礎本体を在来工法にて行い、5の金物を取り付ければ前記本発明を実施するための最良の第1の形態と同様の効果が得られる。
イ、9,14,に替えて長尺角材を使用すれば前記本発明を実施するための最良の第1の形態と同様の効果が得られる。
ウ、木材の種類を変えて間伐材、間伐集成材、一般集成材を使用すれば前記本発明を実施するための最良の第1の形態と同様の効果が得られる。The second embodiment for carrying out the present invention shown in FIG. 4 to FIG. 4 is mainly different from the best first embodiment for carrying out the present invention.
A. If the basic body is made by a conventional construction method and 5 hardwares are attached, the same effect as the first preferred embodiment for carrying out the present invention can be obtained.
If a long square material is used in place of (a), (9), (14), and (14), the same effects as those of the best first embodiment for carrying out the present invention can be obtained.
C. If thinned wood, thinned laminated timber, or general laminated timber is used by changing the type of wood, the same effect as the best first embodiment for carrying out the present invention can be obtained.
図−1ないし図4に示す本発明を実施するための第3の形態において、前記本発明を実施するための最良の第1の形態と主に異なる点は、
エ、前記イ、の材料及び土台、柱材壁材、それぞれの断面を大きくして、梁材の垂直部材12をラチス、矩形孔丸形孔等加工を施し軽量にし、組立梁にしても前記本発明を実施するための最良の第1の形態と同様の結果が得られる。(大スパン構造)図−14参照
オ、前記材料を小屋組みに使用しても前記本発明を実施するための最良の第1の形態と同様の結果が得られる。(大スパン屋根)The third embodiment for carrying out the present invention shown in FIGS. 1 to 4 mainly differs from the best first embodiment for carrying out the present invention.
The materials and foundations of the above-mentioned a, the base, the wall material of the pillar material, the respective cross sections are enlarged, and the
本発明は 建築物を 製造する産業で利用される。 The present invention is used in an industry for manufacturing buildings.
1 高さ調整基礎用形鋼鉄材
2 基礎用形鋼鉄材
3 基礎用形鋼鉄材補強形鋼鉄材
4 床板取り付け用形鋼鉄材
5 アンカーセットアングル
6 土台 内壁材、間仕切り材
7 外壁材兼通し柱
8 外梁、側桁受け材
9 梁下材
10 梁中材
11 梁上材受け
12 梁垂直材
13 子梁材
14 梁上材(上側木製フランジ)
15 梁材押さえ兼巾木
16 フクロナット
17 長尺ボルト
18 供回り防止座金一体式先付けナット束、母屋兼用材)1 Height-adjustable
15 Beam material presser and
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007057814A JP2008190312A (en) | 2007-02-06 | 2007-02-06 | Slender wood assembly type integral construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007057814A JP2008190312A (en) | 2007-02-06 | 2007-02-06 | Slender wood assembly type integral construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2008190312A true JP2008190312A (en) | 2008-08-21 |
Family
ID=39750652
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2007057814A Pending JP2008190312A (en) | 2007-02-06 | 2007-02-06 | Slender wood assembly type integral construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2008190312A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105279292A (en) * | 2014-06-30 | 2016-01-27 | 上海神机软件有限公司 | Drawing output system and method of construction engineering templates as well as template layout system and method |
-
2007
- 2007-02-06 JP JP2007057814A patent/JP2008190312A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105279292A (en) * | 2014-06-30 | 2016-01-27 | 上海神机软件有限公司 | Drawing output system and method of construction engineering templates as well as template layout system and method |
CN105279292B (en) * | 2014-06-30 | 2019-07-05 | 上海神机软件有限公司 | Construction project template drawing output system and method, row's modular system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20100058687A1 (en) | Method of constructing a multi-storey building using prefabricated modular panels | |
CN102337765A (en) | Wall structure using bearing wall panel for wooden building and construction method thereof | |
JP3581426B2 (en) | Structural materials and floor and roof structures of wooden buildings and construction methods using them | |
GB2287047A (en) | Building construction of composite boards | |
JP2023514035A (en) | MODULAR COMPOSITE ACTION PANEL AND STRUCTURAL SYSTEM USING THE SAME | |
JP4799107B2 (en) | Mouth structure of wooden structure material, horizontal member, column base structure and column base metal fittings, wooden frame having the same and method of assembling the same | |
JP7071802B2 (en) | How to adjust the seismic shelter installation structure | |
JP2008190312A (en) | Slender wood assembly type integral construction method | |
JP3854106B2 (en) | How to build a wooden house | |
JP2008223358A (en) | Building construction method | |
JP6860354B2 (en) | Building structure | |
JP3886750B2 (en) | How to build a wooden house | |
JP4411478B2 (en) | Wooden frame unit housing | |
JPH05195575A (en) | Panel and framework precut panel built-in construction method | |
US20230417049A1 (en) | Pre-manufactured load bearing walls for a multi-story building | |
JP7364267B2 (en) | wooden building structure | |
RU2766109C2 (en) | Prefabricated load-bearing structure of flooring and method for its formation | |
JP2980199B2 (en) | Building structure | |
JP2009215750A (en) | Chamber unit reinforcing structure of wooden house | |
JP2007262771A (en) | Aseismatic reinforcement structure | |
JP3574131B2 (en) | Architectural liner plate and building using the same | |
JP2004218236A (en) | Earthquake-resistant repair method for existing wooden building | |
JP2005325610A (en) | Floor structure | |
JP2519384B2 (en) | Auxiliary surface of wooden prefabricated building | |
JPH0562178B2 (en) |